About this file

This document provides details for a federal solicitation seeking proposals to replace refrigeration units at a Department of Veterans Affairs medical center. The solicitation will be issued as a 100% set-aside for service-disabled veteran-owned small businesses. Interested offerors are asked to read the forthcoming request for proposals and associated documents in their entirety prior to submitting questions. Proposals will be due approximately 30 calendar days after the anticipated issue date of June 7, 2021. The contract performance period is 180 calendar days following issuance of the notice to proceed. The work location is the Overton Brooks VA Medical Center in Shreveport, Louisiana. Offerors must be registered in the System for Award Management database and verified as a service-disabled veteran-owned small business in the Vendor Information Pages database to be considered for award. The project number is 36C25621R0127 and the North American Industry Classification System code is 236220.

View the file

Other files

File Type Posted
36C25621R0127 0004.docx DOCX document
RFI 2.docx DOCX document
36C25621R0127 0003.docx DOCX document
Revised 7-15-21 SOW - REPLACE NFS AND PHARMACY REFRIGERATORS AND FREEZERS.docx DOCX document
36C25621R0127 0002.docx DOCX document
Revised 7-15-21 DRWGS SHEETS - Replace NFS and Pharmacy Refridgerators and Freezers.pdf PDF
Replace NFS and Pharmacy Refrigerators and Freezers - Sign In Sheet.pdf PDF
Project Requirements Questions - NFS Freezers and Refrigerator.docx DOCX document
36C25621R0127 0001.docx DOCX document
09 30 13 - Ceramin and Porcelain Tiling.docx DOCX document
01 35 26 - Safety Requirements.docx DOCX document
09 91 00 - Painting.docx DOCX document
EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx DOCX document
27 05 11 - Requirements for Communications Installations.docx DOCX document
EXHIBIT E SURETY FORM.docx DOCX document
23 21 13 - Hydronic Piping.docx DOCX document
23 31 00 - HVAC Ducts and Casings.docx DOCX document
01 42 19 - Reference Standards.docx DOCX document
22 05 11 - Common Work Results for Plumbing.docx DOCX document
02 82 13 13 - Glovebag Asbestos Abatement.docx DOCX document
26 05 11 - Requirements for Electrical Installations.docx DOCX document
08 11 13 - Hollow Metal Doors and Frames.docx DOCX document
23 23 00 - Refigerant Piping.docx DOCX document
23 34 00 - HVAC Fans.docx DOCX document
26 51 00 - Interior Lighting.docx DOCX document
Revised 4-17-21 SPEC 11 41 21 - Walk In Coolers and Freezers.docx DOCX document
21 08 00 - Commissioning of Fire Suppression Systems.docx DOCX document
26 05 26 - Grounding and Bonding for Electrical Systems.docx DOCX document
EXHIBIT A PERFORMANCE RELEVANCY SURVEY (1).docx DOCX document
05 50 00 - Metal Fabrications.docx DOCX document
26 29 11 - Motor Controllers.docx DOCX document
23 08 00 - Comissioning of HVAC System.docx DOCX document
23 82 00 - Convection Heating and Cooling Units.docx DOCX document
09 29 00 - Gypsum Board.docx DOCX document
EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY v2.docx DOCX document
09 65 13 - Resilient Base and Accessories.docx DOCX document
27 15 00 - Communications Structured Cabling.docx DOCX document
02 41 00 - Demolition.docx DOCX document
01 33 23 - Shop Drawings_Product Data and Samples.docx DOCX document
10 14 00 - Signage.docx DOCX document
09 51 00 - Acoustical Ceilings.docx DOCX document
02 82 13 31 - Asbestos Transite Abatement.docx DOCX document
26 05 33 - Raceway and Boxes for Electrical Systems.docx DOCX document
23 07 11 - HVAC and Boiler Plant Insulation.docx DOCX document
01 45 00 - Quality Control.docx DOCX document
23 05 11 - Common Work Results for HVAC.docx DOCX document
08 90 00 - Louvers and Vents.docx DOCX document
21 13 13 - Wet-Pipe Sprinkler Systems.docx DOCX document
01 00 00 - General Requirements.docx DOCX document
Revised 4-17-21 SOW - REPLACE NFS AND PHARMACY REFRIGERATORS AND FREEZERS.docx DOCX document
Show 40 more

Latest 50 of 72 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25621R0127 X 06-22-2021 667-21-4-513-0184 667-21-101 Department of Veterans Affairs Overton Brooks VA Medical Center (90C) 510 East Stoner Avenue Shreveport

LA

71101 Department of Veterans Affairs Overton Brooks VA Medical Center (90C) 510 East Stoner Avenue Shreveport

LA

71101 Kaitlyn West 660-525-2238 Note: Any reference contained herein concerning "bid" or "bidder" means "offer" or "offeror".

This procurement is 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) under Public Law (PL) 109-461. Offerors must be verified as a SDVOSB in the VetBiz Vendor Information Pages (VIP at http://www.vetbiz.va.gov.

Offers received from contractors who are not SDVOSB verified in VetBiz will not be considered for award.

Federal Acquistion Regulations require that federal contractors register in the System For Award Management (SAM) database at https://www.sam.gov and enter all mandatory information into the system. Award cannot be made until the contractor has registered. Offerors are encouraged to ensure that they are registered in SAM prior to submitting a proposal.

Project No. 667-21-101 Replace NFS and Pharmacy Refrigerators and Freezers Overton brooks VA Medical Center has a requirement to replace seven walk-in refrigeration units for Nutrition and Food Service and Pharmacy Department in Building 1, Basement Floor at Overton Brooks VAMC in Shreveport, LA.

SITE VISIT: Please see information in solicitation provision FAR 52.236-27 SITE VISIT (CONSTRUCTION) ALTERNATE I.

Forward all questions to the Contracting Officer after the Site Visit but no-later-than 14 calendar days prior to the date set for receipt of proposals. All Q&A's will be posted by Amendment.

MAGNITUDE OF CONSTRUCTION PROJECT: In accordance with FAR 36.204 and VAAR 836.204 DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS, the above described project falls between the following price range: $500,000.00 to $1,000,000.00

NAICS CODE: 236220 SMALL BUSINESS SIZE STANDARD: $38.5M

GEOGRAPHICAL AREA WHERE WORK IS TO BE PERFORMED: Shreveport, Louisiana

X 52.211-10 X 3:00pm

CDT

07-22-2021 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

X Department of Veterans Affairs Overton Brooks VA Medical Center (90C) 510 East Stoner Avenue Shreveport

LA

71101 FSC e-Invoice Payment http://www.fsc.va.gov/fsc/einvoice.asp Invoice Setup Information 1-877-489-6135 invoice must be submitted electronically

1-877-489-6135 X Kaitlyn N. West

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 PRICE/COST SCHEDULE5
ITEM INFORMATION5
Continuation of SF1449 Block 176
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS6
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS8
A.2 GENERAL PROPOSAL INFORMATION8
A.3 PROPOSAL PREPARATION AND EVALUATION INFORMATION10
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)16
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)16
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)16
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)17
2.5 52.228-1 BID GUARANTEE (SEP 1996)19
2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)19
2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)20
2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)20
2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)21
2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)21
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)22
2.12 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008)22
REPRESENTATIONS AND CERTIFICATIONS23
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020) (JUL 2020) (DEVIATION)23
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (OCT 2020)26
3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)29
3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (FEB 2021)30
GENERAL CONDITIONS33
4.1 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)33
4.2 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018)33
4.3 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)34
4.4 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)35
4.5 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2020)35
4.6 52.219-14 LIMITATIONS ON SUBCONTRACTING (MAR 2020) (JUN 2020) (DEVIATION)36
4.7 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)38
4.8 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (NOV 2020)38
4.9 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)41
4.10 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)42
4.11 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (FEB 2021)43
4.12 SUPPLEMENTAL INSURANCE REQUIREMENTS47
4.13 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)48
4.14 852.219-10DEV VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (NOV 2020) (DEVIATION)50
4.15 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)53
4.16 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)54
4.17 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)54
4.18 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)55
4.19 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)56
4.20 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)56
4.21 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)57
4.22 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)58
4.23 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)59
4.24 Contractor Performance Assessment Reporting System (CPARS):60
ATTACHMENTS61

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
JB
__________________
__________________

Scope of Work: The contractor shall provide all materials, labor, equipment, and supervision to replace seven walk-in refrigeration units for Nutrition and Food Service and Pharmacy Department in Building 1, Basement Floor, Overton Brooks VA Medical Center. Contractor shall replace the existing refrigeration boxes and mechanical components, repair existing plumbing leaks above the boxes, expand the refrigeration mechanical equipment room by demolishing an adjacent closet space, install adequate ventilation inside the mechanical room, increase accessibility to related spaces, provide a temporary covered walkway and ramps for the temporary refrigeration units onsite, and all work defined within this scope of work, projection drawings, and specifications. All work shall be performed as specified herein and shall be in accordance with all applicable codes indicated in the Department of Veterans Affairs (VA) Design Manuals and any other applicable codes. The Contractor shall provide all necessary labor, materials, tools, equipment, licenses, permits, and services for completion of this project. The Contractor shall be responsible for all materials delivered and work performed until completion and acceptance of the entire work. Time Duration: 180 Days

GRAND TOTAL
__________________

Continuation of SF1449 Block 17 Offeror shall complete the following Division Price Breakdown:

MATERIAL
LABOR
EQUIPMENT
TOTAL
DIVISION 01:
GENERAL REQUIREMENTS
DIVISION 02:
EXISTING CONDITIONS
DIVISION 03:
CONCRETE
DIVISION 04:
MASONRY
DIVISION 05:
METALS
DIVISION 06:
WOOD, PLASTICS & COMPOSITES
DIVISION 07:
THERMAL & MOISTURE PROTECTION
DIVISION 08:
OPENINGS
DIVISION 09:
FINISHES
DIVISION 10:
SPECIALTIES
DIVISION 11:
EQUIPMENT
DIVISION 12:
FURNISHINGS
DIVISION 13:
SPECIAL CONSTRUCTION
DIVISION 14:
CONVEYING EQUIPMENT
DIVISION 21:
FIRE SUPPRESSION
DIVISION 22:
PLUMBING
DIVISION 23:
HVAC
DIVISION 25:
INTEGRATED AUTOMATION
DIVISION 26:
ELECTRICAL
DIVISION 27:
COMMUNICATIONS
DIVISION 28:
ELECTRONIC SAFETY AND SECURITY
DIVISION 31:
EARTHWORK
DIVISION 32:
EXTERIOR IMPROVEMENTS
DIVISION 33:
UTILITIES

SUBTOTAL COST:

GENERAL LIABILITY / INSURANCE:

OVERHEAD & PROFIT:

BOND:

PROJECT TOTAL COST:

Page 1 of Page 1 of

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

(a) All offer materials will be posted on https://beta.sam.gov/ (System for Award Management). No hard copies will be available.

(b) An offer guarantee is required in an amount not less than 20 percent of the offer price but shall not exceed $3,000,000. Failure to furnish the required offer guarantee in the proper form and amount, by the time set for opening of offers, will require rejection of the offer in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.

(c) The offeror to whom award is made will be required to furnish two bonds, a Performance Bond, SF 25, and a Payment Bond, SF 25A, each in the penal sum of 100% of the award amount.

(End of Clause)

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

A.2 GENERAL PROPOSAL INFORMATION

GENERAL PROPOSAL INFORMATION

Project: 667-21-101 Replace NFS and Pharmacy Refrigerators and Freezers Issuing Office: NCO 16 Location of Project: Overton Brooks VA Medical Center Point of Contact: Kaitlyn West, Contracting Officer, NCO 16 – Shreveport, LA E-mail: kaitlyn.west1@va.gov

1. Service-Disabled Veteran-Owned Small Business Verification: This action is a 100% set aside for verified Service Disabled Veteran Owned Small Businesses (SDVOSB). The award of this solicitation shall not be delayed due to loss of SDVOSB verification. Proposals submitted by non-verified SDVOSB shall be excluded from award consideration.

1. VETS-4212: Title 38, USC Section 4212(d) and Public Law 105-339, requires that federal contractors report, at least annually, the number and category of veterans who are within their workforce. This VETS-4212 report can be submitted per the instructions at https://www.dol.gov/agencies/vets/programs/vets4212. For assistance contact VETS-4212 customer support at 1-866-237-0275 or vets4212-customersupport@dolncc.dol.gov. For procurement awards in excess of $150,000, this report must be completed and accepted prior to any Federal contract award. Therefore, all potential contractors are encouraged to file every year.

2. Past Safety Record: VHA DIRECTIVE 7715 SAFETY AND HEALTH DURING CONSTRUCTION requires that Contracting Officers evaluate and consider past safety records of prospective contractors in awarding contracts. OFFERORS SHALL SUBMIT EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY AS A PART OF THE OFFER PACKAGE.

All offerors shall submit information pertaining to their past Safety and Environmental record using Exhibit D. The information must show that the offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA violation(s) in the past three years. If those totals are exceeded, the offeror shall attach an explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.

All offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If an offeror’s EMR is above 1.0, offeror must attach a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the EMR, and the anticipated date the EMR may be reduced to 1.0 or below.

Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.

If the NCCI cannot issue an EMR because the offeror lacks insurance history, offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead, and include a letter from the NCCI indicating that is has assigned offeror a Unity Rating of 1.0.

This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors

The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.

OFFERORS WHO FAIL TO SUBMIT EXHIBIT D AND THE ADDITIONAL REQUIRED INFORMATION AS A PART OF THEIR PROPOSAL PACKAGE WILL BE EXCLUDED FROM AWARD CONSIDERATION IF AWARD IS MADE WITHOUT DISCUSSIONS.

1. Site Visit: An organized site is scheduled as shown in clause 52.236-27. Only one site visit will be conducted. Attendance at the site visit is not mandatory, but highly suggested for proper proposal preparation.

1. Requests for Information (RFIs): RFI’s are due no later than (NLT) 12:00 PM CST Time 14 days prior to the date set for receipt of proposals and will not be accepted after this date. RFI’s should be submitted by email to the Contracting Officer, Kaitlyn West at kaitlyn.west1@va.gov . Responses will be provided by amendment to the solicitation in a question and answer format. Example: Subject Line of the RFI e-mail should be as follows: Company Name, RFI #1, 36C256-21-R-0127 and Project Title.

1. Proposal Due Date: Proposals are due NLT the date/time shown in Block 13a of Standard Form (SF) 1442. All proposals will be submitted via email to kaitlyn.west@va.gov.

1. Magnitude of Construction: Pursuant to VAAR 836.204 the magnitude of construction is between $500,000.00 and $1,000,000.00.

1. North American Industry Classification (NAICS) code: The applicable NAICS code for this procurement is 236220 Commercial and Institutional Building Construction. The Small Business size standard is $39.5 Million.

1. Wage Determination (WD): The applicable Davis Bacon WD for this solicitation is incorporated as an attachment to this solicitation.

1. Period of Performance: The successful offeror shall begin performance within 10 calendar days after receiving the notice to proceed and complete all work within the time specified in the award. All punch list items must be completed during the established period of performance.

1. Funding: Award is contingent upon the availability of appropriated funds. The Government does not compensate vendors for proposal development and submission.

1. Superintendence: The offeror shall provide, from his own staff, a competent 30 hour OSHA certified superintendent. This individual shall be 100% full time dedicated and assigned to this project while work is being performed on site. The offeror shall not divide or split up their superintendence duties among multiple projects at the same facility. Each project stands alone and requires a dedicated superintendent to be allocated and funded to that particular project.

12. Holidays: The following federal holidays are observed:

New Year's DayMartin Luther King Jr.’s BirthdayPresident's Day
Memorial DayIndependence DayLabor Day
Columbus DayVeterans DayThanksgiving Day

Christmas Day

Any other holiday proclaimed by the President as a Federal Holiday.

When a holiday falls on a Sunday, the following Monday will be observed as a legal holiday. When a holiday falls on a Saturday, the preceding Friday is observed by U.S. Government agencies.

A.3 PROPOSAL PREPARATION AND EVALUATION INFORMATION

This part describes the precise mechanism for evaluating and selecting offers for this procurement for:

PROJECT NO. 667-21-101 Replace NFS and Pharmacy Refrigerators and Freezers A. To assure timely and equitable evaluation of proposals, offerors must follow the instructions contained herein. Proposals must be complete, self-sufficient, and respond directly to the requirements of this solicitation. Offerors are required to meet all solicitation requirements. The Government reserves the right to make a final determination on a proposal’s acceptability/ unacceptability solely on the basis of the proposal submitted and to proceed without requesting additional information. Failure to meet a requirement may result in an offer being removed from consideration for award.

B. Offerors must provide all requested information for each factor. Proposals must address each element of the factors as applicable to be considered responsive to this solicitation. Factor headings should be highlighted in yellow or typed in bold text for identification. It is the offeror’s responsibility to ensure the submitted proposal is in the proper format and the provided information is clear and free of ambiguities.

C. Offeror’s proposal should contain the offeror’s best terms from a price standpoint. Offerors are cautioned to submit sufficient information and in the format specified in the proposal instructions. Communication conducted to resolve minor or clerical errors would not constitute discussions and the Contracting Officer reserves the right to award a contract without the opportunity for proposals revisions or discussions.

D. Evaluations: - Factor 1 (Technical Factor) is more important than Factor 2 (Past Performance). All Non-Priced Factors (Technical and Past Performance), when combined, are approximately equal in importance to Price (Factor 3).

E. THE GOVERNMENT RESERVES THE RIGHT TO AWARD TO OTHER THAN THE OFFEROR WITH THE LOWEST PRICED PROPOSAL OR HIGHEST RATED TECHNICAL PROPOSAL. The source selection process will be a negotiated source selection process utilizing a tradeoff strategy for all non-price evaluation factors in accordance with FAR 15.101 and FAR 15.101-1 respectively. Offers will be evaluated using the evaluation factors listed. It is the offeror's responsibility to ensure the completeness of the proposal. The SSEB may evaluate solely on the information provided in the initial proposal and will not assume that an offeror possesses any capability that is not specifically identified in the proposal.

a. The objective of the source selection is to select the offer that represents the best value to the Government. In order to select the offeror representing the best value, the Government will rate the offers by conducting a comparative assessment of all acceptable offers against source selection criteria in the solicitation. Benefits associated with additional costs will be identified and considered by trading off difference in capability and price. If one offeror has better capability and lower price, then that will be the better value. If one offeror has the better capability and the higher price, then the source selection authority (Contracting Officer) will decide when the difference in capability is worth the difference in price. NOTE: Price will be evaluated but not ranked by CO.

Proposal size will be limited as shown and font/size shall be no smaller than Time New Roman 11. If these page limits are exceeded, the pages in excess of the limit will not be read or considered.

VOLTITLECOPIES PAGE LIMITS
ITECHNICAL PROPOSAL125*
IIPAST PERFORMANCE125*
IIIPRICE1Completed SF1442/SF1442 BACK with
acknowledgement of amendments and
completed Schedule of Offer Items

*EXHIBIT A PERFORMANCE RELEVANCY SURVEY and EXHIBIT B PAST AND PRESENT PERFORMANCE QUESTIONNAIRE do not count against the 25-page limit for Past Performance.

F. Basis for Contract Award:

1. Source Selection: This acquisition will be a “Best Value” source selection process utilizing a tradeoff strategy among cost/price and non-cost/price factors in accordance with FAR 15.101 and FAR 15.101-1 respectively. This process enables the government to consider other than the lowest priced offeror, or other than the highest technically rated offeror. The Government intends to award a single Firm-Fixed-Price contract for construction to the best overall proposal which is determined to be the best value to the Government.

2. Awarding Without Discussions: In accordance with FAR 52.215-1(f) (4), the Government intends to evaluate proposals and award the contract without discussions. Communication between the Government and offerors will be limited to exchanges for clarification as described in FAR 15.306(a). In accordance with FAR 15.306(b)(1)(i) communications may be held with offerors before establishment of the competitive range if the offerors past performance information is the determining factor preventing them from being placed with the competitive range. Such communications shall address adverse past performance information to which the offeror has not had a prior opportunity to respond. Any proposal that does not have a reasonable chance of receiving award may be accordingly eliminated from competition and further evaluation. A competitive range may be established if discussions are determined to be necessary by the Contracting Officer. Should the Contracting Officer determine that discussions are necessary, they will be held with only those offerors determined to be in the competitive range, after which final proposal revisions will be requested. Final proposal revisions shall be submitted as specified and will be due at a time and place to be determined. Firms submitting final proposal revisions will not be requested to re-submit any documents which are unchanged from their initial proposals. Offerors shall submit necessary changes as individual paragraphs or otherwise as briefly as possible, together with a table of contents, which clarifies where within the initial proposal additional or changed documents would be placed.

3. Relative Weight of Evaluation Factors: Evaluations: - Factor 1 (Technical Factor) is more important than Factor 2 (Past Performance). All Non-Priced Factors (Technical and Past Performance), when combined, are approximately equal in importance to Price (Factor 3).

G. EVALUATION FACTORS

Factor 1— Technical: Construction Management Technical Evaluation for Construction Management will be based on the following significant subfactors which are of equal importance:

SUBFACTORS:

· Subfactor 1a. Corporate Construction Project Experience;

· Subfactor 1b. Key Project Personnel Construction Experience; and

· Subfactor 1c. Technical/Management Approach (To Include Phasing)

1a. Corporate Construction Project Experience: The offeror shall demonstrate relevant corporate construction project experience, primarily involving large medical facilities and to include any projects that involved Phasing. Provide a list of projects successfully completed by the offeror of similar size, scope, and complexity (in a Hospital facility or similar working conditions) within the last 3 years of proposal issuance date.

1b. Key Project Personnel Construction Experience: Provide the names of the offeror’s proposed project management personnel (i.e. Site Superintendent, Project Manager,) along with a description of the individual’s experience and a list of successfully completed projects of similar size, scope, and complexity (in a Hospital facility or similar working conditions) within the last 3 years (recent) from proposal issuance date. Superintendent shall have a minimum of three (3) years of experience managing or supervising multiple projects of similar size and scope. If the person listed as proposed superintendent is not a current employee of the offeror but intends to become one upon award of the contract, OFFEROR SHALL SUBMIT A COPY OF A COMMITMENT LETTER FROM THAT PERSON AS A PART OF THE TECHNICAL PROPOSAL to verify offeror will be hiring him/her and he/she intends to accept the position.

1c. Technical/Management Approach (To Include Phasing): Contractor shall explain how the project will be accomplished with no interruptions of services in adjacent patient care areas. Contractor shall demonstrate a clear understanding of the project requirements including critical milestones and critical path. Demonstrate techniques for maintaining on-time schedule performance. Contractor shall provide a detailed explanation as to how the project will be implemented and managed to ensure compliance with all OSHA Construction Standards, and Fire and Life Safety issues, and security measures. Contractor shall provide a site-specific Quality Control Plan describing techniques for maintaining quality control for workmanship. In addition, contractor shall explain their understanding of Phasing on this project and how they plan to accomplish Phasing with minimal interruption to the Government.

In addition to the above, offerors shall provide a confirmation letter from an acceptable Surety, indicating their company’s bonding capacity and capability.

2. Factor 2 — Past Performance:

The Offeror shall demonstrate recent (within the last three years from proposal issuance date) successful performance under contracts (ongoing or completed) which are similar in scope, magnitude, and complexity to the subject requirement via SUBMISSION WITH PAST PERFORMANCE PROPOSAL OF EXHIBIT A PERFORMANCE RELEVANCY SURVEY. SUBMIT EXHIBIT A ON NO LESS THAN FIVE (5) PROJECTS, including information on problems encountered and corrective actions.

Past Performance Questionnaire – Offerors shall prepare and forward to prior client(s) for submission to the Contracting Office EXHIBIT B PAST AND PRESENT PERFORMANCE QUESTIONNAIRE for all the projects listed by contractor and submitted using EXHIBIT A PERFORMANCE RELEVANCY SURVEY. This includes correspondence explaining the requirement to obtain an independent evaluation of prior contract performance and the Past and Present Performance Questionnaire for use in evaluating Past Performance. It is preferred that these are the same projects for ease of evaluation and comparison.

Completed Past Performance Questionnaires shall be submitted to the Contracting Office so as to arrive not later than the closing date/time for receipt of proposals shown on the SF1442. Completed questionnaires shall be forwarded via email to kaitlyn.west1@va.gov The subject line shall state 36C25621R0127 Past Performance for (Name of Company.) NOTE: Offeror shall not review the Past Performance Questionnaire prior to submission. Past Performance Questionnaire must be submitted by the client/evaluator directly to the Contracting Office. It is the offeror’s responsibility to follow up with their references to ensure that the Past Performance Questionnaires have been submitted by the offer due date to the Contracting Office.

Again, Offerors should follow-up and encourage references to get the questionnaires to the Contracting Office by the time set for receipt of proposals. Do not include copies of the letters or questionnaires in the proposal.

The Government may evaluate Past Performance information through the use of Exhibit B completed by the offeror's references; use data independently obtained from other Government or commercial sources, including, but not limited to, Government databases; and/or rely upon personal business experience with the offeror. The evaluation may take into account Past Performance information regarding predecessor companies, key personnel who have relevant experience, and/or subcontractors that will perform major or critical aspects of the requirement when such information is relevant to this acquisition. Past Performance information on contracts not listed by the offeror, or that of planned subcontractors, may also be evaluated. The Government may contact references and contact parties other than those identified by the offeror, and information received may be used in the evaluation of the offeror’s Past Performance. While the Government may elect to consider data obtained from other sources, the burden of providing current accurate and complete Past Performance information rests with the offeror. The Government reserves the right to obtain and evaluate Past Performance information from any source it deems appropriate.

An offeror with limited or no past performance may receive a rating based on the evaluation of its subcontractors and/or key personnel, provided an EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT FORM has been executed and included in the proposal for proposed subcontractors and/or potential key personnel not employed by the offeror. These ratings shall have the same weight as the ratings of the offeror. Offerors without a record of relevant past performance will be assigned a neutral rating in accordance with FAR 15.305(a)(2)(iv). However, the proposal of an offeror with no relevant Past Performance history, while rated “Neutral” in Past Performance, may not represent the most advantageous proposal to the Government and thus, may be an unsuccessful proposal when compared to the proposal of other offerors.

Performance Currency, Trends, and Relevancy: The Government will consider the currency, trends and relevancy of the performance information while conducting its performance evaluation. For the purpose of this solicitation, performance currency is performance occurring within the last three (3) years from the proposal issuance date. Within this period, performance occurring later in the period may have greater significance than work occurring earlier in the period. For example, performance information for work occurring during March 2019 may have greater importance than performance information for work occurring during March 2017. Performance Trends may, depending upon the circumstances, have greater significance than sporadic incidents of "Exceptional" or "Unsatisfactory" performance. For the purpose of this solicitation, Performance Relevancy is defined as contracts (ongoing or completed) which are similar in scope, magnitude, and complexity to the current requirement. Higher relevancy will be assessed for contracts that are similar to the effort, or portion of effort, for which that contractor is being proposed, and may contribute to an overall higher relevancy score for the offeror. Based on the evaluation of offers, the Government will assign a performance confidence rating for each proposal at the factor level. The evaluation will consider the sub-factors as described herein. Following assignment of the performance confidence rating for each proposal, each offeror will receive a final risk rating for performance based on the cumulative rating of performance currency, trends and relevancy.

Past Performance Evaluation will be based on the following subfactors in descending order of importance:

SUBFACTORS

· VA Health Care Construction Experience (to include Projects with Phasing);

· Non-VA Health Care Construction Experience (to include Projects with Phasing);

· Timely Performance Under Previous Construction Projects; and

· Previous Experience in the Geographic Area Covered by this Requirement

2a. VA Health Care Construction Experience: Successful completion of previous construction projects within the past 3 years (recent) in with the same magnitude of construction (relevancy) for the Department of Veterans Affairs to include phasing projects.

2b. Non-VA Health Care Construction Experience: Successful completion of previous construction projects within the past 3 years (recent) in with the same magnitude of construction (relevancy) outside the Department of Veterans Affairs in the health care field. To include large facility and projects that involved phasing.

2c. Timely Performance Under Previous Construction Projects: Demonstrated ability to perform of similar size, scope, and complexity (within the same magnitude of construction) successfully in accordance with approved progress schedules under previous construction projects.

2d. Previous Experience in the Geographic Area Covered by this Requirement: Demonstrated ability to successfully perform construction projects in the location being proposed on. Those offerors who have had recent (within last 3 years) successful projects in the location proposed will be given a higher rating for this subfactor.

3. Factor 3 — Price:

The purpose of the price evaluation is to determine fair and reasonable pricing in relation to the solicitation requirements. Offerors shall submit pricing in the Schedule, the SF1442 Back, and in the conintinuation page of SF 1442 (Block 17) as a part of their price proposal.

2.1 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade
Goals for female participation for each trade
29.3 %
6.9 %

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is

(End of Provision)

2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers.

(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers.

(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations.

(End of Provision)

2.5 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be percent of the bid price or , whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.6 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)

(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—

(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.

(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.

(End of Provision)

2.7 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Kaitlyn N. West Contracting Officer Hand-Carried Address:

Department of Veterans Affairs Overton Brooks VA Medical Center (90C) 510 East Stoner Avenue Shreveport LA 71101 Mailing Address:

Department of Veterans Affairs Overton Brooks VA Medical Center (90C) 510 East Stoner Avenue Shreveport LA 71101

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.8 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— Monday, June 28, 2021 at 10:00 am CST

(c) Participants will meet at— Overton Brooks VAMC, Conference Room 2W62, Shreveport, LA (End of Provision)

2.9 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
OCT 2018
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
AUG 2020
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.215-1
INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION
JAN 2017
52.229-11
TAX ON CERTAIN FOREIGN PROCUREMENTS—NOTICE AND REPRESENTATION
JUN 2020
52.236-28
PREPARATION OF PROPOSALS—CONSTRUCTION
OCT 1997

2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (OCT 2018)

(a) Any protest filed by an interested party shall—

(1) Include the name, address, fax number, email and telephone number of the protester;

(2) Identify the solicitation and/or contract number;

(3) Include an original signed by the protester or the protester’s representative and at least one copy;

(4) Set forth a detailed statement of the legal and factual grounds of the protest, including a description of resulting prejudice to the protester, and provide copies of relevant documents;

(5) Specifically request a ruling of the individual upon whom the protest is served;

(6) State…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .