24.- Exhibit M14_ Underground Fuel Storage Tank Inspection Requirements .pdf

PDF 30 KB Posted

Attached to
Laredo Texas Full Maintenance; Operations and Maintenance; Custodial, Grounds, and Related Services
Solicitation number
47PH0225R0006
Issued by

About this file

This document is a UST (Underground Storage Tank) Regulatory Inspection Requirements chart detailing mandatory inspection and maintenance activities. The chart specifies various regulatory requirements, their inspection frequencies, and responsible parties, primarily categorized into monthly, annually, and three-year intervals. Key requirements include monthly tasks like manual tank gauging, interstitial monitoring sensor status checks, release detection equipment walkthrough inspections, and spill bucket inspections, which are primarily performed by Operations & Maintenance (O&M) personnel.

Longer-interval requirements include three-year inspections for corrosion protection, piping tightness testing, overfill protection, and sump tightness testing, which are typically conducted by a UST Contractor. Additionally, the chart indicates some annual requirements such as registration/delivery certificate verification by GSA, handheld release detection equipment inspection, and release detection equipment testing. Other notable requirements include maintaining records of debris/water removal within 96 hours and conducting operator training every three years. The document serves as a comprehensive guide for maintaining regulatory compliance and ensuring the proper monitoring and maintenance of underground storage tank systems.

View the file

Other files

File Type Posted
47PH0225R0006 Amendment 0003 Attendees to the Pre-Proposal Walk Thru Laredo Texas Full Maintenance 2 of 12.pdf PDF
47PH0225R0006 Amendment 0003 PDF Form SF1449-21 Solicitation for Commercial Products 3 of 12.pdf PDF
47PH0225R0006 Amendment 0003 Excel Doc Figure L-1 Combined Management Plan 7 of 12.xlsx XLSX spreadsheet
47PH0225R0006 Amendment 0003 SF30 0 OF 12.pdf PDF
47PH0225R0006 Amendment 0003 Specification Laredo Texas Full Maintenance Operations and Maintenance1 of 12.pdf PDF
47PH0225R0006 Amendment 0003 BL-1 Fire Extinguisher Report 9 of 12.xlsx XLSX spreadsheet
47PH0225R0006 Amendment 0003 - Notes by Gemini Pre-Proposal Meeting Laredo - 10 of 12.pdf PDF
47PH0225R0006 Amendment 0002 SF30 PDF Form 12 of 12.pdf PDF
47PH0225R0006 Attachment 2_ Wage Determination Laredo Texas 3 of 7.pdf PDF
1.- Exhibit C1- Custodial R7 Recycling & Solid Waste Trash Report - APR24.pdf PDF
2.- Exhibit C-2 M1-FM Quality Assurance Surveillance Plan (1).pdf PDF
12.- Exhibit M2 - Green Purchasing Report (1) (1).pdf PDF
17.- Exhibit M7 - Electrical Testing Technicians Requisites.pdf PDF
20.- Exhibit M10 Final Refrigerant Management SOP 2022.pdf PDF
47PH0225R0006 Amendment 0001 SF30 1 of 4.pdf PDF
4.- Exhibit C4 - Solid Waste Audit Reports (1).pdf PDF
5. Exhibit C5 - Building Information Sheet - Columbia Land Port Of Entry (1).pdf PDF
6. Exhibit C5 - Building Information Sheet - Covent Land Port Of Entry (1).pdf PDF
11.- Exhibit M1 - O_M QASP Template (2).pdf PDF
18.- Exhibit M8_ Miscellaneous Best Practices Shave Energy.pdf PDF
5. Exhibit C5 - Building Information Sheet - Columbia Land Port Of Entry.pdf PDF
9. Exhibit C5 - Building Information Sheet - Border Patrol Sector Headquarters.pdf PDF
10. Exhibit C5 - Building Information Sheet - George P. Kazen Federal Courthouse.pdf PDF
14.- Exhibit M4 Building Operating Plan Template.pdf PDF
21.- Exhibit M11_ Flag Policy.pdf PDF
22.- Exhibit M12_ Flushing Stagnant Plumbing.pdf PDF
23.- Exhibit M13 Sample Fuel Storage Tank Management Plan.pdf PDF
29.- BL2 Inventory to Include Fire Alarm Devices - List of Assets.pdf PDF
36.- Figure B-3 FM 5 Year Contract 10.30.24 .xlsx XLSX spreadsheet
38.- Figure L-2 Past Performance Reference Questionnaire.pdf PDF
3.- Exhibit C3 - Pest Control Work and Inspection Report.pdf PDF
7. Exhibit C5 - Building Information Sheet - Juarez Lincoln Land Port of Entry.pdf PDF
11.- Exhibit M1 - O_M QASP Template (1).pdf PDF
19.- Exhibit M9 2022 GSA PBS PM Guide (1).pdf PDF
28.- BL1_ Extinguisher Report - List of Assets.pdf PDF
32.- BL6 Work Order History - List of Work Orders.pdf PDF
33.- BL7 Energy_&_Water_Monthly_Report_template.docx.pdf PDF
37.- Figure L-1 Combined Management Plan 7.18.24.xlsx XLSX spreadsheet
1.- Exhibit C1- Custodial R7 Recycling & Solid Waste Trash Report - APR24.pdf PDF
4.- Exhibit C4 - Solid Waste Audit Reports.pdf PDF
6. Exhibit C5 - Building Information Sheet - Covent Land Port Of Entry.pdf PDF
13.- Exhibit M3_ Environmentally Sustainable Products and GSA Attribute Preferences.pdf PDF
15.- Exhibit M5 - Smart Buildings.pdf PDF
16.- Exhibit M6 - Water Treatment.pdf PDF
17.- Exhibit M7 - Qualification of Electrical Testing Technicians.pdf PDF
18.- Exhibit M8_ Miscellaneous Best Practices Shave Energy (1).pdf PDF
26.- Exhibit M16_ Equipment Condition Critical Assessment Report.pdf PDF
27.- Exhibit M17_ AHU MERV.pdf PDF
30.- BL4 Elevator Information - List of Assets.pdf PDF
35.- FIGURE B-2 FM Union and Non Union Contracts REVISED 6.5.25.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UST Regulatory Inspection Requirements Regulatory Requirement Frequency Date Due Performed by

Registration/Delive ry Certificate

Annually GSA

Corrosion Protection 3 year inspection

UST

Contractor

Manual Tank Gauge (stick)

Monthly O&M

Interstitial Monitoring Sensor Status

Monthly O&M

Release Detection Equipment walkthrough Inspection

Monthly O&M

Inspect handheld release detection equipment (stick) walkthrough

Annually O&M

Test Release Detection Equipment for Proper Operation

Annually UST Contractor

Piping Tightness Testing

3 years UST Contractor

Spill bucket inspection Monthly O&M

Spill Bucket & 3 years UST

Sump Tightness Testing

Contractor

Annual Walkthrough log for all containment sumps

Annually &M

Records showing removal of debris/water removed

96 hours O&M

Overfill Protection Inspection

3 years UST Contractor

Operator Training 3 years O&M