20260304_Asset_Protection_Project_Schedule.pdf

PDF 2 MB Posted

Attached to
Asset Protection - Landscaping
Solicitation number
911-0213-26
Issued by
Trinity County, California

About this file

This is a construction project schedule document for Solano County's Asset Protection Project, a comprehensive flood mitigation initiative designed to protect county properties from seasonal stormwater damage. The project encompasses multiple county facilities located at Union Avenue, Clay Street, Delaware Street, and Texas Street addresses, with work including barrier walls, berms, landscaping, hardscape, flood gates, underground utility reconfiguration, and pump systems. The schedule indicates a project duration spanning from November 12, 2025 (Notice to Proceed) through March 26, 2027 (Project Completion), with substantial completion targeted for February 12, 2027. The work is organized into 10 phased construction activities, with design activities commencing immediately, including design completion by December 11, 2025, city abandonment by February 6, 2026, and permit approval by February 27, 2026. Two separate bid packages are scheduled: demonstration packages with bid periods from March 2-17, 2026, and site utilities packages with bid periods from February 11 through March 6, 2026. Construction phases are staggered throughout 2026 and early 2027, with individual phase completions ranging from Phase 1 (August 25, 2026) through Phase 10 (February 10, 2027), incorporating utility coordination, grading, drainage installation, electrical and irrigation systems, hardscaping, landscaping, and site finalization activities.

The schedule reflects a complex, federally funded FEMA project requiring extensive procurement planning, including submittals review periods, certificate of insurance submissions, and long-lead procurement activities for specialized equipment such as pumps and vaults, with lead times extending from June through October 2026. The project involves multiple construction work phases executed concurrently and sequentially, with critical path activities including storm drain installation, utility coordination, and barrier wall construction. Closeout activities are scheduled from February 12 through March 26, 2027, including final billings, closeout documentation, and reimbursement requests, indicating adherence to federal grant administration requirements typical of FEMA-funded disaster mitigation projects.

View the file

Other files

File Type Posted
20260313_WRA_Redlined_Volume_2_Drawings.pdf PDF
20260223_Revised_Volume_1_Asset_Protection_IFC_Drawing_Set_-_Select_Drawings.pdf PDF
20260219_Asset_Protection_Pre-Bid_Conference_Sign-In_Sheet.pdf PDF
20260223_Revised_Section_31_23_16_Structure_Excavation_and_Backfill.pdf PDF
20260223_Revised_Volume_1_Asset_Protection_IFC_Drawing_Set_-_Select_Drawings.pdf PDF
20260219_Asset_Protection_Pre-Bid_Conference_Slides.pdf PDF
20260223_Revised_Section_31_00_00_Embankment_Construction.pdf PDF
20260223_Temporary_Sewer_Bypass_Drawing_Sheet_SS1.pdf PDF
20260223_Offsite_Sanitary_Sewer_Improvements_Civil_Specifications_100%_Set.pdf PDF
20260223_Revised_Section_31_23_16_Structure_Excavation_and_Backfill.pdf PDF
20260303_Revised_Section_09_90_00_Painting_and_Coating.pdf PDF
20260223_Offsite_Sanitary_Sewer_Improvements_Drawings_100%_Submittal.pdf PDF
20260223_Temporary_Sewer_Bypass_Drawing_Sheet_SS1.pdf PDF
20260303_Revised_Section_09_90_00_Painting_and_Coating.pdf PDF
20260223_Revised_Section_31_23_16_Structure_Excavation_and_Backfill.pdf PDF
20260303_Revised_Section_09_90_00_Painting_and_Coating.pdf PDF
20260219_Asset_Protection_Pre-Bid_Conference_Sign-In_Sheet.pdf PDF
20260223_Offsite_Sanitary_Sewer_Improvements_Drawings_100%_Submittal.pdf PDF
20260223_Offsite_Sanitary_Sewer_Improvements_Civil_Specifications_100%_Set.pdf PDF
20260223_Sanitary_Sewer_Bypass_Specification.pdf PDF
PO_TERMS_CONDITIONS.pdf PDF
PO_TERMS_CONDITIONS.pdf PDF
PO_TERMS_CONDITIONS.pdf PDF
PO_TERMS_CONDITIONS.pdf PDF
Exhibit_C_-_General_Terms_6_12_18.pdf PDF
Exhibit_C_-_General_Terms_6_12_18.pdf PDF
Exhibit_C_-_General_Terms_6_12_18.pdf PDF
Exhibit_C_-_General_Terms_6_12_18.pdf PDF
20251208_Volume_1_Asset_Protection_IFC_Drawing_Set_Building_Div_Approved.pdf PDF
20251208_Volume_1_Asset_Protection_IFC_Drawing_Set_Building_Div_Approved.pdf PDF
20251211_Volume_2_Parking_and_Security_Improvements_IFC_Rev_1_Drawing_Set_Building_Div_Approved.pdf PDF
20251211_Volume_2_Parking_and_Security_Improvements_IFC_Rev_1_Drawing_Set_Building_Div_Approved.pdf PDF
20251211_Volume_2_Parking_and_Security_Improvements_IFC_Rev_1_Drawing_Set_Building_Div_Approved.pdf PDF
20251211_Volume_2_Parking_and_Security_Improvements_IFC_Rev_1_Drawing_Set_Building_Div_Approved.pdf PDF
20260210_Asset_Protection_Landscaping_-_Project_Manual.pdf PDF
20260210_Asset_Protection_Landscaping_-_Project_Manual.pdf PDF
Hazard_Mitigation_Assistance_Contracting_Guidance_for_FEMA-Eligible_Projects,_Non-State_Subrecipients.pdf PDF
Hazard_Mitigation_Assistance_Contracting_Guidance_for_FEMA-Eligible_Projects,_Non-State_Subrecipients.pdf PDF
Hazard_Mitigation_Assistance_Contracting_Guidance_for_FEMA-Eligible_Projects,_Non-State_Subrecipients.pdf PDF
Hazard_Mitigation_Assistance_Contracting_Guidance_for_FEMA-Eligible_Projects,_Non-State_Subrecipients.pdf PDF
Hazard_Mitigation_Assistance_Contracting_Guidance_for_FEMA-Eligible_Projects,_Non-State_Subrecipients.pdf PDF
20260119_Asset_Protection_Project_Schedule.pdf PDF
Access_Requirements.pdf PDF
Access_Requirements.pdf PDF
Access_Requirements.pdf PDF
Access_Requirements.pdf PDF
20210903_Geotech_Report_CE&G.pdf PDF
20210903_Geotech_Report_CE&G.pdf PDF
20210903_Geotech_Report_CE&G.pdf PDF
20210903_Geotech_Report_CE&G.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AREA LITE

AREA LITE

NO

PARKING

RESERVED

RESERVED

NO

PARKING

RESERVED

NO

PARKING

NO

PARKING

NO

PARKING

NO

PA

RK

IN

G

NO

PARKING

NO

PARKING

NO

PARKING

NO

PARKING

B

BB

B

B

B

B

B

B

B

B

B

B

B

B

B

BB

B

B

B

B

B

B

B

B

B

B

BB

B

B

NO

PA

RK

IN

G

NO

PARKING

NO

PARKING

CR

IC

C R

IC IC

IC

IC

C R

C R

C R

CR

IC

IC

CR

C R

C R

C R

CR

IC

IC

IC

IC

CR

C R

CR

C R

C R

CR

C R

C R

CONSTRUCTION

PHASING

X:

\1

\1

4.

\T

EC

H \C

AD

\P

AR

KI

N G

L O

T

IM

PR

O

VE

M

EN

TS

\G -0

C

O N

ST

R

U C

TI

O

N P

H

AS

IN

G

.D W

G

/2

1/

:4 9:

P

M

SHEET CONTENTS

or l

00 60 120

9B-2

5 4

9A 9B-1

Activity ID Activity Name Start Finish

Solano County Asset Protection - Live FileSolano County Asset Protection - Live File 11-12-25 03-26-27

MILESTONESMILESTONES 11-12-25 03-26-27

MILE-10 NTP 11-12-25

MILE-250 Construction Start 03-02-26

LOE-100 Phase 1 Level of Effort 04-28-26 08-25-26

LOE-150 Phase 4 Level of Effort 04-28-26 08-07-26

LOE-160 Phase 6 Level of Effort 04-28-26 10-30-26

LOE-170 Phase 2 Level of Effort 04-28-26 11-25-26

LOE-180 Phase 9 Level of Effort 04-28-26 02-12-27

LOE-190 Phase 3 Level of Effort 04-28-26 11-02-26

MILE-110 Phase 6C Completion 06-27-26

MILE-140 Phase 6A Completion 07-30-26

MILE-130 Phase 4 Completion 08-07-26

MILE-190 Phase 1 Completion 08-25-26

LOE-110 Phase 7 Level of Effort 09-24-26 12-12-26

LOE-120 Phase 8 Level of Effort 09-24-26 12-16-26

LOE-140 Phase 5 Level of Effort 09-24-26 12-22-26

MILE-200 Phase 6 Completion 11-02-26

MILE-210 Phase 6B Completion 11-02-26

MILE-160 Phase 3 Completion 11-02-26

LOE-130 Phase 10 Level of Effort 11-17-26 02-10-27

MILE-220 Phase 2 Completion 11-28-26

MILE-170 Phase 7 Completion 12-14-26

MILE-100 Phase 8 Completion 12-16-26

MILE-150 Phase 5 Completion 12-22-26

MILE-180 Phase 10 Completion 02-10-27

MILE-120 Phase 9 Completion 02-12-27

MILE-240 Substantial Completion 02-12-27*

MILE-230 Project Completion 03-26-27

ASSET PROTECTION - FEMAASSET PROTECTION - FEMA 11-12-25 03-26-27

DesignDesign 11-12-25 02-27-26

DESIGN-100 Design Completion 11-12-25 12-11-25

DESIGN-110 City Abandonment 12-12-25 02-06-26

DESIGN-120 Permit Approval 02-09-26 02-27-26

AwardsAwards 11-12-25 05-04-26

AWARD-100 Draft Bid Packages 11-12-25 01-09-26

AWARD-110 County Review and Approval of Bid Packages 01-12-26 01-16-26

AWARD-120 Bid Period 01-19-26 03-10-26

AWARD-130 Unseal of Bid and NOI 03-11-26 03-19-26

AWARD-140 Bid Protest Period 03-20-26 04-02-26

AWARD-150 NTP 04-03-26 04-03-26

AWARD-160 Submittals and Review Period 04-06-26 05-01-26

AWARD-170 COI 05-04-26 05-04-26

Bid Packages 1 - Demo PackageBid Packages 1 - Demo Package 03-02-26 04-27-26

AWARD-180 Bid Period - Demo Packages 03-02-26* 03-17-26

AWARD-190 Unseal of Bid and NOI - Demo Packages 03-18-26 03-19-26

AWARD-200 Bid Protest Period - Demo Packages 03-20-26 03-29-26

AWARD-210 NTP - Demo Packages 03-30-26 03-30-26

AWARD-220 Submittals and Review Period - Demo Packages 03-31-26 04-27-26

AWARD-230 COI - Demo Packages 04-27-26 04-27-26

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027

NTP

Construction Start

Phase 1 Level of Effort

Phase 4 Level of Effort

Phase 6 Level of Effort

Phase 2 Level of Effort

Phase 9 Level of Effort

Phase 3 Level of Effort

Phase 6C Completion

Phase 6A Completion

Phase 4 Completion

Phase 1 Completion

Phase 7 Level of Effort

Phase 8 Level of Effort

Phase 5 Level of Effort

Phase 6 Completion

Phase 6B Completion

Phase 3 Completion

Phase 10 Level of Effort

Phase 2 Completion

Phase 7 Completion

Phase 8 Completion

Phase 5 Completion

Phase 10 Completion

Phase 9 Completion

Substantial Completion

Project Completion

Design Completion

City Abandonment

Permit Approval

Draft Bid Packages

County Review and Approval of Bid Packages

Bid Period

Unseal of Bid and NOI

Bid Protest Period

NTP

Submittals and Review Period

COI

Bid Period - Demo Packages

Unseal of Bid and NOI - Demo Packages

Bid Protest Period - Demo Packages

NTP - Demo Packages

Submittals and Review Period - Demo Packages

COI - Demo Packages

Data Date: 11-11-25 Print Date: 03-04-26 09:23

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

Solano County Asset Protection - Live File

Full Schedule

Bid Packages 2 - Site UtilitiesBid Packages 2 - Site Utilities 02-11-26 04-21-26

AWARD-240 Bid Period - Demo Packages 02-11-26* 03-06-26

AWARD-250 Unseal of Bid and NOI - Site Utilities 03-09-26 03-13-26

AWARD-260 Bid Protest Period - Site Utilities 03-14-26 03-23-26

AWARD-270 NTP - Site Utilities 03-24-26 03-24-26

AWARD-280 Submittals and Review Period - Site Utilities 03-25-26 04-21-26

AWARD-290 COI - Site Utilities 04-21-26 04-21-26

ProcurementProcurement 11-12-25 10-06-26

PRO-100 Front End Development for Pumps and Vaults 11-12-25 02-09-26

PRO-110 Long Lead Pump Submittals and Review 04-22-26 06-03-26

PRO-140 Pump Lead Time 06-04-26 10-06-26

PRO-130 Pump Vault Lead Time 06-04-26 07-16-26

PRO-150 Pumps/Electrical/Controls Lead Time 06-04-26 10-06-26

ConstructionConstruction 04-28-26 02-12-27

Phased WorkPhased Work 04-28-26 02-12-27

Phase 1Phase 1 04-28-26 08-25-26

P1-CON-100 Call 811 and Markout Utilities 04-28-26 04-30-26

P1-CON-110 Setup Construction Fencing and Barriers 05-01-26 05-06-26

P1-CON-120 Setup Temporary Access 05-01-26 05-06-26

P1-CON-130 Setup SWPPP 05-07-26 05-12-26

P1-CON-140 Clear and Grub from 00+00 to 05+00 05-13-26 05-19-26

P1-CON-150 Cap Off Utilities and Irrigation Lines 05-20-26 05-21-26

P1-CON-160 Demo Existing Sidewalk 05-22-26 05-28-26

P1-CON-170 Excavate and Remove Storm Drain Pipes and Basin 05-29-26 06-09-26

P1-CON-180 Rough Grade From 00+00 to 01+75 06-10-26 06-15-26

P1-CON-190 Rough Grade From 01+75 to 05+52 06-16-26 06-20-26

P1-CON-200 Install New Storm Drainage Lines and Basins 06-22-26 07-02-26

P1-CON-210 Fine Grade and Build Berm 07-03-26 07-27-26

P1-CON-220 Install Irrigatiion Mains 07-28-26 08-04-26

P1-CON-230 Install Irrigation Branches 08-05-26 08-07-26

P1-CON-240 Form and Pour Mow Bands at Berm 08-05-26 08-10-26

P1-CON-250 Install Landscaping 08-11-26 08-21-26

P1-CON-260 Remove Construction Fencing and Barriers 08-22-26 08-25-26

Phase 2Phase 2 04-28-26 11-28-26

Clay StreetClay Street 04-28-26 11-28-26

P2-CON-CLAY-100 Call 811 and Markout Utilities 04-28-26 04-28-26

P2-CON-CLAY-110 Setup Construction Fencing and Barriers 04-29-26 05-02-26

P2-CON-CLAY-120 Setup Road Closure 04-29-26 04-30-26

P2-CON-CLAY-130 Setup SWPPP 05-04-26 05-05-26

P2-CON-CLAY-140 Clear and Grub 05-06-26 05-07-26

P2-CON-CLAY-150 Demo Existing Pavement and Sidewalk 05-08-26 05-19-26

P2-CON-CLAY-160 Excavate and Remove Storm Drain Pipes and Basin 05-20-26 05-26-26

P2-CON-CLAY-170 Setup Dewatering 05-20-26 05-22-26

P2-CON-CLAY-180 Rough Grade 05-27-26 06-01-26

P2-CON-CLAY-190 Install New Storm Drainage Lines and Basins 06-02-26 06-24-26

P2-CON-CLAY-200 Excavate Retaining Wall Footings and Flood Gate 06-02-26 06-09-26

P2-CON-CLAY-210 Install New Sewer Line (Add Alt) 06-02-26 06-24-26

P2-CON-CLAY-220 Install Retaining Wall Footings and Flood Gate 06-10-26 06-17-26

P2-CON-CLAY-230 Backfill Retaining Wall Footings and Form Retaining Walls 06-10-26 06-18-26

P2-CON-CLAY-240 Inspect Underground Utilities 06-25-26 06-26-26

P2-CON-CLAY-250 Backfill Storm Drain Trenches Backfill to Grade 06-27-26 07-09-26

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027

Bid Period - Demo Packages

Unseal of Bid and NOI - Site Utilities

Bid Protest Period - Site Utilities

NTP - Site Utilities

Submittals and Review Period - Site Utilities

COI - Site Utilities

Front End Development for Pumps and Vaults

Long Lead Pump Submittals and Review

Pump Lead Time

Pump Vault Lead Time

Pumps/Electrical/Controls Lead Time

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub from 00+00 to 05+00

Cap Off Utilities and Irrigation Lines

Demo Existing Sidewalk

Excavate and Remove Storm Drain Pipes and Basin

Rough Grade From 00+00 to 01+75

Rough Grade From 01+75 to 05+52

Install New Storm Drainage Lines and Basins

Fine Grade and Build Berm

Install Irrigatiion Mains

Install Irrigation Branches

Form and Pour Mow Bands at Berm

Install Landscaping

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Road Closure

Setup SWPPP

Clear and Grub

Demo Existing Pavement and Sidewalk

Excavate and Remove Storm Drain Pipes and Basin

Setup Dewatering

Rough Grade

Install New Storm Drainage Lines and Basins

Excavate Retaining Wall Footings and Flood Gate

Install New Sewer Line (Add Alt)

Install Retaining Wall Footings and Flood Gate

Backfill Retaining Wall Footings and Form Retaining Walls

Inspect Underground Utilities

Backfill Storm Drain Trenches Backfill to Grade

Data Date: 11-11-25 Print Date: 03-04-26 09:23

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P2-CON-CLAY-260 Trench for Electrical 07-10-26 07-15-26

P2-CON-CLAY-270 Install Underground Conduits 07-16-26 07-21-26

P2-CON-CLAY-280 Inspect Underground Electrical 07-22-26 07-23-26

P2-CON-CLAY-290 Backfill Electrical Trench 07-24-26 07-30-26

P2-CON-CLAY-300 Complete Fine Grade 07-31-26 08-13-26

P2-CON-CLAY-310 Pour Retaining Walls 07-31-26 08-01-26

P2-CON-CLAY-320 Form and Pour Curbs 08-14-26 08-27-26

P2-CON-CLAY-330 Pull Electrical 08-14-26 08-19-26

P2-CON-CLAY-340 Form and Pour Sidewalks 08-28-26 09-09-26

P2-CON-CLAY-350 Place AC Pavement 11-10-26 11-17-26

P2-CON-CLAY-360 Paint Striping 11-17-26 11-20-26

P2-CON-CLAY-370 Install Signage 11-17-26 11-23-26

P2-CON-CLAY-390 Paint and Coatings 11-17-26 11-23-26

P2-CON-CLAY-380 Remove Construction Fencing and Barriers 11-23-26 11-28-26

Texas StreetTexas Street 04-28-26 08-14-26

Storm DrainStorm Drain 04-28-26 06-25-26

P2-CON-TEXAS-100 Call 811 and Markout Utilities 04-28-26 05-01-26

P2-CON-TEXAS-110 Setup Construction Fencing and Barriers 05-02-26 05-02-26

P2-CON-TEXAS-120 Setup Temporary Access 05-02-26 05-02-26

P2-CON-TEXAS-130 Setup SWPPP 05-04-26 05-04-26

P2-CON-TEXAS-140 Clear and Grub 05-05-26 05-06-26

P2-CON-TEXAS-150 Demo Existing Pavement 05-07-26 05-09-26

P2-CON-TEXAS-160 Excavate and Remove Storm Drain Pipes and Basin 05-11-26 05-15-26

P2-CON-TEXAS-170 Setup Dewatering 05-11-26 05-11-26

P2-CON-TEXAS-180 Rough Grade 05-16-26 05-18-26

P2-CON-TEXAS-190 Install New Storm Drainage Lines and Basins 05-19-26 06-02-26

P2-CON-TEXAS-200 Backfill Storm Drain Trenches and Fine Grade 06-03-26 06-13-26

P2-CON-TEXAS-210 Complete Fine Grade 06-15-26 06-16-26

P2-CON-TEXAS-220 Place AC Pavement 06-17-26 06-18-26

P2-CON-TEXAS-230 Paint Striping 06-19-26 06-20-26

P2-CON-TEXAS-240 Install Signage 06-19-26 06-20-26

P2-CON-TEXAS-390 Paint and Coatings 06-19-26 06-23-26

P2-CON-TEXAS-250 Remove Construction Fencing and Barriers 06-24-26 06-25-26

Sewer (Add ALT)Sewer (Add ALT) 06-26-26 08-14-26

P2-CON-TEXAS-260 Setup Construction Fencing and Barriers 06-26-26 06-26-26

P2-CON-TEXAS-270 Setup Temporary Access 06-26-26 06-26-26

P2-CON-TEXAS-280 Setup SWPPP 06-27-26 06-27-26

P2-CON-TEXAS-290 Demo Existing Pavement 06-29-26 07-01-26

P2-CON-TEXAS-300 Excavate and Remove New Sewer Line (Add Alt) 07-02-26 07-08-26

P2-CON-TEXAS-310 Setup Dewatering 07-02-26 07-02-26

P2-CON-TEXAS-320 Rough Grade 07-09-26 07-10-26

P2-CON-TEXAS-330 Install New Sewer Line (Add Alt) 07-11-26 08-03-26

P2-CON-TEXAS-340 Complete Fine Grade 08-04-26 08-05-26

P2-CON-TEXAS-350 Place AC Pavement 08-06-26 08-07-26

P2-CON-TEXAS-360 Paint Striping 08-08-26 08-10-26

P2-CON-TEXAS-370 Install Signage 08-08-26 08-10-26

P2-CON-TEXAS-400 Paint and Coatings 08-08-26 08-12-26

P2-CON-TEXAS-380 Remove Construction Fencing and Barriers 08-13-26 08-14-26

Phase 3Phase 3 04-28-26 11-02-26

P3-CON-100 Call 811 and Markout Utilities 04-28-26 05-01-26

P3-CON-110 Setup Construction Fencing and Barriers 05-02-26 05-07-26

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027

Trench for Electrical

Install Underground Conduits

Inspect Underground Electrical

Backfill Electrical Trench

Complete Fine Grade

Pour Retaining Walls

Form and Pour Curbs

Pull Electrical

Form and Pour Sidewalks

Place AC Pavement

Paint Striping

Install Signage

Paint and Coatings

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Demo Existing Pavement

Excavate and Remove Storm Drain Pipes and Basin

Setup Dewatering

Rough Grade

Install New Storm Drainage Lines and Basins

Backfill Storm Drain Trenches and Fine Grade

Complete Fine Grade

Place AC Pavement

Paint Striping

Install Signage

Paint and Coatings

Remove Construction Fencing and Barriers

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Demo Existing Pavement

Excavate and Remove New Sewer Line (Add Alt)

Setup Dewatering

Rough Grade

Install New Sewer Line (Add Alt)

Complete Fine Grade

Place AC Pavement

Paint Striping

Install Signage

Paint and Coatings

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Data Date: 11-11-25 Print Date: 03-04-26 09:23

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P3-CON-120 Setup Temporary Access 05-02-26 05-05-26

P3-CON-130 Setup SWPPP 05-08-26 05-09-26

P3-CON-140 Cap Off Utilities and Irrigation Lines 05-11-26 05-12-26

P3-CON-150 Demo Existing Pavement and Sidewalk 05-13-26 05-23-26

P3-CON-160 Rough Grade 05-26-26 05-30-26

P3-CON-170 Excavate and Remove Storm Drain Pipes and Basin 06-01-26 06-05-26

P3-CON-180 Install New Storm Drainage Lines and Basins 06-06-26 06-23-26

P3-CON-190 Backfill Storm Drain Trenches and to Grade 06-24-26 07-06-26

P3-CON-200 Trench for Shallow Underground Electrical 07-07-26 07-14-26

P3-CON-210 Excavate Retaining Wall Footings and Flood Gate 07-07-26 07-14-26

P3-CON-220 Install Underground Electrical Conduit 07-15-26 07-20-26

P3-CON-230 Install Retaining Wall Footings and Flood Gate 07-15-26 07-22-26

P3-CON-250 Backfill Electrical Trench to Grade 07-21-26 07-31-26

P3-CON-260 Pull Electrical Wire 07-21-26 08-03-26

P3-CON-270 Install Irrigations Mains 07-21-26 07-28-26

P3-CON-240 Backfill Retaining Wall Footings and Form Retaining Walls 07-23-26 07-31-26

P3-CON-290 Install Irrigation Branches 07-29-26 08-08-26

P3-CON-280 Complete Fine Grade 08-01-26 08-06-26

P3-CON-300 Form and Pour Curbs 08-07-26 08-18-26

P3-CON-310 Form and Pour Sidewalks 08-19-26 08-29-26

P3-CON-320 Set Fence Pole Bases and Poles 08-19-26 08-29-26

P3-CON-330 Excavate for Light Pole Bases 08-19-26 08-24-26

P3-CON-340 Set Cages and Finish Conduit 08-25-26 08-29-26

P3-CON-350 Install Fencing 08-31-26 09-09-26

P3-CON-360 Form and Pour Light Pole Bases 08-31-26 09-10-26

P3-CON-370 Set Light Poles 09-11-26 09-16-26

P3-CON-380 Place AC Pavement 09-17-26 09-23-26

P3-CON-390 Pull Wire for Security 09-24-26 09-28-26

P3-CON-400 Install Landscaping 09-29-26 10-06-26

P3-CON-410 Install Vehicle Gates and Card Readers 09-29-26 10-06-26

P3-CON-420 Paint Parking Striping 10-07-26 10-17-26

P3-CON-450 Paint and Coatings 10-07-26 10-12-26

P3-CON-430 Set Wheel Stops 10-19-26 10-29-26

P3-CON-440 Remove Construction Fencing and Barriers 10-30-26 11-02-26

Phase 4Phase 4 04-28-26 08-07-26

P4-CON-100 Call 811 and Markout Utilities 04-28-26 05-01-26

P4-CON-110 Setup Construction Fencing and Barriers 05-02-26 05-02-26

P4-CON-120 Setup Temporary Access 05-02-26 05-02-26

P4-CON-130 Setup SWPPP 05-04-26 05-04-26

P4-CON-140 Clear and Grub 05-05-26 05-06-26

P4-CON-150 Cap Off Utilities and Irrigation Lines 05-07-26 05-08-26

P4-CON-160 Demo Existing Pavement and Sidewalk 05-09-26 05-12-26

P4-CON-170 Excavate and Remove Storm Drain Pipes and Basin 05-13-26 05-15-26

P4-CON-180 Rough Grade 05-16-26 05-18-26

P4-CON-190 Install New Storm Drainage Lines and Basins 05-19-26 05-21-26

P4-CON-200 Trench for Electrical for Gate 05-19-26 05-19-26

P4-CON-210 Install Electrical Conduit for Electrical for Gate 05-20-26 05-22-26

P4-CON-220 Backfill Storm Drain Trenches and Fine Grade 05-22-26 06-03-26

P4-CON-230 Install Footing for Retaining Wall and Fencing 05-23-26 06-01-26

P4-CON-240 Trench for Electrical 06-04-26 06-05-26

P4-CON-250 Install Underground Electrical Conduit 06-06-26 06-08-26

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027

Setup Temporary Access

Setup SWPPP

Cap Off Utilities and Irrigation Lines

Demo Existing Pavement and Sidewalk

Rough Grade

Excavate and Remove Storm Drain Pipes and Basin

Install New Storm Drainage Lines and Basins

Backfill Storm Drain Trenches and to Grade

Trench for Shallow Underground Electrical

Excavate Retaining Wall Footings and Flood Gate

Install Underground Electrical Conduit

Install Retaining Wall Footings and Flood Gate

Backfill Electrical Trench to Grade

Pull Electrical Wire

Install Irrigations Mains

Backfill Retaining Wall Footings and Form Retaining Walls

Install Irrigation Branches

Complete Fine Grade

Form and Pour Curbs

Form and Pour Sidewalks

Set Fence Pole Bases and Poles

Excavate for Light Pole Bases

Set Cages and Finish Conduit

Install Fencing

Form and Pour Light Pole Bases

Set Light Poles

Place AC Pavement

Pull Wire for Security

Install Landscaping

Install Vehicle Gates and Card Readers

Paint Parking Striping

Paint and Coatings

Set Wheel Stops

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Cap Off Utilities and Irrigation Lines

Demo Existing Pavement and Sidewalk

Excavate and Remove Storm Drain Pipes and Basin

Rough Grade

Install New Storm Drainage Lines and Basins

Trench for Electrical for Gate

Install Electrical Conduit for Electrical for Gate

Backfill Storm Drain Trenches and Fine Grade

Install Footing for Retaining Wall and Fencing

Trench for Electrical

Install Underground Electrical Conduit

Data Date: 11-11-25 Print Date: 03-04-26 09:23

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P4-CON-260 Install Irrigations Mains 06-06-26 06-09-26

P4-CON-270 Backfill Electrical Trench 06-09-26 06-12-26

P4-CON-280 Complete Fine Grade 06-13-26 06-15-26

P4-CON-290 Form and Pour Perimeter Fencing Posts 06-13-26 06-18-26

P4-CON-300 Form and Pour Curbs 06-19-26 06-30-26

P4-CON-310 Set Lightpoles Bases, Light Poles and Bollards 07-01-26 07-03-26

P4-CON-320 Form and Pour Sidewalks 07-06-26 07-16-26

P4-CON-330 Place AC Pavement 07-17-26 07-18-26

P4-CON-340 Pull Electrical Wire and Security Wire 07-17-26 07-18-26

P4-CON-350 Paint Parking Striping 07-20-26 07-23-26

P4-CON-360 Install Landscaping 07-20-26 07-23-26

P4-CON-370 Pull Wire for Lights and Security 07-20-26 07-21-26

P4-CON-430 Paint and Coatings 07-20-26 07-24-26

P4-CON-380 Install Security Fencing and Gates 07-24-26 08-04-26

P4-CON-390 Install Irrigation Branches 07-25-26 07-27-26

P4-CON-400 Set Wheel Stops 07-28-26 07-31-26

P4-CON-410 Install Card Readers 08-05-26 08-06-26

P4-CON-420 Remove Construction Fencing and Barriers 08-07-26 08-07-26

Phase 5Phase 5 09-24-26 12-22-26

P5-CON-100 Call 811 and Markout Utilities 09-24-26 09-28-26

P5-CON-110 Setup Construction Fencing and Barriers 09-29-26 09-29-26

P5-CON-120 Setup Temporary Access 09-29-26 09-29-26

P5-CON-130 Setup SWPPP 09-30-26 09-30-26

P5-CON-140 Clear and Grub 10-01-26 10-02-26

P5-CON-150 Cap Off Utilities and Irrigation Lines 10-03-26 10-05-26

P5-CON-160 Demo Existing Pavement and Sidewalk 10-06-26 10-08-26

P5-CON-170 Excavate and Remove Storm Drain Pipes and Basin 10-09-26 10-14-26

P5-CON-180 Rough Grade 10-15-26 10-17-26

P5-CON-190 Install New Storm Drainage Lines and Basins 10-19-26 10-23-26

P5-CON-200 Backfill Storm Drain Trenches and Fine Grade 10-24-26 11-04-26

P5-CON-210 Trench for Electrical 11-05-26 11-10-26

P5-CON-220 Install Underground Electrical Conduit 11-12-26 11-14-26

P5-CON-230 Install Irrigations Mains 11-12-26 11-14-26

P5-CON-240 Backfill Electrical Trench 11-16-26 11-18-26

P5-CON-250 Complete Fine Grade 11-19-26 11-20-26

P5-CON-260 Form and Pour Curbs 11-21-26 12-01-26

P5-CON-270 Form and Pour Sidewalks 12-02-26 12-08-26

P5-CON-280 Place AC Pavement 12-09-26 12-10-26

P5-CON-290 Paint Parking Striping 12-11-26 12-12-26

P5-CON-300 Install Landscaping 12-11-26 12-11-26

P5-CON-310 Pull Wire and Makeup for Lights and Security 12-11-26 12-15-26

P5-CON-350 Paint and Coatings 12-11-26 12-16-26

P5-CON-320 Install Irrigation Branches 12-17-26 12-17-26

P5-CON-330 Set Wheel Stops 12-18-26 12-19-26

P5-CON-340 Remove Construction Fencing and Barriers 12-21-26 12-22-26

Phase 6Phase 6 04-28-26 10-31-26

Phase 6A North Oval and PlatformPhase 6A North Oval and Platform 04-28-26 07-30-26

P6A-CON-100 Call 811 and Markout Utilities 04-28-26 05-01-26

P6A-CON-110 Setup Construction Fencing and Barriers 05-02-26 05-07-26

P6A-CON-120 Setup Temporary Access 05-02-26 05-07-26

P6A-CON-130 Setup SWPPP 05-08-26 05-08-26

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027

Install Irrigations Mains

Backfill Electrical Trench

Complete Fine Grade

Form and Pour Perimeter Fencing Posts

Form and Pour Curbs

Set Lightpoles Bases, Light Poles and Bollards

Form and Pour Sidewalks

Place AC Pavement

Pull Electrical Wire and Security Wire

Paint Parking Striping

Install Landscaping

Pull Wire for Lights and Security

Paint and Coatings

Install Security Fencing and Gates

Install Irrigation Branches

Set Wheel Stops

Install Card Readers

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Cap Off Utilities and Irrigation Lines

Demo Existing Pavement and Sidewalk

Excavate and Remove Storm Drain Pipes and Basin

Rough Grade

Install New Storm Drainage Lines and Basins

Backfill Storm Drain Trenches and Fine Grade

Trench for Electrical

Install Underground Electrical Conduit

Install Irrigations Mains

Backfill Electrical Trench

Complete Fine Grade

Form and Pour Curbs

Form and Pour Sidewalks

Place AC Pavement

Paint Parking Striping

Install Landscaping

Pull Wire and Makeup for Lights and Security

Paint and Coatings

Install Irrigation Branches

Set Wheel Stops

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Data Date: 11-11-25 Print Date: 03-04-26 09:23

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P6A-CON-140 Clear and Grub 05-09-26 05-11-26

P6A-CON-150 Cap Off Utilities and Irrigation Lines 05-12-26 05-13-26

P6A-CON-160 Demo Existing Pavement and Sidewalk 05-14-26 05-16-26

P6A-CON-170 Rough Grade 05-18-26 05-22-26

P6A-CON-180 Trench for Electrical 05-23-26 05-26-26

P6A-CON-190 Install Underground Electrical Conduit 05-27-26 05-28-26

P6A-CON-200 Set Pull and Junction Boxes 05-29-26 06-01-26

P6A-CON-210 Backfill Electrical Trench 06-02-26 06-05-26

P6A-CON-220 Set Lightpoles Bases, Light Poles and Bollards 06-06-26 06-08-26

P6A-CON-230 Trench and Install Storm Drain Line 06-06-26 06-09-26

P6A-CON-240 Install Irrigations Mains 06-09-26 06-10-26

P6A-CON-250 Backfill Storm Drain Line 06-10-26 06-11-26

P6A-CON-260 Form and Pour Curbs 06-11-26 06-22-26

P6A-CON-270 Form and Pour Foundations for Stairs and Walls 06-12-26 06-23-26

P6A-CON-280 Form and Pour Slab 06-23-26 07-03-26

P6A-CON-290 Backfill Foundations 06-24-26 06-27-26

P6A-CON-300 Form and Pour Stairs 06-29-26 07-07-26

P6A-CON-310 Fine Grade Site 07-06-26 07-07-26

P6A-CON-320 Form and Pour Sidewalks 07-08-26 07-14-26

P6A-CON-330 Pull Wire and Makeup for Lights and Security 07-15-26 07-17-26

P6A-CON-340 Install Pre-Fab Seats 07-15-26 07-17-26

P6A-CON-350 Install Landscaping 07-18-26 07-23-26

P6A-CON-360 Install Irrigation Branches 07-24-26 07-27-26

P6A-CON-370 Remove Construction Fencing and Barriers 07-28-26 07-30-26

Phase 6B South OvalPhase 6B South Oval 07-31-26 10-31-26

P6B-CON-100 Setup Construction Fencing and Barriers 07-31-26 08-03-26

P6B-CON-110 Setup Temporary Access 08-04-26 08-08-26

P6B-CON-120 Setup SWPPP 08-10-26 08-10-26

P6B-CON-130 Clear and Grub 08-11-26 08-12-26

P6B-CON-140 Cap Off Utilities and Irrigation Lines 08-13-26 08-14-26

P6B-CON-150 Demo Existing Pavement and Sidewalk 08-15-26 08-18-26

P6B-CON-160 Rough Grade 08-19-26 08-29-26

P6B-CON-170 Trench for Electrical 08-31-26 09-02-26

P6B-CON-180 Install Underground Electrical Conduit 09-03-26 09-05-26

P6B-CON-190 Set Pull and Junction Boxes 09-08-26 09-09-26

P6B-CON-200 Backfill Electrical Trench 09-10-26 09-14-26

P6B-CON-210 Set Lightpoles Bases, Light Poles and Bollards 09-15-26 09-19-26

P6B-CON-220 Install Irrigations Mains 09-21-26 09-24-26

P6B-CON-230 Fine Grade Site 09-21-26 09-22-26

P6B-CON-240 Form and Pour Curbs 09-25-26 09-30-26

P6B-CON-250 Form and Pour Sidewalks 10-01-26 10-12-26

P6B-CON-260 Pull Electrical Wire and Security Wire 10-13-26 10-16-26

P6B-CON-270 Install Landscaping 10-17-26 10-24-26

P6B-CON-280 Install Irrigation Branches 10-26-26 10-28-26

P6B-CON-290 Remove Construction Fencing and Barriers 10-29-26 10-31-26

Phase 6C Law and Justice CenterPhase 6C Law and Justice Center 05-02-26 06-27-26

P6C-CON-100 Setup Construction Fencing and Barriers 05-02-26 05-02-26

P6C-CON-110 Setup Temporary Access 05-04-26 05-04-26

P6C-CON-120 Setup SWPPP 05-05-26 05-05-26

P6C-CON-130 Clear and Grub 05-06-26 05-07-26

P6C-CON-140 Cap Off Utilities and Irrigation Lines 05-08-26 05-09-26

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027

Clear and Grub

Cap Off Utilities and Irrigation Lines

Demo Existing Pavement and Sidewalk

Rough Grade

Trench for Electrical

Install Underground Electrical Conduit

Set Pull and Junction Boxes

Backfill Electrical Trench

Set Lightpoles Bases, Light Poles and Bollards

Trench and Install Storm Drain Line

Install Irrigations Mains

Backfill Storm Drain Line

Form and Pour Curbs

Form and Pour Foundations for Stairs and Walls

Form and Pour Slab

Backfill Foundations

Form and Pour Stairs

Fine Grade Site

Form and Pour Sidewalks

Pull Wire and Makeup for Lights and Security

Install Pre-Fab Seats

Install Landscaping

Install Irrigation Branches

Remove Construction Fencing and Barriers

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Cap Off Utilities and Irrigation Lines

Demo Existing Pavement and Sidewalk

Rough Grade

Trench for Electrical

Install Underground Electrical Conduit

Set Pull and Junction Boxes

Backfill Electrical Trench

Set Lightpoles Bases, Light Poles and Bollards

Install Irrigations Mains

Fine Grade Site

Form and Pour Curbs

Form and Pour Sidewalks

Pull Electrical Wire and Security Wire

Install Landscaping

Install Irrigation Branches

Remove Construction Fencing and Barriers

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Cap Off Utilities and Irrigation Lines

Data Date: 11-11-25 Print Date: 03-04-26 09:23

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P6C-CON-150 Demo Existing Pavement and Sidewalk 05-11-26 05-13-26

P6C-CON-160 Rough Grade 05-14-26 05-15-26

P6C-CON-170 Fine Grade Site 05-16-26 05-18-26

P6C-CON-180 Form and Pour Curbs and Wall 05-19-26 06-05-26

P6C-CON-190 Form and Pour Sidewalks 06-06-26 06-17-26

P6C-CON-200 Install Expansion Joints 06-18-26 06-20-26

P6C-CON-210 Install Landscaping 06-22-26 06-23-26

P6C-CON-220 Install Signage 06-24-26 06-24-26

P6C-CON-230 Remove Construction Fencing and Barriers 06-25-26 06-27-26

Phase 7Phase 7 09-24-26 12-12-26

P7-CON-100 Call 811 and Markout Utilities 09-24-26 09-24-26

P7-CON-110 Setup Construction Fencing and Barriers 09-25-26 09-25-26

P7-CON-120 Setup Temporary Access 09-25-26 09-25-26

P7-CON-130 Setup SWPPP 09-26-26 09-26-26

P7-CON-140 Clear and Grub 09-28-26 09-29-26

P7-CON-150 Cap Off Utilities and Irrigation Lines 09-30-26 10-01-26

P7-CON-160 Demo Existing Pavement and Sidewalk 10-02-26 10-05-26

P7-CON-170 Excavate and Remove Storm Drain Pipes and Basin 10-06-26 10-10-26

P7-CON-180 Rough Grade 10-12-26 10-13-26

P7-CON-190 Install New Storm Drainage Lines and Basins 10-14-26 10-24-26

P7-CON-200 Install Footing for Barrier Wall 10-14-26 10-24-26

P7-CON-210 Backfill Storm Drain Trenches and Fine Grade 10-26-26 10-30-26

P7-CON-230 Trench for Electrical 10-26-26 10-27-26

P7-CON-220 Form and Pour Barrier Wall 1A and 1B 10-26-26 10-31-26

P7-CON-240 Install Underground Electrical Conduit 10-31-26 11-02-26

P7-CON-250 Backfill Electrical Trench 11-03-26 11-04-26

P7-CON-280 Install Irrigations Mains 11-03-26 11-04-26

P7-CON-260 Complete Fine Grade 11-05-26 11-06-26

P7-CON-270 Form and Pour Footings for Fencing 11-05-26 11-07-26

P7-CON-290 Backfill Around Footings 11-09-26 11-09-26

P7-CON-300 Form and Pour Curbs 11-10-26 11-17-26

P7-CON-310 Set Lightpoles Bases, Light Poles and Bollards 11-18-26 11-21-26

P7-CON-320 Form and Pour Sidewalks 11-18-26 11-24-26

P7-CON-330 Pull Electrical Wire and Security Wire 11-23-26 11-25-26

P7-CON-340 Place AC Pavement 11-25-26 12-02-26

P7-CON-350 Paint Parking Striping 12-03-26 12-03-26

P7-CON-360 Install Landscaping 12-03-26 12-05-26

P7-CON-370 Pull Wire for Lights and Security 12-03-26 12-04-26

P7-CON-410 Paint and Coatings 12-03-26 12-07-26

P7-CON-380 Install Irrigation Branches 12-07-26 12-08-26

P7-CON-390 Set Wheel Stops 12-09-26 12-09-26

P7-CON-400 Remove Construction Fencing and Barriers 12-10-26 12-12-26

Phase 8Phase 8 09-24-26 12-16-26

P8-CON-100 Call 811 and Markout Utilities 09-24-26 09-24-26

P8-CON-110 Setup Construction Fencing and Barriers 09-25-26 09-25-26

P8-CON-120 Setup Temporary Access 09-25-26 09-25-26

P8-CON-130 Setup SWPPP 09-26-26 09-26-26

P8-CON-140 Clear and Grub 09-28-26 09-29-26

P8-CON-150 Demo Existing Pavement and Sidewalk 09-30-26 10-05-26

P8-CON-160 Excavate and Remove Storm Drain Pipes and Basin 10-06-26 10-10-26

P8-CON-170 Setup Dewatering 10-06-26 10-06-26

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027

Demo Existing Pavement and Sidewalk

Rough Grade

Fine Grade Site

Form and Pour Curbs and Wall

Form and Pour Sidewalks

Install Expansion Joints

Install Landscaping

Install Signage

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Cap Off Utilities and Irrigation Lines

Demo Existing Pavement and Sidewalk

Excavate and Remove Storm Drain Pipes and Basin

Rough Grade

Install New Storm Drainage Lines and Basins

Install Footing for Barrier Wall

Backfill Storm Drain Trenches and Fine Grade

Trench for Electrical

Form and Pour Barrier Wall 1A and 1B

Install Underground Electrical Conduit

Backfill Electrical Trench

Install Irrigations Mains

Complete Fine Grade

Form and Pour Footings for Fencing

Backfill Around Footings

Form and Pour Curbs

Set Lightpoles Bases, Light Poles and Bollards

Form and Pour Sidewalks

Pull Electrical Wire and Security Wire

Place AC Pavement

Paint Parking Striping

Install Landscaping

Pull Wire for Lights and Security

Paint and Coatings

Install Irrigation Branches

Set Wheel Stops

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Demo Existing Pavement and Sidewalk

Excavate and Remove Storm Drain Pipes and Basin

Setup Dewatering

Data Date: 11-11-25 Print Date: 03-04-26 09:23

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P8-CON-180 Rough Grade 10-12-26 10-15-26

P8-CON-190 Install New Storm Drainage Lines and Basins 10-16-26 10-21-26

P8-CON-200 Backfill Storm Drain Trenches and Fine Grade 10-22-26 10-27-26

P8-CON-210 Complete Fine Grade 10-28-26 10-30-26

P8-CON-220 Install Footing for Barrier Wall 10-28-26 11-07-26

P8-CON-230 Form and Pour Barrier Wall 1A and 1B 11-09-26 11-16-26

P8-CON-240 Form and Pour Curbs 11-17-26 11-25-26

P8-CON-250 Form and Pour Sidewalks 11-28-26 12-03-26

P8-CON-260 Place AC Pavement 12-04-26 12-09-26

P8-CON-270 Paint Striping 12-10-26 12-15-26

P8-CON-280 Install Signage 12-10-26 12-12-26

P8-CON-300 Paint and Coatings 12-10-26 12-15-26

P8-CON-290 Remove Construction Fencing and Barriers 12-16-26 12-16-26

Phase 9Phase 9 04-28-26 02-12-27

Phase 9APhase 9A 04-28-26 12-03-26

P9A-CON-100 Call 811 and Markout Utilities 04-28-26 05-01-26

P9A-CON-110 Safe Off 05-02-26 05-02-26

P9A-CON-120 Cap Off Utilities and Irrigation Lines 05-02-26 05-04-26

P9A-CON-130 Install Construction Site Fencing 05-04-26 05-04-26

P9A-CON-140 Setup Temporary Access 05-04-26 05-04-26

P9A-CON-150 Setup SWPPP 05-05-26 05-05-26

P9A-CON-160 Clear and Grub 05-06-26 05-06-26

P9A-CON-170 Demo Site 05-07-26 05-12-26

P9A-CON-180 Rough Grade Area 9A 05-13-26 05-21-26

P9A-CON-190 Excavate Underground Storm Drain 05-22-26 06-01-26

P9A-CON-200 Install Storm Drain Lines 06-02-26 06-02-26

P9A-CON-210 Install Underground Electrical 06-03-26 06-03-26

P9A-CON-220 Install New Pump Vault 07-17-26 07-17-26

P9A-CON-230 Install New Pump 10-06-26 10-07-26

P9A-CON-240 Connect Storm Drain Lines to New Pump 10-07-26 10-08-26

P9A-CON-250 Connect Electrical Lines to New Pump 10-08-26 10-09-26

P9A-CON-260 Connect Storm Drain Lines to New Pump 10-09-26 10-10-26

P9A-CON-270 Excavate Footing for Wall 10-10-26 10-14-26

P9A-CON-280 Fine Grade and Build Berm 10-10-26 10-20-26

P9A-CON-290 Install Footing for Wall 10-14-26 10-15-26

P9A-CON-300 Form and Pour Wall 10-15-26 10-27-26

P9A-CON-310 Install Security Fencing 10-27-26 10-28-26

P9A-CON-320 Pull Wire for Lights and Security 10-28-26 10-29-26

P9A-CON-330 Form and Pour Curbs 10-29-26 11-10-26

P9A-CON-340 Form and Pour Sidewalks 11-10-26 11-23-26

P9A-CON-350 Paint Parking Striping 11-23-26 11-24-26

P9A-CON-390 Paint and Coatings 11-23-26 11-30-26

P9A-CON-360 Install Landscaping 11-30-26 12-01-26

P9A-CON-370 Set Wheel Stops 12-01-26 12-02-26

P9A-CON-380 Remove Construction Fencing and Barriers 12-02-26 12-03-26

Phase 9BPhase 9B 04-28-26 02-12-27

P9B1-CON-100 Call 811 and Markout Utilities 04-28-26 05-01-26

P9B1-CON-110 Safe Off 05-02-26 05-02-26

P9B1-CON-120 Install Construction Site Fencing 05-04-26 05-04-26

P9B1-CON-130 Cap Off Utilities and Irrigation Lines 05-04-26 05-05-26

P9B1-CON-140 Setup Temporary Access 05-04-26 05-04-26

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027

Rough Grade

Install New Storm Drainage Lines and Basins

Backfill Storm Drain Trenches and Fine Grade

Complete Fine Grade

Install Footing for Barrier Wall

Form and Pour Barrier Wall 1A and 1B

Form and Pour Curbs

Form and Pour Sidewalks

Place AC Pavement

Paint Striping

Install Signage

Paint and Coatings

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Safe Off

Cap Off Utilities and Irrigation Lines

Install Construction Site Fencing

Setup Temporary Access

Setup SWPPP

Clear and Grub

Demo Site

Rough Grade Area 9A

Excavate Underground Storm Drain

Install Storm Drain Lines

Install Underground Electrical

Install New Pump Vault

Install New Pump

Connect Storm Drain Lines to New Pump

Connect Electrical Lines to New Pump

Connect Storm Drain Lines to New Pump

Excavate Footing for Wall

Fine Grade and Build Berm

Install Footing for Wall

Form and Pour Wall

Install Security Fencing

Pull Wire for Lights and Security

Form and Pour Curbs

Form and Pour Sidewalks

Paint Parking Striping

Paint and Coatings

Install Landscaping

Set Wheel Stops

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Safe Off

Install Construction Site Fencing

Cap Off Utilities and Irrigation Lines

Setup Temporary Access

Data Date: 11-11-25 Print Date: 03-04-26 09:23

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P9B1-CON-150 Setup SWPPP 05-05-26 05-05-26

P9B1-CON-160 Clear and Grub 05-06-26 05-06-26

P9B1-CON-170 Demo Site 05-07-26 05-12-26

P9B1-CON-180 Install Sanitary By-Pass 05-13-26 05-18-26

Area 9B1Area 9B1 05-19-26 11-20-26

P9B1-CON-190 Excavate and Install Shoring 05-19-26 05-30-26

P9B1-CON-200 Install Foundations 06-01-26 06-05-26

P9B1-CON-210 Install Pre-Cast Rings 07-17-26 07-22-26

P9B1-CON-220 Install SD Piping 07-23-26 07-24-26

P9B1-CON-230 Install Pumps 10-06-26 10-10-26

P9B1-CON-240 Install Electrical 10-10-26 10-16-26

P9B1-CON-250 Install Waterproofing 10-16-26 10-21-26

P9B1-CON-260 Backfill and Strip Forms 10-21-26 10-24-26

P9B1-CON-270 Connect Pumps 10-24-26 11-03-26

P9B1-CON-280 Excavate Footing for Wall 11-03-26 11-05-26

P9B1-CON-290 Install Footing for Wall 11-05-26 11-10-26

P9B1-CON-300 Form and Pour Wall 11-10-26 11-20-26

Area 9B2Area 9B2 06-01-26 02-12-27

P9B2-CON-100 Excavate and Install Shoring - Pump Vaults 06-01-26 06-11-26

P9B2-CON-110 Pour Foundations - Pump Vaults 06-12-26 06-17-26

P9B2-CON-120 Install Pre-Cast Rings - Pump Vaults 07-17-26 07-22-26

P9B2-CON-130 Install SD Piping - Pump Vaults 07-23-26 07-24-26

P9B2-CON-140 Waterproof - Pump Vaults 07-25-26 07-27-26

P9B2-CON-150 Backfill Precast Vaults and Strip Forms - Pump Vaults 07-28-26 07-30-26

P9B2-CON-160 Excavate and Install Shoring - 5 SIde Vault 07-31-26 08-05-26

P9B2-CON-170 Trench for Electrical After Backfill 07-31-26 08-03-26

P9B2-CON-180 Install Undergroud Electrical After Backfill 08-04-26 08-07-26

P9B2-CON-190 Form and Pour Foundation - 5 Side Vault 08-06-26 08-08-26

P9B2-CON-200 Install Undergroud Storm Drain After Backfill 08-08-26 08-19-26

P9B2-CON-210 Form and Pour Walls - 5 Side Vault 08-10-26 08-12-26

P9B2-CON-220 Setup Shoring for Lid - 5 Side Vault 08-13-26 08-13-26

P9B2-CON-230 Form and Pour Lid - 5 Side Vault 08-14-26 08-17-26

P9B2-CON-250 Form and Pour Equipment Pads 08-20-26 08-26-26

P9B2-CON-270 Set Electrical Equipment 08-27-26 08-28-26

P9B2-CON-280 Set Mechanical and Storm Drain Equipment 08-27-26 09-08-26

P9B2-CON-240 Install Pumps 10-06-26 10-12-26

P9B2-CON-260 Install Electrical 10-12-26 10-17-26

P9B2-CON-290 Install Waterproofing 10-17-26 10-20-26

P9B2-CON-300 Backfill- 5 Side Vault 10-20-26 10-23-26

P9B2-CON-310 Pull Wire and Terminate Electrical 10-22-26 11-03-26

P9B2-CON-320 Connect Pumps 10-24-26 11-03-26

P9B2-CON-330 Test and Energize Equipment 11-03-26 11-07-26

P9B2-CON-340 Excavate Footing for Wall (Continue from 9A-A) 11-20-26 11-25-26

P9B2-CON-350 Install Footing for Wall 11-25-26 12-05-26

P9B2-CON-360 Form and Pour Wall 12-05-26 12-15-26

P9B2-CON-370 Install Security Fencing 12-15-26 12-28-26

P9B2-CON-380 Install Devices and Pull Wire for Lights and Security 12-28-26 01-04-27

P9B2-CON-390 Form and Pour Curbs 01-04-27 01-13-27

P9B2-CON-400 Form and Pour Sidewalks 01-13-27 01-19-27

P9B2-CON-410 Pave Area 01-19-27 01-28-27

P9B2-CON-420 Paint Parking Striping 01-28-27 02-01-27

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027

Setup SWPPP

Clear and Grub

Demo Site

Install Sanitary By-Pass

Excavate and Install Shoring

Install Foundations

Install Pre-Cast Rings

Install SD Piping

Install Pumps

Install Electrical

Install Waterproofing

Backfill and Strip Forms

Connect Pumps

Excavate Footing for Wall

Install Footing for Wall

Form and Pour Wall

Excavate and Install Shoring - Pump Vaults

Pour Foundations - Pump Vaults

Install Pre-Cast Rings - Pump Vaults

Install SD Piping - Pump Vaults

Waterproof - Pump Vaults

Backfill Precast Vaults and Strip Forms - Pump Vaults

Excavate and Install Shoring - 5 SIde Vault

Trench for Electrical After Backfill

Install Undergroud Electrical After Backfill

Form and Pour Foundation - 5 Side Vault

Install Undergroud Storm Drain After Backfill

Form and Pour Walls - 5 Side Vault

Setup Shoring for Lid - 5 Side Vault

Form and Pour Lid - 5 Side Vault

Form and Pour Equipment Pads

Set Electrical Equipment

Set Mechanical and Storm Drain Equipment

Install Pumps

Install Electrical

Install Waterproofing

Backfill- 5 Side Vault

Pull Wire and Terminate Electrical

Connect Pumps

Test and Energize Equipment

Excavate Footing for Wall (Continue from 9A-A)

Install Footing for Wall

Form and Pour Wall

Install Security Fencing

Install Devices and Pull Wire for Lights and Security

Form and Pour Curbs

Form and Pour Sidewalks

Pave Area

Paint Parking Striping

Data Date: 11-11-25 Print Date: 03-04-26 09:23

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P9B2-CON-450 Paint and Coatings 01-28-27 02-03-27

P9B2-CON-430 Install Landscaping 02-03-27 02-09-27

P9B2-CON-440 Remove Construction Fencing and Barriers 02-09-27 02-12-27

Phase 10Phase 10 11-17-26 02-10-27

P10-CON-100 Call 811 and Markout Utilities 11-17-26 11-19-26

P10-CON-110 Setup Construction Fencing and Barriers 11-19-26 11-20-26

P10-CON-120 Setup Temporary Access 11-19-26 11-20-26

P10-CON-130 Setup SWPPP 11-20-26 11-21-26

P10-CON-140 Clear and Grub 11-21-26 11-24-26

P10-CON-150 Cap Off Utilities and Irrigation Lines 11-24-26 11-25-26

P10-CON-160 Demo Existing Sidewalk 11-25-26 12-01-26

P10-CON-170 Excavate and Remove Storm Drain Pipes and Basin 12-01-26 12-07-26

P10-CON-180 Start Dewatering 12-01-26 12-03-26

P10-CON-190 Rough Grade 12-07-26 12-10-26

P10-CON-200 Install New Storm Drainage Lines and Basins 12-10-26 12-17-26

P10-CON-210 Trench for Electrical 12-10-26 12-12-26

P10-CON-220 Install Footing for Wall 12-10-26 12-19-26

P10-CON-230 Install Underground Electrical Conduit 12-12-26 12-17-26

P10-CON-240 Backfill Electrical Trench 12-17-26 12-19-26

P10-CON-250 Fine Grade and Build Berm 12-19-26 12-28-26

P10-CON-260 Form and Pour Wall 12-19-26 12-26-26

P10-CON-270 Form and Pour Curbs 12-26-26 01-14-27

P10-CON-280 Install Irrigatiion Mains 12-28-26 01-02-27

P10-CON-290 Form and Pour Sidewalk 01-02-27 01-12-27

P10-CON-310 Install Landscaping 01-12-27 01-21-27

P10-CON-300 Set Lightpoles Bases, Light Poles and Bollards 01-14-27 01-23-27

P10-CON-330 Install Irrigation Branches 01-21-27 01-26-27

P10-CON-340 Install Security Fencing and Gates 01-21-27 01-30-27

P10-CON-320 Place AC Pavement 01-23-27 02-02-27

P10-CON-350 Paint Parking Striping 02-02-27 02-04-27

P10-CON-360 Pull Wire and Makeup for Lights and Security 02-02-27 02-09-27

P10-CON-380 Paint and Coatings 02-02-27 02-08-27

P10-CON-370 Remove Construction Fencing and Barriers 02-09-27 02-10-27

FEMA CloseoutFEMA Closeout 02-12-27 03-26-27

CLOS-CON-100 Final Billings 02-12-27 02-26-27

CLOS-CON-120 Closeout Documentation 02-12-27 03-26-27

CLOS-CON-110 Reimbursement Request 02-26-27 03-19-27

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2026 2027

Paint and Coatings

Install Landscaping

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Cap Off Utilities and Irrigation Lines

Demo Existing Sidewalk

Excavate and Remove Storm Drain Pipes and Basin

Start Dewatering

Rough Grade

Install New Storm Drainage Lines and Basins

Trench for Electrical

Install Footing for Wall

Install Underground Electrical Conduit

Backfill Electrical Trench

Fine Grade and Build Berm

Form and Pour Wall

Form and Pour Curbs

Install Irrigatiion Mains

Form and Pour Sidewalk

Install Landscaping

Set Lightpoles Bases, Light Poles and Bollards

Install Irrigation Branches

Install Security Fencing and Gates

Place AC Pavement

Paint Parking Striping

Pull Wire and Makeup for Lights and Security

Paint and Coatings

Remove Construction Fencing and Barriers

Final Billings

Closeout Documentation

Reimbursement Request

Data Date: 11-11-25 Print Date: 03-04-26 09:23

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort