10-Change Order Form.pdf.pdf

PDF 201 KB Posted

Attached to
Pipeline Work Order Construction Services - WORCs 6
Solicitation number
IFB-26-00426
Issued by
Hillsborough County, Florida

About this file

This is a Hillsborough County Change Order Form (revised January 29, 2025) used to document modifications to construction contracts executed by the county. The form provides a structured template for authorizing changes and modifications to existing contracts, allowing for adjustments to contract sums, project completion timelines, and other contract terms. The document requires identification of the change order number, bid number, contractor name, project number, and CPA number, along with documentation of whether the change involves time modifications, extra work, credits, or other adjustments. The form necessitates detailed descriptions of proposed changes, cost impact analysis, and documented reasons for the modifications.

The Change Order Form establishes procedures for calculating the revised contract sum by documenting the original contract sum (total Guaranteed Maximum Price), net changes from previous change orders, the contract sum prior to the current change order, and the final contract sum including the current modification. The form requires contractor acknowledgment that all claims for additional time extension and monetary compensation resulting from the changes are waived, except those terms conflicting with the change order. Execution requires approval from the Hillsborough County Board of County Commissioners, the county attorney (for legal sufficiency), the procurement department, and the department fiscal director. The document includes provisions for notarization of contractor signatures (whether corporation, partnership, or individual) and requires surety consent to any change orders affecting contract amounts or completion dates, with corresponding adjustments to performance and payment bonds.

View the file

Other files

File Type Posted
25-Payment Bond.pdf PDF
7-Payment Assistance (SBE Set-Aside).pdf.pdf PDF
4-Allowance Authorization Release Form.pdf.pdf PDF
20-Attachment A - Supplemental Specifications - 10.09.2026.pdf PDF
5-Application for Payment.pdf.pdf PDF
6-Consent of Surety-Change Order.pdf.pdf PDF
12-Substitute W9 Form.pdf.pdf PDF
17-SBE Goal Participation SBE-1 Form Tutorial.mp4 MP4 file
16-Subcontractor Letter of Intent .pdf PDF
9-Consent of Surety to Final Payment.pdf.pdf PDF
18-Attachment B - Utility Accomodation Guide and ROW Use Procedures.pdf PDF
14-Contractors Affidavit for Payment of Debts and Claims 02.18.2026.pdf PDF
22-1. Terms and Conditions.pdf PDF
8-Subcontractors Statement of Satisfaction.pdf.pdf PDF
15-AFFIDAVIT OF COMPLIANCE - Denying Doing Business with a Foreign Country of Concern 02.26.2026.docx DOCX document
24-Bid Bond.pdf PDF
1-Drug Free Workplace Form.doc.doc DOC document
2-Florida Trench Safety Act, Certification and Disclosure Statement.pdf.pdf PDF
19-Attachment C - Insurance Requirements.pdf PDF
23-Agreement - IFB-26-00426.pdf PDF
21-NEW SBE Subcontractors Material Suppliers List SBE-1 Form-10.2026.pdf PDF
13-Direct Deposit Authorization Form 5.15.2025.pdf.pdf PDF
3-Vendor Eligibility Check Prior to Contract Award.pdf.pdf PDF
11-Insurance Certificate.doc.doc DOC document
26-Performance Bond.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised 01.29.2025

HILLSBOROUGH COUNTY

CHANGE ORDER FORM

CONTRACT: CHANGE ORDER NO.:

BID NO:

CONTRACTOR: PROJECT NO:

CPA NO:

TIME CHANGE EXTRA WORK CREDIT OTHER

The Contractor is hereby authorized and directed to make the following changes and modifications to the aforesaid Contract in accordance with all requirements applicable thereto.

DESCRIPTION OF CHANGE:

COST

IMPACT

FINAL

COMPLETION

DAYS

REASON FOR CHANGE:

The original Contract Sum (TOTAL GMP) was . . . . . . . . . . . . $____________ Net change by previous Change Orders . . . . . . . . . . . . . . . . $____________ The Contract Sum prior to this Change Order was . . . . . . . . . . . . . $____________ The Contract Sum will be by this Change Order. . . . . . $ ____________ (increased, decreased or unchanged) The new Contract Sum including this Change Order will be . . . . . . . . . . $ ____________

The Final Completion Milestone prior to this Change Order was .

The time for Final Completion Milestone will be ______________ by __________( )days.

(extended, reduced or unchanged) The Final Milestone for this change order therefore is therefore

The Contractor waives any and all claims to additional time extension and/or additional monetary compensation resulting from these changes and all cost associated with the change order as herein addressed.

Excepting those terms and provisions conflicting with this Change Order which are hereby changed to conform hereto, the aforesaid Contract as amended by all previous change orders hereto is otherwise reaffirmed in its entirety.

IN WITNESS WHEREOF, this Change Order No. _______ to __________________________________ has been executed by the parties hereto or their duly authorized representatives.

ATTEST: VICTOR D. CRIST COUNTY: HILLSBOROUGH COUNTY FLORIDA

Clerk of Circuit Court

BY: BY:

Deputy Clerk Chair, Board of County Commissioners

BOCC Document Number Date of BOCC approval

ATTEST: CONTRACTOR:

BY:

Witness Authorized Signature (SEAL)

TITLE:

DATE:

BOCC Staff Approval Date

Department Fiscal Department Director Procurement County Attorney:

Approved as to Form and Legal Sufficiency

(ACKNOWLEDGMENT OF CONTRACTOR, IF A CORPORATION)

STATE OF )

COUNTY OF )

The foregoing instrument was acknowledged before me by means of physical presence or online notarization this day of , 20 , by ______________________ (Name of person) as____________________________ for ___________________________________________________.

(ie. Officer, attorney in fact) (Name of party on behalf of whom instrument was executed.)

(Signature of Notary Public)

(Print, Type, or Stamp Name of Notary Public)

Personally Known OR Produced Identification

Type of Identification Produced ______________________

(ACKNOWLEDGMENT OF CONTRACTOR, IF A PARTNERSHIP OR INDIVIDUAL)

STATE OF )

COUNTY OF )

The foregoing instrument was acknowledged before me by means of physical presence or online notarization this day of , 20 , by .

(Name of person acknowledging)

(Signature of Notary Public)

(Print, Type, or Stamp Name of Notary Public)

Personally Known OR Produced Identification

Type of Identification Produced ______________________

CONSENT OF SURETY TO CHANGE ORDER

CONTRACT TITLE:

CONTRACTOR (PRINCIPAL):

SURETY:

AGENT:

The SURETY does hereby acknowledge and agree to Change Order No. to the above referenced contract with Hillsborough County, the contract amount (increasing/decreasing) by $ , and/or extending the completion date by ( ) calendar days. The SURETY further acknowledges that the performance bond and/or payment bond furnished under the aforementioned contract is accordingly changed to reflect the change in contract amount, and/or time included in Change Order No. .

This Consent is dated this day of , 20 .

SURETY:

BY: (SEAL)

Authorized Signature

-OR-

BY: (SEAL)

As Attorney in Fact (Attach Power of Attorney)

Printed Name

STATE OF FLORIDA

COUNTY OF HILLSBOROUGH

The foregoing instrument was acknowledged before me by means of physical presence or online notarization this ___ day of ____________, 20___, __________________________ by (Name of person) ________________________ for _________________________________________________.

(ie. Officer, attorney in fact) (Name of party on behalf of whom instrument was executed.)

(Signature of Notary Public) (Print, Type, or Stamp Name of Notary Public)

Personally Know OR Produced Identification

Type of Identification Produced __________________