23 82 00 - Convection Heating and Cooling Units.docx

DOCX document 31 KB Posted

Attached to
Z1DZ--667-21-4-513-0184 - Project 667-21-101 Replace NFS and Pharmacy Refrigerators and Freezers (VA-21-00058352)
Solicitation number
36C25621R0127
Issued by

About this file

This document includes a federal solicitation for replacing refrigerators and freezers at a Veterans Affairs medical center, along with the related project specifications. The solicitation will be issued as a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses to replace NFS and pharmacy refrigerators and freezers at the Overton Brooks VA Medical Center in Shreveport, Louisiana. The tentative RFP issue date is June 7, 2021, with proposals due around July 7, 2021. The anticipated contract award date is approximately 30 days after receipt of proposals. The contract performance period is 180 calendar days from notice to proceed. The estimated construction cost ranges from $500,000 to $1 million. Interested offerors should review the full RFP and associated documents prior to submitting any questions by the specified cut-off date. Only one site visit will be conducted as outlined in the RFP. Offerors must be registered and verified as SDVOSBs in the Vendor Information Pages database to be considered for award.

View the file

Other files

File Type Posted
36C25621R0127 0004.docx DOCX document
RFI 2.docx DOCX document
36C25621R0127 0003.docx DOCX document
Revised 7-15-21 SOW - REPLACE NFS AND PHARMACY REFRIGERATORS AND FREEZERS.docx DOCX document
36C25621R0127 0002.docx DOCX document
Revised 7-15-21 DRWGS SHEETS - Replace NFS and Pharmacy Refridgerators and Freezers.pdf PDF
Replace NFS and Pharmacy Refrigerators and Freezers - Sign In Sheet.pdf PDF
Project Requirements Questions - NFS Freezers and Refrigerator.docx DOCX document
36C25621R0127 0001.docx DOCX document
09 30 13 - Ceramin and Porcelain Tiling.docx DOCX document
01 35 26 - Safety Requirements.docx DOCX document
09 91 00 - Painting.docx DOCX document
EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx DOCX document
27 05 11 - Requirements for Communications Installations.docx DOCX document
EXHIBIT E SURETY FORM.docx DOCX document
23 21 13 - Hydronic Piping.docx DOCX document
23 31 00 - HVAC Ducts and Casings.docx DOCX document
01 42 19 - Reference Standards.docx DOCX document
22 05 11 - Common Work Results for Plumbing.docx DOCX document
02 82 13 13 - Glovebag Asbestos Abatement.docx DOCX document
26 05 11 - Requirements for Electrical Installations.docx DOCX document
08 11 13 - Hollow Metal Doors and Frames.docx DOCX document
23 23 00 - Refigerant Piping.docx DOCX document
23 34 00 - HVAC Fans.docx DOCX document
26 51 00 - Interior Lighting.docx DOCX document
Revised 4-17-21 SPEC 11 41 21 - Walk In Coolers and Freezers.docx DOCX document
21 08 00 - Commissioning of Fire Suppression Systems.docx DOCX document
26 05 26 - Grounding and Bonding for Electrical Systems.docx DOCX document
EXHIBIT A PERFORMANCE RELEVANCY SURVEY (1).docx DOCX document
05 50 00 - Metal Fabrications.docx DOCX document
26 29 11 - Motor Controllers.docx DOCX document
23 08 00 - Comissioning of HVAC System.docx DOCX document
09 29 00 - Gypsum Board.docx DOCX document
EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY v2.docx DOCX document
09 65 13 - Resilient Base and Accessories.docx DOCX document
36C25621R0127_1.docx DOCX document
27 15 00 - Communications Structured Cabling.docx DOCX document
02 41 00 - Demolition.docx DOCX document
01 33 23 - Shop Drawings_Product Data and Samples.docx DOCX document
10 14 00 - Signage.docx DOCX document
09 51 00 - Acoustical Ceilings.docx DOCX document
02 82 13 31 - Asbestos Transite Abatement.docx DOCX document
26 05 33 - Raceway and Boxes for Electrical Systems.docx DOCX document
23 07 11 - HVAC and Boiler Plant Insulation.docx DOCX document
01 45 00 - Quality Control.docx DOCX document
23 05 11 - Common Work Results for HVAC.docx DOCX document
08 90 00 - Louvers and Vents.docx DOCX document
21 13 13 - Wet-Pipe Sprinkler Systems.docx DOCX document
01 00 00 - General Requirements.docx DOCX document
Revised 4-17-21 SOW - REPLACE NFS AND PHARMACY REFRIGERATORS AND FREEZERS.docx DOCX document
Show 40 more

Latest 50 of 72 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 23 82 00 CONVECTION HEATING AND COOLING UNITS

PART 1 - GENERAL

1.1 DESCRIPTION

Fan-coil units for mechanical room.

1.2 RELATED WORK

A. Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS.

B. Section 23 05 11, COMMON WORK RESULTS FOR HVAC: General mechanical requirements and items, which are common to more than one section of Division 23.

C. Section 23 05 41, NOISE and VIBRATION CONTROL FOR HVAC PIPING and EQUIPMENT: Noise requirements.

D. Section 23 05 93, TESTING, ADJUSTING, and BALANCING FOR HVAC: Flow rates adjusting and balancing.

E. Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS: Requirements for commissioning, systems readiness checklists, and training.

F. Section 23
09
23,
DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC: Valve

operators.

G. Section 23

13, HYDRONIC PIPING: Heating hot water and chilled water piping.

H. Section 23
82
16,
AIR COILS: Additional coil requirements.

1.3 QUALITY ASSURANCE

Refer to Paragraph, QUALITY ASSURANCE, in Section 23 05 11, COMMON WORK RESULTS FOR HVAC.

1.4 SUBMITTALS

A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and SAMPLES.

B. Manufacturer's Literature and Data: Fan-Coil units.

C. Certificates:

1. Compliance with paragraph, QUALITY ASSURANCE.

2. Compliance with specified standards.

D. Operation and Maintenance Manuals: Submit in accordance with paragraph, INSTRUCTIONS, in Section 01 00 00, GENERAL REQUIREMENTS.

E. Completed System Readiness Checklists provided by the Commissioning Agent and completed by the contractor, signed by a qualified technician and dated on the date of completion, in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.

PROJECT 667-21-101 REPLACE NFS & PHARMACY

REFRIGERATORS AND FREEZERS

VETERANS ADMINISTRATION, SHREVEPORT, LA

04-11

23 82 00 -

1.5 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.

B. American National Standards Institute / Air Conditioning, Heating and Refrigeration Institute (ANSI/AHRI):

440-08..................Performance Rating of Room Fan Coils

1.6 GUARANTY

In accordance with FAR clause 52.246-21.

PART 2 - PRODUCTS

2.1 ROOM FAN-COIL UNITS

A. Capacity Certification: AHRI 440.

B. Safety Compliance: NEC compliant and UL listed.

C. Noise Levels: Operating at full cooling capacity, sound power level shall not exceed by more than 5 dB the numerical value of sound pressure levels associated with noise criteria specified in Section 23 05 51, NOISE AND VIBRATION CONTROL FOR HVAC PIPING AND EQUIPMENT. Select units at intermediate speed, for compliance with the noise criteria.

D. Chassis: Galvanized steel, acoustically and thermally insulated to attenuate noise and prevent condensation.

E. Cabinet: Minimum 1.3 mm (l8 gage) steel reinforced and braced. Arrange components and provide adequate space for installation of piping package and control valves. Finish shall be factory-baked enamel in manufacturer's standard color on all exposed surfaces.

l. Vertical Exposed Cabinet Unit: Provide 1.6 mm (l6 gage) steel front panel with 13 mm (l/2-inch) thick fiberglass insulation and provide screw-type levelers.

a. Air outlet grilles: Adjustable four-way air deflection located in the top panel.

b. Provide two hinged access doors (one each side) equipped with key operated cam-lock fasteners in the unit top panel located to provide access to the unit controls.

1. Horizontal Unit: Provide exposed type as shown. Provide supports and vibration isolators for horizontal units as recommended by the manufacturer.

a. Exposed Units: Fully enclosed cabinet with hinged bottom access panel with cam-lock fasteners. Provide stamped integral inlet and discharged grilles in front of cabinet.

F. Fans: Centrifugal, forward curved, double width type wheels, galvanized steel or polyester resin construction, statically and dynamically balanced, direct driven.

l. Motors: Premium efficiency, 3-speed permanent split capacitor type with integral thermal overload protection, for operation at not more than l200 RPM.

2. Provide a fan speed selector switch, with off, low, medium, and high positions. Switch shall have a set of auxiliary contacts which are open when the switch is in the "off" position and closed when the switch in any of the other positions. On vertical units, mount switch in a junction box in the cabinet of each unit. On ceiling- suspended horizontal and concealed units, switch shall be wall mounted.

G. Cooling Coil: Hydronic: Copper tubes, 10 mm (three-eighths inch) minimum inside diameter, not less than 4.3 mm (0.0l7 inch) thick with copper or aluminum fins. Coils shall be pressure tested for bursting and strength in accordance with Underwriters Laboratories, Inc., requirements for pressure tested coils, and shall be designed to provide adequate heat transfer capacity. Provide manual air vent at high point of each coil and drain at each low point.

H. Piping Package: Factory furnished with unit by the manufacturer or field-installed by the contractor to fit control valves provided by the controls supplier. Submit manufacturer's detailed drawings of the piping in the end compartments for approval prior to fabrication of the piping packages. Provide ball stop valves on the supply and return pipes and balancing fittings on the return pipes.

I. Drain pans: Furnish galvanized steel with solderless drain connections and molded polystyrene foam insulating liner:

1. Auxiliary drain pan: Located under control valve and piping within the unit enclosure to prevent dripping.

2. Secondary Drain Pan: Provide a secondary drain pan located underneath the unit, constructed to extend a minimum of 50 mm (2 inches) beyond the edges of the unit and be a minimum of 38 mm (1-

1/2 inches deep) provided with a water detection device to deactivate the cooling in the unit.

J. Air Filter: Manufacturer's standard throwaway type, not less than 25 mm (1 inch) thick, MERV 7, supported to be concealed from sight and be tight fitting to prevent air by-pass. Filters shall have slide out frames and be easily replaced without removing enclosure or any part thereof.

K. Control valves and remote wall mounted space thermostats or unit mounted return air thermostats, where shown or specified are to be field installed. Provide two-way modulating control valves unless shown or specified otherwise.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Work shall be installed as shown and according to the manufacturer’s diagrams and recommendations.

B. Handle and install units in accordance with manufacturer's written instructions.

C. Support units rigidly so they remain stationary at all times. Cross-bracing or other means of stiffening shall be provided as necessary. Method of support shall be such that distortion and malfunction of units cannot occur.

3.2 OPERATIONAL TEST

Refer to Section 23 05 11, COMMON WORK RESULTS FOR HVAC.

3.3 STARTUP AND TESTING

The Commissioning Agent will observe startup and contractor testing of selected equipment. Coordinate the startup and contractor testing schedules with the COR and Commissioning Agent. Provide a minimum of 7 days prior notice.

3.4 COMMISSIONING

A. Provide commissioning documentation in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS for all inspection, start up, and contractor testing required above and required by the System Readiness Checklist provided by the Commissioning Agent.

B. Components provided under this section of the specification will be tested as part of a larger system. Refer to Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS and related sections for contractor responsibilities for system commissioning.

3.5 DEMONSTRATION AND TRAINING

A. Provide services of manufacturer’s technical representative for four hours to instruct VA personnel in operation and maintenance of units.

B. Submit training plans and instructor qualifications in accordance with the requirements of Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS.

- - - E N D - - -