About this file

This pre-bid conference presentation document was prepared by Trinity County, California, for the Asset Protection Pumps & Vaults project scheduled for January 6, 2026, with an updated conference date of February 19, 2026. The project encompasses a comprehensive flood mitigation initiative protecting multiple county properties across Union Avenue, Clay Street, Delaware Street, and Texas Street locations. The landscaping scope represents one component of a multi-prime procurement that includes fencing and gates, painting and coating, electrical work, miscellaneous metals, earthwork and paving, concrete, and site utilities. The broader Asset Protection Project incorporates storm walls, berms, raised access points, and passive storm gates designed to protect county assets from seasonal stormwater flooding. The mandatory pre-bid conference is scheduled for February 19, 2026, with sealed bids due March 9, 2026, at 2:00 p.m. via the Solano County OpenGov E-Procurement Portal. Contractors must achieve substantial completion within 231 calendar days from the Notice to Proceed, with final completion required within 30 days thereafter.

All contractors and subcontractors must be registered with the California Department of Industrial Relations and maintain current contractor licenses at bid submission. The project is federally funded through OES/FEMA, requiring compliance with Davis-Bacon Act prevailing wage requirements and federal procurement standards under Title 2 CFR 200.318-200.326. Bidders must submit a 10 percent bid bond or certified check with their proposal and furnish performance and payment bonds equal to 100 percent of the contract amount upon award, plus a one-year warranty bond for 10 percent of the final contract price. A 5 percent retainage will be held from progress payments, made monthly at 95 percent of approved work in place, until 35 days after the Notice of Completion. Liquidated damages of $2,000 per calendar day apply for delays beyond the contract completion date. The contract does not become effective until all certificates of insurance, business and professional licenses, and applicable certifications are on file with the County.

View the file

Other files

File Type Posted
20260304_Asset_Protection_Project_Schedule.pdf PDF
20260311_WRA_Redlined_Volume_1_Drawings.pdf PDF
20260313_WRA_Redlined_Volume_2_Drawings.pdf PDF
20260317_Asset_Protection_Project_-_Landscaping_-_Addendum_5.pdf PDF
20260303_Revised_Section_09_90_00_Painting_and_Coating.pdf PDF
20260223_Temporary_Sewer_Bypass_Drawing_Sheet_SS1.pdf PDF
20260223_Sanitary_Sewer_Bypass_Specification.pdf PDF
20260223_Revised_Volume_1_Asset_Protection_IFC_Drawing_Set_-_Select_Drawings.pdf PDF
20260223_Revised_Section_31_23_16_Structure_Excavation_and_Backfill.pdf PDF
20260223_Revised_Section_31_00_00_Embankment_Construction.pdf PDF
20260223_Offsite_Sanitary_Sewer_Improvements_Drawings_100%_Submittal.pdf PDF
20260223_Offsite_Sanitary_Sewer_Improvements_Civil_Specifications_100%_Set.pdf PDF
20260219_Asset_Protection_Pre-Bid_Conference_Slides.pdf PDF
20260219_Asset_Protection_Pre-Bid_Conference_Sign-In_Sheet.pdf PDF
PO_TERMS_CONDITIONS.pdf PDF
Exhibit_C_-_General_Terms_6_12_18.pdf PDF
20251208_Volume_1_Asset_Protection_IFC_Drawing_Set_Building_Div_Approved.pdf PDF
20251211_Volume_2_Parking_and_Security_Improvements_IFC_Rev_1_Drawing_Set_Building_Div_Approved.pdf PDF
20260210_Asset_Protection_Landscaping_-_Project_Manual.pdf PDF
Hazard_Mitigation_Assistance_Contracting_Guidance_for_FEMA-Eligible_Projects,_Non-State_Subrecipients.pdf PDF
20260119_Asset_Protection_Project_Schedule.pdf PDF
Access_Requirements.pdf PDF
20210903_Geotech_Report_CE&G.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ASSET PROTECTION

PUMPS & VAULTS

JANUARY 6, 2026

KCONNER

Text Box

FEBRUARY 19, 2026

JGonzal4 Text Box *This is not a contract document. For reference only

KCONNER

Text Box

FEBRUARY 19, 2026

AGENDA

• Asset Protection Project Background

• Pump Station Scope

• Schedule

• Access Requirements

• Bidding Instructions

• Addendum 1

• Questions

JGonzal4 Text Box *This is not a contract document. For reference only

KCONNER

Text Box

KCONNER

Text Box

• Asset Protection Project Background

• Scope Review

• Schedule

• Access Requirements

• Bidding Instructions

• Questions

JGonzal4 Text Box *This is not a contract document. For reference only

Storm Walls

Berms

Raised Access Points

Passive Storm Gates

JGonzal4

PUMPS & VAULTS

JANUARY 6, 2026

JGonzal4 Text Box *This is not a contract document. For reference only

KCONNER

Text Box

SCOPES INCLUDES

1. Fencing and Gates

2. Painting and Coating

3. Electrical

4. Miscellaneous Metals

5. Earthwork and Paving

6. Landscaping

7. Concrete

8. Site Utilities