This document includes a federal contract solicitation and project specifications for resilient flooring installation. The Overton Brooks VA Medical Center is seeking to replace refrigerators and freezers in their Nutrition and Food Service and Pharmacy departments under Project 667-21-101. Interested Service-Disabled Veteran-Owned Small Businesses should monitor the beta.SAM website for solicitation number 36C25621R0127 releasing on or around June 7th, 2021, with proposals due July 7th. The contract award will occur within 30 days of proposal receipt. The 180-day performance period will commence with the Notice to Proceed. The project location is 510 E. Stoner Ave, Shreveport, LA 71101. Specifications cover resilient base and accessories installation in accordance with provided drawings and ASTM standards.

View the file

Other files

File Type Posted
36C25621R0127 0004.docx DOCX document
RFI 2.docx DOCX document
36C25621R0127 0003.docx DOCX document
Revised 7-15-21 SOW - REPLACE NFS AND PHARMACY REFRIGERATORS AND FREEZERS.docx DOCX document
36C25621R0127 0002.docx DOCX document
Revised 7-15-21 DRWGS SHEETS - Replace NFS and Pharmacy Refridgerators and Freezers.pdf PDF
Replace NFS and Pharmacy Refrigerators and Freezers - Sign In Sheet.pdf PDF
Project Requirements Questions - NFS Freezers and Refrigerator.docx DOCX document
36C25621R0127 0001.docx DOCX document
09 30 13 - Ceramin and Porcelain Tiling.docx DOCX document
01 35 26 - Safety Requirements.docx DOCX document
09 91 00 - Painting.docx DOCX document
EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx DOCX document
27 05 11 - Requirements for Communications Installations.docx DOCX document
EXHIBIT E SURETY FORM.docx DOCX document
23 21 13 - Hydronic Piping.docx DOCX document
23 31 00 - HVAC Ducts and Casings.docx DOCX document
01 42 19 - Reference Standards.docx DOCX document
22 05 11 - Common Work Results for Plumbing.docx DOCX document
02 82 13 13 - Glovebag Asbestos Abatement.docx DOCX document
26 05 11 - Requirements for Electrical Installations.docx DOCX document
08 11 13 - Hollow Metal Doors and Frames.docx DOCX document
23 23 00 - Refigerant Piping.docx DOCX document
23 34 00 - HVAC Fans.docx DOCX document
26 51 00 - Interior Lighting.docx DOCX document
Revised 4-17-21 SPEC 11 41 21 - Walk In Coolers and Freezers.docx DOCX document
21 08 00 - Commissioning of Fire Suppression Systems.docx DOCX document
26 05 26 - Grounding and Bonding for Electrical Systems.docx DOCX document
EXHIBIT A PERFORMANCE RELEVANCY SURVEY (1).docx DOCX document
05 50 00 - Metal Fabrications.docx DOCX document
26 29 11 - Motor Controllers.docx DOCX document
23 08 00 - Comissioning of HVAC System.docx DOCX document
23 82 00 - Convection Heating and Cooling Units.docx DOCX document
09 29 00 - Gypsum Board.docx DOCX document
EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY v2.docx DOCX document
36C25621R0127_1.docx DOCX document
27 15 00 - Communications Structured Cabling.docx DOCX document
02 41 00 - Demolition.docx DOCX document
01 33 23 - Shop Drawings_Product Data and Samples.docx DOCX document
10 14 00 - Signage.docx DOCX document
09 51 00 - Acoustical Ceilings.docx DOCX document
02 82 13 31 - Asbestos Transite Abatement.docx DOCX document
26 05 33 - Raceway and Boxes for Electrical Systems.docx DOCX document
23 07 11 - HVAC and Boiler Plant Insulation.docx DOCX document
01 45 00 - Quality Control.docx DOCX document
23 05 11 - Common Work Results for HVAC.docx DOCX document
08 90 00 - Louvers and Vents.docx DOCX document
21 13 13 - Wet-Pipe Sprinkler Systems.docx DOCX document
01 00 00 - General Requirements.docx DOCX document
Revised 4-17-21 SOW - REPLACE NFS AND PHARMACY REFRIGERATORS AND FREEZERS.docx DOCX document
Show 40 more

Latest 50 of 72 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 09 65 13 RESILIENT BASE AND ACCESSORIES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Resilient base (RB) adhered to interior walls and partitions.

1.2 APPLICABLE PUBLICATIONS

A. Comply with references to extent specified in this section.

B. ASTM International (ASTM):

1. F1344-15 - Rubber Floor Tile.

2. F1859-14 - Rubber Sheet Floor Covering without Backing.

3. F1860-14 - Rubber Sheet Floor Covering with Backing.

4. F1861-08 (2012) e1 - Resilient Wall Base.

5. D4259-88 (2012) - Abrading Concrete.

C. Federal Specifications (Fed. Spec.):

1. RR-T-650E - Treads, Metallic and Non-Metallic, Skid-Resistant.

D. International Concrete Repair Institute (ICRI):

1. 310.2R-13 - Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, and Polymer Overlays.

1.3 SUBMITTALS

A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

B. Manufacturer's Literature and Data:

1. Description of each product.

2. Adhesives and primers indicating manufacturer's recommendation for each application.

3. Installation instructions.

C. Operation and Maintenance Data:

1. Care instructions for each exposed finish product.

1.4 DELIVERY

A. Deliver products in manufacturer's original sealed packaging.

B. Mark packaging, legibly. Indicate manufacturer's name or brand, type, color, production run number, and manufacture date.

C. Before installation, return or dispose of products within distorted, damaged, or opened packaging.

PROJECT 667-21-101 REPLACE NFS & PHARMACY

REFRIGERATORS AND FREEZERS

VETERANS ADMINISTRATION, SHREVEPORT, LA

02-01-16

09 65 13 -

RESILIENT BASE AND ACCESSORIES

1.5 STORAGE AND HANDLING

A. Store products indoors in dry, weathertight facility.

B. Protect products from damage when handling and during construction operations.

1.6 FIELD CONDITIONS

A. Environment:

1. Product Temperature: Minimum 21 degrees C (70 degrees F) for minimum 48 hours before installation.

2. Work Area Ambient Temperature Range: 21 to 27 degrees C (70 to 80 degrees F) continuously, beginning 48 hours before installation.

3. Install products when building is permanently enclosed and when wet construction is completed, dried, and cured.

1.7 WARRANTY

A. Construction Warranty: FAR clause 52.246-21, "Warranty of Construction."

PART 2 - PRODUCTS

2.1 PRODUCTS

A. Provide each product from one manufacturer and from one production run.

2.2 RESILIENT BASE

A. Resilient Base: 3 mm (1/8 inch) thick, 100 mm (4 inches) high.

1. Type: Rubber or vinyl; use one type throughout.

2. ASTM F1861, Type TP thermoplastic rubber or Type TV thermoplastic vinyl, Group 2 - layered.

B. Applications:

1. Carpet Flooring Locations: Style A - Straight.

2. Other Locations: Style B - Cove.

2.3 ADHESIVES

A. Adhesives: Low pollutant-emitting, water based type recommended by adhered product manufacturer for each application.

PART 3 - EXECUTION

3.1 PREPARATION

A. Examine and verify substrate suitability for product installation.

B. Protect existing construction and completed work from damage.

C. Remove existing base to permit new installation.

1. Dispose of removed materials.

D. Correct substrate deficiencies.

1. Fill cracks, pits, and depressions with leveling compound.

2. Remove protrusions; grind high spots.

3. Apply leveling compound to achieve 3 mm (1/8 inch) in 3 m (10 feet) maximum surface variation.

E. Clean substrates. Remove contaminants capable of affecting subsequently installed product's performance.

1. Mechanically clean concrete floor substrate according to ASTM D4259.

2. Surface Profile: ICRI Guideline No. 310.2R.

F. Allow substrate to dry and cure.

G. Perform flooring manufacturer’s recommended bond, substrate moisture content, and pH tests.

3.2 INSTALLATION GENERAL

A. Install products according to manufacturer's instructions.

1. When instructions deviate from specifications, submit proposed resolution for Contracting Officer consideration.

3.3 RESILIENT BASE INSTALLATION

A. Applications:

1. Install resilient base in rooms scheduled on Drawings.

2. Install resilient base on casework and other curb supported fixed equipment.

3. Extend resilient base into closets, alcoves, and cabinet knee spaces, and around columns within scheduled room.

B. Lay out resilient base with minimum number of joints.

1. Length: 600 mm (24 inches) minimum, each piece.

2. Locate joints 150 mm (6 inches) minimum from corners and intersection of adjacent materials.

C. Installation:

1. Apply adhesive uniformly for full contact between resilient base and substrate.

2. Set resilient base with hairline butted joints aligned along top edge.

D. Factory form corners and end stops.

E. Roll resilient base ensuring complete adhesion.

3.4 CLEANING

A. Remove excess adhesive before adhesive sets.

B. Clean exposed resilient base surfaces. Remove contaminants and stains.

1. Clean with mild detergent. Leave surfaces free of detergent residue.

C. Polish exposed resilient base to gloss sheen.

3.5 PROTECTION

A. Protect products from construction traffic and operations.

1. Maintain protection until directed by Contracting Officer's Representative.

B. Replace damaged products and re-clean.

1. Damaged Products include cut, gouged, scraped, torn, and un-bonded products.