Construction_Services_Agreement_2025_Template_ver_3_-_3rd_Party_Interlocal.pdf
PDF 1 MB Posted
- Solicitation number
- 25-8575
- Issued by
- Collier County, Miami City, Florida
About this file
This is a Construction Services Agreement template (2025 version 3) between the Board of County Commissioners of Collier County, Florida, and the City of Marco Island for a jointly coordinated construction project involving two separate dock facilities. The agreement governs the construction of the Collier County Sheriff's Office (CCSO) Dock and the Marco Island Police Department (MPD) Dock, with the County overseeing costs for the CCSO Dock and the City directly issuing purchase orders and processing payments for the MPD Dock. The solicitation, identified as Bid No. 25-8575, was advertised on January 8, 2026, with sealed bids due no later than February 23, 2026, at 3:00 p.m. A non-mandatory pre-bid meeting is scheduled for January 26, 2026, at 10:00 a.m., followed by a non-mandatory site visit at 990 N. Barfield Drive, Marco Island 34145. The contract encompasses all labor, materials, tools, equipment, utilities, and services necessary to complete the work in accordance with the Contract Documents, including plans and specifications prepared by the Design Professional. Contract time is specified in days from the Commencement Date, with Substantial Completion and Final Completion milestones defined throughout the agreement.
The contract amount is divided between the two owners, with specific dollar amounts to be inserted for each entity's portion, plus an allocated Owner's Allowance. The Contractor must provide Performance and Payment Bonds equal to 100% of the Contract Amount for each owner, with costs borne by the Contractor. The agreement requires 5% retainage on monthly progress payments in accordance with Florida Statute 255.078, though the County may reduce this rate at its discretion. Liquidated damages are assessed for failure to achieve Substantial Completion within the specified contract time. The project is subject to all federal, state, and local laws, including compliance with the Immigration Reform and Control Act, Florida's E-Verify requirements, prevailing wage standards where applicable, and public records retention under Florida Statute Chapter 119. The Contractor must obtain all necessary insurance coverage as detailed in Exhibit B-3, comply with safety regulations including OSHA requirements, and maintain comprehensive project records. No damages for delay are permitted; the Contractor's sole remedy is a time extension. The agreement includes provisions for changes in scope through Change Orders and Work Directives, with pricing limited to actual costs plus specified markups.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Services Agreement: [2025_ver.3]
CONSTRUCTION AGREEMENT
THE BOARD OF COUNTY COMMISSIONERS OF COLLIER COUNTY, FLORIDA, (“County”), a political subdivision of the State of Florida, and City of Marco Island,“, a municipal corporation organized under the laws of the State of Florida (the “CITY”) (collectively, “OWNER”) hereby contracts with 1-Company name ("Contractor") of 2-Company Address, a 3-Business Entity type, authorized to do business in the State of Florida, to perform all work ("Work") in connection with 4-Project Name, Invitation to Bid No. 5-Bid # ("Project"), as said Work is set forth in the Plans and Specifications prepared by 6-Engineer’s Name, the Engineer and/or Architect of Record ("Design Professional") and other Contract Documents hereafter specified.
Owner and Contractor, for the consideration herein set forth, agree as follows:
Section 1. Interlocal Agreement
This is a jointly coordinated construction project between the COUNTY and the CITY , pursuant to their Interlocal Agreement recorded on May 16, 2025 at OR 6469, PG 1804 of the Official Records for Collier County, Florida (hereafter, the “Interlocal Agreement”), which is incorporated into this Tri-Party Construction Agreement by reference. In part, the County is overseeing and responsible for costs related to the construction of the Collier County Sheriff’s Office’s Dock (the “CCSO Dock”) and the City shall be solely responsible for directly issuing a purchase order and processing all payments directly to the Contractor for the construction of the Marco Island Police Department Dock (the “MPD Dock”) as set forth in the Interlocal Agreement.
Section 2. Contract Documents.
A. The Contract Documents consist of this Agreement, the Exhibits described in Section 6 hereof, the Legal Advertisement, the Bidding Documents and any duly executed and issued addenda, Change Orders, Work Directive Changes, Field Orders, and amendments relating thereto. All of the foregoing Contract Documents are incorporated by reference and made a part of this Agreement (all of said documents including the Agreement sometimes being referred to herein as the "Contract Documents" and sometimes as the "Agreement" and sometimes as the “Contract”). A copy of the Contract Documents shall be maintained by Contractor at the Project site at all times during the performance of the Work.
B. Owner shall furnish to the Contractor one reproducible set of the Contract Documents and the appropriate number of sets of the Construction Documents, signed and sealed by the Design Professional, as are reasonably necessary for permitting.
Section 3. Scope of Work.
Contractor agrees to furnish and pay for all management, supervision, financing, labor, materials, tools, fuel, supplies, utilities, equipment and services of every kind and type necessary to diligently, timely, and fully perform and complete in a good and workmanlike manner the Work required by the Contract Documents.
Applicable if Grant Funded.
To the extent the Project is a “public works project,” all iron or steel products used to perform the Work must be produced in the United States, which means that all manufacturing processes, from initial melting through application of coatings, occur in the United States, other than metallurgical processes to refine steel additives. Per Section 255.0993, F.S. Contractor understands that this project is funded in whole or in part by grant monies and agrees to comply with all grant requirements identified in Exhibit I.
Section 4. Contract Amount.
The Project payments to the Contractor will be made consistent with the Interlocal Agreement:
COUNTY: In consideration of the faithful performance by Contractor of the covenants in this Agreement to the full satisfaction and acceptance of County, County agrees to pay, or cause to be paid, to Contractor the following amount in accordance with the terms of this Agreement: X- Amount of Dollars Described in Words (Dollars in Numbers).
CITY: In consideration of the faithful performance by Contractor of the covenants in this Agreement to the full satisfaction and acceptance of City, City agrees to pay, or cause to be paid, to Contractor the following amount in accordance with the terms of this Agreement: X-Amount of Dollars Described in Words (Dollars in Numbers).
The amount of X-Amount of Allowance described in Words (Allowance amount in numbers) has been allocated as an Owner’s Allowance. Any allowance dollar amount that has been included in the Contractor’s Bid Schedule amount is not a guaranteed portion of the aforementioned Contract Amount but rather is only eligible for reimbursement by the Owner if and subject to whether a specific dollar amount of the allowance is expressly authorized by the Owner and formally agreed upon and memorialized by the Parties in writing (the “Owner’s Allowance”).
Any dollar portion of an Owner’s Allowance that is not authorized by the Owner and memorialized by the Parties in writing, via Change Order, shall not be eligible for reimbursement/payment by the Owner as part of a Payment Application submitted by the Contractor. The County and City shall bear responsibility for payment of any Owner’s Allowance to the Contractor depending on whether that portion of the Owner’s Allowance utilized covers an expense as to the construction of the CCSO Dock or the MPD Dock.
The total combined amount for the project (herein, “Contract Amount”) is: X-Amount in Dollars Described in Words (Dollars in Numbers), not including the above stated Owner’s Allowance.
Section 5. Bonds.
A. If applicable, the Contractor shall provide Performance and Payment Bonds, in the form prescribed in Exhibit B-1 and B-2, in the amount of 100% of the Contract Amount for each Owner (one for the CCSO Dock project (County), and one for the MPD Dock project (City)), plus any approved allowance as provided in Section 3, the costs of which are to be paid by Contractor.
The Performance and Payment Bonds shall be underwritten by a surety authorized to do business in the State of Florida and otherwise acceptable to Owner; provided, however, the surety shall meet the requirements of the Department of the Treasury Fiscal Service, “Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as Acceptable Reinsurance Companies” circular. This circular may be accessed via the web at https://fiscal.treasury.gov/surety-bonds/list-certified-companies.html. Should the Contract Amount be less than $500,000, the requirements of Section 287.0935, F.S. shall govern the rating and classification of the surety.
https://fiscal.treasury.gov/surety-bonds/list-certified-companies.html
B. If the surety for any bond furnished by Contractor is declared bankrupt, becomes insolvent, its right to do business is terminated in the State of Florida, or it ceases to meet the requirements imposed by the Contract Documents, the Contractor shall, within five (5) calendar days thereafter, substitute at its cost and expense another bond and surety, both of which shall be subject to the Owner's approval.
C. The Surety for value received agrees that no change, extension of time, alteration or addition to the terms of the Agreement, the specifications accompanying the Agreement, or to the work to be performed under the Agreement shall in any way affect its obligation on this bond, except as provided herein, and waive notice of any change, extension of time, alteration or addition to the terms of the Agreement or the work performed. The Surety agrees that modifications and changes to the terms and conditions of the Agreement that increase the total amount to be paid the Contractor shall automatically increase the obligation of the Surety on this bond and notice to the Surety is not required for such increased obligation.
Section 6. Contract Time and Liquidated Damages.
A. Time of Performance.
Time is of the essence in the performance of the Work under this Agreement. The "Commencement Date" shall be established in the written Notice to Proceed to be issued by the Project Manager, as hereinafter defined. Contractor shall commence the Work within five (5) calendar days from the Commencement Date. No Work shall be performed at the Project site prior to the Commencement Date. Any Work performed by Contractor prior to the Commencement Date shall be at the sole risk of Contractor. Contractor shall achieve Substantial Completion within X- (X-Days in Numbers) calendar days from the Commencement Date (herein "Contract Time"). The date of Substantial Completion of the Work (or designated portions thereof) is the date certified by the Design Professional when construction is sufficiently complete, in accordance with the Contract Documents, so Owner can occupy or utilize the Work (or designated portions thereof) for the use for which it is intended, as more particularly defined herein at Section 16, Defined Terms. Contractor shall achieve Final Completion within X (X-Days in numbers) calendar days after the date the Punch List is delivered to the Contractor. Final Completion shall occur when the Agreement is completed in its entirety, is accepted by the Owner as complete and is so stated by the Owner as completed. As used herein and throughout the Contract Documents, the phrase "Project Manager" refers to the Owner's duly authorized representative and shall mean the Department Administrator or Division Director, as applicable, acting directly or through duly authorized representatives.
B. Liquidated Damages in General.
Owner and Contractor recognize that, since time is of the essence for this Agreement, Owner will suffer financial loss if Contractor fails to achieve Substantial Completion within the time specified above, as said time may be adjusted as provided for herein. In such event, the total amount of Owner’s damages, will be difficult, if not impossible, to definitely ascertain and quantify. Should Contractor fail to achieve Substantial Completion within the number of calendar days established herein, Owner shall be entitled to assess, as liquidated damages, but not as a penalty, X Amount of Dollars Described in Words (Dollars in Numbers) for each calendar day thereafter until Substantial Completion is achieved. Further, in the event Substantial Completion is reached, but the Contractor fails to reach Final Completion within the required time period, Owner shall also be entitled to assess, and Contractor shall be liable for all actual damages incurred by Owner as a result of Contractor failing to timely achieve Final Completion. The Project shall be deemed to be substantially completed on the date specified by the Project Manager (or at his/her direction, the Design Professional) as memorialized in the Certificate of Substantial Completion issued pursuant to the terms hereof, and as more particularly defined herein at Section 16, Defined Terms. Contractor hereby expressly waives and relinquishes any right which it may have to seek to characterize the above noted liquidated damages as a penalty, which the parties agree represents a fair and reasonable estimate of the Owner’s actual damages at the time of contracting if Contractor fails to Substantially or Finally Complete the Work within the required time periods.
C. Computation of Time Periods.
When any period of time is referenced by days herein, it shall be computed to exclude the first day and include the last day of such period. If the last day of any such period falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such day shall be omitted from the computation, and the last day shall become the next succeeding day which is not a Saturday, Sunday, or legal holiday.
D. Determination of Number of Days of Default.
For all contracts, the Owner will count default days in calendar days.
E. Right of Collection.
The Owner has the right to apply any amounts due Contractor under this Agreement or any other agreement between Owner and Contractor, as payment on such liquidated damages due under this Agreement in Owner’s sole discretion. Notwithstanding anything herein to the contrary, Owner retains its right to liquidated damages due under this Agreement even if Contractor, at Owner’s election and in its sole discretion, is allowed to continue and to finish the Work, or any part of it, after the expiration of the Contract Time including granted time extensions.
F. Completion of Work by Owner.
In the event Contractor defaults on any of its obligations under the Agreement and Owner elects to complete the Work, in whole or in part, through another contractor or its own forces, the Contractor and its surety shall continue to be liable for the liquidated damages under the Agreement until Owner achieves Substantial and Final Completion of the Work, as more particularly defined herein at Section 16, Defined Terms. Owner will not charge liquidated damages for any delay in achieving Substantial or Final Completion as a result of any unreasonable action or delay on the part of the Owner.
G. Final Acceptance by Owner.
The Owner shall consider the Agreement complete when the Contractor has completed in its entirety all of the Work and the Owner has accepted all of the Work and notified the Contractor in writing that the Work is complete. Once the Owner has approved and accepted the Work, Contractor shall be entitled to final payment in accordance with the terms of the Contract Documents.
H. Recovery of Damages Suffered by Third Parties.
Contractor shall be liable to Owner to the extent Owner incurs damages from a third party as a result of Contractor’s failure to fulfill all of its obligations under the Contract Documents. Owner’s recovery of any delay related damages under this Agreement through the liquidated damages does not preclude Owner from recovering from Contractor any other non-delay related damages that may be owed to it arising out of or relating to this Agreement.
Section 7. Exhibits Incorporated.
Exhibits Incorporated: The following documents are expressly agreed upon, attached hereto, and made a part of this Agreement for Solicitation #11-Insert ITB # and Name.
Exhibit A-1: Contractor’s Bid Schedule Exhibit A-2: Contractor’s Bid Submittal Forms and Addendums Exhibit A-3: Contractor’s List of Key Personnel Assigned to the Project Exhibit B-1: Payment Bond Form Not Applicable Exhibit B-2: Performance Bond Form Not Applicable Exhibit B-3: Insurance Requirements Exhibit C: Release and Affidavit Form Exhibit D-1: Contractor Application for Payment Form Exhibit D-2: Schedule of Values Exhibit D-3: Stored Materials Record Exhibit E-1: Change Order Form Exhibit E-2 Work Directive Form Exhibit F-1: Certificate of Substantial Completion Form Exhibit F-2: Certificate of Final Completion Exhibit F-3: Punch List Form Exhibit G-1: Final Payment Checklist Exhibit G-2: Warranty Exhibit H: General Terms and Conditions Exhibit I-1: Supplemental Terms and Conditions Applicable Not Applicable Exhibit I-2: Affidavit Regarding Labor and Services
The following documents are expressly agreed to be incorporated by reference and made a part of this Agreement for Solicitation 12-Insert ITB # and Name. The complete contract documents, including Addendum with attachments, are available on the County’s on-line bidding system, which the parties agree comprise the final integrated agreement executed by the parties.
Sections corresponding to any checked box ( ) expressly apply to the terms of this Agreement and are available through the County’s on-line bidding.
Exhibit J: Technical Specifications Exhibit K: Permits Exhibit L: Standard Details Exhibit M: Plans and Specifications prepared by: 13-Engineer’s Name Exhibit N: Environmental Health and Safety Requirements for Construction Projects
Section 8. Notices
A. All notices required or made pursuant to this Agreement by the Contractor to Owner/County shall be deemed duly served if delivered by U.S. Mail or E-mail, addressed to the following:
Collier County Board of County Commissioners, FL c/o [Division Name]
[Address] [Address]
Attn: [Project Manager, Title] Phone: [Number]
Email: [Email]
B. All notices required or made pursuant to this Agreement by the Contractor to Owner/City shall be deemed duly served if delivered by U.S. Mail or E-mail, addressed to the following:
City of Marco Island Utilities Department
[Address] [Address]
Attn: [Project Manager, Title] Phone: [Number]
Email: [Email]
C. All notices required or made pursuant to this Agreement by Owner to Contractor shall be made in writing and shall be deemed duly served if delivered by U.S. Mail, or E-mail, addressed to the following:
[Contractor Name] [Address] [Address]
Attn: [Point of Contact, Title] Phone: [Number]
Email: [email]
D. Either party may change its above noted address by giving written notice to the other party in accordance with the requirements of this Section.
Section 9. PUBLIC ENTITY CRIMES.
9.1 By its execution of this Contract, Construction Contractor acknowledges that it has been informed by Owner of the terms of Section 287.133(2)(a), F.S. which reads as follows:
"A person or affiliate who has been placed on the convicted vendor list following a conviction for a public entity crime may not submit a bid on a contract to provide any goods or services to a public entity for the construction or repair of a public building or public work, may not submit bids on leases of real property to a public entity, may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity in excess of the threshold amount provided in s. 287.017 for CATEGORY TWO for a period of 36 months from the date of being placed on the convicted vendor list."
Section 10. Modification.
No modification or change to the Agreement shall be valid or binding upon the parties unless in writing and executed by the party or parties intended to be bound by it.
Section 11. Successors and Assigns.
Subject to other provisions hereof, the Agreement shall be binding upon and shall inure to the benefit of the successors and assigns of the parties to the Agreement.
Section 12. Governing Law.
The Agreement shall be interpreted under, and its performance governed by the laws of the State of Florida.
Section 13. No Waiver.
The failure of the Owner to enforce at any time or for any period of time any one or more of the provisions of the Agreement shall not be construed to be and shall not be a waiver of any such provision or provisions or of its right thereafter to enforce each and every such provision.
Section 14. Entire Agreement.
Each of the parties hereto agrees and represents that the Agreement comprises the full and entire agreement between the parties affecting the Work contemplated, and no other agreement or understanding of any nature concerning the same has been entered into or will be recognized, and that all negotiations, acts, work performed, or payments made prior to the execution hereof shall be deemed merged in, integrated, and superseded by the Agreement.
Section 15. Severability.
Should any provision of the Agreement be determined by a court to be unenforceable, such a determination shall not affect the validity or enforceability of any other section or part thereof.
Section 16. Change Order Authorization.
The Project Manager shall have the authority on behalf of the Owner to execute all Change Orders and Work Directive Changes to the Agreement to the extent that authority is provided for under the Owner’s Procurement Ordinance, as amended, and the terms of the Contract Documents.
Section 17. Construction.
(i) Any doubtful or ambiguous language contained in this Agreement shall not be construed against the party who physically prepared this Agreement. The rule sometimes referred to as "fortius contra proferentum" (pursuant to which ambiguities in a contractual term which appears on its face to have been inserted for the benefit of one of the parties shall be construed against the benefited party) shall not be applied to the construction of this Agreement.
(ii) Defined Terms: The following Defined Terms used in the Agreement shall be understood to be defined as expressly set forth below. Other terms referenced in the Agreement shall be understood as they may separately be defined herein or if not so defined shall be understood consistent with their natural and ordinary meaning.
(a) “Application for Payment” shall mean the form provided by the Owner that is to be used by the Contractor in requesting a progress or final payment and which is to include such supporting documentation as is required by the Contract Documents.
(b) “Construction Project” shall mean a Project, funded by Owner funds that involves the process of building, altering, repairing, improving, or demolishing any public structure or building, or other public improvements of any kind to any real property owned or under the control of the Owner, which Work is being performed under a Construction Contract.
(c) “Construction Services” shall mean all labor and materials to be provided by Contractor in connection with the construction, alteration, repair, demolition, reconstruction, or any other improvements to real property. Construction Services also means Work.
(d) “Contract” or “Contract Documents” shall refer to those documents described in Section 1, subsection A of the Agreement.
(e) “Defective” shall mean an adjective which, when modifying the Work, refers to Work that is unsatisfactory, faulty, deficient or otherwise does not conform to the Contract Documents.
(f) “Department” shall mean the Department or Division initiating and managing the Project on behalf of the Owner.
(g) “Director” shall mean the Director or Administrator of the Department or Division initiating and managing the Project on behalf of the Owner.
(h) “Final Acceptance” shall mean acceptance of the Work by the Owner as evidenced by the signature of the Project Manager or Design Professional upon the Certificate of Final Completion form, Exhibit F-2. Final Acceptance shall be deemed to have taken place only if and when such signature is affixed to such certificate. The Certificate of Final Completion shall be signed only after the Project Manager has assurance by tests, inspection, or otherwise that all of the provisions of the Contract Documents have been carried out, including completion of the Punch List form, Exhibit F-3.
(i) “Professional” or “Design Professional” shall mean the professional architectural/engineering firm designated to perform the design, Construction Engineering and Inspection (“CEI”) services, by an existing agreement, or resident in-house Owner engineering services for the Work. At times, Owner staff may perform the design for the Work in-house and shall be considered the Professional in relation to the Work or a particular portion of the Work.
(j) “Project” shall mean the total construction, of which the Work to be provided under the Contract Documents may be the whole or a part as indicated elsewhere in the Contract Documents.
(k) “Project Manager” shall mean an individual employed by the Owner and assigned to manage and administer the Project which is the subject of the Contract Documents.
(l) “Proper Invoice” shall mean an invoice that conforms with all statutory requirements and all requirements specified in the Contract Documents.
(m) “Punch List” shall mean the approved list of incomplete and/or deficient Work that shall be completed by the Owner and Contractor after Substantial Completion but before the Final Acceptance can be certified by the Project Manager. The Punch List enumerates the items required to render complete, satisfactory and acceptable all Work by the Contractor. The Punch List is developed by the Contractor, Owner and Professional (if any) in accordance with the provisions of the Contract and within the time frames required therein. The Punch List essentially includes items of a minor nature; major items must be completed before Substantial Completion and cannot be considered to be Punch List work.
(n) “Schedule of Values” shall mean a schedule showing all activities of the Work subdivided into component parts in sufficient detail to serve as the basis for measuring quantities in place and/or calculating amounts for progress payments during construction. The Schedule of Values shall be satisfactory in form and substance to the Project Manager.
(o) “Substantial Completion” shall mean the status of completion of the Work which, in the opinion of the Project Manager as evidenced by a definitive Certificate of Substantial Completion, is complete in accordance with the Contract Documents, except for minor outstanding items listed on the Punch List. Substantial Completion includes, but is not limited to, the following occurring: (1) the Work can be safely utilized for the purposes for which it was intended; (2) all regulatory agency requirements are satisfied, including occupancy permits, operating certificates and similar releases, (3) all operational testing has successfully occurred; (4) all required training has successfully occurred; (5) all close-out documents (such as as-built drawings, certifications, warranties, guaranties, test reports, test logs, operational manuals, etc.) have been provided by the Contractor and accepted by the Owner, and permit acceptance by permitting agencies, if applicable, see Exhibit F-1.
(p) “Work” shall mean the Work to be performed under this Agreement and shall consist of furnishing all tools, equipment, materials, supplies, and manufactured articles and for furnishing all transportation and services, including fuel, power, water, and essential communications, and for the performance of all labor, work, or other operations required for the fulfillment of the Agreement in strict accordance with the Specifications, schedules, Drawings, and other Contract Documents as herein defined, all of which are made a part hereof, and including such detailed sketches as may be furnished by the Professional from time to time during construction in explanation of said Contract Documents. The Work shall be complete, and all work, materials, and services not expressly shown or called for in the Contract Documents, which may be necessary for the complete and proper construction of the Work in good faith, shall be performed, furnished, and installed by the Contractor as though originally so specified or shown, at no increase in cost to the Owner.
(q) “Written Directive” shall mean a written directive and also referred to as work directive, as required by in Exhibit H, Section 10.1, in the form that appears in
Exhibit E-2 that is issued to a Contractor from Owner in instances where the parties cannot agree on price and/or costs associated with work arising from differing, unforeseen or emergency site conditions and the work in question is part of the “critical path” of the contract schedule. A written directive should ultimately be followed up with an agreed upon Change Order. A verbal Work Directive may only be issued in extraordinary emergencies when necessary to protect and promote the public interest, which shall be followed up with a written Work Directive within five (5) business days.
Section 18. Order of Precedence
In the event of any conflict between or among the terms of any of the Contract Documents, the terms of the Construction Agreement and the General Terms and Conditions shall take precedence over the terms of all other Contract Documents, except the terms of any Supplemental Conditions shall take precedence over the Construction Agreement and the General Terms and Conditions. To the extent any conflict in the terms of the Contract Documents including the Owner’s Board approved Executive Summary cannot be resolved by application of the Supplemental Conditions, if any, or the Construction Agreement and the General Terms and Conditions, the conflict shall be resolved by imposing the more strict or costly obligation under the Contract Documents upon the Contractor at Owner’s discretion.
Remainder of the page is left blank intentionally.
IN WITNESS WHEREOF, the parties have executed this Agreement on the date(s) indicated below.
CONTRACTOR:
TWO WITNESSES: 15-[Contractor Name]
FIRST WITNESS
_____________________________ By: _____________________________ Print Name
______________________________ Print Name and Title
SECOND WITNESS
______________________________ Date:
Print Name
ATTEST: OWNER:
Crystal K. Kinzel, Clerk of Courts BOARD OF COUNTY COMMISSIONERS & Comptroller OF COLLIER COUNTY FLORIDA
BY: BY:
____________________, Chairman
Date: ______ OWNER:
Approved as to Form and Legality:
______________County Attorney
Print Name
CITY OF MARCO ISLAND
BY: _____________________________
Casey Lucius, City Manager
ATTEST:
By:________________________
Joan Taylor, City Clerk
Date: ______________________
Approved as to form and legality:
By: Alan L. Gabriel, City Attorney
EXHIBIT A-1: CONTRACTOR’S BID SCHEDULE
(FOLLOWING THIS PAGE)
EXHIBIT A-2: CONTRACTOR’S BID SUBMITTAL FORMS AND ADDENDUM
(FOLLOWING THIS PAGE)
EXHIBIT A-3: CONTRACTOR’S KEY PERSONNEL ASSIGNED TO THE PROJECT
Name Personnel Category
[ ] Construction Superintendent
[ ] Project Manager
EXHIBIT B-1: PUBLIC PAYMENT BOND
(Following This Page)
EXHIBIT B – 1: PUBLIC PAYMENT BOND
Bond No. Contract No.
KNOW ALL MEN BY THESE PRESENTS: That as Principal/Contractor, located at , Telephone: (Business Address and Telephone Number), and , as Surety, located at , Telephone: (Business Address and Telephone Number) a duly organized corporation, nationally recognized surety company licensed and/or registered to engage in the surety business in the State of Florida and enter into agreements of surety with a resident or non-resident agent licensed to conduct business in the State of Florida and existing under and by virtue of the laws of the State of Florida, are held and firmly bound to Collier County Board of County Commissioners, located at 3299 Tamiami Trail East, Suite 102, Naples, FL 34112-5746, Telephone: (239) 252-8999 as Obligee in the sum of ), this includes allowance, lawful money of the United States of America, for the payment of which, well and truly be made to the Obligee. The Principal/Contractor and the Surety bind themselves and each of their heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents as follows:
WHEREAS, Principal/Contractor has entered into a contract dated as of the day of
, 20 with Obligee for (Project) with the
Obligee, to furnish at Principal/Contractor’s own cost, charges, and expense all the necessary materials, equipment, and/or labor, in strict and express accordance with the Contract, which
Contract and all exhibits, is made a part of this Bond as fully and completely as if said Contract were set forth herein, is referred to as the Contract.
NOW, THEREFORE, the conditions of this obligation are such that, the above bounded
Principal/Contractor shall promptly make payments to all persons supplying materials, equipment, services and/or labor used directly or indirectly by said Principal/Contractor or subcontractors in the prosecution of the work provided for in the Contract in accordance with Sections 255.05 or
713.23, Florida Statutes; then this obligation shall be null and void and of no further force and effect; otherwise to remain in full force and effect;
AND, the said SURETY for value received, hereby stipulates and agrees that no change involving any extension of time, or addition to the terms of the Contract or to the services to be performed, or materials to be furnished thereunder, shall effect said obligation of the SURETY on this bond, and the SURETY does hereby waive notice of any such changes, extension of time, alterations, or additions of the terms of the Contract, or to the work, or to the scope of services, or any other changes, compliance or noncompliance to the terms of the Contract as to the work or scope of services. The Surety agrees that modifications and changes to the terms and conditions of the
Agreement that increase the total amount to be paid the Contractor shall automatically increase the obligation of the Surety on this bond and notice to the Surety is not required for such increased obligation. Claimant shall give written notice to the Principal/Contractor and to the SURETY as requested by Sections 255.05 or 713.23, Florida Statutes. Any actions against the
Principal/Contractor or the SURETY shall be brought within the time specified by Section 255.05 or Section 713.23, Florida Statutes.
IN WITNESS WHEREOF, the above parties have executed this instrument this day of
, 20 , the name and corporate seal of each corporate party being hereto affixed and these presents duly signed by its undersigned representative, pursuant to authority of its governing body.
Signed, sealed and delivered in the presence of:
PRINCIPAL/CONTRACTOR:
Signature Name and Title
STATE OF _________
COUNTY OF _________
The foregoing instrument was acknowledged before me by means of ___ physical presence or ___ online notarization, this ___ day of _________ 20___ by ___________________________, as _______________________________ of _________________________________ a _____________________corporation, on behalf of the corporation. He/She is personally known to me OR has produced ___________________________________ identification and did (did not) take an oath.
My Commission Expires: ________________________________________ (Signature of Notary)
(AFFIX OFFICIAL SEAL) __________________________________
(Legibly Printed) Notary Public, State of _______________________
Commission No.: ___________________________
SURETY:
Authorized Signature ________________________________________
(Printed Name ) (Business Address)
Attest:
CORPORATE ACKNOWLEDGMENT
STATE OF
COUNTY OF
The foregoing instrument was acknowledged before me this day of , 20__ by (name of officer or agent, title of officer or agent), of _____________________________________(name of corporation acknowledging), a _______________(state or place of incorporation) corporation, on behalf of the corporation.
He/She is (personally known to me) (or has produced identification) ______________________________(type of identification) (as identification) and (did/did not) take an oath.
Signature of Person Taking
Acknowledgment
Name of Acknowledger Typed, Printed or Stamped
EXHIBIT B-2: PUBLIC PERFORMANCE BOND
EXHIBIT B – 2: PUBLIC PERFORMANCE BOND
Bond No. Contract No.
KNOW ALL MEN BY THESE PRESENTS: That as Principal/Contractor, located at , Telephone: (Business Address and Telephone Number), and , as Surety, located at , Telephone: (Business Address and Telephone Number) a duly organized corporation, nationally recognized surety company licensed and/or registered to engage in the surety business in the State of Florida and enter into agreements of surety with a resident or non-resident agent licensed to conduct business in the State of Florida and existing under and by virtue of the laws of the State of Florida, are held and firmly bound to Collier County Board of County Commissioners , located at 3299 Tamiami Trail East, Suite 102, Naples, FL 34112-5746, Telephone: (239) 252-8999 as Obligee in the sum of ($ ), lawful money of the United States of America, for the payment of which, well and truly be made to the Obligee. The Principal/Contractor and the Surety bind themselves and each of their heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents as follows: In the event of a default by the Principal/Contractor, the Surety shall assume all obligations of the Principal/Contractor under the Contract including providing the required scope of services set forth in the Contract assuming all warranties, providing all as built drawings, meeting all indemnification and insurance requirements, payment of royalties and license fees, providing for the safety of persons and property and all other obligations of the Principal/Contractor under the Contract.
WHEREAS, Principal has entered into a contract dated as of the day of , 20 with Obligee for (Project) with the Obligee, to furnish at Principal/Contractor own cost, charges, and expense all the necessary materials, equipment, and/or labor, in strict and express accordance with the Contract, which Contract and all exhibits, is made a part of this Bond as fully and completely as if said Contract were set forth herein, is referred to as the Contract.
NOW THEREFORE, THE CONDITION OF THIS BOND and obligation is such that, the above bonded Principal/Contractor shall in all respects fully, promptly, and faithfully comply with the terms and conditions of the Contract, including all exhibits, and shall indemnify and save harmless the Obligee against and from all costs, expenses, damages, including but not limited to damages for delay due to the Principal/Contractor’s default, attorney's fees, including appellate proceedings, injury, or loss of which said Obligee may be subject by reason of any wrongdoing, misconduct, want of care or skill, negligence, failure to petition within the prescribed time, delay or default, including patent infringements, on the part of said Principal/Contractor, its agents, or employees, in the execution or performance of the Contract; then this obligation shall be void;
otherwise, to remain in full force and effect for the term of the Contract, including any and all guarantee periods as specifically mentioned in the Contract;
AND, the Surety, for value received, hereby stipulates and agrees that no changes, extensions of time, alterations or additions to the terms of the Contract or other work and service to be performed hereunder, or materials to be furnished thereunder or the specifications referred to therein shall in anywise affect the Surety’s obligations under this bond, and the Surety does hereby waive notice of any such changes, extensions of time, alterations or additions to the terms of the Contract, or to the scope of services including the work, or to work or to the specifications to be provided by the Principal/Contractor or any other changes, compliance or noncompliance to the terms of the Contract as to the scope of services. The Surety shall be responsible for delay, damages or liquidated damages due to Principal/Contractor’s default and consequential damages for Surety's failure to fulfill its responsibilities as set forth herein. The Surety agrees that modifications and changes to the terms and conditions of the Agreement that increase the total amount to be paid the Contractor shall automatically increase the obligation of the Surety on this bond and notice to the Surety is not required for such increased obligation.
This instrument shall be construed in all respects as a common law bond. It is expressly understood that the time provisions and statute of limitations under Section 255.05, Florida
Statutes, shall not apply to this bond. Any suit under this bond must be instituted within five years from the date Obligee obtained actual knowledge of the cause of action.
IN WITNESS WHEREOF, the above parties have executed this instrument this _____ day of _______________, 20 ____, the name and corporate seal of each corporate party being hereto affixed and these presents duly signed by its undersigned representative, pursuant to authority of its governing body.
Signed, sealed and delivered in the presence of:
PRINCIPAL/CONTRACTOR:
Signature
Name and Title
STATE OF _________
COUNTY OF _________
The foregoing instrument was acknowledged before me by means of ___ physical presence or ___ online notarization, this ___ day of _________ 20___ by ___________________________, as _______________________________ of _________________________________ a _____________________corporation, on behalf of the corporation. He/She is personally known to me OR has produced ___________________________________ identification and did (did not) take an oath.
My Commission Expires: ________________________________________ (Signature of Notary)
(AFFIX OFFICIAL SEAL) __________________________________
(Legibly Printed)
SURETY:
Authorized Signature ________________________________________ (Printed Name ) (Business Address)
ATTEST:
CORPORATE ACKNOWLEDGMENT
STATE OF
COUNTY OF
The foregoing instrument was acknowledged before me this day of , 20__ by (name of officer or agent, title of officer or agent), of _____________________________________(name of corporation acknowledging), a _______________(state or place of incorporation) corporation, on behalf of the corporation.
He/She is (personally known to me) (or has produced identification) ______________________________(type of identification) (as identification) and (did/did not) take an oath.
Signature of Person Taking
Acknowledgment
Name of Acknowledger Typed, Printed or Stamped
EXHIBIT B-3: INSURANCE REQUIREMENTS
EXHIBIT B-3: INSURANCE REQUIREMENTS
The Contractor shall at its own expense, carry and maintain insurance coverage from responsible companies duly authorized to do business in the State of Florida as set forth herein. The Contractor shall procure and maintain property insurance upon the entire project, if required, to the full insurable value of the scope of work.
The County and the Contractor waive against each other and the County’s separate Contractors, Design Consultant, Subcontractors, agents and employees of each and all of them, all damages covered by property insurance provided herein, except such rights as they may have to the proceeds of such insurance. The Contractor and County shall, where appropriate, require similar waivers of subrogation from the County’s separate Contractors, Design Consultants and Subcontractors and shall require each of them to include similar waivers in their contracts. Collier County shall be responsible for purchasing and maintaining its own liability insurance. Certificates issued as a result of the award of this solicitation must identify “For any and all work performed on behalf of Collier County”, or the specific solicitation number/contract number and title. The General Liability Policy provided by Contractor to meet the requirements of this solicitation shall name Collier County, Florida, as an additional insured as to the operations of Contractor under this solicitation and shall contain a severability of interests provisions. The Certificate Holder shall be named as Collier County Board of County Commissioners, OR, Board of County Commissioners in Collier County, OR Collier County Government, OR Collier County. The Certificates of Insurance must state the Contract Number, or Project Number, or specific Project description, or must read: For any and all work performed on behalf of Collier County.
The amounts and types of insurance coverage shall conform to the minimum requirements set forth herein with the use of Insurance Services Office (ISO) forms and endorsements or their equivalents. If Contractor has any self-insured retentions or deductibles under any of the below listed minimum required coverage, Contractor must identify on the Certificate of Insurance the nature and amount of such self- insured retentions or deductibles and provide satisfactory evidence of financial responsibility for such obligations. All self-insured retentions or deductibles will be Contractor’s sole responsibility. Coverage(s) shall be maintained without interruption from the date of commencement of the Work until the date of completion and acceptance of the scope of work by the County or as specified in this solicitation, whichever is longer. The Contractor and/or its insurance carrier shall provide thirty (30) days written notice to the County of policy cancellation or non-renewal on the part of the insurance carrier or the Contractor. The Contractor shall also notify the County, in a like manner, within twenty-four (24) hours after receipt, of any notices of expiration, cancellation, non-renewal or material change in coverage or limits received by Contractor from its insurer and nothing contained herein shall relieve Contractor of this requirement to provide notice. In the event of a reduction in the aggregate limit of any policy to be provided by Contractor hereunder, Contractor shall immediately take steps to have the aggregate limit reinstated to the full extent permitted under such policy.
Should at any time the Contractor not maintain the insurance coverage(s) required herein, the County may terminate the Agreement or at its sole discretion shall be authorized to purchase such coverage(s) and charge the Contractor for such coverage(s) purchased. If Contractor fails to reimburse the County for such costs within thirty (30) days after demand, the County has the right to offset these costs from any amount due Contractor under this Agreement or any other agreement between the County and Contractor. The County shall be under no obligation to purchase such insurance, nor shall it be responsible for the coverage(s) purchased or the insurance company or companies used. The decision of the County to purchase such insurance coverage(s) shall in no way be construed to be a waiver of any of its rights under the Contract Documents. If the initial or any subsequently issued Certificate of Insurance expires prior to the completion of the scope of work, the Contractor shall furnish to the County renewal or replacement Certificate(s) of Insurance not later than ten (10) calendar days after the expiration date on the certificate. Failure of the Contractor to provide the County with such renewal certificate(s) shall be considered justification for the County to terminate any and all contracts.
[2024_ver.1]
INSURANCE AND BONDING REQUIREMENTS
Insurance / Bond Type Required Limits
1. Worker’s Compensation Statutory Limits of Florida Statutes, Chapter 440 and all Federal Government
Statutory Limits and Requirements
Evidence of Workers’ Compensation coverage or a Certificate of Exemption issued by the State of Florida is required. Entities that are formed as Sole Proprietorships shall not be required to provide a proof of exemption. An application for exemption can be obtained online at https://apps.fldfs.com/bocexempt/
2. Employer’s Liability $___________ single limit per occurrence
3. Commercial General Liability (Occurrence Form) patterned after the current ISO form
Bodily Injury and Property Damage
$_______________single limit per occurrence, $2,000,000 aggregate for Bodily Injury Liability and Property Damage Liability. The General Aggregate Limit shall be endorsed to apply per project. This shall include Premises and Operations; Independent Contractors; Products and Completed Operations and Contractual Liability.
4. Indemnification To the maximum extent permitted by Florida law, the Contractor/Vendor shall defend, indemnify and hold harmless Collier County, its officers and employees from any and all liabilities, damages, losses and costs, including, but not limited to, reasonable attorneys’ fees and paralegals’ fees, to the extent caused by the negligence, recklessness, or intentionally wrongful conduct of the Contractor/ Vendor or anyone employed or utilized by the Contractor/Vendor in the performance of this Agreement.
5. Automobile Liability $_________ Each Occurrence; Bodily Injury & Property Damage, Owned/Non-owned/Hired; Automobile Included
6. Other insurance as noted: Watercraft $ __________ Per Occurrence
United States Longshoreman's and Harborworker's Act coverage shall be maintained where applicable to the completion of the work.
$ __________ Per Occurrence
Maritime Coverage (Jones Act) shall be maintained where applicable to the completion of the work.
$ __________ Per Occurrence
Aircraft Liability coverage shall be carried in limits of not less than $5,000,000 each occurrence if applicable to the completion of the Services under this Agreement.
$ __________ Per Occurrence
Pollution $ __________ Per Occurrence
Professional Liability $ ___________ Per claim & in the aggregate
Project Professional Liability $__________ Per Occurrence
Valuable Papers Insurance $__________ Per Occurrence
Cyber Liability $__________ Per Occurrence
Technology Errors & Omissions $__________ Per Occurrence
7. Bid bond Shall be submitted with proposal response in the form of certified funds, cashiers’ check or an irrevocable letter of credit, a cash bond posted with the County Clerk, or proposal bond in a sum equal to 5% of the cost proposal. All checks shall be made payable to the Collier County Board of County Commissioners on a bank or trust company located in the State of Florida and insured by the Federal Deposit Insurance Corporation.
https://apps.fldfs.com/bocexempt/
8. Performance and Payment Bonds
For projects in excess of $200,000, bonds shall be submitted with the executed contract by Proposers receiving award, and written for 100% of the Contract award amount, the cost borne by the Proposer receiving an award. The Performance and Payment Bonds shall be underwritten by a surety authorized to do business in the State of Florida and otherwise acceptable to Owner; provided, however, the surety shall be rated as “A-“ or better as to general policy holders rating and Class V or higher rating as to financial size category and the amount required shall not exceed 5% of the reported policy holders’ surplus, all as reported in the most current Best Key Rating Guide, published by A.M.
Best Company, Inc. of 75 Fulton Street, New York, New York 10038.
9. Vendor shall ensure that all subcontractors comply with the same insurance requirements that he is required to meet. The same Vendor shall provide County with certificates of insurance meeting the required insurance provisions.
10. Collier County must be named as "ADDITIONAL INSURED" on the Insurance Certificate for Commercial General Liability where required. This insurance shall be primary and non-contributory with respect to any other insurance maintained by, or available for the benefit of, the Additional Insured and the Vendor’s policy shall be endorsed accordingly.
11. The Certificate Holder shall be named as Collier County Board of…
This is the start of the file's text. The full file is on GovTribe.