This Scope of Work document outlines construction requirements for floating dock facilities for the Collier County Sheriff's Office (CCSO) and Marco Police Department (MPD) in Marco Island, Florida, under Bid No. 25-8575. The base scope includes procurement and installation of a 44.4-foot CCSO floating dock with associated piles, access gangway, fixed dock, utilities connections, and one 16,000-pound boat lift. An alternate scope encompasses a 127.6-foot MPD floating dock with associated piles, utilities, and multiple boat lifts (10K, 20K, and one dual jet ski lift). Optional scope for both projects includes dredging services. A non-mandatory pre-bid meeting and site visit are scheduled for January 26, 2026, at 10:00 a.m., with sealed bids due electronically by February 23, 2026, at 3:00 p.m. The project requires continuous coordination with CCSO to maintain vessel accessibility at the existing 990 N. Barfield Drive marina during construction, and potentially with a building general contractor if concurrent construction occurs. The contract will be awarded to the lowest responsible bidder.
Bidders must demonstrate a minimum of ten years of marine construction experience and provide five references not older than four years for work of similar magnitude. All project personnel must clear background checks from both Collier County Facilities and the Collier County Sheriff's Office. The CCSO base scope is not subject to Davis Bacon prevailing wage requirements; however, the MPD alternate scope is subject to Davis Bacon, Build America Buy America (BABA), and American Iron and Steel (AIS) provisions, with EPA grant requirements applicable only to MPD dock construction. The anticipated project budget is $500,000 for the base bid and all alternates, with a $14,300 Owner's Allowance for unforeseen conditions. Liquidated damages are assessed at $183 per calendar day for failure to achieve substantial completion within 180 days. The contractor must utilize Collier County's Procore project management platform for all project management activities and provide comprehensive insurance coverage, including watercraft, maritime, and pollution liability insurance. West Indian Manatee preservation provisions and Clean Water Act Section 404 and 401 compliance are required.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CCSO Floating Dock Scope of Work (Base Scope)
The Collier County Sheriff’s Office (CCSO) needs a new floating dock to store and deploy their law enforcement vessel. The County has engaged J. Foster Consulting for the design services of the dock and the optional associated dredging. State and Federal permits for the project have been applied by J. Foster Consulting. The contractor will be responsible for all local permitting.
The project will include – but is not limited to – the following base scope:
• Procure and install the 44.4’ long CCSO floating dock (Refer to sheet 6 of the floating dock plans) and associated:
o Piles.
o Access gangway and fixed dock.
o Utilities (To be tied into 990 N. Barfield Dr existing services)
• Procure and install one 16K boat lift.
Optional scope includes:
• Dredging associated with the CCSO floating dock.
The CCSO existing marina located at 990 N Barfield Drive will remain open during construction and the vessels will need to remain on site and be accessible. Contractor will be required to continuously coordinate with the CCSO during the project to ensure their needs are continuously met. It is possible that the CCSO existing building could be demolished, and a new building could be in construction in concurrence with this project. Therefore, Contractor could also be required to continuously coordinate with the building general contractor as well.
A 4’x8’ construction sign displaying the project name, the stakeholders’ names and the stakeholder’s logos will need to be installed at the site along with a permit box containing all copies of all required permits.
The Contractor shall use Collier County’s project management platform (Procore) and utilize all tools including Requests for Information (RFIs), Submittals, Daily Log, Photos, Drawings, Specification, Meetings, Schedule, Transmittals, Inspections, Incidents, Budget, Documents, and Directory. The Contractor will be given full access to Procore and will be empowered to manage the RFI and Submittal workflows, document management, meeting management, and all other project management tools to ensure an efficient project. The Contractor will have the ability to invite subcontractors to the project to ensure full participation, access to the latest drawings, and efficient handling of RFIs and submittals.
All workers involved with this project – from the superintendent to the least skilled workman
– must clear both Collier County Facilities background check, and Collier County Sheriff’s Office background check to access the property.
The contractor must have a minimum of 10 years of experience with marine construction and provide a minimum of 5 references not older than 4 years for work of similar magnitude.
The contract will be awarded to the lowest responsible bidder. Davis Bacon is not applicable to the CCSO dock construction. Contractor shall adhere to the provisions for preservation of the West Indian Manatee provided with this solicitation.
MPD Floating Dock Scope of Work (Alternate Scope)
The Marco Police Department (MPD) also needs a new floating dock to store and deploy their law enforcement vessels. The MPD dock will be accessed from the CCSO dock. The City has also engaged J. Foster Consulting for the design services of their dock and the optional associated dredging. State and Federal permits for the project have been applied by J. Foster Consulting. The contractor will be responsible for all local permitting.
The project will include – but is not limited to – the following base scope:
• Procure and install the 127.6’ long MPD floating dock (Refer to sheet 6 of the floating dock plans), associated piles and utilities (To be tied into 807 E. Elkcam existing services).
• Procure and install 10K and 20K boat lifts and one dual jet ski lift.
Optional scope includes:
• Dredging associated with the MPD floating dock.
The County is responsible for soliciting and managing the construction of the MPD dock. The City is responsible for directly issuing a purchase order and processing all payments to the contractor. The MPD dock is the recipient of an EPA grant. The requirements associated with that grant only apply to the construction of the MPD dock. The City is responsible for the management of the EPA grant.
The adjacent CCSO existing marina located at 990 N Barfield Drive will remain open during construction and the vessels will need to remain on site and be accessible. Contractor will be required to continuously coordinate with the CCSO during the project to ensure their needs are continuously met.
A 4’x8’ construction sign displaying the project name, the stakeholders’ names and the stakeholder’s logos will need to be installed at the site along with a permit box containing all copies of all required permits.
The Contractor shall use Collier County’s project management platform (Procore) and utilize all tools including Requests for Information (RFIs), Submittals, Daily Log, Photos, Drawings, Specification, Meetings, Schedule, Transmittals, Inspections, Incidents, Budget, Documents, and Directory. The Contractor will be given full access to Procore and will be empowered to manage the RFI and Submittal workflows, document management, meeting management, and all other project management tools to ensure an efficient project. The Contractor will have the ability to invite subcontractors to the project to ensure full participation, access to the latest drawings, and efficient handling of RFIs and submittals.
The contractor must have a minimum of 10 years of experience with marine construction and provide a minimum of 5 references not older than 4 years for work of similar magnitude.
The contract will be awarded to the lowest responsible bidder. The contractor shall not discriminate based on race, color, national origin, or sex in the performance of this project.
Davis Bacon is applicable for the MPD dock construction. Contractor shall adhere to the current prevailing wage determination (found at https://sam.gov/search/?index=dbra&page=1&pageSize=25&sort=-modifiedDate&sfm%5Bstatus%5D%5Bis_active%5D=true) as well as Build America Buy America (BABA) and the American Iron and Steel (AIS) provisions.
All aspects of the City alternate scope will adhere to the provisions set forth in the Federal Code of Regulations and the Environmental Protection Agency General Terms and Conditions. Contractor shall adhere to the provisions for preservation of the West Indian Manatee provided with this solicitation.