This is Addendum 5 to the landscaping component of the Asset Protection Project issued by the Solano County Department of General Services, Capital Projects Management Division. The addendum modifies the original bid documents dated February 10, 2026, for landscaping work at the Asset Protection Project located at 550/600 Union Avenue, Fairfield, California 94533. The project scope includes planting, irrigation systems, sod lawn installation, and demolition of existing irrigation systems designed to protect county properties from seasonal stormwater flooding. The addendum revises the project completion timeline to 314 calendar days from the Notice to Proceed and extends the bid submission deadline to 2:00 PM local time on March 20, 2026, via the Solano County OpenGov E-Procurement Portal. A mandatory pre-bid conference was previously held on February 19, 2026. Bidders are required to acknowledge receipt of all five addenda issued for this procurement on either the Bid Form or through OpenGov to be considered responsive.
The addendum incorporates revised landscape drawings by WRA Environmental Consultants with redlined revisions marked up on March 11, 2026 (Volume 1) and March 13, 2026 (Volume 2), establishes a revised Project Schedule dated March 4, 2026, and removes the planting window restriction of October 15th through December 31st from the specifications. Liquidated damages are assessed at $2,000 per calendar day for delays beyond the 314-calendar-day contract completion period. Bidders must submit a 10 percent bid bond or certified check with their proposal, and upon award, furnish performance and payment bonds equal to 100 percent of the contract amount plus a one-year warranty bond for 10 percent of the final contract price. All contractors and subcontractors must be registered with the California Department of Industrial Relations, maintain current California contractor's licenses, and comply with Davis-Bacon Act prevailing wage requirements, as the project is federally funded through OES/FEMA.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
March 17, 2026
Asset Protection Project – Landscaping
Addendum 5 Page 1
DEPARTMENT OF GENERAL SERVICES
Capital Projects Management Division
MARK A. HUMMEL, AIA
Capital Projects Manager MAHummel@SolanoCounty.gov
(707) 784-7908
675 Texas Street, Suite 2500 Fairfield, CA 94533-6342 707-784-7900 www.solanocounty.gov
ANTHONY L. TAVE, P.E.
Director General Services ALTave@SolanoCounty.gov
(707) 784-7902
DUSTIN D. LENO, MBA, A.A.E.
Assistant Director DDLeno@SolanoCounty.gov
(707) 784-2781
DATE: March 17, 2026
TO: All Interested Bidders
SUBJECT: Addendum 5
Additional Documents to be Included in Contract Documents for:
located at 550/600 Union Avenue, Fairfield, CA 94533
This ADDENDUM shall be considered part of the bid documents for the above-mentioned project as though it had been issued at the same time and shall be incorporated integrally therewith. Where provisions of the following supplementary data differ from those of the original bid documents, this ADDENDUM shall govern and take precedence.
Bidders are notified that they shall make any necessary adjustment(s) in their estimates on account of this ADDENDUM.
It will be construed that each bidder’s proposal is submitted with full knowledge of all modifications and supplemental data specified herein.
The clarifications and/or additions and/or deletions that are described in this ADDENDUM shall be included in the
Specifications and/or Drawings.
This ADDENDUM supersedes the original PROJECT MANUAL dated February 10, 2026, where it contradicts them; all other conditions remain unchanged.
The bid date has changed; bids are now due by 2:00 PM local time, March 20, 2026, via OpenGov.
Acknowledgment of receipt of this ADDENDUM is required on the Bid Form. The Acknowledgment Form is included in
SECTION 00 41 00 – BID FORM, which is included in the PROJECT MANUAL dated February 10, 2026.
ADDENDUM NO. 5
Addendum No. 5 is being issued to the Contract Bid Documents for the above-referenced project.
I. The PROJECT MANUAL dated February 10, 2026, is amended as follows:
A. In SECTION 01 11 00 - NOTICE TO BIDDERS, paragraph III is revised to read:
Sealed bid will be accepted until 2:00 p.m., local time, March 20, 2026, via OpenGov.
B. In SECTION 00 41 00 - BID FORM, paragraph H is revised to read:
LUMP SUM BASE BID for work included in this Contract necessary to complete the Asset
Protection Project located at 550/600 Union Avenue, Fairfield, California 94533 as shown in the drawings and specifications. Contractor shall Substantially Complete the Project within 314 calendar days from the Notice to Proceed. The undersigned is aware the Agreement includes provisions for Liquidated Damages as specified in Section 00 73 00 of the Bidding and Contract
Requirements if the Project is not completed within the agreed time of completion.
Addendum 5 Page 2
C. In SECTION 00 52 00 - AGREEMENT BETWEEN OWNER AND CONTRACTOR, the second paragraph of Article 3, “TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION,” is revised to read:
The Contractor agrees that the Work will be substantially completed in 314 calendar days from the
Notice to Proceed. The Contractor agrees that the County will suffer economic damages, which may be difficult to quantify, in the event that the Work is not completed within this time period and therefore, Contractor agrees to pay the County liquidated damages in the amount outlined in
Document 00 73 00/ Supplementary Conditions, Article 1.4, Liquidated Damages for each and every calendar day of delay beyond the 314 calendar days provided above.
D. In SECTION 00 73 00 - SUPPLEMENTARY CONDITIONS, under paragraph 1.3, “ARTICLE 8
– TIME,” the definition of “CONTRACT TIME” is revised to read:
8.1.5 CONTRACT TIME: The Contractor shall substantially complete the Work of the Contract within 314 CALENDAR DAYS from the NOTICE TO PROCEED.
E. In SECTION 01 11 00 - SUMMARY OF WORK, under paragraph 1.04 “SPECIFICATIONS,” new paragraph D is inserted and reads as follows:
D. The documents released for bid also include the Project Schedule dated March 4, 2026.
F. In SECTION 01 11 00 - SUMMARY OF WORK, under paragraph 1.05 “DRAWINGS,” new paragraph D is inserted and reads as follows:
D. For additional clarification: notwithstanding paragraph 1.05.B, the documents released for bid also include landscape drawings by WRA Environmental Consultants with redlined revisions for Volume 1 marked up on March 11, 2026 and Volume 2 marked up on March
13, 2026:
1. Volume 1, Sheet L-201, “LANDSCAPE PLAN - NORTHEAST ENTRY.”
2. Volume 1, Sheet L-204, “PLANTING LEGEND, DETAILS AND NOTES.”
3. Volume 1, Sheet L-205, “LANDSCAPE DETAILS.”
4. Volume 1, Sheet L-301, “IRRIGATION PLAN - NORTHEAST ENTRY.”
5. Volume 1, Sheet L-304, “IRRIGATION NOTES AND LEGEND.”
6. Volume 1, Sheet L-305, “IRRIGATION DETAILS.”
7. Volume 1, Sheet L-307, “IRRIGATION DETAILS.”
8. Volume 1, Sheet L-308, “WATER USE CALCULATIONS.”
9. Volume 2, Sheet L-201, “LANDSCAPE PLAN - NORTHEAST CORNER.”
10. Volume 2, Sheet L-202, “LANDSCAPE PLAN- NORTHEAST ENTRY.”
11. Volume 2, Sheet L-203, “LANDSCAPE DETAILS, TYPICAL LAYOUTS, AND
NOTES.”
Addendum 5 Page 3
12. Volume 2, Sheet L-302, “IRRIGATION NOTES AND LEGEND.”
13. Volume 2, Sheet L-303, “IRRIGATION DETAILS.”
G. In SECTION 32 90 00 - PLANTING, paragraph 3.1.B “Planting Window,” the sentence “Trees and shrubs shall be planted between October 15th and December 31st or as approved by the
Landscape Architect” is deleted.
II. The OpenGov portal for this project is revised as follows:
A. The following documents are added:
1. This ADDENDUM 5 dated March 17, 2026.
2. Revised Project Schedule dated March 4, 2026.
3. Landscape drawings by WRA Environmental Consultants with redlined revisions for
Volume 1 marked up on March 11, 2026.
4. Landscape drawings by WRA Environmental Consultants with redlined revisions for
Volume 2 marked up on March 13, 2026.
III. Clarifications:
A. Since there are five (5) Addenda for this bid package, and SECTION 00 41 00 - BID FORM only has slots for acknowledgment of three (3) Addenda, the acknowledgement of Addenda 4 and 5 can be written anywhere on the BID FORM. That said, as long as all five (5) Addenda are acknowledged on either OpenGov, SECTION 00 41 00 - BID FORM, or both, the bid will be considered responsive with respect to addenda acknowledgments.
END OF ADDENDUM 5