2025-12-08 Indy CRWL Project Manual.pdf

PDF 5 MB Posted

Attached to
PN2023-13 City of Independence Corvallis Road Waterline
Solicitation number
S-K12730-00015199
Issued by
Multnomah County, Oregon

About this file

This is a Project Manual for the City of Independence's Corvallis Road Waterline Improvements project (PN: 2023-13), prepared by Keller Associates under Oregon Buys listing S-K12730-00015199. The project involves construction of approximately 2,175 feet of 12-inch diameter waterline installation, including potable water services, fire hydrants, valves, and necessary fittings. Major work components include abandonment of two existing waterlines, earthwork and excavation, backfill placement with native and imported materials, paving and surface repair, sidewalk reconstruction, and disinfection and pressure testing of installed water lines. The contract is structured as a unit price contract with mobilization costs not exceeding 5 percent of the contract amount, temporary erosion and sediment control paid as a lump sum with milestone-based payments, and various line items for pipe installation, fittings, hydrants, valves, and restoration work. The contractor must submit a detailed construction schedule within 60 days of the Notice to Proceed, with 2 percent of the total contract price retained until the original CPM schedule submittal is completed. A total of 15 days' time extension is allowed for temporary poor weather or other foreseeable delays, provided the contractor documents each delay within seven calendar days.

Pricing terms are based on unit prices for specific materials and services as listed in the bid schedule, with payment processed through monthly progress applications. The contractor is required to comply with State Prevailing Wage Rates per ORS 279C.800 to 279C.870 and must obtain all necessary permits including building, electrical, plumbing, and NPDES construction permits at no additional cost to the owner. The contractor shall hire an independent testing laboratory at their expense to perform quality control tests on earthwork, trench backfill, asphalt pavement, and concrete. All materials and equipment must comply with current applicable codes and standards, including NSF/ANSI certifications for potable water system components. The project requires comprehensive submittals including shop drawings, product data, construction schedules, and as-built record drawings, with the engineer's standard review period being 14 days. A preconstruction conference must be convened to establish working procedures, and bi-weekly progress meetings will be held throughout construction. Final completion includes substantial completion review, closeout procedures, and a one-year maintenance guarantee period for seeded areas.

View the file

Other files

File Type Posted
10.Exhibit 13.pdf PDF
2025-12-08 Indy CRWL Bid Documents.pdf PDF
11.Exhibit 14.pdf PDF
08.Exhibit 5.pdf PDF
07.Exhibit 1.pdf PDF
ADD 04 R1.pdf PDF
Signed Notice of Intent.pdf PDF
2026JAN07 CRWL ADD03.pdf PDF
CORV RD WATERLINE 2025-12-08 BID SET.pdf PDF
2026JAN06 CRWL ADD02~1.pdf PDF
02.Section G.pdf PDF
01.Section F.pdf PDF
09.Exhibit 12.pdf PDF
2025DEC19 CRWL ADDENDUM 01.pdf PDF
06.Section P.pdf PDF
03.Section H.pdf PDF
Independence-3-01 GTES Report 013024.pdf PDF
04.Section I.pdf PDF
05.Section K.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

FOR THE:

City of Independence Corvallis Road Waterline

PN: 2023-13

Oregon Buys: S-K12730-00015199

Professional of Record Certification:

Seal w/signature

I certify that the Special Provision Section(s) listed below are applicable to the design for the Corvallis Road Waterline Improvements. Special Provisions were prepared by me or under my supervision.

All Sections.

FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST

City of Independence, Corvallis Road Waterline Improvements

Keller Project: 223055-007

TOC-1

Table of Contents Technical Specifications (Project Manual)

ENGINEER OF RECORD SIGNATURE SHEETS

DIVISION 01 – GENERAL REQUIREMENTS

PROFESSIONAL OF RECORD CERTIFICATION

SECTION 01 11 00 – SUMMARY OF WORK

SECTION 01 14 13 – ACCESS TO SITE

SECTION 01 22 00 – UNIT PRICE MEASUREMENT AND PAYMENT

SECTION 01 25 13 – PRODUCT SUBSTITUTION PROCEDURES

SECTION 01 29 00 – PAYMENT PROCEDURES

SECTION 01 31 19 – PROJECT MEETINGS

SECTION 01 32 16 – CONSTRUCTION PROGRESS SCHEDULE

SECTION 01 33 00 – SUBMITTAL PROCEDURES

SECTION 01 45 00 – QUALITY CONTROL

SECTION 01 57 23 – TEMPORARY EROSION AND SEDIMENT CONTROL

SECTION 01 71 13 – MOBILIZATION

SECTION 01 71 23.16 – CONSTRUCTION SURVEYING

SECTION 01 71 33 – PROTECTION OF ADJACENT CONSTRUCTION

SECTION 01 74 30 – SITE PRESSURE PIPE TESTING AND DISINFECTION

SECTION 01 77 00 – CLOSEOUT PROCEDURES

DIVISION 02 – EXISTING CONDITIONS

SECTION 02 41 00 – DEMOLITION

SECTION 02 41 00.01 – PIPELINE REMOVAL

SECTION 02 41 00.02 – PIPELINE ABANDONMENT

SECTION 02 41 13.13 – PAVING REMOVAL

DIVISION 31 – EARTHWORK

SECTION 31 00 00 – EARTHWORK

SECTION 31 05 19.13 – GEOTEXTILES FOR EARTHWORK

SECTION 31 11 00 – CLEARING AND GRUBBING

SECTION 31 23 33 – TRENCHING AND BACKFILLING

SECTION 31 23 33.33 – FLOWABLE FILL

SECTION 31 40 00 – SHORING

DIVISION 32 – EXTERIOR IMPROVEMENTS

SECTION 32 12 16.01 – TRENCH RESURFACING

SECTION 32 13 13 – CONCRETE FOR EXTERIOR IMPROVEMENTS

SECTION 32 91 13 – SEEDING

TOC-2

DIVISION 40 – PROCESS INTERCONNECTIONS

SECTION 40 05 00 – PIPING, GENERAL

SECTION 40 05 19 – DUCTILE IRON PIPE AND FITTINGS

SECTION 40 05 31 – PVC PROCESS AND YARD PIPING

SECTION 40 05 51 – VALVES, GENERAL

SECTION 40 05 57 – ACTUATORS FOR PROCESS VALVES AND GATES

SECTION 40 05 61 – GATE VALVES

SECTION 40 05 54 – BUTTERFLY VALVES

SECTION 40 05 81.13 – FIRE HYDRANTS

SUMMARY OF WORK 01 11 00 - 1

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 WORK INCLUDED

A. The Work to be performed under this Contract shall consist of furnishing plant, tools, equipment, materials, supplies, and manufactured articles, and furnishing all labor, transportation, and services, including fuel, power, water, temporary dewatering, and essential communications, and performing all work or other operations required for the fulfillment of the Contract in strict accordance with the Contract Documents. The Work shall be complete, and all work, materials, and services not expressly indicated or called for in the Contract Documents which may be necessary for the complete and proper construction of the Work in good faith shall be provided by the Contractor as though originally so indicated, at no increase in cost to the Owner. The Contractor shall provide all materials and equipment required for construction.

B. The Contractor is responsible for following the provisions of these Contract Documents, including but not limited to: the following of Plans and Specifications; the timely, complete, and accurate submittal of shop drawings; the work of and correlation with thier subcontractors and suppliers, timely performance of the Contract, and timely payment of suppliers and subcontractors. Nothing stated in the Contract Documents or Specifications shall be construed to relieve the Contractor of these basic responsibilities.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Overview: The Work compromises construction of the Corvallis Road Waterline

Improvements (PN 2023-13) which generally consists the installation of 2,175 feet of 12 inch diameter waterline, asphalt pavement repair, reconstruction of demolished sidewalks, water service connections (complete), hydrants, valves, paving, and all labor, Equipment, Materials, and incidentals necessary to complete the Work as specified.

B. Project Elements – The major project elements of the Corvallis Road Waterline

Improvements project are generally described below:

1. The abandonment of two existing waterlines.

2. Installation of new waterline.

3. Installation of potable water services, fire hydrants, valves, and necessary fittings as shown on the plans.

4. Earthwork and excavation for waterline installation.

5. Placement of all backfill, including native and imported materials.

6. Paving and surface repair, including reconstruction of removed sidewalks, for waterline installation.

SUMMARY OF WORK 01 11 00 - 2

7. Disinfection and pressure testing of installed water lines.

8. All Labor, Materials, and Incidentals required to complete the Work as shown or directed.

1.3 CONTRACT METHOD

A. The Work hereunder will be constructed under a unit price contract.

1.4 WORK BY OTHERS

A. The Contractor’s attention is directed to the fact that work will be conducted at the site by the City staff during the performance of the Work under this Contract. The Contractor shall conduct its operations so as to cause a minimum of interference with the Work of the plant staff.

B. Interference with Work on Utilities: The Contractor shall cooperate fully with all utility forces of the Owner or forces of other public or private agencies engaged in the construction, relocation, alteration, or otherwise rearranging of any facilities that interfere with the progress of the Work, and shall schedule the Work so as to minimize interference with said construction.

1.5 CONSTRUCTION PROGRESS SCHEDULE

A. Work under the contract shall be scheduled and performed in such a manner as to result in the least possible disruption to the operation of the existing treatment facilities. Contractor shall not operate any existing valves, pumps, or motors. The Contractor shall submit to the

Engineer a construction schedule covering the entire work before any work is commenced.

The schedule shall be as described in Section 01 33 00, complete with estimated dates for start and finish of each item of work. The construction constraints are as described in

Section 01 35 13. The construction sequences described therein are suggested methods to accomplish the work. The Contractor shall remain responsible for the successful completion of all work.

B. To minimize the period of disruption of water system operation, all new piping and/or facilities should be constructed, and all preparations should be made for fast connection to existing piping and facilities.

C. Submit preliminary construction progress schedules as required in the General Conditions within ten (10) days after the award of the contract. The progress schedule is to be in reproducible form and subject to the approval of the Engineer.

D. Commence work on or before a date to be specified in a written "Notice to Proceed" and complete all phases of the work as specified in the Agreement.

E. The time is computed on a calendar basis, and a total of 15 days’ time extension will be allowed for temporary poor weather or other foreseeable delays, provided that the

Contractor documents each delay within seven (7) calendar days. Contractor acknowledges that construction during the winter will require cold-weather construction methods.

SUMMARY OF WORK 01 11 00 - 3

F. Refer to 01 32 16 – Construction Progress Schedule for additional information.

1.6 PUBLIC WORKS CONTRACTOR’S LICENSE

A. Any Contractor, Subcontractor, or Specialty Contractor is required to have a current license as a Public Works Contractor in the State where the work is to be completed in order to submit a bid or proposal on this contract.

1.7 CODES AND STANDARDS

A. Where codes and standards are referred to, they are the current approved codes. It is the duty of the Contractor to obtain from its supplier any material for this work and to submit evidence, if requested, that provided material is in compliance with the applicable codes and standards.

1.8 FEDERAL, STATE, AND LOCAL LAWS

A. Conform to all applicable State and local laws in carrying out obligations under the contract.

B. Meet the requirements and recommendations of the Manual of Accident Prevention in

Construction; Associated General Contractors of America, Inc., and the Occupational

Safety and Health Act.

1.9 PRODUCT SUBSTITUTIONS

A. Use equipment and materials specified by name in these Specifications or on Plans.

Alternate equipment must be approved in accordance with the bidding documents. If alternate equipment is approved, an addendum will be issued prior to the bid to receive consideration. Alternative equipment suppliers shall be reviewed after bid opening during the shop drawing review process as outlined in Section 01 33 00 – Submittal Procedures.

B. Request approval for substitutions by submitting written evidence and convincing Engineer of equality of item and suitability for the service and/or construction conditions anticipated.

C. If alternative equipment or materials are approved, make required changes in structures, piping, systems, etc., necessary to accommodate alternate items without additional cost to the Owner except as specifically noted for Owner-furnished materials.

1.10 PERMITS

A. The Contractor shall be responsible for obtaining and paying for all construction and inspection permits as required by the State of Oregon, Polk County, and the City of

Independence. This includes but is not limited to building, electrical, and plumbing permits.

B. A 1200-C National Pollutant Discharge Permit (NPDES) from the Oregon Department of

Environmental Quality (DEQ) is not anticipated for this project if typical construction means and methods are employed. The Contractor shall be responsible for obtaining and paying for a 1200-C permit and all compliance duties associated with the 1200-C NPDES

SUMMARY OF WORK 01 11 00 - 4

permit. Erosion and sediment control best management practices, as shown on the Contract

Documents, must be installed regardless of whether a permit from Oregon DEQ is required or not.

1.11 WAGE RATES

A. All Contractors and subcontractors performing work on the project shall comply with State

Prevailing Wage Rates (ORS 279C.800 to 279C.870) or Davis-Bacon wage rates as applicable to the project.

PART 2 - PRODUCTS NOT USED

PART 3 - EXECUTION NOT USED

END OF SECTION 01 11 00

ACCESS TO SITE 01 14 13 - 1

SECTION 01 14 13 - ACCESS TO SITE

PART 1 - GENERAL

1.1 WORK INCLUDED

A. The Contractor shall make its own investigation of the condition of available public and private roads and of clearances, restrictions, bridge load limits, and other limitations affecting transportation and ingress and egress to the site of the Work. It shall be the

Contractor's responsibility to construct and maintain any haul roads required for its construction operations.

1.2 TEMPORARY CROSSINGS

A. General: Continuous, unobstructed, safe, and adequate pedestrian and vehicular access shall be provided to fire hydrants, commercial and industrial establishments, churches, schools, parking lots, service stations, motels, fire and police stations, and hospitals. Safe and adequate public transportation stops and pedestrian crossings at intervals not exceeding

300 feet shall be provided. The Contractor shall cooperate with parties involved in the delivery of mail and removal of trash and garbage so as to maintain existing schedules for such services. Vehicular access to residential driveways shall be maintained to the property line except when necessary construction precludes such access for reasonable periods of time.

B. Temporary Bridges or Steel Plates: Wherever necessary, to maintain vehicular crossings, the Contractor shall provide suitable temporary bridges or steel plates over unfilled excavations, except in such cases as the Contractor shall secure the written consent of the responsible individuals or authorities to omit such temporary bridges or steel plates, which written consent shall be delivered to the Engineer prior to excavation. All such bridges or steel plates shall be maintained in service until access is provided across the backfilled excavation. Temporary bridges or steel plates for street and highway crossing shall conform to the requirements of the authority having jurisdiction in each case, and the

Contractor shall adopt designs furnished by said authority for such bridges or steel plates, or shall submit designs to said authority for approval, as may be required.

C. Street Use: Nothing herein shall be construed to entitle the Contractor to the exclusive use of any public street, alleyway, or parking area during the performance of the Work hereunder, and it shall conduct its operations to not interfere unnecessarily with the authorized work of utility companies or other agencies in such streets, alleyways, or parking areas. No street shall be closed to the public without first obtaining permission of the Engineer and proper governmental authority. Where excavation is being performed in primary streets or highways, one lane in each direction shall be kept open to traffic at all times unless otherwise indicated. Toe boards shall be provided to retain excavated material if required by the Engineer or the agency having jurisdiction over the street or highway.

Fire hydrants on or adjacent to the Work shall be kept accessible to fire-fighting equipment at all times. Temporary provisions shall be made by the Contractor to assure the use of sidewalks and the proper functioning of all gutters, storm drain inlets, and other drainage

ACCESS TO SITE 01 14 13 - 2

facilities.

1.3 CONTRACTOR'S WORK AND STORAGE AREA

A. The Contractor shall identify a location for storage and shop area for its construction operations of the Work. At completion of Work, the Contractor shall return this area to its original condition, including grading and landscaping.

B. The Contractor shall be responsible for conducting their Work so there is the least possible interference with or hazard to the traveling public or the affected community.

C. The Contractor shall make its own arrangements for any necessary off-Site storage or shop areas necessary for the proper execution of the Work.

D. The Contractor shall construct and use a separate storage area for hazardous materials used in constructing the Work as specified in Section 01 57 23.

1. For the purpose of this paragraph, hazardous materials to be stored in the separate area are all products labeled with any of the following terms: Warning, Caution, Poisonous, Toxic, Flammable, Corrosive, Reactive, or Explosive. In addition, whether or not so labeled, the following materials shall be stored in the separate area: diesel fuel, gasoline, new and used motor oil, hydraulic fluid, cement, paints and paint thinners, two-part epoxy coatings, sealants, asphaltic products, glues, solvents, wood preservatives, sand blast materials, and spill absorbent.

2. Hazardous materials shall be stored in groupings according to the Material Safety

Data Sheets.

3. The Contractor shall develop and submit to the Engineer a plan for storing and disposing of the materials above.

4. The Contractor shall obtain and submit to the Engineer a single EPA number for wastes generated at the Site.

5. The separate storage area shall meet all the requirements of all authorities having jurisdiction over the storage of hazardous materials.

6. The separate storage area shall be inspected by the local Fire Chief prior to construction of the area, upon completion of construction of the area, and upon cleanup and removal of the area.

7. All hazardous materials that are delivered in containers shall be stored in the original containers until use. Hazardous materials that are delivered in bulk shall be stored in containers that meet the requirements of authorities having jurisdiction.

1.4 PARKING

A. The Contractor shall:

ACCESS TO SITE 01 14 13 - 3

1. Provide temporary parking areas for its employees and construction equipment.

2. The Contractor shall direct its employees to park in areas indicated.

3. Traffic and parking areas shall be maintained in a sound condition, free of excavated material, construction equipment, mud, and construction materials. The

Contractor shall repair breaks, potholes, low areas that collect standing water, and other deficiencies.

PART 2 - PRODUCTS NOT USED

END OF SECTION 01 14 13

UNIT PRICE MEASUREMENT AND PAYMENT 01 22 00 - 1

SECTION 01 22 00 - UNIT PRICE MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 WORK INCLUDED

A. Measurement and payment will be made as specified in this Section and in accordance with the provisions of the General Conditions.

B. This Specification covers all measurement and payment for the Work.

PART 2 - PRODUCTS NOT USED

PART 3 - EXECUTION

3.1 INCIDENTAL WORK

A. All Work not specifically identified in this Section shall be considered incidental to other items; no special payment will be given for incidental work.

B. The Contractor may choose to install imported trench backfill material instead of using the excavated trench material. Imported trench backfill material shall meet the Unified Soil

Classification of GW, GP, GM, GC, SW, SM, or SC. The Owner will not pay extra for any imported trench backfill material. The Contractor is advised to review the geotechnical report and become familiar with the soils in the area.

C. The Contractor shall install trench backfill using crushed rock base where specified in the plans.

D. Prior to performing any demolition work, the area to be demolished shall be measured and agreed upon by the Engineer and Contractor. If demolition occurs prior to this measurement and agreement with the Engineer, the Engineer will measure only the area that, in the opinion of the Engineer, should have been the limits of demolition. Repairs to areas outside of these demolition limits, as determined by the Engineer, shall be replaced or reconstructed at no cost to the Owner.

3.2 BASE BID PAY ITEMS

A. Mobilization

1. Paid by the lump sum, not to exceed five (5) percent of the contract amount.

2. Not more than sixty percent of the amount bid for mobilization will be paid on the first monthly progress payment, provided that the contractor has initiated productive work on the project.

UNIT PRICE MEASUREMENT AND PAYMENT 01 22 00 - 2

3. Up to forty percent of the amount bid for mobilization will be paid on the second monthly progress payment, provided that the contractor has initiated productive work on the project.

4. The Contractor's attention is directed to the condition that two (2) percent of the total Contract Price will be deducted from any money due the Contractor as progress payments until all mobilization items listed above have been completed as specified. The aforementioned amount will be retained by the Owner as the agreed estimated value of completing all of the mobilization items listed. Any such retention of money for failure to complete all such mobilization items as a lump-sum item shall be in addition to the retention of any payments due to the Contractor as specified in Article 6 of the Agreement Form or Article 15 of the General

Conditions of the Contract.

5. Includes cost of bonds, mobilization, demobilization, submittal costs, schedule preparation, temporary facilities, and any other costs associated with project setup and mobilization that are not specifically identified under other bid items.

B. Temporary Erosion and Sediment Control

1. Paid by the lump sum.

2. Partial payments will be made as follows:

When the initial Contractor developed ESCP, narrative, and schedule are complete and accepted, and the initial erosion control devices are installed

25%

When 50 percent of the Contract is complete, excluding advances on Materials

25%

When 75 percent of the Contract is complete, excluding advances on Materials

25%

At completion of the Work covered by this section 25%

3. Includes all labor, those erosion and sediment materials not specifically included in the Schedule of Values, equipment, and incidentals for permitting (i.e., permit application and renewal fees), inspecting, reporting, maintaining, and removing erosion sediment control devices in conformance with Section 01 57 23 – Temporary Erosion and Sediment Control.

C. Clearing and Grubbing & Removal of Obstructions

1. Paid by a lump sum.

2. Includes all permitting costs, labor, materials, and equipment required to clear, grub, or remove existing surfaces within the limits of the pipeline replacement as shown on the Contract Plans and all other items incidental thereto.

UNIT PRICE MEASUREMENT AND PAYMENT 01 22 00 - 3

D. Traffic Control, Complete

1. Paid by the lump sum.

2. Includes all permitting costs, labor, materials, and equipment required to provide temporary construction traffic control as specified and all other items incidental thereto.

E. Construction Surveying

1. Paid by the lump sum.

2. Includes all labor, materials, and equipment required to layout and stake proposed improvements, replacement of any survey monuments as specified and all other items incidental thereto in conformance with 01 71 23.16 - Construction

Surveying. Also includes as-built survey of storm structure locations and pipe inverts.

F. Water Service Line, Complete

1. Paid by each.

a. 1-inch diameter

b. 2-inch diameter

2. Pays for the complete installation of specified diameter water service lines.

3. Includes all labor, materials, equipment, and incidentals for installation of the water service, including asphalt or concrete pavement saw cutting, surfacing removal, removal of surfacing, bedding, utility crossings and parallel support/shoring, bedding and backfill, disinfection, pipe testing, resurfacing, piping identification tape, tracer wire, pipe anchors, and all other appurtenances or incidentals not itemized in the bid schedule.

G. C900 PVC Water Main, Restrained, with Class B Backfill, Complete

1. Paid by the linear foot of pipe of each pipe diameter, measured along the horizontal centerline of installed pipe.

a. 6-inch, 8-inch, and 12-inch diameter pipe

2. Pays for the complete installation of a DR18 C900 Polyvinyl Chloride (PVC) water pipe.

3. Includes all labor, materials, equipment, and incidentals for installation of the pipe, including asphalt or concrete pavement saw cutting, surfacing removal, bedding, utility crossings and parallel support/shoring, bedding and backfill, disinfection, pipe testing, resurfacing, piping identification tape, tracer wire, pipe thrust block, anchors or restraints, and all other appurtenances or incidentals not itemized in the bid schedule.

UNIT PRICE MEASUREMENT AND PAYMENT 01 22 00 - 4

H. Water Main Fitting (Bends, Elbows, Tees, Crosses, Reducers, Caps, Blind Flanges, etc.), Complete

1. Paid by each by pipe diameter.

a. Includes 2, 6, 8, 10, and 12-inch diameter fittings

2. Includes all labor, materials, equipment, and incidentals for installation of the fitting, including asphalt or concrete pavement saw cutting, surfacing removal, excavation, shoring, fitting, connections, thrust blocks, restraint, cleaning, disinfection, testing, bedding, backfill, and all other appurtenances or incidentals not itemized in the bid schedule.

3. Includes providing polywrap corrosion protection sleeves or coatings and repair of such items if damaged during transportation or installation.

I. Fire Hydrant Assemblies, Complete

1. Paid by each.

2. Includes all labor, materials, equipment, and incidentals for installing the hydrant, including the hydrant, valve, pipe, bollards, thrust blocks, restraint, fittings, valve boxes, connections, drain rock, filter fabric, spare parts, saw cutting, surfacing removal, excavation, shoring, bedding, backfilling, testing, and all other appurtenances or incidentals not itemized in the bid schedule.

J. 2-inch Diameter Temporary Blowoff, Complete

1. Paid by each.

2. Includes all labor, materials, equipment, and incidentals for installing the blowoff, including the blowoff, valve, pipe, thrust blocks, restraint, fittings, valve boxes, connections, drain rock, filter fabric, spare parts, saw cutting, surfacing removal, excavation, shoring, bedding, backfilling, testing, and all other appurtenances or incidentals not itemized in the bid schedule.

K. 12-inch Butterfly Valve, Complete

1. Paid by each.

2. Includes all labor, materials, equipment, and incidentals for installing the valve, including the valve, fittings, valve boxes, connections, asphalt or concrete pavement saw cutting, surfacing removal, excavation, shoring, bedding, backfilling, testing, operators (manual actuators), and all other appurtenances or incidentals not itemized in the bid schedule.

3. Includes providing polywrap corrosion protection sleeves or coatings and repair of such items if damaged during transportation or installation.

L. Gate Valve, Complete

UNIT PRICE MEASUREMENT AND PAYMENT 01 22 00 - 5

1. Paid by each.

a. 6-, 8-, and 10-inch diameter.

2. Includes all labor, materials, equipment, and incidentals for installing the valve, including the valve, fittings, valve boxes, connections, asphalt or concrete pavement saw cutting, surfacing removal, excavation, shoring, bedding, backfilling, testing, manual actuators, and all other appurtenances or incidentals not itemized in the bid schedule.

3. Includes providing polywrap corrosion protection sleeves or coatings and repair of such items if damaged during transportation or installation.

M. Trench Resurfacing

1. Either gravel or asphalt pavement.

2. Paid by square yard of surfacing restored, measured along the horizontal centerline of pipe and City standard trench width from edge to edge of the surface replaced.

3. Includes all labor, materials, and equipment necessary to restore surfaces after pipeline installation is complete and tested, and all other miscellaneous work or materials not itemized in the bid schedule.

N. Native Surface Restoration

1. Paid by square yard of surfacing restored, measured along the horizontal centerline of pipe and City standard trench width.

2. Includes all labor, materials, and equipment to restore disturbed areas within the right-of-way, consisting of landscaping or any other surface other than concrete sidewalks or pavement. Also includes all other miscellaneous work or materials not itemized in the bid schedule.

O. Concrete Sidewalk, includes curb and gutter, excavation, and base aggregate, Complete

1. Paid by square yard of concrete sidewalk restored.

2. Includes all labor, materials, and equipment necessary to restore concrete sidewalks, curbs, and gutters after pipeline installation is complete and tested, as well as all other miscellaneous work or materials not itemized in the bid schedule.

P. Pipeline Abandonment or Removal

1. Paid by the lump sum.

2. Includes all labor, materials, surface restoration, equipment, and incidentals required to abandon existing pipes using controlled low-strength material plugs, or to remove existing pipes, as necessary for the completion of the Work, and all other miscellaneous Work or materials not itemized in the bid schedule.

UNIT PRICE MEASUREMENT AND PAYMENT 01 22 00 - 6

Q. Bollards, Complete

1. Paid by the lump sum.

2. Includes all labor, materials, surface restoration, equipment, and incidentals required to install concrete-filled bollards as necessary for the completion of the

Work, and all other miscellaneous Work or materials not itemized in the bid schedule.

R. As-Built Record Drawings

1. Paid by a lump sum.

2. Includes all labor, materials, equipment, and incidentals required to maintain a hard-copy set of as-built record drawings clearly documenting approved changes and deviations from the Contract Documents. The As-Built Record Drawings will be submitted to the Owner for review with applications for payment at 50%, substantial completion, and Substantial Completion.

3. Partial payments will be made as follows:

When 50 percent of the Contract is complete, excluding advances on Materials

25%

When 75 percent of the Contract is complete, excluding advances on Materials

25%

At Substantial Completion 50%

3.3 FIXED PRICE BID ITEMS

A. Administrative Reserve

1. This is a time and materials charge account available to the Owner to be used to reimburse the Contractor for Work not identified or implied in the Contract

Documents. Refer to Section 01 35 14 – Administrative Reserve.

END OF SECTION 01 22 00

PRODUCT SUBSTITUTION PROCEDURES 01 25 13 - 1

SECTION 01 25 13 - PRODUCT SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 WORK INCLUDED

A. This document describes the requirements for submission of product information and procedures for consideration of substitutions by Owner, including products proposed to be used by Contractor under "or equal" or "acceptable alternate" provisions.

B. Where equipment, materials or process have been specifically named, it is the intention of the Engineer to use these items. If a Contractor desires to have an alternate considered, they are to provide the following information. It will be the responsibility of the Contractor to convince the Engineer that the alternate materials are equal and will perform the intended function at or above that of the specified equipment. The burden of proof is on the

Contractor to convince the Engineer that the product is equal for the purpose of a particular function.

C. Substitution or Alternative Product Options: The alternative materials shall be submitted to Engineer no less than 10 business days before the bid opening. Engineer shall evaluate the materials, and if Engineer approves the substitution, an addendum shall be issued allowing the equipment alternatives.

1.2 DEFINITIONS

A. The word “Products,” as used herein, is defined to include purchased items form incorporation into the work, regardless of whether specifically purchased for the project or taken from Contractor’s stock of previously purchased products. The word “Materials,” is defined as products which must be substantially cut, shaped, worked, mixed, finished, refined, or otherwise fabricated, processed, installed, or applied to form units of work. The word “Equipment” is defined as products with operation parts, regardless of whether motorized or manually operated, and particularly including products with service connections (wiring, piping, and other like items). Definitions in this paragraph are not intended to negate the meaning of other terms used in the Contract Documents, including

“specialties”, “system”, “structure”, “finishes”, “accessories”, “furnishings”, “special construction”, and similar items, which are self-explanatory and have recognized meanings in the construction industry.

B. Neither “Products” nor “Materials” nor “Equipment” includes machinery and equipment used for preparation, fabrication, conveying and erection of the Goods.

1.3 CONTRACTOR’S OPTIONS

A. For products specified only by reference standards, select any product meeting standards, by any manufacturer.

B. For products specified by naming several products or manufacturers, select any product and manufacturer named.

PRODUCT SUBSTITUTION PROCEDURES 01 25 13 - 2

C. For products specified by naming one or more products, but indicating the option of selecting equivalent products by stating "or equal" or "acceptable alternate" after specified product, Contractor must submit request, as required for substitution, for any product not specifically named.

1. “Or-Equal” Items: if in the Engineer’s sole judgment an item of material or equipment proposed by Contractor is functionally equal to that named and sufficiently similar so that no change in related work will be required, it may be considered by the Engineer as an “or-equal” item, in which case review and approval of the proposed item may in the Engineer’s sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. For the purpose of the paragraph, a proposed item of material or equipment will be considered functionally equal to an item so named if:

a. It is at least equal in quality, durability, appearance, strength and design characteristics.

b. It will reliably perform at least equally well the function imposed by the design concept of the complete project as a functioning whole;

c. There is no increase in cost to the Owner, and

d. It will conform to the detailed requirements of the item named in the

Contract Documents.

D. For products specified by name, brand, model, etc., the Contractor shall provide information as required below for the Engineer to review and determine under their sole discretion that the product is acceptable.

1.4 SUBSTITUTIONS

A. If in the Engineer’s sole judgment an item of material or equipment proposed by Contractor does not qualify as an “or-equal” item, it will be considered a proposed substitute item and subject to the review process.

B. If Contractor wishes to furnish or use a substitute item of material or equipment, Contractor shall first make written application to the Engineer for review of a proposed substitute item of material or equipment. The application shall certify that the proposed substitute will adequately perform the function and achieve the results called for by the general design, be similar in substance to the specified and be suited to the same use that is specified.

C. The procedure for review by the Engineer will include the following:

1. If the Contractor wishes to provide a substitution item, the Contractor shall make written application to the Engineer.

2. Unless otherwise provided by law or authorized in writing by the Engineer, the request shall be submitted within a 35-day period after award of the Contract.

PRODUCT SUBSTITUTION PROCEDURES 01 25 13 - 3

3. Wherever a proposed substitution item has not been submitted within said 35-day period, or wherever the submission of a proposed substitution material or equipment has been judged to be unacceptable by the Engineer, the Contractor shall provide the material or equipment indicated in the Contract Documents.

4. The Engineer will evaluate each proposed substitution within a reasonable period of time.

5. As applicable, no shop drawing submittals shall be made for a substitution item nor shall any substitution item be ordered, installed, or utilized without the

Engineer’s prior written acceptance of the Contractor’s request.

6. The Engineer will record the time required by the Engineer in evaluating substitutions proposed by the Contractor and in making changes by the Contractor in Contract Documents occasioned thereby.

D. Contractor shall submit sufficient information as provided below to allow the Engineer to determine that the item of material or equipment proposed is essentially equivalent to that named and therefore an acceptable substitute, therefore. Requests for review of proposed substitute items of materials or equipment will not be accepted by the Engineer from anyone other than the Contractor. Include the following minimum information in the application:

1. The Contractor shall certify that the proposed substitution will perform adequately the functions and achieve the results called for by the general design and be similar and of equal substance to that indicated and be suited to the same use as the specified.

2. For products:

a. Product identification, including manufacturer's name and address.

b. Manufacturer's literature:

1) Product description

2) Performance and test data

3) Reference standards

3. Samples.

4. Name and address of similar projects on which product was used and date of installation.

5. All variations of the proposed substitute item for the specified shall be identified in the application and available engineering, sales, maintenance, repair and replacement service shall be indicated.

6. The application shall state the extent, if any, to which the use of the proposed substitute will prejudice Contractor’s achievement of delivery on time, whether or

PRODUCT SUBSTITUTION PROCEDURES 01 25 13 - 4

not use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provision of any other direct contract with

Owner for work on the project) to adapt the design to the proposed substitute item and whether or not incorporation or use of the substitute in connection with the work is subject to payment of any license fee or royalty.

7. Relation to separate contracts.

8. The application shall also contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and claims of other sellers affected by any resulting change, all of which will be considered by the Engineer in evaluating the proposed substitute item.

E. In making request for substitution, Contractor shall:

1. Investigate proposed product or method and determine that it is equal or superior in all respects to that specified.

2. Provide the same guarantee for substitution as for product or method specified.

3. Coordinate installation of accepted substitution into work, making such changes as may be required for work to be complete in all respects.

4. Waive all claims for additional costs related to substitution which consequently become apparent.

5. Ensure cost data is complete and includes all related costs under this contract, but excludes:

a. Costs under separate contracts

b. Engineer's redesign

F. Substitutions will not be considered if:

1. They are indicated or implied on shop drawings or project data submittals without formal request submitted in accord with Paragraph 1.05.

2. Acceptance will require substantial revision of work.

3. Not AIS or BABA compliant.

G. Contractor shall provide all data in support of any proposed substitute or “or-equal” at Contractor’s expense.

PRODUCT SUBSTITUTION PROCEDURES 01 25 13 - 5

PART 2 - PRODUCTS NOT USED

END OF SECTION 01 25 13

PAYMENT PROCEDURES 01 29 00 - 1

SECTION 01 29 00 – PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 WORK INCLUDED

A. Measurement and payment will be made as specified in this Section and in accordance with the provisions of the General Conditions.

B. The Contractor is informed that 2% of the total Contract Price will be deducted from any money due the Contractor as progress payments until the Original CPM Schedule

Submittal outlined in Section 01 32 16 has been completed as specified. The aforementioned amount will be retained by the Owner as agreed, estimated value of completing the original schedule. Any such retention of money for failure to complete all such mobilization items as a lump-sum item shall be in addition to the retention of any payments due to the Contractor as specified in the General Conditions of the Contract.

C. The Contractor is alerted to the provisions in Section 3.1 of Section 01 71 13 regarding payment provisions for Mobilization.

1.2 SCHEDULE OF VALUES

A. The Contractor shall prepare and submit a detailed Schedule of Values to the Engineer within 10 days from the effective date of the Contract. The detailed Schedule of Values shall be based on the values listed in the Bid Schedule. Because the ultimate requirement is to develop a detailed Schedule of Values, sufficient detailed breakdown shall be provided to meet this requirement. The Engineer shall be the sole judge of acceptable numbers, details and description of values established. If, in the opinion of the Engineer, a greater number of Schedule of Values items than proposed by the Contractor is necessary, the

Contractor shall add the additional items so identified by the Engineer.

B. The minimum detail of breakdown of the major Work components is indicated.

1. Mobilization and demobilization 2% of contract time - no breakdown required.

2. Construction schedule.

3. Unit price items listed as Lump Sum-breakdown required.

4. Other Unit price items-no breakdown required.

5. All other Work not specifically included in the above items shall be broken down as necessary for establishment of pay items.

C. The Contractor and Engineer shall meet and jointly review the detailed Schedule of Values within 35 days from the date of Notice to Proceed. The value allocations and extent of detail shall be reviewed to determine any necessary adjustments to the values and to determine if sufficient detail has been proposed. Any adjustments deemed necessary to the

PAYMENT PROCEDURES 01 29 00 - 2

value allocation or level of detail shall be made by the Contractor, and a revised detailed

Schedule of Values shall be submitted within 40 days from the date of Notice to Proceed.

1.3 CHANGES TO SCHEDULE OF VALUES

A. Changes to the schedule of values shall be made to reflect Owner-approved change orders.

B. In the event that the Contractor and Engineer agree to adjust the original Schedule of

Values because of inequities discovered in the original accepted detailed Schedule of

Values, increases and equal decreases to values.

1.4 ADMINISTRATIVE RESERVE

A. This is a contingency item to be paid on a time and materials charge account basis to reimburse the Contractor for work not identified or implied in the contract documents. This bid item is intended to address unanticipated items such as unspecified exploratory excavations, unmarked utilities, unforeseeable subsurface conditions, and conditions that are clearly different than those indicated in the contract documents.

B. The Engineer will provide a Work Change Directive document on the terms for completing the additional work. Within five (5) days after the request from the Engineer, the Contractor shall submit to the Engineer a complete price breakdown of labor, equipment, and materials to complete the additional requested work not included in the contract documents.

C. All work is at the directive of the Engineer. Any work completed without the written authorization of the Owner and the Engineer will be denied payment.

PART 2 - PRODUCTS NOT USED

END OF SECTION 01 29 00

PROJECT MEETINGS 01 31 19 - 1

SECTION 01 31 19 - PROJECT MEETINGS

PART 1 - GENERAL

1.1 WORK INCLUDED

A. Contractor shall attend all Project meetings. Contractor’s representative shall include Supervisor or Superintendent and shall have the required authority to commit the

Contractor to solutions agreed upon. Other Contractor and subcontractor representatives may attend Project meetings as desired.

B. Contractor shall provide all pertinent Work-related reports or documents for each meeting as requested by the Owner.

C. Engineer will record minutes of all meetings and will furnish one (1) copy to the

Contractor. Recipients of copies may make and distribute such other copies as they wish.

D. Contractor shall advise the Engineer of any inaccuracies, discrepancies, objections, or missing items in the minutes within five (5) calendar days of receipt of the minutes.

1.2 PRECONSTRUCTION CONFERENCE

A. A preconstruction conference will be convened to designate responsible personnel, discuss scheduling, shop drawing procedures, pay applications processing, project supervision, coordination, progress reports, payrolls, labor provisions, and to establish a working understanding among the parties as to the Work. The Contractor will be responsible to have all subcontractors and major suppliers represented at the preconstruction meeting.

B. The purpose of the conference is to designate responsible personnel and establish a working relationship. Matters requiring coordination will be discussed and procedures for handling such matters established. The complete agenda will be furnished to the Contractor prior to the meeting date. However, the Contractor should be prepared to discuss all of the items listed below.

1. Status of Contractor’s insurance and bonds.

2. Issuance of Notice to Proceed

3. Contractor’s tentative schedules.

4. Transmittal, review, and distribution of Contractor’s submittals.

5. Processing applications for payment.

6. Maintaining record documents.

7. Critical work sequencing.

PROJECT MEETINGS 01 31 19 - 2

8. Field decisions and Change Orders.

9. Use of Site, office and storage areas, security, housekeeping, and Owner’s needs.

10. Major equipment deliveries and priorities.

11. Contractor’s assignments for safety and first aid.

12. Daily Report Form.

13. Submittal Transmittal Form which the Engineer will furnish.

C. Unless previously submitted to the Engineer, the Contractor shall bring to the conference one copy each of the following:

1. A preliminary schedule of Shop Drawings, Samples, and proposed Substitute or

Equal submittals listed in the Bid.

2. A list of all permits and licenses the Contractor shall obtain indicating the agency required to grant the permit, the expected date of submittal for the permit, and required date for receipt of the permit.

3. A preliminary schedule of values in accordance with the bid schedule.

4. A 60-day plan of operation in accordance with Section 01 32 16 – Construction

Progress Schedule.

5. Procurement schedule of major equipment and materials and items requiring long-lead time.

D. The Engineer will preside at the preconstruction conference and will arrange for keeping and distributing the minutes to all persons in attendance.

E. The Contractor and its subcontractors should plan on the conference taking no more than

1 full working day.

1.3 PROGRESS MEETINGS

A. The Engineer will arrange and chair bi-weekly progress meetings. These meetings will be held at the project site and held throughout the course of construction. The Contractor is to ensure that an authorized representative, having authority to act for and on behalf of the

Contractor and having full knowledge of the Work and the contract schedule attend the meetings.

B. Representatives of the Contractor's suppliers and subcontractors, and parties providing services for the same, may attend the meeting if the Contractor elects to invite them to assist the Contractor's representatives at the meetings.

C. Relay agenda items to Engineer at least 24 hours prior to meeting.

PROJECT MEETINGS 01 31 19 - 3

D. Suggested Agenda

1. Review of Work progress

2. Field observations, problems, and conflicts

3. Problems that impede construction schedules

4. Review of off-site fabrication and delivery schedules

5. Corrective measure and procedures to regain projected schedules

6. Revisions to construction schedules

7. Plan progress schedules during succeeding work period

8. Coordination of schedules

9. Review submittal schedules, field orders, change orders, RFIs, and pay applications;

expedite as required

10. Maintenance of quality standards

11. Review proposed changes for effect on construction schedules and on completion dates

12. Other business

1.4 OTHER MEETINGS

A. Other meetings will be held from time to time as may be requested by the Owner or

Contractor. Time and place of meeting shall be as mutually agreed upon. Those required to be in attendance at meetings shall be as requested.

B. Other meetings shall also include meetings with regulatory agencies. When requested, the

Contractor shall attend meetings held or required by governmental regulatory agencies having jurisdiction of the Work.

C. Other meetings also include Post-Construction Conference. The Post-Construction

Conference will be held prior to initial acceptance of the Work to discuss and resolve all unsettled matters.

PART 2 - PRODUCTS NOT USED

END OF SECTION 01 31 19

CONSTRUCTION PROGRESS SCHEDULE 01 32 16 - 1

SECTION 01 32 16 - CONSTRUCTION PROGRESS SCHEDULE

PART 1 - GENERAL

1.1 WORK INCLUDED

A. Scheduling of the Work shall be performed by the Contractor in accordance with the requirements of this Section. The purpose of the Construction Schedule is to allow the

Contractor to prepare an orderly plan to aid in the timely completion of the project.

B. Development of the schedule and project status reporting requirements of the Contract shall employ computerized Critical Path Method (CPM) scheduling.

C. The approved Construction Schedule shall be used to plan and execute the Work, to measure the progress of the Work, and to aid in evaluating time extensions.

D. Failure to maintain the Construction Schedule in an approved status may result in the

Owner withholding a monetary penalty against the responsible Contractor(s) until the schedule is approved as set forth in 3.4 of this Section.

PART 2 - PRODUCTS

2.1 CONSTRUCTION SCHEDULE

A. Prepare a detailed construction schedule in graphic form showing duration and proposed dates of starting and completing each major division of the Work. The schedule is to be consistent with the time and order of Work requirements of the specifications, and is to be the basis of the Contractor’s operations. Prepare the schedule utilizing a Gantt chart (bar type) or similar method that connects related activities.

B. Sufficient detail shall be included for the identification of subdivisions of the major components listed below. The major components should be broken in into activities such as excavation, backfill, surface restoration, traffic control, testing/commissioning, water service, water main, hydrants, and other activities as required.

1. Mobilization

2. Clearing/grubbing and erosion control

3. Traffic Control

4. Waterline (main)

5. Water Services

6. Hydrants

CONSTRUCTION PROGRESS SCHEDULE 01 32 16 - 2

C. Submit a horizontal bar chart with separate line for each section of Work, identifying first work day of each week.

D. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities. Indicate the early and late start, early and late finish, float dates, and duration. Clearly indicate critical path and activities/items on the critical path.

E. Indicate estimated percentage of completion for each item of Work at each submission.

F. Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates.

PART 3 - EXECUTION

3.1 INITIAL SCHEDULE SUBMITTAL

A. The Contractor shall submit two short-term schedule documents at the Pre-construction

Conference which shall serve as the Contractor's Plan of Operation for the initial 60-day period of the Contract Time, and to identify the manner in which the Contractor intends to complete all Work within the Contract Time.

B. The bar chart shall show the accomplishment of the Contractor's early activities

(mobilization,…