20260304_Asset_Protection_Project_Schedule.pdf
PDF 2 MB Posted
- Attached to
- Asset Protection - Landscaping
- Solicitation number
- 911-0213-26
- Issued by
- Trinity County, California
About this file
This is a construction project schedule document for Solano County's Asset Protection Project, a comprehensive flood mitigation initiative designed to protect county properties from seasonal stormwater damage. The project encompasses multiple county facilities located at Union Avenue, Clay Street, Delaware Street, and Texas Street addresses, with work including barrier walls, berms, landscaping, hardscape, flood gates, underground utility reconfiguration, and pump systems. The schedule indicates a project duration spanning from November 12, 2025 (Notice to Proceed) through March 26, 2027 (Project Completion), with substantial completion targeted for February 12, 2027. The work is organized into 10 phased construction activities, with design activities commencing immediately, including design completion by December 11, 2025, city abandonment by February 6, 2026, and permit approval by February 27, 2026. Two separate bid packages are scheduled: demonstration packages with bid periods from March 2-17, 2026, and site utilities packages with bid periods from February 11 through March 6, 2026. Construction phases are staggered throughout 2026 and early 2027, with individual phase completions ranging from Phase 1 (August 25, 2026) through Phase 10 (February 10, 2027), incorporating utility coordination, grading, drainage installation, electrical and irrigation systems, hardscaping, landscaping, and site finalization activities.
The schedule reflects a complex, federally funded FEMA project requiring extensive procurement planning, including submittals review periods, certificate of insurance submissions, and long-lead procurement activities for specialized equipment such as pumps and vaults, with lead times extending from June through October 2026. The project involves multiple construction work phases executed concurrently and sequentially, with critical path activities including storm drain installation, utility coordination, and barrier wall construction. Closeout activities are scheduled from February 12 through March 26, 2027, including final billings, closeout documentation, and reimbursement requests, indicating adherence to federal grant administration requirements typical of FEMA-funded disaster mitigation projects.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AREA LITE
AREA LITE
NO
PARKING
RESERVED
RESERVED
NO
PARKING
RESERVED
NO
PARKING
NO
PARKING
NO
PARKING
NO
PA
RK
IN
G
NO
PARKING
NO
PARKING
NO
PARKING
NO
PARKING
B
BB
B
B
B
B
B
B
B
B
B
B
B
B
B
BB
B
B
B
B
B
B
B
B
B
B
BB
B
B
NO
PA
RK
IN
G
NO
PARKING
NO
PARKING
CR
IC
C R
IC IC
IC
IC
C R
C R
C R
CR
IC
IC
CR
C R
C R
C R
CR
IC
IC
IC
IC
CR
C R
CR
C R
C R
CR
C R
C R
CONSTRUCTION
PHASING
X:
\1
\1
4.
\T
EC
H \C
AD
\P
AR
KI
N G
L O
T
IM
PR
O
VE
M
EN
TS
\G -0
C
O N
ST
R
U C
TI
O
N P
H
AS
IN
G
.D W
G
/2
1/
:4 9:
P
M
SHEET CONTENTS
or l
00 60 120
9B-2
5 4
9A 9B-1
Activity ID Activity Name Start Finish
Solano County Asset Protection - Live FileSolano County Asset Protection - Live File 11-12-25 03-26-27
MILESTONESMILESTONES 11-12-25 03-26-27
MILE-10 NTP 11-12-25
MILE-250 Construction Start 03-02-26
LOE-100 Phase 1 Level of Effort 04-28-26 08-25-26
LOE-150 Phase 4 Level of Effort 04-28-26 08-07-26
LOE-160 Phase 6 Level of Effort 04-28-26 10-30-26
LOE-170 Phase 2 Level of Effort 04-28-26 11-25-26
LOE-180 Phase 9 Level of Effort 04-28-26 02-12-27
LOE-190 Phase 3 Level of Effort 04-28-26 11-02-26
MILE-110 Phase 6C Completion 06-27-26
MILE-140 Phase 6A Completion 07-30-26
MILE-130 Phase 4 Completion 08-07-26
MILE-190 Phase 1 Completion 08-25-26
LOE-110 Phase 7 Level of Effort 09-24-26 12-12-26
LOE-120 Phase 8 Level of Effort 09-24-26 12-16-26
LOE-140 Phase 5 Level of Effort 09-24-26 12-22-26
MILE-200 Phase 6 Completion 11-02-26
MILE-210 Phase 6B Completion 11-02-26
MILE-160 Phase 3 Completion 11-02-26
LOE-130 Phase 10 Level of Effort 11-17-26 02-10-27
MILE-220 Phase 2 Completion 11-28-26
MILE-170 Phase 7 Completion 12-14-26
MILE-100 Phase 8 Completion 12-16-26
MILE-150 Phase 5 Completion 12-22-26
MILE-180 Phase 10 Completion 02-10-27
MILE-120 Phase 9 Completion 02-12-27
MILE-240 Substantial Completion 02-12-27*
MILE-230 Project Completion 03-26-27
ASSET PROTECTION - FEMAASSET PROTECTION - FEMA 11-12-25 03-26-27
DesignDesign 11-12-25 02-27-26
DESIGN-100 Design Completion 11-12-25 12-11-25
DESIGN-110 City Abandonment 12-12-25 02-06-26
DESIGN-120 Permit Approval 02-09-26 02-27-26
AwardsAwards 11-12-25 05-04-26
AWARD-100 Draft Bid Packages 11-12-25 01-09-26
AWARD-110 County Review and Approval of Bid Packages 01-12-26 01-16-26
AWARD-120 Bid Period 01-19-26 03-10-26
AWARD-130 Unseal of Bid and NOI 03-11-26 03-19-26
AWARD-140 Bid Protest Period 03-20-26 04-02-26
AWARD-150 NTP 04-03-26 04-03-26
AWARD-160 Submittals and Review Period 04-06-26 05-01-26
AWARD-170 COI 05-04-26 05-04-26
Bid Packages 1 - Demo PackageBid Packages 1 - Demo Package 03-02-26 04-27-26
AWARD-180 Bid Period - Demo Packages 03-02-26* 03-17-26
AWARD-190 Unseal of Bid and NOI - Demo Packages 03-18-26 03-19-26
AWARD-200 Bid Protest Period - Demo Packages 03-20-26 03-29-26
AWARD-210 NTP - Demo Packages 03-30-26 03-30-26
AWARD-220 Submittals and Review Period - Demo Packages 03-31-26 04-27-26
AWARD-230 COI - Demo Packages 04-27-26 04-27-26
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027
NTP
Construction Start
Phase 1 Level of Effort
Phase 4 Level of Effort
Phase 6 Level of Effort
Phase 2 Level of Effort
Phase 9 Level of Effort
Phase 3 Level of Effort
Phase 6C Completion
Phase 6A Completion
Phase 4 Completion
Phase 1 Completion
Phase 7 Level of Effort
Phase 8 Level of Effort
Phase 5 Level of Effort
Phase 6 Completion
Phase 6B Completion
Phase 3 Completion
Phase 10 Level of Effort
Phase 2 Completion
Phase 7 Completion
Phase 8 Completion
Phase 5 Completion
Phase 10 Completion
Phase 9 Completion
Substantial Completion
Project Completion
Design Completion
City Abandonment
Permit Approval
Draft Bid Packages
County Review and Approval of Bid Packages
Bid Period
Unseal of Bid and NOI
Bid Protest Period
NTP
Submittals and Review Period
COI
Bid Period - Demo Packages
Unseal of Bid and NOI - Demo Packages
Bid Protest Period - Demo Packages
NTP - Demo Packages
Submittals and Review Period - Demo Packages
COI - Demo Packages
Data Date: 11-11-25 Print Date: 03-04-26 09:23
SOLANOC-ASSET-LF-1-1-2-1 | #
123 Complete
Milestone
Critical Milestones
Summary Milestones
Actual Work
Remaining Work
Critical Remaining Work
Remaining Level of Effort
Actual Level of Effort
Solano County Asset Protection - Live File
Full Schedule
Bid Packages 2 - Site UtilitiesBid Packages 2 - Site Utilities 02-11-26 04-21-26
AWARD-240 Bid Period - Demo Packages 02-11-26* 03-06-26
AWARD-250 Unseal of Bid and NOI - Site Utilities 03-09-26 03-13-26
AWARD-260 Bid Protest Period - Site Utilities 03-14-26 03-23-26
AWARD-270 NTP - Site Utilities 03-24-26 03-24-26
AWARD-280 Submittals and Review Period - Site Utilities 03-25-26 04-21-26
AWARD-290 COI - Site Utilities 04-21-26 04-21-26
ProcurementProcurement 11-12-25 10-06-26
PRO-100 Front End Development for Pumps and Vaults 11-12-25 02-09-26
PRO-110 Long Lead Pump Submittals and Review 04-22-26 06-03-26
PRO-140 Pump Lead Time 06-04-26 10-06-26
PRO-130 Pump Vault Lead Time 06-04-26 07-16-26
PRO-150 Pumps/Electrical/Controls Lead Time 06-04-26 10-06-26
ConstructionConstruction 04-28-26 02-12-27
Phased WorkPhased Work 04-28-26 02-12-27
Phase 1Phase 1 04-28-26 08-25-26
P1-CON-100 Call 811 and Markout Utilities 04-28-26 04-30-26
P1-CON-110 Setup Construction Fencing and Barriers 05-01-26 05-06-26
P1-CON-120 Setup Temporary Access 05-01-26 05-06-26
P1-CON-130 Setup SWPPP 05-07-26 05-12-26
P1-CON-140 Clear and Grub from 00+00 to 05+00 05-13-26 05-19-26
P1-CON-150 Cap Off Utilities and Irrigation Lines 05-20-26 05-21-26
P1-CON-160 Demo Existing Sidewalk 05-22-26 05-28-26
P1-CON-170 Excavate and Remove Storm Drain Pipes and Basin 05-29-26 06-09-26
P1-CON-180 Rough Grade From 00+00 to 01+75 06-10-26 06-15-26
P1-CON-190 Rough Grade From 01+75 to 05+52 06-16-26 06-20-26
P1-CON-200 Install New Storm Drainage Lines and Basins 06-22-26 07-02-26
P1-CON-210 Fine Grade and Build Berm 07-03-26 07-27-26
P1-CON-220 Install Irrigatiion Mains 07-28-26 08-04-26
P1-CON-230 Install Irrigation Branches 08-05-26 08-07-26
P1-CON-240 Form and Pour Mow Bands at Berm 08-05-26 08-10-26
P1-CON-250 Install Landscaping 08-11-26 08-21-26
P1-CON-260 Remove Construction Fencing and Barriers 08-22-26 08-25-26
Phase 2Phase 2 04-28-26 11-28-26
Clay StreetClay Street 04-28-26 11-28-26
P2-CON-CLAY-100 Call 811 and Markout Utilities 04-28-26 04-28-26
P2-CON-CLAY-110 Setup Construction Fencing and Barriers 04-29-26 05-02-26
P2-CON-CLAY-120 Setup Road Closure 04-29-26 04-30-26
P2-CON-CLAY-130 Setup SWPPP 05-04-26 05-05-26
P2-CON-CLAY-140 Clear and Grub 05-06-26 05-07-26
P2-CON-CLAY-150 Demo Existing Pavement and Sidewalk 05-08-26 05-19-26
P2-CON-CLAY-160 Excavate and Remove Storm Drain Pipes and Basin 05-20-26 05-26-26
P2-CON-CLAY-170 Setup Dewatering 05-20-26 05-22-26
P2-CON-CLAY-180 Rough Grade 05-27-26 06-01-26
P2-CON-CLAY-190 Install New Storm Drainage Lines and Basins 06-02-26 06-24-26
P2-CON-CLAY-200 Excavate Retaining Wall Footings and Flood Gate 06-02-26 06-09-26
P2-CON-CLAY-210 Install New Sewer Line (Add Alt) 06-02-26 06-24-26
P2-CON-CLAY-220 Install Retaining Wall Footings and Flood Gate 06-10-26 06-17-26
P2-CON-CLAY-230 Backfill Retaining Wall Footings and Form Retaining Walls 06-10-26 06-18-26
P2-CON-CLAY-240 Inspect Underground Utilities 06-25-26 06-26-26
P2-CON-CLAY-250 Backfill Storm Drain Trenches Backfill to Grade 06-27-26 07-09-26
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027
Bid Period - Demo Packages
Unseal of Bid and NOI - Site Utilities
Bid Protest Period - Site Utilities
NTP - Site Utilities
Submittals and Review Period - Site Utilities
COI - Site Utilities
Front End Development for Pumps and Vaults
Long Lead Pump Submittals and Review
Pump Lead Time
Pump Vault Lead Time
Pumps/Electrical/Controls Lead Time
Call 811 and Markout Utilities
Setup Construction Fencing and Barriers
Setup Temporary Access
Setup SWPPP
Clear and Grub from 00+00 to 05+00
Cap Off Utilities and Irrigation Lines
Demo Existing Sidewalk
Excavate and Remove Storm Drain Pipes and Basin
Rough Grade From 00+00 to 01+75
Rough Grade From 01+75 to 05+52
Install New Storm Drainage Lines and Basins
Fine Grade and Build Berm
Install Irrigatiion Mains
Install Irrigation Branches
Form and Pour Mow Bands at Berm
Install Landscaping
Remove Construction Fencing and Barriers
Call 811 and Markout Utilities
Setup Construction Fencing and Barriers
Setup Road Closure
Setup SWPPP
Clear and Grub
Demo Existing Pavement and Sidewalk
Excavate and Remove Storm Drain Pipes and Basin
Setup Dewatering
Rough Grade
Install New Storm Drainage Lines and Basins
Excavate Retaining Wall Footings and Flood Gate
Install New Sewer Line (Add Alt)
Install Retaining Wall Footings and Flood Gate
Backfill Retaining Wall Footings and Form Retaining Walls
Inspect Underground Utilities
Backfill Storm Drain Trenches Backfill to Grade
Data Date: 11-11-25 Print Date: 03-04-26 09:23
SOLANOC-ASSET-LF-1-1-2-1 | #
123 Complete
Milestone
Critical Milestones
Summary Milestones
Actual Work
Remaining Work
Critical Remaining Work
Remaining Level of Effort
Actual Level of Effort
P2-CON-CLAY-260 Trench for Electrical 07-10-26 07-15-26
P2-CON-CLAY-270 Install Underground Conduits 07-16-26 07-21-26
P2-CON-CLAY-280 Inspect Underground Electrical 07-22-26 07-23-26
P2-CON-CLAY-290 Backfill Electrical Trench 07-24-26 07-30-26
P2-CON-CLAY-300 Complete Fine Grade 07-31-26 08-13-26
P2-CON-CLAY-310 Pour Retaining Walls 07-31-26 08-01-26
P2-CON-CLAY-320 Form and Pour Curbs 08-14-26 08-27-26
P2-CON-CLAY-330 Pull Electrical 08-14-26 08-19-26
P2-CON-CLAY-340 Form and Pour Sidewalks 08-28-26 09-09-26
P2-CON-CLAY-350 Place AC Pavement 11-10-26 11-17-26
P2-CON-CLAY-360 Paint Striping 11-17-26 11-20-26
P2-CON-CLAY-370 Install Signage 11-17-26 11-23-26
P2-CON-CLAY-390 Paint and Coatings 11-17-26 11-23-26
P2-CON-CLAY-380 Remove Construction Fencing and Barriers 11-23-26 11-28-26
Texas StreetTexas Street 04-28-26 08-14-26
Storm DrainStorm Drain 04-28-26 06-25-26
P2-CON-TEXAS-100 Call 811 and Markout Utilities 04-28-26 05-01-26
P2-CON-TEXAS-110 Setup Construction Fencing and Barriers 05-02-26 05-02-26
P2-CON-TEXAS-120 Setup Temporary Access 05-02-26 05-02-26
P2-CON-TEXAS-130 Setup SWPPP 05-04-26 05-04-26
P2-CON-TEXAS-140 Clear and Grub 05-05-26 05-06-26
P2-CON-TEXAS-150 Demo Existing Pavement 05-07-26 05-09-26
P2-CON-TEXAS-160 Excavate and Remove Storm Drain Pipes and Basin 05-11-26 05-15-26
P2-CON-TEXAS-170 Setup Dewatering 05-11-26 05-11-26
P2-CON-TEXAS-180 Rough Grade 05-16-26 05-18-26
P2-CON-TEXAS-190 Install New Storm Drainage Lines and Basins 05-19-26 06-02-26
P2-CON-TEXAS-200 Backfill Storm Drain Trenches and Fine Grade 06-03-26 06-13-26
P2-CON-TEXAS-210 Complete Fine Grade 06-15-26 06-16-26
P2-CON-TEXAS-220 Place AC Pavement 06-17-26 06-18-26
P2-CON-TEXAS-230 Paint Striping 06-19-26 06-20-26
P2-CON-TEXAS-240 Install Signage 06-19-26 06-20-26
P2-CON-TEXAS-390 Paint and Coatings 06-19-26 06-23-26
P2-CON-TEXAS-250 Remove Construction Fencing and Barriers 06-24-26 06-25-26
Sewer (Add ALT)Sewer (Add ALT) 06-26-26 08-14-26
P2-CON-TEXAS-260 Setup Construction Fencing and Barriers 06-26-26 06-26-26
P2-CON-TEXAS-270 Setup Temporary Access 06-26-26 06-26-26
P2-CON-TEXAS-280 Setup SWPPP 06-27-26 06-27-26
P2-CON-TEXAS-290 Demo Existing Pavement 06-29-26 07-01-26
P2-CON-TEXAS-300 Excavate and Remove New Sewer Line (Add Alt) 07-02-26 07-08-26
P2-CON-TEXAS-310 Setup Dewatering 07-02-26 07-02-26
P2-CON-TEXAS-320 Rough Grade 07-09-26 07-10-26
P2-CON-TEXAS-330 Install New Sewer Line (Add Alt) 07-11-26 08-03-26
P2-CON-TEXAS-340 Complete Fine Grade 08-04-26 08-05-26
P2-CON-TEXAS-350 Place AC Pavement 08-06-26 08-07-26
P2-CON-TEXAS-360 Paint Striping 08-08-26 08-10-26
P2-CON-TEXAS-370 Install Signage 08-08-26 08-10-26
P2-CON-TEXAS-400 Paint and Coatings 08-08-26 08-12-26
P2-CON-TEXAS-380 Remove Construction Fencing and Barriers 08-13-26 08-14-26
Phase 3Phase 3 04-28-26 11-02-26
P3-CON-100 Call 811 and Markout Utilities 04-28-26 05-01-26
P3-CON-110 Setup Construction Fencing and Barriers 05-02-26 05-07-26
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027
Trench for Electrical
Install Underground Conduits
Inspect Underground Electrical
Backfill Electrical Trench
Complete Fine Grade
Pour Retaining Walls
Form and Pour Curbs
Pull Electrical
Form and Pour Sidewalks
Place AC Pavement
Paint Striping
Install Signage
Paint and Coatings
Remove Construction Fencing and Barriers
Call 811 and Markout Utilities
Setup Construction Fencing and Barriers
Setup Temporary Access
Setup SWPPP
Clear and Grub
Demo Existing Pavement
Excavate and Remove Storm Drain Pipes and Basin
Setup Dewatering
Rough Grade
Install New Storm Drainage Lines and Basins
Backfill Storm Drain Trenches and Fine Grade
Complete Fine Grade
Place AC Pavement
Paint Striping
Install Signage
Paint and Coatings
Remove Construction Fencing and Barriers
Setup Construction Fencing and Barriers
Setup Temporary Access
Setup SWPPP
Demo Existing Pavement
Excavate and Remove New Sewer Line (Add Alt)
Setup Dewatering
Rough Grade
Install New Sewer Line (Add Alt)
Complete Fine Grade
Place AC Pavement
Paint Striping
Install Signage
Paint and Coatings
Remove Construction Fencing and Barriers
Call 811 and Markout Utilities
Setup Construction Fencing and Barriers
Data Date: 11-11-25 Print Date: 03-04-26 09:23
SOLANOC-ASSET-LF-1-1-2-1 | #
123 Complete
Milestone
Critical Milestones
Summary Milestones
Actual Work
Remaining Work
Critical Remaining Work
Remaining Level of Effort
Actual Level of Effort
P3-CON-120 Setup Temporary Access 05-02-26 05-05-26
P3-CON-130 Setup SWPPP 05-08-26 05-09-26
P3-CON-140 Cap Off Utilities and Irrigation Lines 05-11-26 05-12-26
P3-CON-150 Demo Existing Pavement and Sidewalk 05-13-26 05-23-26
P3-CON-160 Rough Grade 05-26-26 05-30-26
P3-CON-170 Excavate and Remove Storm Drain Pipes and Basin 06-01-26 06-05-26
P3-CON-180 Install New Storm Drainage Lines and Basins 06-06-26 06-23-26
P3-CON-190 Backfill Storm Drain Trenches and to Grade 06-24-26 07-06-26
P3-CON-200 Trench for Shallow Underground Electrical 07-07-26 07-14-26
P3-CON-210 Excavate Retaining Wall Footings and Flood Gate 07-07-26 07-14-26
P3-CON-220 Install Underground Electrical Conduit 07-15-26 07-20-26
P3-CON-230 Install Retaining Wall Footings and Flood Gate 07-15-26 07-22-26
P3-CON-250 Backfill Electrical Trench to Grade 07-21-26 07-31-26
P3-CON-260 Pull Electrical Wire 07-21-26 08-03-26
P3-CON-270 Install Irrigations Mains 07-21-26 07-28-26
P3-CON-240 Backfill Retaining Wall Footings and Form Retaining Walls 07-23-26 07-31-26
P3-CON-290 Install Irrigation Branches 07-29-26 08-08-26
P3-CON-280 Complete Fine Grade 08-01-26 08-06-26
P3-CON-300 Form and Pour Curbs 08-07-26 08-18-26
P3-CON-310 Form and Pour Sidewalks 08-19-26 08-29-26
P3-CON-320 Set Fence Pole Bases and Poles 08-19-26 08-29-26
P3-CON-330 Excavate for Light Pole Bases 08-19-26 08-24-26
P3-CON-340 Set Cages and Finish Conduit 08-25-26 08-29-26
P3-CON-350 Install Fencing 08-31-26 09-09-26
P3-CON-360 Form and Pour Light Pole Bases 08-31-26 09-10-26
P3-CON-370 Set Light Poles 09-11-26 09-16-26
P3-CON-380 Place AC Pavement 09-17-26 09-23-26
P3-CON-390 Pull Wire for Security 09-24-26 09-28-26
P3-CON-400 Install Landscaping 09-29-26 10-06-26
P3-CON-410 Install Vehicle Gates and Card Readers 09-29-26 10-06-26
P3-CON-420 Paint Parking Striping 10-07-26 10-17-26
P3-CON-450 Paint and Coatings 10-07-26 10-12-26
P3-CON-430 Set Wheel Stops 10-19-26 10-29-26
P3-CON-440 Remove Construction Fencing and Barriers 10-30-26 11-02-26
Phase 4Phase 4 04-28-26 08-07-26
P4-CON-100 Call 811 and Markout Utilities 04-28-26 05-01-26
P4-CON-110 Setup Construction Fencing and Barriers 05-02-26 05-02-26
P4-CON-120 Setup Temporary Access 05-02-26 05-02-26
P4-CON-130 Setup SWPPP 05-04-26 05-04-26
P4-CON-140 Clear and Grub 05-05-26 05-06-26
P4-CON-150 Cap Off Utilities and Irrigation Lines 05-07-26 05-08-26
P4-CON-160 Demo Existing Pavement and Sidewalk 05-09-26 05-12-26
P4-CON-170 Excavate and Remove Storm Drain Pipes and Basin 05-13-26 05-15-26
P4-CON-180 Rough Grade 05-16-26 05-18-26
P4-CON-190 Install New Storm Drainage Lines and Basins 05-19-26 05-21-26
P4-CON-200 Trench for Electrical for Gate 05-19-26 05-19-26
P4-CON-210 Install Electrical Conduit for Electrical for Gate 05-20-26 05-22-26
P4-CON-220 Backfill Storm Drain Trenches and Fine Grade 05-22-26 06-03-26
P4-CON-230 Install Footing for Retaining Wall and Fencing 05-23-26 06-01-26
P4-CON-240 Trench for Electrical 06-04-26 06-05-26
P4-CON-250 Install Underground Electrical Conduit 06-06-26 06-08-26
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027
Setup Temporary Access
Setup SWPPP
Cap Off Utilities and Irrigation Lines
Demo Existing Pavement and Sidewalk
Rough Grade
Excavate and Remove Storm Drain Pipes and Basin
Install New Storm Drainage Lines and Basins
Backfill Storm Drain Trenches and to Grade
Trench for Shallow Underground Electrical
Excavate Retaining Wall Footings and Flood Gate
Install Underground Electrical Conduit
Install Retaining Wall Footings and Flood Gate
Backfill Electrical Trench to Grade
Pull Electrical Wire
Install Irrigations Mains
Backfill Retaining Wall Footings and Form Retaining Walls
Install Irrigation Branches
Complete Fine Grade
Form and Pour Curbs
Form and Pour Sidewalks
Set Fence Pole Bases and Poles
Excavate for Light Pole Bases
Set Cages and Finish Conduit
Install Fencing
Form and Pour Light Pole Bases
Set Light Poles
Place AC Pavement
Pull Wire for Security
Install Landscaping
Install Vehicle Gates and Card Readers
Paint Parking Striping
Paint and Coatings
Set Wheel Stops
Remove Construction Fencing and Barriers
Call 811 and Markout Utilities
Setup Construction Fencing and Barriers
Setup Temporary Access
Setup SWPPP
Clear and Grub
Cap Off Utilities and Irrigation Lines
Demo Existing Pavement and Sidewalk
Excavate and Remove Storm Drain Pipes and Basin
Rough Grade
Install New Storm Drainage Lines and Basins
Trench for Electrical for Gate
Install Electrical Conduit for Electrical for Gate
Backfill Storm Drain Trenches and Fine Grade
Install Footing for Retaining Wall and Fencing
Trench for Electrical
Install Underground Electrical Conduit
Data Date: 11-11-25 Print Date: 03-04-26 09:23
SOLANOC-ASSET-LF-1-1-2-1 | #
123 Complete
Milestone
Critical Milestones
Summary Milestones
Actual Work
Remaining Work
Critical Remaining Work
Remaining Level of Effort
Actual Level of Effort
P4-CON-260 Install Irrigations Mains 06-06-26 06-09-26
P4-CON-270 Backfill Electrical Trench 06-09-26 06-12-26
P4-CON-280 Complete Fine Grade 06-13-26 06-15-26
P4-CON-290 Form and Pour Perimeter Fencing Posts 06-13-26 06-18-26
P4-CON-300 Form and Pour Curbs 06-19-26 06-30-26
P4-CON-310 Set Lightpoles Bases, Light Poles and Bollards 07-01-26 07-03-26
P4-CON-320 Form and Pour Sidewalks 07-06-26 07-16-26
P4-CON-330 Place AC Pavement 07-17-26 07-18-26
P4-CON-340 Pull Electrical Wire and Security Wire 07-17-26 07-18-26
P4-CON-350 Paint Parking Striping 07-20-26 07-23-26
P4-CON-360 Install Landscaping 07-20-26 07-23-26
P4-CON-370 Pull Wire for Lights and Security 07-20-26 07-21-26
P4-CON-430 Paint and Coatings 07-20-26 07-24-26
P4-CON-380 Install Security Fencing and Gates 07-24-26 08-04-26
P4-CON-390 Install Irrigation Branches 07-25-26 07-27-26
P4-CON-400 Set Wheel Stops 07-28-26 07-31-26
P4-CON-410 Install Card Readers 08-05-26 08-06-26
P4-CON-420 Remove Construction Fencing and Barriers 08-07-26 08-07-26
Phase 5Phase 5 09-24-26 12-22-26
P5-CON-100 Call 811 and Markout Utilities 09-24-26 09-28-26
P5-CON-110 Setup Construction Fencing and Barriers 09-29-26 09-29-26
P5-CON-120 Setup Temporary Access 09-29-26 09-29-26
P5-CON-130 Setup SWPPP 09-30-26 09-30-26
P5-CON-140 Clear and Grub 10-01-26 10-02-26
P5-CON-150 Cap Off Utilities and Irrigation Lines 10-03-26 10-05-26
P5-CON-160 Demo Existing Pavement and Sidewalk 10-06-26 10-08-26
P5-CON-170 Excavate and Remove Storm Drain Pipes and Basin 10-09-26 10-14-26
P5-CON-180 Rough Grade 10-15-26 10-17-26
P5-CON-190 Install New Storm Drainage Lines and Basins 10-19-26 10-23-26
P5-CON-200 Backfill Storm Drain Trenches and Fine Grade 10-24-26 11-04-26
P5-CON-210 Trench for Electrical 11-05-26 11-10-26
P5-CON-220 Install Underground Electrical Conduit 11-12-26 11-14-26
P5-CON-230 Install Irrigations Mains 11-12-26 11-14-26
P5-CON-240 Backfill Electrical Trench 11-16-26 11-18-26
P5-CON-250 Complete Fine Grade 11-19-26 11-20-26
P5-CON-260 Form and Pour Curbs 11-21-26 12-01-26
P5-CON-270 Form and Pour Sidewalks 12-02-26 12-08-26
P5-CON-280 Place AC Pavement 12-09-26 12-10-26
P5-CON-290 Paint Parking Striping 12-11-26 12-12-26
P5-CON-300 Install Landscaping 12-11-26 12-11-26
P5-CON-310 Pull Wire and Makeup for Lights and Security 12-11-26 12-15-26
P5-CON-350 Paint and Coatings 12-11-26 12-16-26
P5-CON-320 Install Irrigation Branches 12-17-26 12-17-26
P5-CON-330 Set Wheel Stops 12-18-26 12-19-26
P5-CON-340 Remove Construction Fencing and Barriers 12-21-26 12-22-26
Phase 6Phase 6 04-28-26 10-31-26
Phase 6A North Oval and PlatformPhase 6A North Oval and Platform 04-28-26 07-30-26
P6A-CON-100 Call 811 and Markout Utilities 04-28-26 05-01-26
P6A-CON-110 Setup Construction Fencing and Barriers 05-02-26 05-07-26
P6A-CON-120 Setup Temporary Access 05-02-26 05-07-26
P6A-CON-130 Setup SWPPP 05-08-26 05-08-26
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027
Install Irrigations Mains
Backfill Electrical Trench
Complete Fine Grade
Form and Pour Perimeter Fencing Posts
Form and Pour Curbs
Set Lightpoles Bases, Light Poles and Bollards
Form and Pour Sidewalks
Place AC Pavement
Pull Electrical Wire and Security Wire
Paint Parking Striping
Install Landscaping
Pull Wire for Lights and Security
Paint and Coatings
Install Security Fencing and Gates
Install Irrigation Branches
Set Wheel Stops
Install Card Readers
Remove Construction Fencing and Barriers
Call 811 and Markout Utilities
Setup Construction Fencing and Barriers
Setup Temporary Access
Setup SWPPP
Clear and Grub
Cap Off Utilities and Irrigation Lines
Demo Existing Pavement and Sidewalk
Excavate and Remove Storm Drain Pipes and Basin
Rough Grade
Install New Storm Drainage Lines and Basins
Backfill Storm Drain Trenches and Fine Grade
Trench for Electrical
Install Underground Electrical Conduit
Install Irrigations Mains
Backfill Electrical Trench
Complete Fine Grade
Form and Pour Curbs
Form and Pour Sidewalks
Place AC Pavement
Paint Parking Striping
Install Landscaping
Pull Wire and Makeup for Lights and Security
Paint and Coatings
Install Irrigation Branches
Set Wheel Stops
Remove Construction Fencing and Barriers
Call 811 and Markout Utilities
Setup Construction Fencing and Barriers
Setup Temporary Access
Setup SWPPP
Data Date: 11-11-25 Print Date: 03-04-26 09:23
SOLANOC-ASSET-LF-1-1-2-1 | #
123 Complete
Milestone
Critical Milestones
Summary Milestones
Actual Work
Remaining Work
Critical Remaining Work
Remaining Level of Effort
Actual Level of Effort
P6A-CON-140 Clear and Grub 05-09-26 05-11-26
P6A-CON-150 Cap Off Utilities and Irrigation Lines 05-12-26 05-13-26
P6A-CON-160 Demo Existing Pavement and Sidewalk 05-14-26 05-16-26
P6A-CON-170 Rough Grade 05-18-26 05-22-26
P6A-CON-180 Trench for Electrical 05-23-26 05-26-26
P6A-CON-190 Install Underground Electrical Conduit 05-27-26 05-28-26
P6A-CON-200 Set Pull and Junction Boxes 05-29-26 06-01-26
P6A-CON-210 Backfill Electrical Trench 06-02-26 06-05-26
P6A-CON-220 Set Lightpoles Bases, Light Poles and Bollards 06-06-26 06-08-26
P6A-CON-230 Trench and Install Storm Drain Line 06-06-26 06-09-26
P6A-CON-240 Install Irrigations Mains 06-09-26 06-10-26
P6A-CON-250 Backfill Storm Drain Line 06-10-26 06-11-26
P6A-CON-260 Form and Pour Curbs 06-11-26 06-22-26
P6A-CON-270 Form and Pour Foundations for Stairs and Walls 06-12-26 06-23-26
P6A-CON-280 Form and Pour Slab 06-23-26 07-03-26
P6A-CON-290 Backfill Foundations 06-24-26 06-27-26
P6A-CON-300 Form and Pour Stairs 06-29-26 07-07-26
P6A-CON-310 Fine Grade Site 07-06-26 07-07-26
P6A-CON-320 Form and Pour Sidewalks 07-08-26 07-14-26
P6A-CON-330 Pull Wire and Makeup for Lights and Security 07-15-26 07-17-26
P6A-CON-340 Install Pre-Fab Seats 07-15-26 07-17-26
P6A-CON-350 Install Landscaping 07-18-26 07-23-26
P6A-CON-360 Install Irrigation Branches 07-24-26 07-27-26
P6A-CON-370 Remove Construction Fencing and Barriers 07-28-26 07-30-26
Phase 6B South OvalPhase 6B South Oval 07-31-26 10-31-26
P6B-CON-100 Setup Construction Fencing and Barriers 07-31-26 08-03-26
P6B-CON-110 Setup Temporary Access 08-04-26 08-08-26
P6B-CON-120 Setup SWPPP 08-10-26 08-10-26
P6B-CON-130 Clear and Grub 08-11-26 08-12-26
P6B-CON-140 Cap Off Utilities and Irrigation Lines 08-13-26 08-14-26
P6B-CON-150 Demo Existing Pavement and Sidewalk 08-15-26 08-18-26
P6B-CON-160 Rough Grade 08-19-26 08-29-26
P6B-CON-170 Trench for Electrical 08-31-26 09-02-26
P6B-CON-180 Install Underground Electrical Conduit 09-03-26 09-05-26
P6B-CON-190 Set Pull and Junction Boxes 09-08-26 09-09-26
P6B-CON-200 Backfill Electrical Trench 09-10-26 09-14-26
P6B-CON-210 Set Lightpoles Bases, Light Poles and Bollards 09-15-26 09-19-26
P6B-CON-220 Install Irrigations Mains 09-21-26 09-24-26
P6B-CON-230 Fine Grade Site 09-21-26 09-22-26
P6B-CON-240 Form and Pour Curbs 09-25-26 09-30-26
P6B-CON-250 Form and Pour Sidewalks 10-01-26 10-12-26
P6B-CON-260 Pull Electrical Wire and Security Wire 10-13-26 10-16-26
P6B-CON-270 Install Landscaping 10-17-26 10-24-26
P6B-CON-280 Install Irrigation Branches 10-26-26 10-28-26
P6B-CON-290 Remove Construction Fencing and Barriers 10-29-26 10-31-26
Phase 6C Law and Justice CenterPhase 6C Law and Justice Center 05-02-26 06-27-26
P6C-CON-100 Setup Construction Fencing and Barriers 05-02-26 05-02-26
P6C-CON-110 Setup Temporary Access 05-04-26 05-04-26
P6C-CON-120 Setup SWPPP 05-05-26 05-05-26
P6C-CON-130 Clear and Grub 05-06-26 05-07-26
P6C-CON-140 Cap Off Utilities and Irrigation Lines 05-08-26 05-09-26
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027
Clear and Grub
Cap Off Utilities and Irrigation Lines
Demo Existing Pavement and Sidewalk
Rough Grade
Trench for Electrical
Install Underground Electrical Conduit
Set Pull and Junction Boxes
Backfill Electrical Trench
Set Lightpoles Bases, Light Poles and Bollards
Trench and Install Storm Drain Line
Install Irrigations Mains
Backfill Storm Drain Line
Form and Pour Curbs
Form and Pour Foundations for Stairs and Walls
Form and Pour Slab
Backfill Foundations
Form and Pour Stairs
Fine Grade Site
Form and Pour Sidewalks
Pull Wire and Makeup for Lights and Security
Install Pre-Fab Seats
Install Landscaping
Install Irrigation Branches
Remove Construction Fencing and Barriers
Setup Construction Fencing and Barriers
Setup Temporary Access
Setup SWPPP
Clear and Grub
Cap Off Utilities and Irrigation Lines
Demo Existing Pavement and Sidewalk
Rough Grade
Trench for Electrical
Install Underground Electrical Conduit
Set Pull and Junction Boxes
Backfill Electrical Trench
Set Lightpoles Bases, Light Poles and Bollards
Install Irrigations Mains
Fine Grade Site
Form and Pour Curbs
Form and Pour Sidewalks
Pull Electrical Wire and Security Wire
Install Landscaping
Install Irrigation Branches
Remove Construction Fencing and Barriers
Setup Construction Fencing and Barriers
Setup Temporary Access
Setup SWPPP
Clear and Grub
Cap Off Utilities and Irrigation Lines
Data Date: 11-11-25 Print Date: 03-04-26 09:23
SOLANOC-ASSET-LF-1-1-2-1 | #
123 Complete
Milestone
Critical Milestones
Summary Milestones
Actual Work
Remaining Work
Critical Remaining Work
Remaining Level of Effort
Actual Level of Effort
P6C-CON-150 Demo Existing Pavement and Sidewalk 05-11-26 05-13-26
P6C-CON-160 Rough Grade 05-14-26 05-15-26
P6C-CON-170 Fine Grade Site 05-16-26 05-18-26
P6C-CON-180 Form and Pour Curbs and Wall 05-19-26 06-05-26
P6C-CON-190 Form and Pour Sidewalks 06-06-26 06-17-26
P6C-CON-200 Install Expansion Joints 06-18-26 06-20-26
P6C-CON-210 Install Landscaping 06-22-26 06-23-26
P6C-CON-220 Install Signage 06-24-26 06-24-26
P6C-CON-230 Remove Construction Fencing and Barriers 06-25-26 06-27-26
Phase 7Phase 7 09-24-26 12-12-26
P7-CON-100 Call 811 and Markout Utilities 09-24-26 09-24-26
P7-CON-110 Setup Construction Fencing and Barriers 09-25-26 09-25-26
P7-CON-120 Setup Temporary Access 09-25-26 09-25-26
P7-CON-130 Setup SWPPP 09-26-26 09-26-26
P7-CON-140 Clear and Grub 09-28-26 09-29-26
P7-CON-150 Cap Off Utilities and Irrigation Lines 09-30-26 10-01-26
P7-CON-160 Demo Existing Pavement and Sidewalk 10-02-26 10-05-26
P7-CON-170 Excavate and Remove Storm Drain Pipes and Basin 10-06-26 10-10-26
P7-CON-180 Rough Grade 10-12-26 10-13-26
P7-CON-190 Install New Storm Drainage Lines and Basins 10-14-26 10-24-26
P7-CON-200 Install Footing for Barrier Wall 10-14-26 10-24-26
P7-CON-210 Backfill Storm Drain Trenches and Fine Grade 10-26-26 10-30-26
P7-CON-230 Trench for Electrical 10-26-26 10-27-26
P7-CON-220 Form and Pour Barrier Wall 1A and 1B 10-26-26 10-31-26
P7-CON-240 Install Underground Electrical Conduit 10-31-26 11-02-26
P7-CON-250 Backfill Electrical Trench 11-03-26 11-04-26
P7-CON-280 Install Irrigations Mains 11-03-26 11-04-26
P7-CON-260 Complete Fine Grade 11-05-26 11-06-26
P7-CON-270 Form and Pour Footings for Fencing 11-05-26 11-07-26
P7-CON-290 Backfill Around Footings 11-09-26 11-09-26
P7-CON-300 Form and Pour Curbs 11-10-26 11-17-26
P7-CON-310 Set Lightpoles Bases, Light Poles and Bollards 11-18-26 11-21-26
P7-CON-320 Form and Pour Sidewalks 11-18-26 11-24-26
P7-CON-330 Pull Electrical Wire and Security Wire 11-23-26 11-25-26
P7-CON-340 Place AC Pavement 11-25-26 12-02-26
P7-CON-350 Paint Parking Striping 12-03-26 12-03-26
P7-CON-360 Install Landscaping 12-03-26 12-05-26
P7-CON-370 Pull Wire for Lights and Security 12-03-26 12-04-26
P7-CON-410 Paint and Coatings 12-03-26 12-07-26
P7-CON-380 Install Irrigation Branches 12-07-26 12-08-26
P7-CON-390 Set Wheel Stops 12-09-26 12-09-26
P7-CON-400 Remove Construction Fencing and Barriers 12-10-26 12-12-26
Phase 8Phase 8 09-24-26 12-16-26
P8-CON-100 Call 811 and Markout Utilities 09-24-26 09-24-26
P8-CON-110 Setup Construction Fencing and Barriers 09-25-26 09-25-26
P8-CON-120 Setup Temporary Access 09-25-26 09-25-26
P8-CON-130 Setup SWPPP 09-26-26 09-26-26
P8-CON-140 Clear and Grub 09-28-26 09-29-26
P8-CON-150 Demo Existing Pavement and Sidewalk 09-30-26 10-05-26
P8-CON-160 Excavate and Remove Storm Drain Pipes and Basin 10-06-26 10-10-26
P8-CON-170 Setup Dewatering 10-06-26 10-06-26
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027
Demo Existing Pavement and Sidewalk
Rough Grade
Fine Grade Site
Form and Pour Curbs and Wall
Form and Pour Sidewalks
Install Expansion Joints
Install Landscaping
Install Signage
Remove Construction Fencing and Barriers
Call 811 and Markout Utilities
Setup Construction Fencing and Barriers
Setup Temporary Access
Setup SWPPP
Clear and Grub
Cap Off Utilities and Irrigation Lines
Demo Existing Pavement and Sidewalk
Excavate and Remove Storm Drain Pipes and Basin
Rough Grade
Install New Storm Drainage Lines and Basins
Install Footing for Barrier Wall
Backfill Storm Drain Trenches and Fine Grade
Trench for Electrical
Form and Pour Barrier Wall 1A and 1B
Install Underground Electrical Conduit
Backfill Electrical Trench
Install Irrigations Mains
Complete Fine Grade
Form and Pour Footings for Fencing
Backfill Around Footings
Form and Pour Curbs
Set Lightpoles Bases, Light Poles and Bollards
Form and Pour Sidewalks
Pull Electrical Wire and Security Wire
Place AC Pavement
Paint Parking Striping
Install Landscaping
Pull Wire for Lights and Security
Paint and Coatings
Install Irrigation Branches
Set Wheel Stops
Remove Construction Fencing and Barriers
Call 811 and Markout Utilities
Setup Construction Fencing and Barriers
Setup Temporary Access
Setup SWPPP
Clear and Grub
Demo Existing Pavement and Sidewalk
Excavate and Remove Storm Drain Pipes and Basin
Setup Dewatering
Data Date: 11-11-25 Print Date: 03-04-26 09:23
SOLANOC-ASSET-LF-1-1-2-1 | #
123 Complete
Milestone
Critical Milestones
Summary Milestones
Actual Work
Remaining Work
Critical Remaining Work
Remaining Level of Effort
Actual Level of Effort
P8-CON-180 Rough Grade 10-12-26 10-15-26
P8-CON-190 Install New Storm Drainage Lines and Basins 10-16-26 10-21-26
P8-CON-200 Backfill Storm Drain Trenches and Fine Grade 10-22-26 10-27-26
P8-CON-210 Complete Fine Grade 10-28-26 10-30-26
P8-CON-220 Install Footing for Barrier Wall 10-28-26 11-07-26
P8-CON-230 Form and Pour Barrier Wall 1A and 1B 11-09-26 11-16-26
P8-CON-240 Form and Pour Curbs 11-17-26 11-25-26
P8-CON-250 Form and Pour Sidewalks 11-28-26 12-03-26
P8-CON-260 Place AC Pavement 12-04-26 12-09-26
P8-CON-270 Paint Striping 12-10-26 12-15-26
P8-CON-280 Install Signage 12-10-26 12-12-26
P8-CON-300 Paint and Coatings 12-10-26 12-15-26
P8-CON-290 Remove Construction Fencing and Barriers 12-16-26 12-16-26
Phase 9Phase 9 04-28-26 02-12-27
Phase 9APhase 9A 04-28-26 12-03-26
P9A-CON-100 Call 811 and Markout Utilities 04-28-26 05-01-26
P9A-CON-110 Safe Off 05-02-26 05-02-26
P9A-CON-120 Cap Off Utilities and Irrigation Lines 05-02-26 05-04-26
P9A-CON-130 Install Construction Site Fencing 05-04-26 05-04-26
P9A-CON-140 Setup Temporary Access 05-04-26 05-04-26
P9A-CON-150 Setup SWPPP 05-05-26 05-05-26
P9A-CON-160 Clear and Grub 05-06-26 05-06-26
P9A-CON-170 Demo Site 05-07-26 05-12-26
P9A-CON-180 Rough Grade Area 9A 05-13-26 05-21-26
P9A-CON-190 Excavate Underground Storm Drain 05-22-26 06-01-26
P9A-CON-200 Install Storm Drain Lines 06-02-26 06-02-26
P9A-CON-210 Install Underground Electrical 06-03-26 06-03-26
P9A-CON-220 Install New Pump Vault 07-17-26 07-17-26
P9A-CON-230 Install New Pump 10-06-26 10-07-26
P9A-CON-240 Connect Storm Drain Lines to New Pump 10-07-26 10-08-26
P9A-CON-250 Connect Electrical Lines to New Pump 10-08-26 10-09-26
P9A-CON-260 Connect Storm Drain Lines to New Pump 10-09-26 10-10-26
P9A-CON-270 Excavate Footing for Wall 10-10-26 10-14-26
P9A-CON-280 Fine Grade and Build Berm 10-10-26 10-20-26
P9A-CON-290 Install Footing for Wall 10-14-26 10-15-26
P9A-CON-300 Form and Pour Wall 10-15-26 10-27-26
P9A-CON-310 Install Security Fencing 10-27-26 10-28-26
P9A-CON-320 Pull Wire for Lights and Security 10-28-26 10-29-26
P9A-CON-330 Form and Pour Curbs 10-29-26 11-10-26
P9A-CON-340 Form and Pour Sidewalks 11-10-26 11-23-26
P9A-CON-350 Paint Parking Striping 11-23-26 11-24-26
P9A-CON-390 Paint and Coatings 11-23-26 11-30-26
P9A-CON-360 Install Landscaping 11-30-26 12-01-26
P9A-CON-370 Set Wheel Stops 12-01-26 12-02-26
P9A-CON-380 Remove Construction Fencing and Barriers 12-02-26 12-03-26
Phase 9BPhase 9B 04-28-26 02-12-27
P9B1-CON-100 Call 811 and Markout Utilities 04-28-26 05-01-26
P9B1-CON-110 Safe Off 05-02-26 05-02-26
P9B1-CON-120 Install Construction Site Fencing 05-04-26 05-04-26
P9B1-CON-130 Cap Off Utilities and Irrigation Lines 05-04-26 05-05-26
P9B1-CON-140 Setup Temporary Access 05-04-26 05-04-26
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027
Rough Grade
Install New Storm Drainage Lines and Basins
Backfill Storm Drain Trenches and Fine Grade
Complete Fine Grade
Install Footing for Barrier Wall
Form and Pour Barrier Wall 1A and 1B
Form and Pour Curbs
Form and Pour Sidewalks
Place AC Pavement
Paint Striping
Install Signage
Paint and Coatings
Remove Construction Fencing and Barriers
Call 811 and Markout Utilities
Safe Off
Cap Off Utilities and Irrigation Lines
Install Construction Site Fencing
Setup Temporary Access
Setup SWPPP
Clear and Grub
Demo Site
Rough Grade Area 9A
Excavate Underground Storm Drain
Install Storm Drain Lines
Install Underground Electrical
Install New Pump Vault
Install New Pump
Connect Storm Drain Lines to New Pump
Connect Electrical Lines to New Pump
Connect Storm Drain Lines to New Pump
Excavate Footing for Wall
Fine Grade and Build Berm
Install Footing for Wall
Form and Pour Wall
Install Security Fencing
Pull Wire for Lights and Security
Form and Pour Curbs
Form and Pour Sidewalks
Paint Parking Striping
Paint and Coatings
Install Landscaping
Set Wheel Stops
Remove Construction Fencing and Barriers
Call 811 and Markout Utilities
Safe Off
Install Construction Site Fencing
Cap Off Utilities and Irrigation Lines
Setup Temporary Access
Data Date: 11-11-25 Print Date: 03-04-26 09:23
SOLANOC-ASSET-LF-1-1-2-1 | #
123 Complete
Milestone
Critical Milestones
Summary Milestones
Actual Work
Remaining Work
Critical Remaining Work
Remaining Level of Effort
Actual Level of Effort
P9B1-CON-150 Setup SWPPP 05-05-26 05-05-26
P9B1-CON-160 Clear and Grub 05-06-26 05-06-26
P9B1-CON-170 Demo Site 05-07-26 05-12-26
P9B1-CON-180 Install Sanitary By-Pass 05-13-26 05-18-26
Area 9B1Area 9B1 05-19-26 11-20-26
P9B1-CON-190 Excavate and Install Shoring 05-19-26 05-30-26
P9B1-CON-200 Install Foundations 06-01-26 06-05-26
P9B1-CON-210 Install Pre-Cast Rings 07-17-26 07-22-26
P9B1-CON-220 Install SD Piping 07-23-26 07-24-26
P9B1-CON-230 Install Pumps 10-06-26 10-10-26
P9B1-CON-240 Install Electrical 10-10-26 10-16-26
P9B1-CON-250 Install Waterproofing 10-16-26 10-21-26
P9B1-CON-260 Backfill and Strip Forms 10-21-26 10-24-26
P9B1-CON-270 Connect Pumps 10-24-26 11-03-26
P9B1-CON-280 Excavate Footing for Wall 11-03-26 11-05-26
P9B1-CON-290 Install Footing for Wall 11-05-26 11-10-26
P9B1-CON-300 Form and Pour Wall 11-10-26 11-20-26
Area 9B2Area 9B2 06-01-26 02-12-27
P9B2-CON-100 Excavate and Install Shoring - Pump Vaults 06-01-26 06-11-26
P9B2-CON-110 Pour Foundations - Pump Vaults 06-12-26 06-17-26
P9B2-CON-120 Install Pre-Cast Rings - Pump Vaults 07-17-26 07-22-26
P9B2-CON-130 Install SD Piping - Pump Vaults 07-23-26 07-24-26
P9B2-CON-140 Waterproof - Pump Vaults 07-25-26 07-27-26
P9B2-CON-150 Backfill Precast Vaults and Strip Forms - Pump Vaults 07-28-26 07-30-26
P9B2-CON-160 Excavate and Install Shoring - 5 SIde Vault 07-31-26 08-05-26
P9B2-CON-170 Trench for Electrical After Backfill 07-31-26 08-03-26
P9B2-CON-180 Install Undergroud Electrical After Backfill 08-04-26 08-07-26
P9B2-CON-190 Form and Pour Foundation - 5 Side Vault 08-06-26 08-08-26
P9B2-CON-200 Install Undergroud Storm Drain After Backfill 08-08-26 08-19-26
P9B2-CON-210 Form and Pour Walls - 5 Side Vault 08-10-26 08-12-26
P9B2-CON-220 Setup Shoring for Lid - 5 Side Vault 08-13-26 08-13-26
P9B2-CON-230 Form and Pour Lid - 5 Side Vault 08-14-26 08-17-26
P9B2-CON-250 Form and Pour Equipment Pads 08-20-26 08-26-26
P9B2-CON-270 Set Electrical Equipment 08-27-26 08-28-26
P9B2-CON-280 Set Mechanical and Storm Drain Equipment 08-27-26 09-08-26
P9B2-CON-240 Install Pumps 10-06-26 10-12-26
P9B2-CON-260 Install Electrical 10-12-26 10-17-26
P9B2-CON-290 Install Waterproofing 10-17-26 10-20-26
P9B2-CON-300 Backfill- 5 Side Vault 10-20-26 10-23-26
P9B2-CON-310 Pull Wire and Terminate Electrical 10-22-26 11-03-26
P9B2-CON-320 Connect Pumps 10-24-26 11-03-26
P9B2-CON-330 Test and Energize Equipment 11-03-26 11-07-26
P9B2-CON-340 Excavate Footing for Wall (Continue from 9A-A) 11-20-26 11-25-26
P9B2-CON-350 Install Footing for Wall 11-25-26 12-05-26
P9B2-CON-360 Form and Pour Wall 12-05-26 12-15-26
P9B2-CON-370 Install Security Fencing 12-15-26 12-28-26
P9B2-CON-380 Install Devices and Pull Wire for Lights and Security 12-28-26 01-04-27
P9B2-CON-390 Form and Pour Curbs 01-04-27 01-13-27
P9B2-CON-400 Form and Pour Sidewalks 01-13-27 01-19-27
P9B2-CON-410 Pave Area 01-19-27 01-28-27
P9B2-CON-420 Paint Parking Striping 01-28-27 02-01-27
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027
Setup SWPPP
Clear and Grub
Demo Site
Install Sanitary By-Pass
Excavate and Install Shoring
Install Foundations
Install Pre-Cast Rings
Install SD Piping
Install Pumps
Install Electrical
Install Waterproofing
Backfill and Strip Forms
Connect Pumps
Excavate Footing for Wall
Install Footing for Wall
Form and Pour Wall
Excavate and Install Shoring - Pump Vaults
Pour Foundations - Pump Vaults
Install Pre-Cast Rings - Pump Vaults
Install SD Piping - Pump Vaults
Waterproof - Pump Vaults
Backfill Precast Vaults and Strip Forms - Pump Vaults
Excavate and Install Shoring - 5 SIde Vault
Trench for Electrical After Backfill
Install Undergroud Electrical After Backfill
Form and Pour Foundation - 5 Side Vault
Install Undergroud Storm Drain After Backfill
Form and Pour Walls - 5 Side Vault
Setup Shoring for Lid - 5 Side Vault
Form and Pour Lid - 5 Side Vault
Form and Pour Equipment Pads
Set Electrical Equipment
Set Mechanical and Storm Drain Equipment
Install Pumps
Install Electrical
Install Waterproofing
Backfill- 5 Side Vault
Pull Wire and Terminate Electrical
Connect Pumps
Test and Energize Equipment
Excavate Footing for Wall (Continue from 9A-A)
Install Footing for Wall
Form and Pour Wall
Install Security Fencing
Install Devices and Pull Wire for Lights and Security
Form and Pour Curbs
Form and Pour Sidewalks
Pave Area
Paint Parking Striping
Data Date: 11-11-25 Print Date: 03-04-26 09:23
SOLANOC-ASSET-LF-1-1-2-1 | #
123 Complete
Milestone
Critical Milestones
Summary Milestones
Actual Work
Remaining Work
Critical Remaining Work
Remaining Level of Effort
Actual Level of Effort
P9B2-CON-450 Paint and Coatings 01-28-27 02-03-27
P9B2-CON-430 Install Landscaping 02-03-27 02-09-27
P9B2-CON-440 Remove Construction Fencing and Barriers 02-09-27 02-12-27
Phase 10Phase 10 11-17-26 02-10-27
P10-CON-100 Call 811 and Markout Utilities 11-17-26 11-19-26
P10-CON-110 Setup Construction Fencing and Barriers 11-19-26 11-20-26
P10-CON-120 Setup Temporary Access 11-19-26 11-20-26
P10-CON-130 Setup SWPPP 11-20-26 11-21-26
P10-CON-140 Clear and Grub 11-21-26 11-24-26
P10-CON-150 Cap Off Utilities and Irrigation Lines 11-24-26 11-25-26
P10-CON-160 Demo Existing Sidewalk 11-25-26 12-01-26
P10-CON-170 Excavate and Remove Storm Drain Pipes and Basin 12-01-26 12-07-26
P10-CON-180 Start Dewatering 12-01-26 12-03-26
P10-CON-190 Rough Grade 12-07-26 12-10-26
P10-CON-200 Install New Storm Drainage Lines and Basins 12-10-26 12-17-26
P10-CON-210 Trench for Electrical 12-10-26 12-12-26
P10-CON-220 Install Footing for Wall 12-10-26 12-19-26
P10-CON-230 Install Underground Electrical Conduit 12-12-26 12-17-26
P10-CON-240 Backfill Electrical Trench 12-17-26 12-19-26
P10-CON-250 Fine Grade and Build Berm 12-19-26 12-28-26
P10-CON-260 Form and Pour Wall 12-19-26 12-26-26
P10-CON-270 Form and Pour Curbs 12-26-26 01-14-27
P10-CON-280 Install Irrigatiion Mains 12-28-26 01-02-27
P10-CON-290 Form and Pour Sidewalk 01-02-27 01-12-27
P10-CON-310 Install Landscaping 01-12-27 01-21-27
P10-CON-300 Set Lightpoles Bases, Light Poles and Bollards 01-14-27 01-23-27
P10-CON-330 Install Irrigation Branches 01-21-27 01-26-27
P10-CON-340 Install Security Fencing and Gates 01-21-27 01-30-27
P10-CON-320 Place AC Pavement 01-23-27 02-02-27
P10-CON-350 Paint Parking Striping 02-02-27 02-04-27
P10-CON-360 Pull Wire and Makeup for Lights and Security 02-02-27 02-09-27
P10-CON-380 Paint and Coatings 02-02-27 02-08-27
P10-CON-370 Remove Construction Fencing and Barriers 02-09-27 02-10-27
FEMA CloseoutFEMA Closeout 02-12-27 03-26-27
CLOS-CON-100 Final Billings 02-12-27 02-26-27
CLOS-CON-120 Closeout Documentation 02-12-27 03-26-27
CLOS-CON-110 Reimbursement Request 02-26-27 03-19-27
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027
Paint and Coatings
Install Landscaping
Remove Construction Fencing and Barriers
Call 811 and Markout Utilities
Setup Construction Fencing and Barriers
Setup Temporary Access
Setup SWPPP
Clear and Grub
Cap Off Utilities and Irrigation Lines
Demo Existing Sidewalk
Excavate and Remove Storm Drain Pipes and Basin
Start Dewatering
Rough Grade
Install New Storm Drainage Lines and Basins
Trench for Electrical
Install Footing for Wall
Install Underground Electrical Conduit
Backfill Electrical Trench
Fine Grade and Build Berm
Form and Pour Wall
Form and Pour Curbs
Install Irrigatiion Mains
Form and Pour Sidewalk
Install Landscaping
Set Lightpoles Bases, Light Poles and Bollards
Install Irrigation Branches
Install Security Fencing and Gates
Place AC Pavement
Paint Parking Striping
Pull Wire and Makeup for Lights and Security
Paint and Coatings
Remove Construction Fencing and Barriers
Final Billings
Closeout Documentation
Reimbursement Request
Data Date: 11-11-25 Print Date: 03-04-26 09:23
SOLANOC-ASSET-LF-1-1-2-1 | #
123 Complete
Milestone
Critical Milestones
Summary Milestones
Actual Work
Remaining Work
Critical Remaining Work
Remaining Level of Effort
Actual Level of Effort
File details come from the government source that posted it. Updated .