This document is a Base Bid Proposal and Alternate Bid Proposal for the North Grove Park construction project. The comprehensive bid form details a wide range of construction and landscaping items for park development, including site preparation, concrete work, fencing, irrigation, playground equipment, shade structures, and various park amenities. The project includes 40 line items in the base bid and 5 additional items in the alternate bid, with quantities specified for each item such as 19,500 square feet of 4" concrete sidewalk, 141 5-gallon shrubs, 2 shade structures, and 42,200 square feet of Bermuda grass sod.
The bid proposal includes a $50,000 owner's contingency and allows bidders to provide unit pricing for each specified item, with spaces to fill in total dollar amounts for each line item. The project appears to be a comprehensive park development effort involving multiple construction and landscaping elements, with detailed specifications for materials, quantities, and installation requirements. Bidders are expected to provide precise pricing for each component, from mobilization and site grading to specific amenities like pavilions, drinking fountains, playground equipment, and landscape elements.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item Description of Items with Unit Prices in Written Words Quantity Unit of Measure Unit Price Total Price
Mobilization / General Conditions complete for the sum of
__________________________________ dollars, and
__________________________ cents per Lump Sum
Temporary Construction Fence / Tree Protection Fence complete for the sum of __________________________________ dollars, and
__________________________ cents per Lump Sum
Temporary Silt Fence and Erosion Control Logs (Install / Remove) complete for the sum of __________________________________ dollars, and
__________________________ cents per Lump Sum
Demolition complete for the sum of __________________________________ dollars, and __________________________ cents per Lump Sum Site Grading (rough grading and fine grading) complete for the sum of __________________________________ dollars, and __________________________ cents per Lump Sum Stabilized Decomposed Granite complete for the sum of __________________________________ dollars, and __________________________ cents per Square Foot 4” Concrete Sidewalk complete for the sum of __________________________________ dollars, and __________________________ cents per Square Foot 4” Concrete Sidewalk – Integral Colored Concrete complete for the sum of __________________________________ dollars, and __________________________ cents per Square Foot 12” Concrete Mowstrip complete for the sum of __________________________________ dollars, and __________________________ cents per Square Foot 18” Concrete Mowstrip complete for the sum of __________________________________ dollars, and __________________________ cents per Square Foot Concrete - Vehicular (7" Depth with Curb/Median-20 Spaces) complete for the sum of __________________________________ dollars, and __________________________ cents per Square Foot Concrete – Vehicular Integral Colored and Stamped (7" Depth Crosswalk) complete for the sum of __________________________________ dollars, and __________________________ cents per Square Foot
1 1 LS $ $
2 1 LS $ $
3 1 LS $ $
4 1 LS $ $
5 1 LS $ $
6 5,600 SF $ $
7 19,500 SF $ $
8 5,800 SF $ $
9 650 SF $ $
10 1,780 SF $ $
11 13,400 SF $ $
12 430 SF $ $
Base Bid Proposal
NORTH GROVE PARK
Parking Lot Signage (ADA) complete for the sum of __________________________________ dollars, and __________________________ cents per Each Thermoplastic striping complete for the sum of __________________________________ dollars, and __________________________ cents per Lump Sum Concrete wheel stops complete for the sum of __________________________________ dollars, and __________________________ cents per Each Benches complete for the sum of __________________________________ dollars, and __________________________ cents per Each Trash Receptacles complete for the sum of __________________________________ dollars, and __________________________ cents per Each Picnic Tables complete for the sum of __________________________________ dollars, and __________________________ cents per Each Restroom Structure Enclosure (10’x18’) complete for the sum of __________________________________ dollars, and __________________________ cents per Lump Sum Pipe Rail Fence complete for the sum of __________________________________ dollars, and __________________________ cents per Linear Foot 5 Gallon Shrubs complete for the sum of __________________________________ dollars, and __________________________ cents per Each 3 Gallon Ornamental Grasses complete for the sum of __________________________________ dollars, and __________________________ cents per Each Canopy Trees complete for the sum of __________________________________ dollars, and __________________________ cents per Each Screening Trees complete for the sum of __________________________________ dollars, and __________________________ cents per Each Hardwood Mulch (3” Depth) complete for the sum of __________________________________ dollars, and __________________________ cents per Cubic Yard Bermuda Grass Sod complete for the sum of __________________________________ dollars, and __________________________ cents per Square Foot
13 2 EA $ $
14 1 LS $ $
15 20 EA $ $
16 4 EA $ $
17 2 EA $ $
18 2 EA $ $
19 1 LS $ $
20 980 LF $ $
21 141 EA $ $
22 43 EA $ $
23 23 EA $ $
24 54 EA $ $
25 85 CY $ $
26 42,200 SF $ $
Bermuda Grass Seed
__________________________________ dollars, and __________________________ cents per Square Foot Topsoil (4”) complete for the sum of __________________________________ dollars, and __________________________ cents per Cubic Yard Permanent Irrigation complete for the sum of __________________________________ dollars, and __________________________ cents per Lump Sum Temporary Irrigation complete for the sum of __________________________________ dollars, and __________________________ cents per Lump Sum Shade Structures Over Benches (8’x9’) complete for the sum of __________________________________ dollars, and __________________________ cents per Each Pavilions (12’x12’) complete for the sum of __________________________________ dollars, and __________________________ cents per Each Round Pavilion (24’ Diameter) complete for the sum of __________________________________ dollars, and __________________________ cents per Each Drinking Fountain & Water Service Tap complete for the sum of __________________________________ dollars, and __________________________ cents per Each Bistro String Lighting complete for the sum of __________________________________ dollars, and __________________________ cents per Linear Foot String Light Poles (Black Powder Coated) complete for the sum of __________________________________ dollars, and __________________________ cents per Each Adirondack Chair complete for the sum of __________________________________ dollars, and __________________________ cents per Each Rubberized surfacing w/ Aggregate Subbase complete for the sum of __________________________________ dollars, and __________________________ cents per Square Foot Rubberized surfacing play mounds w/ concrete subbase complete for the sum of __________________________________ dollars, and __________________________ cents per Square Foot Artificial Turf & Subbase complete for the sum of __________________________________ dollars, and __________________________ cents per Square Foot
27 136,000 SF $ $
28 2,300 CY $ $
29 1 LS $ $
30 1 LS $ $
31 2 EA $ $
32 3 EA $ $
33 1 EA $ $
34 1 EA $ $
35 275 LF $ $
36 12 EA $ $
37 6 EA $ $
38 3,300 SF $ $
39 710 SF $ $
40 1,200 SF $ $
Playground Equipment & Shade Sails over Playground
__________________________________ dollars, and __________________________ cents per Lump Sum Veneer Stone Seat Wall complete for the sum of __________________________________ dollars, and __________________________ cents per Face Foot Lighting & Electrical - Pavilion Outlets, Foot Truck Hook-Ups, Misc. Items complete for the sum of __________________________________ dollars, and __________________________ cents per Lump Sum Storm, sewer, all drainage components complete for the sum of complete for the sum of __________________________________ dollars, and __________________________ cents per Lump Sum
$50,000 $50,000
Item Description of Items with Unit Prices in Written Words Quantity Unit of Measure Unit Price Total Price
Cantilever Shade Sail Structure (16’x16’) complete for the sum of __________________________________ dollars, and __________________________ cents per Each Decomposed Granite Trails (West Trails) complete for the sum of __________________________________ dollars, and __________________________ cents per Square Foot 9’x16’ Trellis w/Two 4’ Gliders complete for the sum of __________________________________ dollars, and __________________________ cents per Lump Sum CXT Prefabricated Restroom – Denali 10’-3” x 19’-8” complete for the sum of __________________________________ dollars, and __________________________ cents per Lump Sum Restroom Pad Preparation, Water, Sewer, Utility Extension/Connections complete for the sum of __________________________________ dollars, and __________________________ cents per Lump Sum
41 1 LS $ $
42 66 FF $ $
Owner’s Contingency
A1 2 EA $ $
43 1 LS $ $
44 1 LS $ $
Total Base Bid Including Owner's Contingency: $
Alternate Bid Proposal
NORTH GROVE PARK
Total Alternate Bid: $
A4 1 LS $ $
A5 1 LS $ $
A2 7,600 SF $ $
A3 1 LS