This is a Bid Schedule for ITB #25-8575 issued by Collier County, Florida, for the construction of a floating dock facility at the Collier County Sheriff's Office (CCSO) Marco Substation located at 990 N. Barfield Drive, Marco Island, Florida. The project encompasses two primary scopes: a County scope for CCSO improvements and a City scope for Marco Police Department (MPD) improvements. The County scope includes mobilization/demobilization, four 10-inch diameter timber piles, 74 square feet of fixed dock with aluminum safety ladder, one aluminum gangway, 222 square feet of aluminum-framed floating dock, three floating dock piles, a 16,000-pound boat lift with four timber piles, and utility connections (electrical, plumbing, and fire protection) to the existing service at 990 N. Barfield Drive, plus security infrastructure. The City scope includes comparable components for the MPD floating dock with 638 square feet of dock area, five timber piles, and boat lift options ranging from 10,000 to 20,000 pounds, as well as dual jet ski lift capabilities. Sealed bids are due February 23, 2026, at 3:00 p.m. local time. A non-mandatory pre-bid meeting is scheduled for January 26, 2026, at 10:00 a.m., followed immediately by an optional site visit.
The bid schedule includes ten line items for the County scope and ten alternates for the City scope, with all unit costs and total costs shown as $0.00 in this template document. The County scope includes a $14,300 Owner's Allowance designated for unforeseen conditions and Owner-directed work, which is not guaranteed to be fully expended. The City scope includes a separate $24,800 Owner's Allowance under identical terms. Dredging is offered as optional alternates for both scopes (45 cubic yards for CCSO and 118 cubic yards for MPD). Bid totals are provided for the Base Bid, Base Bid plus Alternate 1 (wood framing substitution for CCSO), Base Bid plus Alternate 2 (dredging), and combined totals. City scope totals are similarly broken down for alternates including wood framing and dredging options. Prospective bidders must register on the Collier County procurement portal at https://procurement.opengov.com/portal/collier-county-fl to access the complete solicitation documents.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Collier County Sheriff's Office (CCSO) Marco Substation Floating Dock Construction ITB #25-8575 Bid Schedule
| Item | Estimated Qty | Unit | Unit Cost | Total Cost | |
| a. Mobilization and Demobilization - County Scope | 1 | L.S | $0.00 | ||
| b. Fixed Dock Piles. 10" Diameter 2.5 CCA PT Timber Piles. Includes Pile Wraps | 4 | E.A | $0.00 | ||
| c. Fixed Dock. Include (1) Aluminum Safety Ladder for Emergency Access Fastened to Fixed Dock | 74 | S.F. | $0.00 | ||
| d. Aluminum Gangway (Refer to Specification Note 1) | 1 | E.A | $0.00 | ||
| e. Aluminum Framed CCSO Floating Dock (Refer to Specification Note 2) | 222 | S.F. | $0.00 | ||
| f. CCSO Floating Dock Piles. 10" Diameter 2.5 CCA PT Timber Piles. Includes Pile Wraps | 3 | E.A. | $0.00 | ||
| g. 16K Boat Lift w/ (4) Timber Piles Per the Plans. Includes Pile Wraps. Refer to Specification Note 3 | 1 | L.S. | $0.00 | ||
| h. Electrical Utilities CCSO dock - Includes tying in to 990 N. Barfield Drive existing service. See Specification Note 4 | 1 | L.S. | $0.00 | ||
| i. Plumbing Utilities CCSO dock - Includes tying in to 990 N. Barfield Drive existing service. See Specification Note 5 | 1 | L.S. | $0.00 | ||
| j. Fire Protection CCSO dock. See Specification Note 6 | 1 | L.S. | $0.00 | ||
| k. Security CCSO dock. See Specification Note 7 | 1 | L.S. | $0.00 | ||
| Total Base Bid | $0.00 | ||||
| ALTERNATES - COUNTY SCOPE | |||||
| Alternate 1 - CCSO Floating Dock To Be Constructed of PT Wood Framing In Lieu of Aluminum Framing | 222 | S.F. | $0.00 | ||
| Alternate 2 - Dredging associated with CCSO floating dock (See Specification Note 8) | 45 | C.Y. | $0.00 |
| Total Base Bid plus Alt 1 | $0.00 |
| Total Base Bid plus Alt 2 | $0.00 |
| Total Base Bid plus Alt 1+2 | $0.00 |
Staff will allocate $14,300 for County's Owner's Allowance - for Owners Use as Directed. This allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owner's Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.
| ALTERNATES - CITY SCOPE | |||
| Alternate 3 - Mobilization and Demobilization - City Scope | 1 | L.S | $0.00 |
| Alternate 4 - Aluminum Framed MPD Floating Dock (Refer to Specification Note 2) | 638 | S.F. | $0.00 |
| Alternate 5 - MPD Floating Dock To Be Constructed of PT Wood Framing In Lieu of Aluminum Framing | 638 | S.F. | $0.00 |
| Alternate 6 - MPD Floating Dock Piles. 10" Diameter 2.5 CCA PT Timber Piles. Includes Pile Wraps | 5 | E.A. | $0.00 |
| Alternate 7 - 20K Boat Lift w/ (4) Timber Piles Per the Plans. Includes Pile Wraps. Refer to Specification Note 3 | 1 | L.S. | $0.00 |
| Alternate 8 - 10K Boat Lift w/ (4) Timber Piles Per the Plans. Includes Pile Wraps. Refer to Specification Note 3 | 1 | L.S. | $0.00 |
| Alternate 9 - Dual Jet Ski Lift w/ (4) Timber Piles Per the Plans. Includes Pile Wraps. Refer to Specification Note 3 | 1 | L.S. | $0.00 |
| Alternate 10 - Electrical Utilities MPD dock - Includes tying in to 807 E. Elkham existing service. See Specification Note 4 | 1 | L.S. | $0.00 |
| Alternate 11 - Plumbing Utilities MPD dock - Includes tying in to 807 E. Elkham existing service. See Specification Note 5 | 1 | L.S. | $0.00 |
| Alternate 12 - Fire Protection MPD dock. See Specification Note 6 | 1 | L.S. | $0.00 |
| Alternate 13 - Dredging associated with MPD floating dock. See Specification Note 8 | 118 | C.Y. | $0.00 |
| Total City Scope | $0.00 | ||
| Total City Scope plus Alt 5 | $0.00 | ||
| Total City Scope plus Alt 13 | $0.00 | ||
| Total City Scope plus Alt 5+13 | $0.00 |
Staff will allocate $24,800 for City's Owner's Allowance - for Owners Use as Directed. This allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance.