This specification document outlines the technical requirements for the Collier County Sheriff's Office (CCSO) Marco Substation Floating Dock Project in Marco Island, Florida, as well as an optional adjacent floating dock for the Marco Island Police Department (MPD). The project requires procurement and installation of marine infrastructure including floating docks, gangways, boat lifts, and utility systems. For the CCSO facility, specifications include a 20-foot minimum gangway with marine-grade aluminum construction and slip-resistant decking; a floating dock with HDPE-encapsulated EPS foam floats, fully welded marine-grade aluminum frame (with PT wood and galvanized steel alternate pricing), composite decking, commercial-grade double-molded dock edging, and cast aluminum cleats; and a boat lift from Golden Boat Lifts featuring all-aluminum construction with SEA-Drive gearbox and stainless steel motors. The MPD dock specifications are similar but require twelve cleats on the eastern side instead of four and three marine utility pedestals instead of one. Both facilities require electrical utility pedestals with LED lighting, shore power receptacles, GFCI receptacles, and hose bibs; marine light bollards; plumbing utilities with potable water supply; fire protection systems compliant with NFPA 1 Chapter 28 and NFPA 303; and security systems including 360-degree cameras mounted on aluminum poles with Point-to-Point units. Sealed bids are due February 23, 2026, at 3:00 p.m., with a non-mandatory pre-bid meeting and site visit scheduled for January 26, 2026, at 10:00 a.m. at 990 N. Barfield Drive, Marco Island.
Contractors are responsible for all design work including signed and sealed electrical, plumbing, and fire protection plans; all permitting and Authority Having Jurisdiction (AHJ) approvals; utility coordination with dock manufacturers; site restoration; staging area development; and provision of barges or work platforms. The contract includes maintenance dredging (approximately 45 cubic yards) if required to maintain navigable waters, with permit plans already completed and applications submitted to State and Federal agencies. All pile wrapping, security ladder installation on the fixed dock, existing utility disconnection and demolition, and penetrations through the seawall for new utilities are contractor responsibilities. The anticipated project budget is $500,000 for base bid and all alternates, with an Owner's Allowance of $14,300 for unforeseen conditions. Qualified marine construction contractors must demonstrate a minimum of ten years of marine construction experience, provide five project references from similar work within the past five years, and ensure all personnel pass background checks from both Collier County Facilities and the Collier County Sheriff's Office. Bidders must submit a certified bid bond equal to five percent of the total bid amount, and successful awardees must provide 100% Performance and Payment Bonds within ten calendar days of award. Liquidated damages are set at $183 per calendar day for failure to achieve substantial completion within 180 days, and contractors must maintain comprehensive insurance coverage including watercraft, maritime, and pollution liability insurance.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CCSO Dock Specification Notes
1. Gangway:
a. Contractor is responsible for securing vendor for the gangway per the following specifications.
b. Marine grade aluminum construction.
c. Aluminum pipe railings with minimum clearance of 42” in-between.
d. Slip resistant aluminum decking.
e. Gangway minimum length shall be 20 feet.
f. Contractor to provide submittals for JFC and owner review and approval.
2. Floating Dock:
a. Contractor is responsible for securing vendor for the floating dock per the following specifications.
b. Floats: HDPE (High-density polyethylene) encapsulated EPS (Expanded Polystyrene) foam.
c. Frame fully welded marine grade aluminum (Base Price). Alternate pricing for PT wood with galvanized steel hardware to be provided.
d. Decking: Composite (Color to be selected via submittal). Use same decking for new fixed dock.
e. Commercial-grade double-molded dock edging to be located on the entire eastern side of the dock.
f. Cast aluminum 14” minimum length cleats. A minimum of four cleats must be located on the eastern side of the dock (Positioning to be selected via submittal)
g. Each pile guide is to be equipped with four rollers.
h. Contractor to provide submittals for JFC and owner review and approval.
3. Boat Lift:
a. Boat lift manufacturer shall be Golden Boat Lifts of N. Fort Myers.
b. All aluminum complete lift driven by SEA-Drive gear box with stainless steel motors.
c. Cradle beams to have angle on seawall side.
d. 19-degree aluminum bunk boards and bunk brackets secured with stainless-steel hardware.
e. Guideposts brackets secured with stainless-steel, weighted guide pipes and PVC guides.
f. Furnish Gem remote control with auto-stop feature.
g. Includes (4) 12” PT timber piles per engineered plans. Piles to be wrapped as specified.
4. Electrical Utilities:
a. One marine utility pedestal to be located on the eastern side of the dock (Positioning to be selected via submittal). Pedestal is to include:
• LED lights controlled via a photocell to illuminate the docking facilities center walkway.
• One 125V 30A shore power receptacle.
• One 120V 20A GFCI general use receptacle.
• Breaker(s) as needed.
• One hose bib (See 5. Plumbing)
b. One marine light bollard (Positioning to be selected via submittal). Bollard is to include:
• LED lights controlled via a photocell to illuminate the docking facilities center walkway.
c. Contractor scope includes supply and installation of all wiring, conduits, necessary penetrations and pipes/hoses from the lift, utility pedestal and light bollard to the service tie-in point.
d. The contractor will be responsible for the electrical design including a signed and sealed plan set and submittals for owner review and approval.
e. The contractor is responsible for all required permitting and AHJ approval prior to construction.
f. Contractor to coordinate all utilities with floating dock manufacturer to ensure adequate chases are installed.
g. The base cost for electrical is to include all work needed to tie into the County CCSO station site electrical service at a location upland of the seawall in the vicinity of the new fixed dock
5. Plumbing Utilities:
a. Includes potable water supply to the utility pedestal hose bib.
b. The contractor will be responsible for the plumbing design including a signed and sealed plan set and submittals for owner review and approval.
c. Contractor responsible for all required permitting and AHJ approval prior to construction.
d. Contractor to coordinate all utilities with floating dock manufacturer to ensure adequate chases are installed.
e. The base cost for plumbing is to include all work needed to tie into the County CCSO station site potable water service at a location upland of the seawall in the vicinity of the new fixed dock
6. Fire Protection
a. Includes the required fire protection to suit the local AHJ requirements and any required connection to site utilities.
b. Contractor will be responsible for the fire protection design including a signed and sealed plan set and submittals for owner review and approval and submission to local agencies and AHJ as required for approval.
c. The contractor is responsible for all required permitting and AHJ approval prior to construction.
d. Contractor to coordinate all utilities with floating dock manufacturer to ensure adequate chases are installed.
e. Below are notes from correspondence with the local fire department for reference.
i. All docks must comply with NFPA 1, Chapter 28 and NFPA 303 “Fire Protection Standard for Marinas and Boatyards”.
ii. The docks must have fire extinguishers in accordance with NFPA 1, Ch. 28, sec.
28.1.6.1
iii. If the docks are required to have a fire standpipe system, it shall be installed in accordance with Ch. 28.1.6.3.1. of NFPA 1.
iv. The standpipe system for firefighting purposes on docks shall be permitted separately. Though a separate permit is required the dock plans shall recognize and note the required condition.
v. Underground or dock standpipe system shall be permitted separately as well.
7. Security/Safety:
a. Supply and installation of the security system outlined below:
• 20-foot Aluminum pole attached to the floating dock framing. (Ensure full field of view for new dock).
• Axis 360° 4 camera unit and mount.
• 120V feed to top of pole.
• Point to Point unit mounted to top of pole.
b. Contractor responsible for the necessary plans, submittals and permitting.
c. Part Numbers (See specification sheets provided separately)
• 360 Camera o Hanwha PNM-C32083RVQ o Mounting Accessories o SBP-250HMW o SBP-300PMW o SBP-390WMW2
• Power Supply o KBC PWB-H4-P2
• Point-Point o KBC WES4-AX-CF
d. Provide and install an aluminum safety ladder fastened to the fixed dock.
8. Dredging:
a. The project may require maintenance dredging to allow for proper use of the boat lift and maintain navigable waters. Permit plans are completed and provided as part of the bid package. Permit applications have been submitted to State and Federal agencies.
9. The contractor will be responsible for restoring the site to pre-project condition.
10. The contractor will be responsible for coordinating an approved staging area/site plan for owner approval.
11. The contractor will ensure CCSO, MPD and City plant operations are not disrupted during construction.
12. Any additional local permitting shall be the responsibility of the contractor.
13. Contractor to locate the existing utilities and disconnect them prior to construction (as required). Perform the necessary demolition and sleeves through the seawall for new utilities.
14. The cost of piles is to include wrapping per the plans.
15. Contractor to provide necessary barges/work platforms to perform the work.
MPD Dock Specification Notes
2. Floating Dock:
a. Contractor is responsible for securing vendor for the floating dock per the following specifications.
b. Floats: HDPE (High-density polyethylene) encapsulated EPS (Expanded Polystyrene) foam.
c. Frame fully welded marine grade aluminum (Base Price). Alternate pricing for PT wood with galvanized steel hardware to be provided.
d. Decking: Composite matching CCSO dock.
e. Commercial-grade double-molded dock edging to be located on the entire eastern side of the dock.
f. Cast aluminum 14” minimum length cleats. A minimum of twelve cleats must be located on the eastern side of the dock (Positioning to be selected via submittal)
g. Each pile guide is to be equipped with four rollers.
3. Boat Lifts:
a. All aluminum complete lifts driven by gear box with stainless steel motors.
b. Cradle beams to have angle on seawall side.
c. 19-degree aluminum bunk boards and bunk brackets secured with stainless-steel hardware.
d. Guideposts brackets secured with stainless-steel, weighted guide pipes and PVC guides.
e. Furnish remote control with auto-stop feature.
f. Includes (4) 12” PT timber piles per engineered plans. Piles to be wrapped as specified.
g. Contractor to provide submittals for JFC and owner review and approval.
4. Electrical Utilities:
a. Three marine utility pedestals to be located on the eastern side of the dock (Positioning to be selected via submittal). Each pedestal is to include:
• LED lights controlled via a photocell to illuminate the docking facilities center walkway.
• One 125V 30A shore power receptacle.
• One 120V 20A GFCI general use receptacle.
• Breaker(s) as needed.
• One hose bib (See 5. Plumbing)
b. One marine light bollard (Positioning to be selected via submittal). Bollard is to include:
• LED lights controlled via a photocell to illuminate the docking facilities center walkway.
c. Contractor scope includes supply and installation of all wiring, conduits, necessary penetrations and pipes/hoses from the lifts, utility pedestals and light bollard to the service tie-in point.
d. The contractor will be responsible for the electrical design including a signed and sealed plan set and submittals for owner review and approval.
e. The contractor is responsible for all required permitting and AHJ approval prior to construction.
f. Contractor to coordinate all utilities with floating dock manufacturer to ensure adequate chases are installed.
g. The cost is to include all the work needed to tie into the City plant electrical service at a location to be determined by the Contractor.
5. Plumbing Utilities:
a. Includes potable water supply to the utility pedestals hose bibs.
b. The contractor will be responsible for the plumbing design including a signed and sealed plan set and submittals for owner review and approval.
c. The contractor is responsible for all required permitting and AHJ approval prior to construction.
d. Contractor to coordinate all utilities with floating dock manufacturer to ensure adequate chases are installed.
e. The cost is to include all the work needed to tie into the City plant potable water service at a location to be determined by the Contractor.
6. Fire Protection
a. Includes the required fire protection to suit the local AHJ requirements and any required connection to site utilities.
b. Contractor will be responsible for the fire protection design including a signed and sealed plan set and submittals for owner review and approval and submission to local agencies and AHJ as required for approval.
c. Contractor responsible for all required permitting and AHJ approval prior to construction.
d. Contractor to coordinate all utilities with floating dock manufacturer to ensure adequate chases are installed.
e. Below are notes from correspondence with the local fire department for reference.
i. All docks must comply with NFPA 1, Chapter 28 and NFPA 303 “Fire Protection Standard for Marinas and Boatyards”.
ii. The docks must have fire extinguishers in accordance with NFPA 1, Ch. 28, sec.
28.1.6.1
iii. If the docks are required to have a fire standpipe system, it shall be installed in accordance with Ch. 28.1.6.3.1. of NFPA 1.
iv. The standpipe system for firefighting purposes on docks shall be permitted separately. Though a separate permit is required the dock plans shall recognize and note the required condition.
v. Underground or dock standpipe system shall be permitted separately as well.
8. Dredging:
a. The project may require maintenance dredging to allow for proper use of the boat lifts and maintain navigable waters. Permit plans are completed and provided as part of the bid package. Permit applications have been submitted to State and Federal agencies.
9. The contractor will be responsible for restoring the site to pre-project condition.
10. The contractor will be responsible for coordinating an approved staging area/site plan for owner approval.
11. The contractor will ensure CCSO, MPD and City plant operations are not disrupted during construction.
12. Any additional local permitting shall be the responsibility of the contractor.
13. Contractor to locate the existing utilities and disconnect them prior to construction (as required).
Perform the necessary demolition and sleeves through the seawall for new utilities.
14. The cost of piles is to include wrapping per the plans.
15. Contractor to provide necessary barges/work platforms to perform the work.