This Supplemental Specifications document, issued by Hillsborough County Water Resources Department in Florida, outlines requirements for construction and installation services of water mains, reclaimed water mains, and wastewater force mains at various County facilities. The contractor must demonstrate working knowledge of underground water/wastewater utilities and experience in utility location and verification, installation of PVC and Ductile Iron mains ranging from 4 to 12 inches in diameter, pipeline modifications at treatment facilities, jack and bore installations, and deep excavations with shoring and dewatering. All work shall be performed in accordance with Hillsborough County Standard Specifications and technical manuals, with the Project Manager serving as the sole determiner of scope for each work site. The contract is structured as a term contract with work orders issued on an as-needed basis, with the County guaranteeing a minimum of $10,000 in usage. The contractor must respond to requests within 24 hours and mobilize crews and equipment within 48 hours of notification. Standard work hours are 7:00 a.m. to 4:00 p.m., Monday through Friday, excluding County holidays and weekends, with non-standard hours requiring written approval and compensation adjustments not to exceed 10 percent of the Work Order cost.

The contract includes a total mobilization allowance of $60,000 distributed among awarded contractors, with a fixed payment of $1,000 per Work Order for mobilization costs. Contractors must furnish all labor, fuel, tools, transportation, materials, equipment, and other necessary expenses. The contractor is responsible for obtaining Right-of-Way Use and Maintenance of Traffic permits at no charge from the County, while the County furnishes environmental agency permits. Payment is based on actual field measurements and unit prices established during the proposal process, with specific bid items including excavation of unsuitable material, fill material, sodding, traffic control, various pipe types and sizes, fittings, valves, fire hydrants, meter services, and dewatering operations. The contractor must submit record drawings with X-Y-Z coordinates linked to the 1983 State Plane coordinate system and must provide pre- and post-construction digital photography. All testing and inspection costs are borne by the contractor, and defective work must be corrected at no additional cost to the County. A Small Business Enterprise (SBE) subcontracting goal of 6 percent has been established for this $12,075,000 estimated contract opportunity.

View the file

Other files

File Type Posted
25-Payment Bond.pdf PDF
7-Payment Assistance (SBE Set-Aside).pdf.pdf PDF
4-Allowance Authorization Release Form.pdf.pdf PDF
5-Application for Payment.pdf.pdf PDF
6-Consent of Surety-Change Order.pdf.pdf PDF
12-Substitute W9 Form.pdf.pdf PDF
17-SBE Goal Participation SBE-1 Form Tutorial.mp4 MP4 file
16-Subcontractor Letter of Intent .pdf PDF
9-Consent of Surety to Final Payment.pdf.pdf PDF
18-Attachment B - Utility Accomodation Guide and ROW Use Procedures.pdf PDF
14-Contractors Affidavit for Payment of Debts and Claims 02.18.2026.pdf PDF
22-1. Terms and Conditions.pdf PDF
8-Subcontractors Statement of Satisfaction.pdf.pdf PDF
15-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
24-Bid Bond.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
19-Attachment C - Insurance Requirements.pdf PDF
23-Agreement - IFB-26-00426.pdf PDF
21-NEW SBE Subcontractors Material Suppliers List SBE-1 Form-10.2026.pdf PDF
13-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
3-Vendor Eligibility Check Prior to Contract Award.pdf.pdf PDF
11-Insurance Certificate.doc.doc DOC document
10-Change Order Form.pdf.pdf PDF
26-Performance Bond.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Supplemental Specifications

SECTION 1

1.1 SCOPE OF WORK

It is anticipated that the work to be performed under this Contract may include but is not limited to the installation of water mains, reclaimed water mains, and wastewater force mains and miscellaneous installations and/or modifications at various water, reclaimed water, and wastewater facilities, pumping stations and equipment utilized by the Hillsborough County Water Resources Department.

Range of Duties - The Contractor shall have a working knowledge of underground water/wastewater utilities and must have experience in each of the following:

• Utility location and verification

• Installation of PVC and Ductile Iron water, reclaimed water and wastewater force mains 4" to

12" inch in diameter in the public right-of-way.

• Replacement of active water, reclaimed water and wastewater force mains located in the public right-of-way.

• Installation or modifications to pipelines at water, reclaimed water, or wastewater treatment facilities 4" to 12" diameter.

• Projects located in the public right-of-way requiring the installation of steel casing pipe by Jack and bore.

• Projects located in the public right-of-way requiring deep excavations, shoring, sheeting, and well point dewatering.

The Contractor(s) shall furnish all labor, fuel, tools, transportation, materials, equipment and all other expenses as may be necessary for the accomplishment of all work as described in the Specifications, and/or as shown on Plans, if any, and/or as directed by the Project Manager in strict accordance with the expressed or obvious intent of this Contract.

The inclusion of the above capabilities does not guarantee that such work will be performed. All work shall be on an as needed basis. The County Project Manager shall be the sole judge as to the Scope of Work for each work site.

1.2 TECHNICAL SPECIFICATIONS

All work regardless of the scope, shall be performed in strict accordance with the Hillsborough County Standard Specifications For Construction (latest edition) and/or Hillsborough County Water, Wastewater, and Reclaimed Water Technical Manual and/or Technical Specifications (latest editions) and/or Hillsborough County Standard Pump Station Drawings, and/or Utility Accommodation Guide (latest edition), and/or Hillsborough County Stormwater Technical Manual (latest edition), The Hillsborough County Standard Pump Station Drawings, Technical Manual, and Technical Specifications may be located on the Water Resources Department Website:

https://www.hillsboroughcounty.org/en/businesses/land-development/technical-publications/public-utilities-technical-specifications

In all conditions the most stringent requirement/specification as determined by the Project Manager shall apply to the project. It is the Contractor's sole responsibility to purchase/locate at their expense the necessary drawings, specifications, and technical guideline material to perform the necessary scope of work and be advised of any updates, modifications, alterations, and any deviations of the above mentioned during the life of the contract.

1.3 CONTRACT ESTIMATED QUANTITIES

https://www.hillsboroughcounty.org/en/businesses/land-development/technical

Unit quantities are provided as a means of comparing bid proposals and as a basis for award. However, these quantities are estimated and actual unit quantities may vary greatly during the term of this contract. THE

BIDDER IS ADVISED THAT THE TOTAL QUANTITY OF WORK REQUESTED MAY BE LESS

THAN THE QUANTITY ESTIMATED, AND IN FACT THE COUNTY ONLY GUARANTEES A

MINIMUM OF $10,000 USAGE ON TIDS CONTRACT.

Bidders are cautioned against predicating their bid prices on an assumed scope of work or estimated bid quantities.

The amount of award represents only the upper dollar limit beyond which no further work shall be ordered, except as may be approved by the Board through a Change Order. It is not known how much or how little work will be ordered during the term of this contract.

Bidder acknowledges that actual quantities may be significantly less than those indicated in the bid, and agrees that, as the Contractor, he/she will not make any claim for damages or for loss of profits because of a difference between the quantities bid and the quantity of work actually ordered.

Work Order pricing shall be based on actual field measurement, not estimated bid or planned quantities.

Because quantities are estimated and actual requirements will not be determined until time of need, Section "Change in the Work" and Section "Change of Contract Price" of the General Terms and Conditions are hereby modified to delete the necessity for a Change Order in the event of line-item quantity over or under runs, provided that total purchases do not exceed the amount of award.

1.4 WORK ORDER ROTATIONAL PROCEDURE

In the event the County awards this contract to more than one Contractor, Work Orders will be issued on a determination of the best overall value for the County.

Value shall be determined by the Project Manager based on the following factors; Scope, Schedule, and Cost.

The Project Manager shall develop a preliminary scope, schedule, and cost estimate for each task order and determine the best value for the County. If it is determined to be in the best interest of the County, a Work Order may be awarded to the Contractor with the lowest time estimate (schedule) for the completion of the work. The Project Manager shall continue the Work Order Assignment Procedure described herein for the duration of the Contract, including all subsequent renewal periods.

1.5 AUTHORIZATION OF WORK

No work may be performed under this term contract except as authorized by a Work Order issued by the Public Utilities Department Director, or designee and a Purchase Order. The Work Order will establish the Notice to Proceed date. The Contractor shall not proceed with, and shall not be compensated for, any work that is not authorized by written Work Order. Verbal authorization may be given when immediate response conditions occur at night and/or on weekends and followed-up with a written authorization within 24 to 48 hours of the occurrence.

1.6 AUTHORIZED CONSTRUCTION DAYS

It is anticipated that this contract may include projects (Work Orders) of both short and long duration. Prior to issuance of a particular Work Order, the Project Manager and the Contractor will mutually agree as to a fair and reasonable anticipated number of days necessary to achieve Substantial and Final Completion on all Work Orders.

Once the number of days has been determined and mutually agreed to, a Work Order may be written as specified in the Contract Documents. The liquidated damages amounts specified in the General Terms and Conditions, entitles the County to assess liquidated damages per calendar day of delay, excluding circumstances that are beyond the control of the Contractor as outlined in the contract. In addition, failure on the Contractor to complete the Work Order work within the time specified in the Work Order may result in no further Work Orders being issued under this Contract and/or termination of this Contract and/or any pending Work Order(s).

1.7 SIMILAR WORK BY OTHER CONTRACTORS

Award of this term contract to a particular Contractor shall impose no obligation on the County to utilize that Contractor for all work of this type which may develop during the period of this contract. This is not an exclusive contract. The County specifically reserves the right to concurrently contract with other companies for work of this type if the County deems such to be in the County's best interest.

1.8 MOBILIZATION ALLOWANCE

A total allowance in the amount of sixty thousand dollars ($60,000.00) shall be included in the Total Award and distributed among the awarded Contractors as determined by the County. The Contractor shall be reimbursed for mobilization costs associated with the transportation and delivery of all equipment and materials required for the Work to the project site. The County will pay a fixed price of $1,000.00 per Work Order for the Contractor's mobilization cost. The Mobilization Allowance is not precluded from being utilized for regular line items included in this Contract.

1.9 PROCEDURE FOR DEVELOPMENT OF A PROPOSAL, EVALUATION OF THE PROPOSAL,

AND ISSUANCE OF WORK ORDERS

Upon identifying the need for work to be performed under this contract, the Project Manager, or other designated staff person, will meet with the Contractor to review the scope of work. This may also include an on-site visit.

The Contractor shall prepare a detailed cost estimate using their bid prices. This shall include a Contractor-developed and detailed statement of work and shop drawings/sketches for the project. The Contractor shall ensure that its proposal is complete using the applicable specifications and standards included herein.

Shop drawings/sketches showing the quantities of line items required and cross-referencing line items on the Contractor's cost estimate shall accompany the initial proposal. The detailed (Contractor-developed) statement of work must be supported by all necessary documentation to indicate that adequate planning to accomplish the required work has been performed. Costs for the aforementioned documentation shall be included in the Contractor's bid prices and will not be paid separately by the County.

The Contractor's bid prices, shall serve as the basis for establishing the value of the work to be performed on a unit price basis.

Timeliness of services: Since the primary goal of work order contracting is the speedy acquisition of cons1ruction services, Contractor responsiveness under the terms of this contract is paramount. Upon notification of a need for routine services, the Contractor shall acknowledge the request and reply to the Project Manager, or designee, within twenty-four (24) hours. The Contractor shall be expected to expeditiously prepare its proposal and in no event shall the proposal preparation time exceed more than five (5) calendar days. Failure to respond within the time specified above may result in: the work being performed by others; no further Work Orders being issued to the Contractor;

termination of the Contract; the filing of a claim by the County against the Performance Bond.

As part of the price proposal, the Contractor shall also develop a schedule for completion of work, if the schedule was not previously provided to the Contractor by the Project Manager.

The Contractor shall submit its proposal to the Project Manager, or his designated representative, who will evaluate the proposal and, if approved, issue a Work Order Notice to Proceed. The Project Manager reserves the right to disapprove the proposal, in which case he shall not have an obligation to issue the work order.

If, in the Project Manager's opinion, additional unit price items or quantities are required to complete the project, a revised work order detailing the additional work will be issued. The Contractor shall review the revisions and submit a detailed cost proposal. The Project Manager will review the Contractor's proposal and, if approved, will issue a revised Work Order.

If, in the Contractor's opinion, additional unit price items or quantities are required to complete the project, it is the Contractor's responsibility to advise the Project Manager, or his designated representative, and obtain approval prior to utilization of said materials.

It shall be the Contractor's responsibility to notify the Project Manager, or his designated representative, if the additional quantities are likely to exceed the Work Order limit and obtain prior approval. Prior approval shall be granted by way of a Revised Work Order.

The Project Manager, or his designated representative, reserves the right to reject any proposal, in which case the Project Manager, or his designated representative, shall have no obligation to issue the Work Order or revised Work Order.

1.10 RESPONSE TIME AND MOBILIZATION

The Contractor should expect to have crews available to notify Florida One Call Center "Sunshine 811", acquire permits and start work at the job site within two (2) days from notification by the Project Manager. The Contractor will be required to respond to the request of the Project Manager within two (2) hours and mobilize with crews and necessary equipment and materials within forty-eight (48) hours of verbal notification, including weekends and holidays. Longer times may be allowed by the Project Manager depending on the urgency of work. Work within Hillsborough County requires permitting by the Contractor. No permit fees will be assessed: however Traffic Control will be the responsibility of the Contractor. The Contractor is responsible to submit Traffic Control Plans per agency requirements and maintain devices for the duration of the project.

1.11 STANDARD WORK HOURS

The standard work hours shall be 7:00 A.M. to 4:00 P.M., Monday through Friday, excluding County-observed holidays and weekends. Work outside these hours shall require twenty-four hours notice to and written approval from the Project Manager. Standard work hours may be impacted by the requirements of Right-of-Way or MOT permits.

1.12 NON-STANDARD WORK HOURS (OVERTIME WORK)

In the event the County requires work to be done outside standard work hours, the Contractor shall be entitled to adjust their Work Order Cost for work performed during non-standard hours in an amount not to exceed ten percent of the Work Order Cost.

1.13 DISPUTES REGARDING WORK ORDERS

In the event the County and Contractor are unable to agree on final quantities or items for the performed work, the County may reject the Contractor's pay request and require the Contractor to provide verifiable documentation as to the quantities and items actually used. The burden of proof is on the Contractor. If the Project Manager finds the verifiable documentation sufficient, the pay application will be processed. If the Project Manager finds the documentation insufficient or unverifiable, the Contractor and the Project Manager may appeal to the Public Utilities Department Director. The decision of the Public Utilities Department Director is final.

If the Contractor refuses or otherwise fails to perform any of its obligations under the Contract or fails to perform the Work Order work, the County reserves the right to take any or all of the following actions:

Obtain the services from another Contractor;

Terminate the Contract;

Debar the Contractor from bidding on County construction projects for a period of up to 24 months;

File a claim against the Contractor's Performance Bond.

If the Contractor believes there is good cause for not performing requested Work, the Contractor may submit Notice which cites the refusal and contains supportive documentation and may appeal an adverse decision to the Public Utilities Department Director.

1.14 PERMITS

The County shall furnish all required environmental agency permits. It shall be the Contractor's sole responsibility to obtain the Right-of-Way Use Permit, and Maintenance of Traffic Permit (MOT) permit for all Work Orders. There will be no charge from Hillsborough County for the Right-of-Way Use and MOT permits. For further information on Permits, please refer to the Terms and Conditions Section 5.4.6.

1.15 PROJECT SIGN

The County will provide the Contractor with portable project identification signs. The signs will display a generic title such that they can be re-used on successive Work Orders during the term of the Contract.

Before mobilization on each Work Order, the Contractor shall display a project identification sign in a prominent location at the project site. The Contractor shall remove and relocate signs to the new Work Order construction sites as needed, or at the direction of the Project Manager, and maintain storage of the signs between Work Orders. The Contractor shall remove and dispose of the signs at the completion of the contract term or as directed by the Project Manager. Disposal of the signs shall be at no additional cost to the County. All costs associated with this item should be included in the Contractor's overhead.

1.16 DOORHANGERS

In the event any activity under this Contract is determined to affect near-by residents, the Contractor will be required to notify the affected residents using door hangers. All residents shall be notified at least twenty-four hours in advance of mobilization. The geographical area of notification shall be determined by the County. The County will provide the Contractor with the door hangers. All costs associated with this item shall be included in the Contractor's overhead.

1.17 RECORD DRAWING SUBMITTAL

The Contractor shall keep adequate records and supporting documentation for each Work Order. Upon completion of the Work Order Work, the Contractor shall furnish to the Project Manager record drawings.

Recording of all information in the field shall be done by the Contractor. Record drawing information shall be kept current during the progress of the Work and available for inspection by the Project Manager. Final payment shall not be made until record drawings have been submitted and approved.

1.18 CONSTRUCTION FEATURE INFORMATION

The following information is to be supplied at the time of Record Drawing submittal. X-Y-Z coordinates of all below grade fittings, plugs, caps, valves, hydrants, taps, and restrained joints. The coordinates shall be linked to the 1983 State Plane coordinate system and the 1988 vertical datum. All horizontal and vertical data shall be accurate to 5/100ths of a foot or 1.5 centimeters.

GPS X-Y-Z coordinates will not be required on urgent repairs.

Contractors electing to use RTK GPS for field data collection are encouraged to tie into the Permanent Reference Network maintained by Hillsborough County. The free network can be found at IP address:

207.156.7.34, ports 5034 thru 5038. Any questions regarding access and/or utilization of the aforementioned network should be directed to the Hillsborough County Survey field office at 813-744-5619.

Any other questions concerning the data reporting requirements included in this section should be directed to the Team Leader for the WRD Project Control Team at 813-612-7756.

1.19 TESTS AND INSPECTIONS

A. TESTS

1) All materials used in the construction of the Project shall be subject to adequate inspection and testing in accordance with accepted standards. Contractor shall select an independent laboratory or inspection agency for making all tests required by the specifications, and shall pay for this laboratory service direct, as a requirement of this Contract. Density testing of trenches and structure backfill (generally of soils, sub-grade, fill, pavement base and sub-base materials), shall be taken at intervals as specified in the Contract Documents, or as directed by the Project Manager. Contractor shall provide advance notice to the Project Manager of required density tests. Reports of these tests shall be submitted for review to the Project Manager within ninety-six hours. The Contractor shall bear the sole responsibility to confirm that all densities meet the County Standards. Contractor shall pay for any re-tests resulting from the Contractor's failure to provide work that does not pass the required tests.

2) Materials of construction, particularly those upon which the strength and durability of the structure may depend, shall be subject to inspection and testing to establish conformance with specifications and suitability for uses intended.

3) Where specific performance or quality is referenced, it is Contractor's responsibility to have the necessary tests performed by qualified persons to show that the contractual requirements are being met. Where no reference is made, tests shall be performed in accordance with the methods prescribed by the American Society for Testing and Materials, or such other organization as would be applicable.

4) If these Contract Documents, or laws, ordinances, rules, regulations or orders of any public authority having jurisdiction to the Work, require any work to specifically be inspected, tested, or approved by someone other than Contractor, the Contractor shall give the Project Manager timely notice of readiness thereof. Contractor shall furnish the Project Manager the required certificates of inspection, testing results or approvals. All such tests shall be in accordance with the methods prescribed by the American Society for Testing and Materials or such other applicable organization as may be required by law or these Contract Documents.

5) Any Work that fails any required test, inspection or approval, or any Work that passes any required tests, but nevertheless does not meet the requirements of the Contract Documents, shall be considered Defective Work. Defective Work may be rejected by the Project Manager. If rejected, the Defective Work shall be corrected by the Contractor at no additional cost to the County. It is the Contractor's sole responsibility to make the necessary changes. The costs of all re-inspections and re-testing shall be borne by Contractor at no additional cost to the County.

B. INSPECTIONS

1) The Project Manager may appoint Inspectors to observe both materials and Work. Such observation may extend to any or all parts of the Work and to the preparation and manufacture of the materials to be used. The Inspector shall not be authorized to alter, revoke, enlarge or relax the provisions of the Work, nor will they be authorized to approve or accept any portion of the completed Work, nor to issue instructions contrary to the Contract. An Inspector is assigned to keep the Project Manager informed on the progress of the Work and the manner in which it is being done. He may call to the attention of Contractor any deviation from the Contract Documents. Without approval from the Project Manager, the Inspector will not have the authority to reject defective materials or to suspend any Work that is being improperly performed.

2) Neither observations by the Project Manager or Inspector, nor inspections, tests or approvals by persons other than the Contractor shall relieve Contractor from its obligations to perform the Work in accordance with the requirements of the Contract Documents.

1.10 DIGITAL PHOTOGRAPHY

Contractor shall take pre-construction and post-construction photos for each Work Order and submit the photos to the Project Manager. The photos shall include all features in the vicinity of the work that might be impacted by the construction. The Project Manager reserves the right to select the views to be photographed. Photos shall be labeled with the date the photo was taken, Work Order number, location (street names), and a brief description of times and activity covered in the photo.

In areas near surface waters, the photos shall include an upstream and downstream view of each bank at the nearest point to the Work and, if applicable, point of crossing. Also, a view of the line route shall be taken from each bank of the crossing and elsewhere as the Project Manager may direct.

1.11 UTILITY COORDINATION

The Contractor and their Subcontractors shall cooperate and coordinate with the owners of all underground or overhead utilities in their removal and rearrangement operation in order that these operations may progress in a reasonable manner, can proceed in accordance with the relocation schedules contained within the contract documents, that duplication or rearrangement work may be reduced to a minimum, and that services rendered by the utility owners will not be unnecessarily interrupted. Any conflicts between the contract work that the Contractor will perform and the utility owner's facilities shall be resolved by the Contractor and the utility owner with the County's concurrence. The Contractor shall also provide survey information including field staking as required to ensure proper relocation of the utilities. In the event of interruption of water, wastewater or other utility services as a result of accidental breakage, exposure, or lack of support, the Contractor shall promptly notify the proper authority and cooperate with the authority in the prompt restoration of service. If water or wastewater service is interrupted and the Contractor is performing or assisting the repair work, the Contractor shall work continuously until the service is restored. Do not begin work around fire hydrants until the local fire authority has approved provisions for continued service.

1.12 UTILITY LOCATION AND VERIFICATION

Utility Location and Verification includes furnishing all materials and performing all work necessary to verify and locate proposed connect points to the existing pipeline, pipe or valve, locating and verifying the horizontal and vertical alignment of all underground utilities within the area of construction to allow the construction of the proposed pipelines to proceed without conflict or disruption to the existing utilities. This includes but is not limited to, water mains and service lines, reclaimed water mains and service lines, meters, sewer laterals, force mains, gas mains with appurtenances and service lines, electric lines, telephone lines, fiber optic cables, traffic signal cables, etc. The costs for Utility Location and Verification are to be included in the unit price for the item with which they are associated. SEPARATE PAYMENT FOR UTILITY LOCATION AND VERIFICATION

SHALL NOT BE MADE BY THE COUNTY.

1.13 SEWAGE SPILLS

All wastewater or other spills resulting from Contractor operations hereunder shall be contained, removed, and cleaned up immediately by the Contractor at no additional cost to the County. The Contractor shall disinfect spills using a disinfectant method approved by the Project Manager. The Contractor shall report all spills immediately to the Project Manager. All required regulatory agencies shall be notified as soon as possible, but in no case later than twenty-four hours from the time of the spill. The Contractor shall provide the regulatory agencies and the Project Manager a detailed written report of the spill, describing the occurrence and all actions taken.

Disposal of Washwater - The Contractor may be allowed to decant excess washwater from a Jet-VAC truck or other pumping truck by directing the flow of the washwater into a sanitary sewer manhole whose location is approved by the Project Manager. Solids shall not be dumped into a manhole but shall be disposed of in an appropriate and permitted location at the Contractor's expense. The Contractor shall not dispose of discharge washwater containing waste and debris into any streets, ditches, canals, rivers, or lakes.

1.14 SITE SAFETY AND CLEAN-UP

The Contractor shall be responsible for site safety and clean-up. The Contractor will be responsible for keeping the site safe for pedestrians and traffic. The Contractor shall dispose of all debris on a daily basis and be responsible for hauling all debris to an appropriate and permitted disposal site. The Contractor will not be allowed to accumulate excess debris on the site, unless approved by the Project Manager. All costs associated with the safety, clean-up, and disposal of debris shall be included in the Contractor's overhead.

1.15 LAYDOWN AREA

The Contractor shall provide his own lay down and material storage areas.

- END OF SECTION -

MEASUREMENT AND PAYMENT

PAGE 01025-1

SECTION O1025 - MEASUREMENT AND PAYMENT

SCOPE OF PAYMENTS

The descriptions in the following sections generally define the work tasks, materials, etc.

associated with each pay item listing. This information is provided to assist the Contractor in assigning and accounting for costs associated with each pay item. Notwithstanding this, it is the Contractor's sole responsibility to fully define and establish the cost for each item and the work in its entirety. The Contractor shall include all costs for completing all WORK identified in the Contract Documents in the bid items listed on the bid form.

Items Included in Payment: The costs for Utility Location and Verification are to be included in the unit price for the item with which they are associated. The CONTRACTOR shall accept the compensation as provided in the contract as full payment for furnishing all materials and for performing all WORK contemplated and embraced under the contract: also for all loss or damage arising out of the nature of the WORK or from the action of the elements, or for any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the WORK until its final acceptance: also for all other costs incurred.

For any item of WORK contained in the proposal, except as might be specifically provide otherwise in the basis of payment clause for the item, the contract unit price for the pay item or items shall include utility location and verification, all labor, equipment, material, tools and incidentals required to complete the work, including cleanup and all requirements of the Section specifying such items of work.

0. MOBILIZATION - The Contractor is expected to spend a reasonable number of hours inspecting the proposed scope of work, acquiring parts materials and equipment, and preparing a detailed cost estimate utilizing the unit price items and/or sources mentioned in the Special Conditions. The County has indicated the specific amount it will compensate the Contractor for Mobilization.

The Price established is intended to compensate the contractor for obtaining of all permits, insurance, and bonds; moving onto the site of all plant and equipment: furnishing and erecting project identification sign, obtaining or taking digital photography (as described in the special conditions), and other items as noted in section 01020, "Mobilization"; and providing sanitary and potable water facilities as required for the proper performance and completion of the WORK.

Only one (1) mobilization fee will be paid per work order for all work performed within a one (1) mile radius.

1. EXCAVATION OF UNSUITABLE MATERIAL FOR PIPELINES

Work Included- Under the Bid Item for Excavation of Unsuitable Material, perform excavation of unsuitable material ordered in writing by the PROJECT REPRESENTATIVE. The Work

SECTION 01025- MEASUREMENT AND PAYMENT

PAGE 01025-2

includes clearing, excavation, protection of existing structures and adjacent property, removal of water, disposal of excavated unsuitable material, and other Work appurtenant to the Excavation of Unsuitable Material as specified.

Measurement for Payment: The quantity of Excavation of Unsuitable Material, in cubic yards, to be measured for payment under this Bid Item will be the total excavation, as ordered and approved, beyond and outside the established lines and grades which would have controlled and been maintained had not the Excavation of Unsuitable Material been ordered. Unauthorized excavation will not be measured for payment.

Payment: Payment for Excavation of Unsuitable Material ordered in writing will be made at the Contract unit price per cubic yard for this Bid Item.

2. ADDITIONAL COMMON FILL MATERIAL

Work Included- Under the Bid Item for Additional Common Fill Material, furnish all labor, materials and equipment, and perform all work necessary to import, furnish, place and compact additional fill in order to re-fill excavation of unsuitable material or to replace excavated material deemed unsuitable for use as backfill by the PROJECT REPRESENTATIVE when all stockpiles of suitable job excavated material have been exhausted.

The CONTRACTOR shall use all surplus common fill, approved as suitable, from excavations in this Contract prior to supplying additional common fill from other sources.

Measurement for Payment: The Additional Common Fill Material, to be measured for payment under this Bid Item will be the additional common fill supplied from sources other than excavations in this Contract as described above.

Payment: Payment for Additional Common Fill Material will be made at the Contract Unit Price per cubic yard for this Bid Item.

3. SODDING

This bid item describes measurement and payment for grassing of completed construction areas by planting sod.

Sodding: Measurement of sodding will be on a square yard basis for the area of sod installed where shown on the drawings, or where directed by the Project Representative. Sod will be paid for on the basis of type, and area installed, as shown on the Proposal. The unit bid price for sodding includes soil preparation, furnishing and installing sod, rolling, mowing, and any other measure necessary to establish and maintain a healthy stand of grass until the work is accepted by the Owner.

No payment will be made for the installation of sod where existing lawn areas are disturbed by the Contractor during the performance of the Work. New sod shall be installed where existing lawn areas are disturbed by the operations of the Contractor. Installation of sod shall be considered a subsidiary obligation of the Contractor and all costs associated therewith shall be included in the unit and lump sum unit prices.

PAGE 01025-3

4. SEDIMENTATION CONTROL

Work Included - This bid item describes measurement and payment for construction of temporary features to protect the work areas and adjacent property from erosion and sedimentation.

Payment - The quantity paid under this item shall be for the installation and maintenance for the job duration of the staked silt fence in linear feet installed per the plans and/or as directed by the Project Representative.

5. ASPHALTIC CONCRETE PAVEMENT REPLACEMENT AND OVERLAY

Work Included- Under the Bid Item for Asphaltic Concrete Pavement Surface (Type SP 12.5) and Overlay (Type SP 9.5), furnish all labor, equipment and materials to place and maintain all asphaltic concrete pavement surface and overlay, as shown, specified and as directed by the

PROJECT REPRESENTATIVE.

Conform Asphaltic Concrete Pavement Surface and Overlay to the requirements of the Specification Section 2100 headed "Restoration of Connecting Pavement Sidewalk and Curb", Section 334 - "Superpave Hot Mix Asphalt" and the Hillsborough County Utility Accommodation Guide.

Measurement for Payment: The quantity of asphaltic concrete to be paid for under this bid item shall be the square yards of material acceptably installed within the limits shown on the drawings or where directed by the Project Representative. The area to be paid for shall be based on the dimensions shown on the drawings or where directed by the Project Representative.

The PROJECT REPRESENTATIVE may specify a maximum thickness of 9 inches of full depth asphalt to be used in lieu of approved base material. A thickness of less than 9 inches may be directed by the PROJECT REPRESENTATIVE depending on the site conditions.

The maximum thickness to be paid for under this bid item shall be 9 inches of material acceptably installed within the limits shown on the drawings or where directed by the Project Representative. The weight conversion that will be used use is (110LBS per square yard @ 1 inch thick)/2000. The unit of measure for full depth asphalt shall be tons.

The unit bid price for asphaltic concrete surface and friction courses shall include the cost of furnishing, placing, and compacting material, rolling, and correcting deficient thickness or cross section of base, surface, and friction courses. In addition, the unit price includes the cost of removal and disposal of existing asphalt.

6. MILLING OF EXISTING PAVEMENT

Work Included - Under the Bid Item for Milling of Existing Pavement, furnish all labor, equipment and materials to mill the appropriate thickness and areas of existing asphalt as shown, specified and as directed by the PROJECT REPRESENTATIVE.

PAGE 01025-4

Equipment - A milling machine with a minimum overall length of 18 feet and a minimum cutting with of 6 feet will be required as described in Section 327 "Milling of existing Asphalt Pavement" of the Technical Specification.

Milling shall be made in thickness increments of one inch and shall include proper removal and disposal of the milled material.

Measurement for Payment: The quantity of Milling of Existing Pavement, I-inch depth, in square yards to be measured for payment under this Bid Item will be the actual area of milled pavement placed in the work within the limits shown, specified or directed.

Payment: Payment for Milling of Existing Pavement will be made at the Contract Unit Price per square yard (SY) of this Bid Item.

7. BASE COURSE

This bid item describes measurement and payment for construction of a base course beneath the proposed roadway surface course. Measurement of base course will be on a square yard basis of the base acceptably constructed within the limits shown on the drawings. Payment for base course shall be according to base material and design thickness, as shown on the Proposal.

The unit bid price includes furnishing and installing the base material, adjustment of a moisture content, compaction, finish grading, and bituminous seal coat. No separate payment shall be made for bituminous material utilized in the prime coat.

8. ROADWAY DENSITY TEST AND PROCTOR

This item provides reimbursement of the cost of density test and proctor. Included in the pay item for "roadway density test and proctor - initial" is the cost to obtain up to four densities and two proctors from a certified testing lab. If additional densities are required, they will be paid for under the pay item for "roadway density test - additional". Copies of the density test will be presented with the application for payment. Should any test indicate that any portion of the materials or workmanship does not comply with Section 02100 of the Technical Specifications, a retest shall be performed at the contractor expense.

9. CONCRETE SIDEWALK AND DRIVEWAYS

This bid item includes construction of concrete sidewalk where shown on the drawings. The quantity to be paid for under this item shall be the area, in square yards acceptably installed to the limits and dimension shown on the drawings, or where directed by the Project Representative.

Payment will be according to design thickness of the sidewalk, as designated on the Proposal.

Payment for this bid item includes formwork, concrete, reinforcing, and finishing.

10. MISCELLANEOUS CONCRETE

PAGE 01025-5

Work Included - Under the Bid Item for Miscellaneous Concrete, furnish and place (3000 psi) un-reinforced concrete as shown, specified or directed. The Work includes, but is not limited to, all materials, mixing, placing, forming, and contouring of the concrete and Work incidental thereto. Provide concrete meeting the requirements of Section 33000.

Measurement for Payment: The quantity of Miscellaneous Concrete, in cubic yards, to be measured for payment under this Bid Item will be the actual volumes of concrete placed in the Work, measured in place, within the lines and grades shown and specified or as ordered. Concrete included for payment under other bid items will not be measured again under this bid item.

Payment: Payment for Miscellaneous Concrete will be made at the Contract unit price per cubic yard for this Bid Item.

11. CONCRETE GUTTER, CURB ELEMENTS AND TRAFFIC SEPARATOR

This bid item includes construction of concrete curb and gutter, concrete traffic separator, valley gutter, special concrete gutter, and any concrete curb shown on the drawings or listed on the Proposal.

The quantity to be paid for under this item is the length, in feet, acceptably installed within the limits shown on the drawings. Payment will be according to type of curb, curb and gutter, gutter, or traffic separator, as designated in the Proposal. The unit bid price for this item includes formwork, concrete, reinforcement, and finishing.

12. CONCRETE REMOVAL

This bid item describes measurement and payment for removal of reinforced concrete and miscellaneous rubble within or outside of the limits of construction, where shown on the drawings or where directed by the Project Representative.

The quantity to be paid for is the volume, in cubic yards actually removed. Measurement will be loose, in the truck, by the Project Representative.

The unit bid prices for concrete removal include labor, materials, special tools, equipment, excavation, backfill, hauling, disposal costs, and incidental items necessary to accomplish the work in accordance with contract documents.

13. TRAFFIC CONTROL DEVICES

Traffic Control Devices include barricades, arrow boards, signs, temporary pavement markers, lights and temporary striping.

For all devices the following applies:

PH = Per hour calculated to the closest 15 minutes.

ED = Each per day calculated by rounding up to the next full day.

LF - Actual Linear Footage Measurement.

PAGE 01025-6

All travel, overhead or any other associated expenses in transportation and setting out will be included in the price. Time is calculated by actual time of persons or equipment on the job site.

14. PVC PIPE FOR WATER, RECLAIMED WATER AND FORCE MAINS

This item describes the measure and payment for polyvinyl chloride (PVC) pipe and high density polyethylene (HDPE) pipe. The quantity to be paid for under this item is the length in feet of piping acceptably installed to the limits shown on the drawings or where directed by the Project Representative.

Water mains shall be color coded blue, reclaimed mains shall be color coded purple, and force mains shall be color coded green. For PVC mains, color shall be an integral part of the pipe material.

Certa-Loc pipe is understood to include the cost of fittings (e.g. coupling, gaskets and glands), excluding those which are for change in direction. Fusible PVC shall include the cost to fuse pipe sections together.

Measurement will be horizontally, above the center of the pipe, and includes the length of any valve or fittings.

Payment will be according to the diameter and thickness class as set forth on the proposal. The unit price includes utility location and verification, furnishing and installing all pipe, vinyl identification tape, metallic detectable tape, two pairs of insulated copper locating wires, and materials above and below ground pipeline alignment; joints and jointing materials; bracing, shoring, and sheeting; clearing, grubbing, stripping, and trenching, including exploratory excavation; excavation, bedding and backfill; constructing the specified protection and adjusting of existing aboveground and underground utilities, mail boxes, and service connections;

maintenance of traffic; disposal of spoil; disinfection and hydrostatic testing; and all other related and necessary materials, work and equipment required to construct a complete operable pipeline.

The unit price shall also include the cost to obtain X-Y-Z coordinates of all fittings, plugs, caps, valves, hydrants, taps and restrained joints. The coordinates shall be linked to the 1983 State Plane coordinate system and the 1988 vertical datum and included on the record drawings. All horizontal and vertical data shall be accurate to 5/100ths of a foot or 1.5 centimeters.

15. DUCTILE IRON PIPE FOR WATER, RECLAIMED WATER AND FORCE MAINS

This item describes the measure and payment for ductile iron pipe. The quantity to be paid for under this item is the length in feet of piping acceptably installed to the limits shown on the drawings or where directed by the Project Representative. All ductile iron pipe shall be polyethylene tube encased.

PAGE 01025-7

Measurement will be horizontally, above the center of the pipe, and includes the length of any valve or fittings.

Payment will be according to the diameter, thickness class, and type of joint, whether push-on-joint or factory-restrained-joint, as set forth on the proposal. The unit price includes utility location and verification, furnishing and installing all pipe, polyethylene tube encasement, vinyl identification tape, metallic detectable tape, and materials above and below ground pipeline alignment; joints and jointing materials; bracing, shoring, and sheeting; clearing, grubbing, stripping, and trenching, including exploratory excavation; bedding and backfill; constructing the specified protection and adjusting of existing aboveground and underground utilities, mail boxes, and service connections; maintenance of traffic; disposal of spoil; disinfection and hydrostatic testing; and all other related and necessary materials, work and equipment required to construct a complete operable pipeline.

Restrained and/or mechanical joint pipe is understood to include the cost of fittings (e.g. gaskets and glands), excluding those which are for change in direction. The payment length shall be the pipe length within the limits of restrained joints.

The unit price shall also include the cost to obtain X-Y-Z coordinates of all fittings, plugs, caps, valves, hydrants, taps and restrained joints. The coordinates shall be linked to the 1983 State Plane coordinate system and the 1988 vertical datum and included on the record drawings. All horizontal and vertical data shall be accurate to 5/100ths of a foot or 1.5 centimeters.

16. DUCTILE IRON PIPE FITTINGS WITH RESTRAINED JOINTS (R.J.) FOR WATER

AND WASTEWATER MAINS.

This bid item describes measurement and payment for ductile iron pipe fittings used in the construction and adjustment of water and wastewater mains. The quantity to be paid for under this item is the number of ductile iron pipe fittings acceptably installed as shown on the drawings or where directed by the Project Representative. This bid item includes, but is not limited to, tees, crosses, plugs and caps, and reducers and increasers.

Payment will be according to the diameter and type of fitting as set forth on the proposal. The unit bid price includes utility location and verification, furnishing and installing all fittings and materials above or below ground along the pipeline alignment; joints and jointing materials, including restraining devices; bracing, shoring, and sheeting; clearing, grubbing, and stripping;

trenching, bedding and backfill; constructing the specified protection and adjusting of existing above-ground and underground utilities and service connections; disposal of barriers as required;

and all other related and necessary materials, work and equipment required to construct a complete, operable pipeline.

Each fitting shall include all restrainers, glands, gaskets, rods, nuts, bolts, etc. to make a complete restrained (Restrained Joint R.J.) fitting.

The unit price shall also include the cost to obtain X-Y-Z coordinates of all fittings, plugs, caps, The coordinates shall be linked to the 1983 State Plane coordinate system and the 1988 vertical

PAGE 01025-8

datum and included on the record drawings. All horizontal and vertical data shall be accurate to 5/100ths of a foot or 1.5 centimeters.

17. VALVES AND VALVE BOXES

This bid item describes measurement and payment for valves of various types, and valve boxes, for water and wastewater pipelines. The quantity to be paid for under this item is the number of valves acceptably installed where shown on the drawings or where directed by the Project Representative.

Measurement will be on an individual basis for each type of valve.

Payment will be according to the diameter, type, and joint requirements, as set forth on the Proposal. The unit bid price includes utility location and verification, furnishing and installing valves, restrainers, glands, gaskets, rods, nuts, bolts, etc. to make a complete restrained (Restrained Joint R.J.) valve, valve boxes and covers, extension sterns, excavation, backfill, dewatering and incidental construction.

18. FIRE HYDRANT ASSEMBLY

This bid item describes measurement and payment for installing new fire hydrant assemblies on existing or proposed water mains. The quantity to be paid for under this item is the number of hydrant assemblies acceptably installed to the limits shown on the drawings or where directed by the Project Representative.

Measurement will be on an individual basis for each hydrant assembly.

Payment will be as set forth on the Proposal. The unit bid price includes all items shown in Specification 331002 - Exhibit No. W-5A.

19. RESIDENTIAL METER SERVICES WITH METER BOX

This item describes measurement and payment for installing residential meter services between the main and the meter. The quantity to be paid for under this item is the number of meter services installed where shown on the drawings or where direct by the PROJECT REPRESENTATIVE.

Measurement will be on an individual basis for each meter service installed.

Payment will be according to the size of the meter installation as set forth in the proposal. The unit bid price includes utility location and verification, furnishing and installing the service saddles, meter box, corporation stops, service piping, curb stops, disinfection, testing, excavation, backfill, dewatering and incidental materials and construction. Short side services shall include up to ten (10) feet of 1" polyethylene pipe between the curb and corporation stop. Long side services shall include up to twenty eight (28) feet of 1" polyethylene pipe between the curb and corporation stop. For services longer than the lengths above, the bid item for 1" polyethylene pipe will apply. Service casing/sleeve paid separately.

Double services, long side only, will be constructed by installing two single services in one 3" diameter service casing.

PAGE 01025-9

20. RESTRAINT DEVICE FOR PVC PIPE BELL JOINTS

This item describes measurement and payment for installing restraint devices (for restraining bell and spigot joints of PVC pipe) on water, reclaimed water, and force mains. The quantity to be paid for under this item is the number of restrained joint devices installed where shown on the drawings or where direct by the PROJECT REPRESENTATIVE.

Measurement will be on an individual basis for each PVC pipe bell joint restrainer installed.

Payment will be according to the size of the pipeline. The unit bid price includes furnishing and installing the restraint joint device, excavation, backfill, dewatering and incidental materials and construction.

21. DIRECTIONAL…