About this file

This document provides specifications for an interior lighting project and details of a related federal contract opportunity for replacing refrigerators and freezers at a VA medical center. The interior lighting specification outlines submittal requirements, product details, installation instructions, and acceptance tests for LED and other interior light fixtures. The federal contract opportunity is a 100% SDVOSB set-aside issued through RFP procedures with a magnitude of construction between $500,000-$1,000,000. Proposals are due around July 7, 2021 for the project work at Overton Brooks VA Medical Center in Shreveport, LA, which includes providing all labor, materials and equipment to replace refrigerators and freezers per the scope of work, drawings and specifications by the 180-day performance period deadline.

View the file

Other files

File Type Posted
36C25621R0127 0004.docx DOCX document
RFI 2.docx DOCX document
36C25621R0127 0003.docx DOCX document
Revised 7-15-21 SOW - REPLACE NFS AND PHARMACY REFRIGERATORS AND FREEZERS.docx DOCX document
36C25621R0127 0002.docx DOCX document
Revised 7-15-21 DRWGS SHEETS - Replace NFS and Pharmacy Refridgerators and Freezers.pdf PDF
Replace NFS and Pharmacy Refrigerators and Freezers - Sign In Sheet.pdf PDF
Project Requirements Questions - NFS Freezers and Refrigerator.docx DOCX document
36C25621R0127 0001.docx DOCX document
09 30 13 - Ceramin and Porcelain Tiling.docx DOCX document
01 35 26 - Safety Requirements.docx DOCX document
09 91 00 - Painting.docx DOCX document
EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx DOCX document
27 05 11 - Requirements for Communications Installations.docx DOCX document
EXHIBIT E SURETY FORM.docx DOCX document
23 21 13 - Hydronic Piping.docx DOCX document
23 31 00 - HVAC Ducts and Casings.docx DOCX document
01 42 19 - Reference Standards.docx DOCX document
22 05 11 - Common Work Results for Plumbing.docx DOCX document
02 82 13 13 - Glovebag Asbestos Abatement.docx DOCX document
26 05 11 - Requirements for Electrical Installations.docx DOCX document
08 11 13 - Hollow Metal Doors and Frames.docx DOCX document
23 23 00 - Refigerant Piping.docx DOCX document
23 34 00 - HVAC Fans.docx DOCX document
Revised 4-17-21 SPEC 11 41 21 - Walk In Coolers and Freezers.docx DOCX document
21 08 00 - Commissioning of Fire Suppression Systems.docx DOCX document
26 05 26 - Grounding and Bonding for Electrical Systems.docx DOCX document
EXHIBIT A PERFORMANCE RELEVANCY SURVEY (1).docx DOCX document
05 50 00 - Metal Fabrications.docx DOCX document
26 29 11 - Motor Controllers.docx DOCX document
23 08 00 - Comissioning of HVAC System.docx DOCX document
23 82 00 - Convection Heating and Cooling Units.docx DOCX document
09 29 00 - Gypsum Board.docx DOCX document
EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY v2.docx DOCX document
09 65 13 - Resilient Base and Accessories.docx DOCX document
36C25621R0127_1.docx DOCX document
27 15 00 - Communications Structured Cabling.docx DOCX document
02 41 00 - Demolition.docx DOCX document
01 33 23 - Shop Drawings_Product Data and Samples.docx DOCX document
10 14 00 - Signage.docx DOCX document
09 51 00 - Acoustical Ceilings.docx DOCX document
02 82 13 31 - Asbestos Transite Abatement.docx DOCX document
26 05 33 - Raceway and Boxes for Electrical Systems.docx DOCX document
23 07 11 - HVAC and Boiler Plant Insulation.docx DOCX document
01 45 00 - Quality Control.docx DOCX document
23 05 11 - Common Work Results for HVAC.docx DOCX document
08 90 00 - Louvers and Vents.docx DOCX document
21 13 13 - Wet-Pipe Sprinkler Systems.docx DOCX document
01 00 00 - General Requirements.docx DOCX document
Revised 4-17-21 SOW - REPLACE NFS AND PHARMACY REFRIGERATORS AND FREEZERS.docx DOCX document
Show 40 more

Latest 50 of 72 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 26 51 00 INTERIOR LIGHTING

PART 1 - GENERAL

1.1

DESCRIPTION:

1.2

A.
This section specifies the furnishing, installation, and connection of the interior lighting systems.The terms “lighting fixture,” “fixture,” and “luminaire” are used interchangeably.

RELATED WORK

A. Section 01 74 19, CONSTRUCTION WASTE MANAGEMENT: Disposal of lamps.

B. Section 02 41 00, DEMOLITION: Removal and disposal of lamps and ballasts.

C. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS: Requirements that apply to all sections of Division 26.

D. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES: Low-voltage conductors.

E. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS: Requirements for personnel safety and to provide a low impedance path to ground for possible ground fault currents.

1.3 QUALITY ASSURANCE

A. Quality Assurance shall be in accordance with Paragraph, QUALIFICATIONS (PRODUCTS AND SERVICES) in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.

1.4 SUBMITTALS

A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements:

1. Shop Drawings:

a. Submit the following information for each type of lighting fixture designated on the LIGHTING FIXTURE SCHEDULE, arranged in order of lighting fixture designation.

b. Material and construction details, include information on housing and optics system.

c. Physical dimensions and description.

d. Wiring schematic and connection diagram.

e. Installation details.

f. Energy efficiency data.

g. Photometric data based on laboratory tests complying with IES Lighting Measurements testing and calculation guides. Lamp data including lumen output (initial and mean), color rendition index (CRI), rated life (hours), and color temperature (degrees Kelvin).

h. For LED lighting fixtures, submit US DOE LED Lighting Facts label, and IES L70 rated life.

2. Manuals:

a. Submit, simultaneously with the shop drawings, complete maintenance and operating manuals, including technical data sheets, wiring diagrams, and information for ordering replacement parts.

b. If changes have been made to the maintenance and operating manuals originally submitted, submit updated maintenance and operating manuals two weeks prior to the final inspection.

3. Certifications: Two weeks prior to final inspection, submit the following.

a. Certification by the Contractor that the interior lighting systems have been properly installed and tested.

1.5 APPLICABLE PUBLICATIONS

A. Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by designation only.

B. American Society for Testing and Materials (ASTM):

C635/C635M REV A-13.....Manufacture, Performance, and Testing of Metal Suspension Systems for Acoustical Tile and Lay- in Panel Ceilings C. Environmental Protection Agency (EPA):

40 CFR 261..............Identification and Listing of Hazardous Waste D. Federal Communications Commission (FCC):

CFR Title 47, Part 15...Radio Frequency Devices CFR Title 47, Part 18...Industrial, Scientific, and Medical Equipment E. Illuminating Engineering Society of North America (IESNA):

LM-79-08................Electrical and Photometric Measurements of Solid-State Lighting Products LM-80-15................Measuring Lumen Maintenance of LED Light Sources

PROJECT 667-21-101 REPLACE NFS & PHARMACY

REFRIGERATORS AND FREEZERS

VETERANS ADMINISTRATION, SHREVEPORT, LA

01-01-18

26 51 00 -

INTERIOR LIGHTING

LM-82-12................Characterization of LED Light Engines and LED Lamps for Electrical and Photometric Properties as a Function of Temperature F. Institute of Electrical and Electronic Engineers (IEEE):

C62.41-91(R1995)........Surge Voltages in Low Voltage AC Power Circuits G. International Code Council (ICC):

IBC-15..................International Building Code H. National Electrical Manufacturer's Association (NEMA):

SSL1-16.................Electronic Drivers for LED Devices, Arrays, or Systems I. National Fire Protection Association (NFPA):

70-17...................National Electrical Code (NEC) 101-18..................Life Safety Code J. Underwriters Laboratories, Inc. (UL): 496-17. Lampholders 924-16..................Emergency Lighting and Power Equipment 1598-08. Luminaires 2108-15.................Low-Voltage Lighting Systems 8750-15.................Light Emitting Diode (LED) Light Sources for Use in Lighting Products

PART 2 - PRODUCTS

2.1 LIGHTING FIXTURES

A. Shall be in accordance with NFPA, UL, as shown on drawings, and as specified.

B. Sheet Metal:

1. Shall be formed to prevent warping and sagging. Housing, trim and lens frame shall be true, straight (unless intentionally curved), and parallel to each other as designed.

2. Wireways and fittings shall be free of burrs and sharp edges, and shall accommodate internal and branch circuit wiring without damage to the wiring.

3. When installed, any exposed fixture housing surface, trim frame, door frame, and lens frame shall be free of light leaks.

4. Hinged door frames shall operate smoothly without binding.Latches shall function easily by finger action without the use of tools.
C. Ballasts and lamps shall be serviceable while the fixture is in its normally installed position.Ballasts shall not be mounted to removable reflectors or wireway covers unless so specified.

D. Recessed fixtures mounted in an insulated ceiling shall be listed for use in insulated ceilings.

E. Mechanical Safety: Lighting fixture closures (lens doors, trim frame, hinged housings, etc.) shall be retained in a secure manner by captive screws, chains, aircraft cable, captive hinges, or fasteners such that they cannot be accidentally dislodged during normal operation or routine maintenance.

F. Metal Finishes:

1. The manufacturer shall apply standard finish (unless otherwise specified) over a corrosion-resistant primer, after cleaning to free the metal surfaces of rust, grease, dirt and other deposits. Edges of pre-finished sheet metal exposed during forming, stamping or shearing processes shall be finished in a similar corrosion resistant manner to match the adjacent surface(s). Fixture finish shall be free of stains or evidence of rusting, blistering, or flaking, and shall be applied after fabrication.

2. Interior light reflecting finishes shall be white with not less than 85 percent reflectances, except where otherwise shown on the drawing.

3. Exterior finishes shall be as shown on the drawings.

G. Lighting fixtures shall have a specific means for grounding metallic wireways and housings to an equipment grounding conductor.

2.2 LED LIGHT FIXTURES

A. General:

1. LED light fixtures shall be in accordance with IES, NFPA, UL, as shown on the drawings, and as specified.

2. LED light fixtures shall be Reduction of Hazardous Substances (RoHS)-compliant.

3. LED drivers shall include the following features unless otherwise indicated:

a. Minimum efficiency: 85% at full load.

b. Minimum Operating Ambient Temperature: -20˚ C. (-4˚ F.)

c. Input Voltage: 120 - 277V (±10%) at 60 Hz.

d. Integral short circuit, open circuit, and overload protection.

e. Power Factor: ≥ 0.95.

f. Total Harmonic Distortion: ≤ 20%.

g. Comply with FCC 47 CFR Part 15.

4. LED modules shall include the following features unless otherwise indicated:

a. Comply with IES LM-79 and LM-80 requirements.

b. Minimum CRI 80 and color temperature 3000˚ K unless otherwise specified in LIGHTING FIXTURE SCHEDULE.

c. Minimum Rated Life: 50,000 hours per IES L70.

d. Light output lumens as indicated in the LIGHTING FIXTURE SCHEDULE.

B. LED Downlights:

1. Housing, LED driver, and LED module shall be products of the same manufacturer.

C. LED Troffers:

1. LED drivers, modules, and reflector shall be accessible, serviceable, and replaceable from below the ceiling.

2. Housing, LED driver, and LED module shall be products of the same manufacturer.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Installation shall be in accordance with the NEC, manufacturer's instructions, and as shown on the drawings or specified.

B. Align, mount, and level the lighting fixtures uniformly.

C. Wall-mounted fixtures shall be attached to the studs in the walls, or to a 20 gauge metal backing plate that is attached to the studs in the walls. Lighting fixtures shall not be attached directly to gypsum board.

D. Lighting Fixture Supports:

1. Shall provide support for all of the fixtures. Supports may be anchored to channels of the ceiling construction, to the structural slab or to structural members within a partition, or above a suspended ceiling.

2. Shall maintain the fixture positions after cleaning and relamping.

3. Shall support the lighting fixtures without causing the ceiling or partition to deflect.

4. Hardware for recessed fixtures:

a. Where the suspended ceiling system is supported at the four corners of the fixture opening, hardware devices shall clamp the fixture to the ceiling system structural members, or plaster frame at not less than four points in such a manner as to resist spreading of the support members and safely lock the fixture into the ceiling system.

b. Where the suspended ceiling system is not supported at the four corners of the fixture opening, hardware devices shall independently support the fixture from the building structure at four points.

5. Hardware for surface mounting fixtures to suspended ceilings:

a. In addition to being secured to any required outlet box, fixtures shall be bolted to a grid ceiling system at four points spaced near the corners of each fixture. The bolts shall be not less than 6 mm (1/4 inch) secured to channel members attached to and spanning the tops of the ceiling structural grid members. Non- turning studs may be attached to the ceiling structural grid members or spanning channels by special clips designed for the purpose, provided they lock into place and require simple tools for removal.

b. In addition to being secured to any required outlet box, fixtures shall be bolted to ceiling structural members at four points spaced near the corners of each fixture. Pre-positioned 6 mm (1/4 inch) studs or threaded plaster inserts secured to ceiling structural members shall be used to bolt the fixtures to the ceiling. In lieu of the above, 6 mm (1/4 inch) toggle bolts may be used on new or existing ceiling provided the plaster and lath can safely support the fixtures without sagging or cracking.

E. Furnish and install the new lamps as specified for all lighting fixtures installed under this project.

F. The electrical and ceiling trades shall coordinate to ascertain that approved lighting fixtures are furnished in the proper sizes and installed with the proper devices (hangers, clips, trim frames, flanges, etc.), to match the ceiling system being installed.

G. Bond lighting fixtures to the grounding system as specified in Section

26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS.

H. At completion of project, replace all defective components of the lighting fixtures at no cost to the Government.

I. Dispose of lamps per requirements of Section 01 74 19, CONSTRUCTION WASTE MANAGEMENT, and Section 02 41 00, DEMOLITION.

3.2 ACCEPTANCE CHECKS AND TESTS

A. Perform the following:

1. Visual Inspection:

a. Verify proper operation by operating the lighting controls.

b. Visually inspect for damage to fixtures, lenses, reflectors, diffusers, and louvers. Clean fixtures, lenses, reflectors, diffusers, and louvers that have accumulated dust, dirt, or fingerprints during construction.

2. Electrical tests:

a. Exercise dimming components of the lighting fixtures over full range of dimming capability by operating the control devices(s) in the presence of the COTR.Observe for visually detectable flicker over full dimming range, and replace defective components at no cost to the Government.
b. Burn-in all lamps that require specific aging period to operate properly, prior to occupancy by Government.Burn-in period to be
40 hours minimum, unless specifically recommended otherwise by the lamp manufacturer.Burn-in dimmed fixtures for at least 100 hours at full voltage, unless specifically recommended otherwise by the lamp manufacturer.Replace any lamps and ballasts which fail during burn-in.

3.3 FOLLOW-UP VERIFICATION

A. Upon completion of acceptance checks and tests, the Contractor shall show by demonstration in service that the lighting systems are in good operating condition and properly performing the intended function.

END OF SECTION

File details come from the government source that posted it. Updated .