2. TMOS Technical Requirements Document (TRD).pdf

PDF 469 KB Posted

Attached to
AN/TMQ-53 Tactical Meteorological Observing System (TMOS), Contractor Logistics Support (CLS) effort
Solicitation number
FA8730-20-R-0050
Issued by

About this file

This solicitation requests proposals for a Contractor Logistics Support (CLS) effort for the AN/TMQ-53 Tactical Meteorological Observing System (TMOS). The Air Force Life Cycle Management Center seeks to establish a five-year indefinite delivery, indefinite quantity contract with concurrent ordering and performance options. Proposals are due by 12:00 p.m. EDT on August 17, 2020. The solicitation is set aside for small businesses with annual receipts less than $16.5 million. The CLS effort includes logistics support for the TMOS to facilitate observation and transmission of meteorological data to forecasting systems from remote locations worldwide. The resulting contract will utilize delivery orders to obligate funds for the minimum order quantity and future requirements over the five-year period.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15 January 1998 Rev1: 16 December 1999

Rev 2: 07 Feb 2004 Rev 3: 19 Jun 2014

TECHNICAL REQUIREMENTS DOCUMENT (TRD)

FOR THE

TACTICAL METEOROLOGICAL OBSERVING SYSTEM (TMOS)

ii

Table of Contents

1 Scope 1

1.1 Identification 1

1.2 System Overview 1

1.3 Document Overview 1

2 Applicable Documents 2 3 System Requirements 2

3.1 Weather Requirements 2

3.2 Additional Weather Requirements 3

3.3 Component Processing Unit 4

3.4 Software Module 4

3.5 Employment 5

3.6 External Interfaces 6

3.7 Communications 9

3.8 Physical Characteristics 10

3.9 Logistics and Readiness 10

3.10 Critical System Characteristics 11

3.11 Integrated Logistics Support 12

4.0 Iridium Requirements 14

4.1 Physical 14

4.2 Software 15

5.0 Notes 17

5.1 Reference Documents 17

5.2 Abbreviations and Acronyms 17

Attachments Photographs of three TMQ-53 transit cases 19 Requirements Correlation Matrix (RCM) 1-1

1.0 SCOPE

1.1 Identification. This technical requirements document (TRD) is applicable to the Tactical Meteorological Observing System (TMOS) Modification.

1.2 System overview. The TMOS will be deployed and maintained by Air Force Weather personnel. The TMOS will be capable of determining surface pressure, wind speed and direction, temperature, dewpoint temperature, relative humidity, precipitation accumulation and rate of fall, cloud coverage, cloud height, surface visibility, present weather, precipitation detection, and lightning (direction and range). The TMOS must be able to facilitate tailoring of the sensor suite to meet specific mission requirements.

The TMOS must automatically collect, display and transmit data to computer based forecast systems (e.g. Joint Environmental Toolkit (JET)). The program is limited to off-the-shelf components. No hardware development is involved. The TMOS will include a geo-locating and automated compass orientation (built-in or electronic) capability for platform location information.

In 2004 Air Force Weather Weapons System (AFWWS) required an expansion to the TMOS to add the capability to disseminate formatted observations via the Iridium Satellite Communications System (Iridium). The capability must provide Combat Weather Teams (CWTs) deployed to remote or isolated environments the ability to transmit METAR and SPECI observations generated by Automated Observing System (AOS) (written by General Dynamics) to the Weather Product Management Dissemination System (WPMDS), or equivalent, without human intervention.

The TMOS shall produce the following observations:

1.2.1 Raw data every 5 seconds and hourly observations while connected to a JET/SCA server.

1.2.2 Aviation Routine Weather Reports/Aviation Selected Special Weather (METAR/SPECI), the traditional weather message that is distributed via the Air Force/NWS/FAA national circuits. METAR/SPECI reports are produced hourly and when special criteria are met.

1.3 Document overview. The purpose of this TRD is to document the full range of required capabilities of the TMOS.

Figure 1.2-1, TMOS Block Diagram, indicates a typical TMOS system configuration.

Figure 1.2-1 TMOS Block Diagram

2.0 APPLICABLE DOCUMENTS

Federal Meteorological Handbook No. 1, “Surface Weather Observations and Reports,” September 2005.

AFMAN 15-111, “Surface Weather Observations,” 27 February 2013.

Weather Systems Support Cadre (WSSC) Concept of Operations (CONOPS)

AFMAN 24-204, “Preparing Hazardous Materials for Military Air Shipment,” 3 December 2012.

3.0 SYSTEM REQUIREMENTS

3.1 Weather Requirements. The weather requirements shall be collected by environmental sensors capable of measuring the required meteorological variables.

These sensors shall provide signal outputs representing the sensed weather element data. Sensors shall comply with the functional and environmental requirements specified in Section 3.10 as well as the reliability, availability, and maintainability performance specified in Section 3.9. Sensors selected shall be Federal Meteorological Handbook 1 (FMH-1) and WMO compliant. Sensor data shall be encoded into digital form either at the sensor or in the system data logger.

3.1.1 Surface Pressure. Surface pressure must be determined to an accuracy of +/-

0.6 millibar (mb) between 640 and 1080 mb. The TMOS must compute, display, and relay pressure altitude, density altitude, altimeter settings, and 3 hour pressure trend/tendency as well as surface pressure.

3.1.2 Wind Speed and Direction. The wind speed must be accurate to +/- 1 knot (kt) from 0 and 24 kts and accurate to +/- 2 kts from 25 kts to 70 kts. Prevailing wind direction must be accurate to +/- 5 degrees. Wind speed (including gusts and squalls) and direction must be reported and displayed in accordance with AFMAN 15-111. Wind sensors must be adjustable to a height range of 6 feet to 12 feet above ground level.

The wind direction sensor shall be aligned to true north.

3.1.3 Temperature. Temperature must be accurate to +/- 1.0 degree (deg) Celsius (C) between -40 deg C to +50 deg C .

3.1.4 Dewpoint. The surface dew point must be determined to an accuracy of +/- 2 deg C from -20 deg C to +30 deg C. This parameter can be determined using temperature, relative humidity, and pressure.

3.1.5 Relative Humidity (RH). Relative Humidity must be displayed upon request and be accurate to +/- 5%. Operating range must be 5% to 100%.

3.1.6 Liquid Precipitation.

3.1.6.1 Must be able to measure liquid precipitation rate of fall up to 3 inches per hour and accurate to the nearest tenth of an inch. Must be able to measure liquid precipitation amounts and the water equivalent of freezing and frozen precipitation.

3.1.6.2 Must be able to measure a minimum amount of .01 inches liquid precipitation.

3.1.6.3 Must report liquid precipitation accumulations from past 24 hours.

3.2 Additional Weather Requirements

3.2.1 Cloud Base Height/Coverage/Vertical Visibility.

3.2.1.1 The cloud cover must be determined to a sky category of clear (no clouds), few (less than 1 okta to 2 oktas), scattered (3 to 4 oktas), broken (5 to 7 oktas), or overcast (8 oktas) from 100 feet to at least 10,000 feet (ft) or greater.

3.2.1.2 The cloud base heights and/or vertical visibility must be accurate to +/- 50 ft up to 5,000 ft, and +/- 100 ft above 5,000 ft.

3.2.1.3 Must be able to detect 3 different layers of clouds simultaneously from 100 feet to 10,000 feet.

3.2.1.4 Eye Safety. The ceilometer sensor shall be designed to have accessible emission limits for laser radiation, with Class 3B maximum accessible emission level applied to direct viewing without optical instruments (excluding ordinary eyeglasses).

3.2.2 Surface Visibility. The surface visibility must be accurate to +/- 10 % of actual conditions. The range for visibility determinations must be from 0.0 kilometers (km) to 10 km. Visibility must be determined in 0.1 km intervals from 0.0 km to 5 km and in 1.0 km intervals from 5 km to 10 km. Visibility must be reported in meters (m), nautical miles (nm), and statute miles (sm), selectable by the user.

3.2.3 Present Weather. Present weather and obscurations must be identified as fog, haze, or precipitation (rain, freezing rain, drizzle, freezing drizzle, snow).

3.2.4 Precipitation Detection. Precipitation type must be identified as liquid, solid, or freezing with 90% accuracy. Precipitation rate must be measured in increments of 0.1 inches per hour with an accuracy of +/- 10%. Precipitation amounts (liquid equivalent) must be measured in increments of 0.01 inches with an accuracy of +/- 10% and measure up to 10 inches over a 6 hour period. The sensor shall report the start and end of a precipitation event within five minutes of the time that it occurs. Precipitation intensity must be identified as light, moderate, and heavy in accordance with AFMAN 15-111. Hourly, three, six, and 24-hour accumulation of precipitation (liquid equivalent of solid) must be reported.

3.2.5 Lightning Detection System (LDS). Lightning detection system must detect cloud-to-ground lightning occurrences out to a minimum of 30 nm in all directions from the lightning sensor with an accuracy of +/- 0.5 nm.

3.3 Component Processing Unit. Each TMOS must contain a component processing unit capable of consolidating inputs from all system sensors and provide single data stream outputs. This unit must be capable of connecting to a hand held display unit or a forecasting system (JET) by direct connection and Radio Frequency (RF). Each component processing unit shall incorporate built-in-test capability. Means shall be provided for bi-directional communication between the users and sensors with support for self-test. Testing of sensors shall not adversely affect the operation of sensors not involved in the test.

3.4 Software Module. Software for the TMOS has to work on Windows based computers (e.g., JET). This module would run on the Component Processing Unit in absence of forecast systems. The software must produce an automated METAR observation per FMH No. 1 that can be easily edited by the user. Daily data archiving must be available both to the computer hard disk drive and to temporary storage media (e.g., CD). Transmission of the observations will use existing AFW methods. (Note:

AFW does not currently plan to automatically send machine-prepared observations. All observations are planned to have weather personnel provide final editing, review, and transmission of data prepared in the METAR and US METAR format.)

3.4.1 Data Processing Timely and accurate observations are critical to precision forecasting, relevant product generation, and sound decision-making inputs for commanders at all levels of operations. The system must provide weather personnel a reliable, in-garrison and deployable capability to ensure accurate data to analyze weather phenomena and assist in the decision-making process. The following data processing capabilities shall be provided:

3.4.1.1 Average the measurements as appropriate for each weather element.

3.4.1.2 Calculate the one-minute observation for display and long line transmission.

3.4.1.3 Prepare hourly METAR/SPECI messages at the hourly report time, +/- 5 minutes around the hour + 55 minutes. The METAR/SPECI messages shall be transmitted at the hourly transmission time. The METAR report shall be adjustable in 1 minute increments over a +/- 5 minutes period around the hour + 55. The transmission time shall be adjustable in 1-second increments from 1 second to 5 minutes following hourly report time.

3.4.1.4 Provide notification via alarms to operators whenever a METAR or SPECI observation is prepared.

3.4.1.5 Continuously monitor data thresholds to determine if special reports are required e.g., ceiling minimums, thunderstorms, and freezing rain. Prepare a SPECI using METAR format whenever processing of an algorithm calls for one. The SPECI transmission shall be within 5 minutes after detection of the need for a special report, adjustable in 1-second increments. Processing shall continue during the period between detection and transmission of the Special Observation.

3.4.1.6 Continuously monitor operator interface functions to incorporate operator changes that affect the algorithm processing and data output.

3.4.1.7 Continuously monitor precipitation accumulation data thresholds to determine if METAR or SPECI reports are required.

3.4.1.8 Prepare a special or urgent special when requested by an operator.

3.5 Employment

3.5.1 Set Up and Tear Down. The TMOS will be capable of being set up or torn down by two people wearing full chemical protective clothing in 60 minutes or less. Set up and tear down will not require special tools not supplied with the TMOS.

3.5.2 Operators. The TMOS will support one person operation once set up is complete.

3.5.3 Siting. Personnel will set up the TMOS at a location as meteorologically representative as possible. Weather equipment must be adequately supported to be stable during high winds and be able to support system, ice and wind loads. These severe conditions are the very weather elements that the automated weather observing systems are supposed to measure and provide data for. The equipment mountings will be designed to support the desired equipment load to eliminate vibration and swaying which can result in erroneous readings.

3.6 External Interfaces. The TMOS must include software capable of operating on computer based systems (e.g., JET).

3.6.1 TMOS Information Flow. Figure 3.6.1-1 below depicts the flow of information from the sensors to a Microsoft Windows based laptop computer and to the Iridium SATCOM or NIPRNet. The TMOS laptop computer must provide METAR and SPECI formatted information interfaces to two sources. The TMOS will interface with two modes of common user LAN connectivity:

The first common user connection, as identified in the TMOS architecture shown in Figure 3.6.1-1, may be connected directly to a base network that is connected to the NIPRNET. METAR and SPECI formatted information will be sent to the Air Force Weather Agency (AFWA) Weather Product Management and Distribution System

(WPMDS).

A second common user connection (shown in Figure 3.6.1-1) makes use of the Iridium SATCOM configuration. The Iridium gateway forwards the METAR and SPECI information to the WPMDS.

The laptop must employ the software module to process and display sensor information.

This information must be sent at a predetermined rate to the WPMDS.

Figure 3.6.1-1: TMOS Data Flow Diagram

The following table lists external connections, data sensitivity, and security controls used to minimize risk.

3.6.2 JET Interface. The TMOS shall provide processed data and formatted METAR and SPECI observations to JET for storage, display, and dissemination. TMOS/JET interface shall provide a continuously updating ASCII text data stream in XML format.

3.6.2.1 Processed Data. Data fields in the Identifier, Time and Wind groups shall be sent every 5 seconds to JET. The frequency of this message delivery shall default to 5 seconds but be configurable in 5 second increments. The rest of the parameter groups shall be added to the message, at a minimum, every 60 seconds. The frequency of these parameter groups shall also be configurable by a Government System

Administrator. The following table identifies the data that shall be sent:

Parameter Group

Parameter Notes

Identifier

Active runway designation

Time Timestamp The time that the processed data message was formed

Wind Instant Wind Speed The Instant wind measurements are actually a 5 second average of the measurements

Instant Wind Direction Directions should not be rounded.

Instant Cross Wind Running Average Wind

Speed 2 minute running average

Running Average Wind Direction

2 minute running average

Running Average Cross Wind

2 minute running average

Wind Variability Per FMH-1 Wind Gust Per FMH-1 Peak Wind Speed Peak wind in the last hour Peak Wind Direction Peak wind in the last hour Time of peak Peak wind in the last hour Discontinuity and Midfield

Winds Same as primary sensor group

Temperature Running Average Air

Temperature Running 5 minute average

Running Average Relative Humidity

Running 5 minute average

Running Average Dewpoint

Running 5 minute average

Pressure Pressure at Field

Elevation (Station Pressure)

All pressures are 1 minute averages.

Altimeter Setting 1 minute average. Must be calculated from the station pressure

Pressure at Sea Level Pressure Altitude Density Altitude Pressure change in the last 3 hr

Present Weather

AFMAN present weather identifier.

Shall be the same as the identifiers in the AFMAN 15- 111 Table 19-1.

Parameter Group

Parameter Notes

Precipitation Rain accumulation in the last 1hr

Rain accumulation in the last 3hr last 6hr last 24 hr

Rain Rate

Sky Condition Vertical Visibility Height base #1 Cloud heights should not be rounded.

Coverage at base #1 See TRD 3.3.5 Height base #2 Coverage at base #2 See TRD 3.3.5 Height base #3 Coverage at base #3 See TRD 3.3.5

Visibility 1 minute average visibility See AFMAN 15-111 Table 18-

10 minute average visibility

Lightning 15 min. cloud to cloud flash count

15 min. cloud to ground flash/stroke

Bearing and distance 0-30 nautical miles

Table 3.6.2.1-1 Required Data

3.7 Communications. The TMOS must communicate with computer based weather systems (e.g., JET). Each TMOS transmission must have identification tagged to each system and capable of remote activation from the weather systems. The TMOS will interface with a remote display which will have two-way connection back to the sensor suite and be co-located with the weather workstation, thus enabling the remote activation required by the user. The remote display will then send the data one-way via a simplex network to the forecast system (JET). This remote capability must be able to direct the TMOS to observe and transmit at selectable time periods, to turn the system on and off, or hold transmission, and respond to automatic query of sensor status. The means of communication must be as follows:

3.7.1 Hardwire. The TMOS must be capable of up to a 200 feet hardwire interface.

This interface must allow data exchange between the TMOS and both the computer based weather system and the hand held display device, with a minimum of one device connected at a time.

3.7.2 Radio Frequency (RF). The TMOS must be capable of RF transmission and receipt up to a minimum of 5 nm. The TMOS RF transmission frequencies must be adjustable to mitigate interference with other mission requirements.

3.7.3 Hand Held Display. The display must be easily readable under all light conditions, using US and metric units, and should have a dimming capability or cover for low light operations. The display will show a minimum reportable value for any and all sensors that comprises the TMOS.

3.8 Physical Characteristics

3.8.1 Weight and Volume. The total packaged weight of the TMOS must be no more than 200 pounds, broken into packaged components that are two-person portable (i.e., no more than 84 pounds). The TMOS must fit on 1/8 of a standard 463L pallet. The 463L pallet dimensions are 108 L x 88 W x 88 H inches.

3.9 Logistics and Readiness

3.9.1 Mission Reliability. The TMOS must have a mission reliability of greater than 95 percent for a 30 day mission. This corresponds to a Mean Time Between Critical Failure (MTBCF) of 3200 hours. The critical path of the TMOS consists of surface wind speed and direction, surface temperature, dew point temperature, surface pressure, and component processor unit, and the data interface with hand held display unit. A critical failure is any hardware or software degradation, indication of failure, or actual failure of the above parameters.

3.9.2 Availability (Up-Time Ratio (UTR)). The TMOS must achieve at least 96 % UTR for the critical path. UTR is the percentage of time that operational equipment is able to satisfy critical mission needs relative to the designated operational capability.

3.9.3 Maintainability (Mean Repair Time (MRT)). The MRT must not exceed 30 minutes. This is the equipment corrective maintenance time. It includes all maintenance actions needed to correct a malfunction, including troubleshooting and removing and replacing LRUs. A LRU is defined as a single sensor or sensor suite that is plugged in or out of the component processing unit. MRT does not include Administrative Logistics Delay Time (ALDT).

3.9.4 Operator Maintenance. The TMOS is highly modular and requires very little operator maintenance. This system replaced the TMQ-33, TMQ-34, and TMQ-36.

Most maintenance will consist of removal and replacement of Line Replaceable Units (LRUs) and batteries. The deploying weather teams will maintain their equipment. If needed, they can contact the WSSC for maintenance assistance and ordering replacement LRUs.

3.9.5 Preventive Maintenance. Preventive or scheduled maintenance must not exceed 120 minutes per 30 day period for the critical path, when in an operational environment. The enhancements will add no more than an additional 120 minutes per 30 days.

3.9.6 Deployability. The TMOS must be deliverable, worldwide, using air and surface transportation methods. The TMOS must operate continuously for 30 days (with spares and supplies) after a period of dormancy not exceeding 1 year (excluding replacement of batteries).

3.9.7 Failure Diagnostics Techniques. The TMOS must be able to continuous self-detect and allow separate technician direct dialog to TMOS components to diagnose possible sensor degradation, component processing unit errors, communication link problems, power interruption, and other failures. The TMOS must display a human readable fault identification message. Field maintenance must allow for the removal and replacement of defective LRUs.

3.10 Critical System Characteristics

3.10.1 Environmental Conditions. The environmental operating conditions for the TMOS routinely exposed to the environment: temperature range from -40 deg C to +50 deg C, humidity range from 5% to 100%, wind range from 0 kts to 70 kts, and altitude from –50 ft to 12,000 ft above Mean Sea Level. Exposed equipment must be able to effectively operate in blowing sand and dust, mist, salt spray, and in all forms of precipitation. TMOS equipment must be protected against environmental contamination (snow, salt, precipitation, etc.) when configured for storage. Outside storage environmental conditions: temperature range from -40 deg C to +60 deg C, humidity range from 0% to 100%.

3.10.2 System Security. The TMOS will operate at the unclassified level. The TMOS will not process classified information. To reduce chances of detection on the battlefield, the system must possess a near silent, lightless capability. Components must emanate as little sound as feasible and any exterior lighting (on-site display/manipulation devices) must minimize the chance of visual detection under all lighting conditions.

3.10.3 Nuclear, Biological, and Chemical (NBC). The TMOS does not require special protection or hardening to survive in an NBC environment. If the TMOS is deployed to a location that becomes affected by biological or chemical agents, operators will continue to use the system as long as they operate in that location.

3.10.4 Power. The TMOS must be capable of operating from international commercial power sources (i.e. 110 to 120 VAC and 220 to 240 VAC, 50Hz - 60 Hz) AC power.

This includes Government Furnished Equipment (GFE) field power generation equipment. The TMOS must be capable of operating independent of an AC power source without interruption and not rely on the replacement of batteries (e.g., nickel/lithium batteries, recharging batteries using solar power, etc.) for a minimum of 30 days in all deployed theaters. The TMOS will rely on AC power, if required by the site, to power all components. When operating on AC power and it is lost, the TMOS’s internal power source (i.e., solar power, batteries, UPS, etc.) must automatically ensure continuous operation for a minimum of 24 hours in a limited mode, if necessary (i.e., reduced operation of some non-critical sensors). Upon restoration of normal power after a shutdown, the TMOS must automatically restart all functions. Failure of the UPS while commercial power is available shall not affect the operation of the TMOS.

3.10.5 Leap Year Calculations. TMOS software must accurately process date/time data (including, but not limited to calculating, comparing, and sequencing) from leap year calculations, to the extent that other information technology, used in combination with TMOS, properly exchanges date/time with it.

3.10.6 Electromagnetic Interference. The TMOS system shall be electromagnetically compatible within itself and with other systems in its operating environment. The operational performance shall not be degraded by electromagnetic environmental effects (E3). Systems will also comply with the applicable DoD, National, and International spectrum management policies and regulations.

3.10.7 Laptop

The TMOS laptop shall be ruggedized to handle the extreme conditions that the system shall be exposed to. This includes drop shock protection and spill-resistant components.

3.11 Integrated Logistics Support

3.11.1 Maintenance Planning. The TMOS will use a two level maintenance concept:

organizational and depot level support. The maintenance concept for the TMOS at the organizational level is for LRU removal and replacement, and preventive maintenance.

Unserviceable LRUs will be sent to the depot.

3.11.2 Support Equipment (SE). Maintenance SE will be kept to a minimum. The maintenance concept will maximize the use of self-diagnostics, technical data, and resident and/or loaded diagnostic software to isolate to the LRU assembly.

3.11.3 Human Systems Integration. The TMOS is being developed to allow fielding within current manpower constraints. It will be used for in-garrison (training) and deployed environments.

3.11.3.1 Training. Major Commands (MAJCOMs) will coordinate on operations and maintenance training requirements with Air Education and Training Command (AETC) via the formal training planning process. Instruction should provide tutorials and training for the general areas of training identified below. Specific training requirements will be developed by the Major Commands when a prototype system becomes available for use.

3.11.3.1.1 Initial Training. This training concept envisions Type 1 (Contractor) operations and maintenance training for the initial cadre of AETC instructors, Weather System Support Cadre (WSSC), and Qualification Operational Test and Evaluation (QOT&E) participants. The contractor will submit their training package to the MAJCOMs periodically during development for evaluation and revision. The contractor will provide the entire training package to the MAJCOMs for evaluation and revision before performing initial training to any organization. Any user/operator manuals developed by the contractor will be evaluated and reviewed by the MAJCOMs prior to fielding of the system. All training materials should be developed using a train the trainer concept and should be distributed to the units as part of system fielding. In 2014 this requirement was deemed irrelevant due to the age of the system and is no longer a contractor requirement.

3.11.3.1.2 Operator Training. The need for Type III (resident) training will be assessed after receipt of the prototype system. If an AETC Supplemental Course is deemed necessary, the MAJCOMs will coordinate on operations and maintenance training requirements with Air Education and Training Command (AETC) via the formal training planning process. Training for this system may be integrated into existing AETC courses. Training requirements will focus on: set up/tear down, graphic user interface (GUI), functionality of the application software, product interpretation, system administration (if any), connectivity to standard weather systems (e.g., JET), maintenance training including: fault detection/isolation, removal/replacement of LRUs, and preventive maintenance (if any), packing and transportation procedures, and review of the system CONOPS and Operations Manuals.

3.11.3.1.3 Unit Level Training. Qualification Training Packages (QTP’s) will be developed by the government. QTP’s will be completed at the unit level. Type IV (job-site/exportable) training material which is part of the QTP, will be developed to allow system familiarization training AF-wide at the unit level.

3.11.4 Other Logistics Considerations

3.11.4.1 Technical Data. Technical orders or vendor documentation for each level of operation and repair will include illustrated parts breakdowns, parts listings, theory of operation, and maintenance and troubleshooting guides.

3.11.4.2 Hazardous Materials. Design of the TMOS will minimize the need for hazardous materials (i.e., batteries containing sulfuric acid) in the operation of the system as defined by AFMAN 24-204.

3.11.4.3 Resupply. The system shall be able to operate for 30 days without resupply.

The need for resupply will be minimized.

3.11.4.4 Materiel Requirements

3.11.4.4.1 Unique or additional depot facility requirements. No unique depot or commercial facilities will be required.

3.11.4.4.2 Special packaging, handling, storage and transportation requirements.

All systems (including the supplies, power sources, etc.) must be packed to withstand reasonable amount of shock and vibration.

3.11.4.4.3 Technical Orders. Technical order documentation for each level of operation and repair will include illustrated parts breakdowns, parts listings, theory of operation, maintenance, and troubleshooting guides.

3.11.4.4.4 Special requirements for disposal of hazardous waste. Operators will work with the local Bio-environmental engineering offices to dispose of environmentally hazardous materials such as batteries. The use of hazardous material in the TMOS will be minimized.

3.11.4.4.5 Spares strategy. The contractor will maintain a Spares Management Program.

3.11.4.4.6 System warranties and guarantees. Specific system and assembly warranties will be obtained for TMOS hardware and software. The TMOS contractor will manage the warranty process for all components and sensors and be the single point of contact for warranty issues. (Operator/users will not contact or ship components/sensors directly to individual manufactures for warranty repair).

4.0 IRIDIUM REQUIREMENTS. The Iridium upgrade provides all hardware and software to interface a standard PC laptop computer to an Iridium interface device, which establishes an IP connection between the laptop and the DISA Iridium NIPRNET Gateway. The system must successfully transmit METAR and SPECI observations 95% of the time. Proposed solutions must meet the following requirements.

4.1 Physical

4.1.1 Iridium upgrade solution consists of at least three components: Iridium modem, Antenna, Software

4.1.2 Modem

4.1.2.1 The modem interfaces with the TMOS PC. In order to make the modem appear as a network connection, drivers must be provided that will integrate it to the computer.

4.1.2.2 External modem dimensions, including any non-removable cables, connectors or power adapter must fit within available space inside existing TMQ-53 transit cases (see Attachment 1).

4.1.2.3 Modem may be powered by either internal or external power supply and must be compatible with 100 – 240 VAC and 50 – 60 Hertz sources. It must contain a set of international power plug adapters to include, but not limited to; U.S, U.K, European and Asian plugs.

4.1.2.4 If external power supply is required, the power supply external dimensions, including any non-removable cables, connectors or power adapter must fit within available space inside existing TMQ-53 transit cases (see Attachment 1).

4.1.2.5 Modem must meet U.S. Government FIPS 140-2 wireless standards.

4.1.2.6 Modem must be compatible with the Defense Information Security Agency (DISA) Iridium NIPRNET Gateway (via use of DISA provisioned SIM Card).

4.1.2.7 Modem and any other “indoor equipment” will operate in a tactical office environment, including, but not limited to temperature extremes ranging from 20F to 120F and frequent power fluctuations.

4.1.3 Antenna

4.1.3.1 Antenna must be approved for continuous outdoor use and must be able to effectively operate in blowing sand and dust, mist, salt spray, and in all forms of precipitation.

4.1.3.2 Must be capable of communication with the Iridium Satellite Constellation from any location on the globe.

4.1.3.3 The antenna must be freestanding for use in a tactical environment, either with its own integrated mast or with a separate tripod mount. The antenna must not be integrated with the TMQ-53 tactical sensor suite.

4.1.3.4 Antenna and mount will be finished in field-neutral color (brown, tan or olive).

4.1.3.5 The antenna and mount, in the stored/transport configuration, must fit within available space inside existing TMQ-53 transit cases (see Attachment 1).

4.1.3.6 Antenna will be provided with a minimum of 50 feet of cable for remote positioning of the antenna from the modem. The cable will be finished in black or another field-neutral color (brown, tan or olive).

4.1.4 Environmental

4.1.4.1 The antenna must operate under the following environmental conditions:

4.1.4.1.1 Temperatures from -40 to +85 degrees C

4.1.4.1.2 Wind speed up to 70 knots

4.1.4.1.3 Elevations to 20,000 feet.

4.1.4.1.4 Relative humidity from 5% to 100%

4.2 Software

4.2.1 All software will be compatible with the current government approved baseline Operating System.

4.2.2 Modem drivers will allow Windows operating system to utilize the Iridium modem.

4.2.3 Software will include an automated dialer program capable of establishing connection with the DISA Iridium gateway, completing transfer of all data and disconnecting from the gateway when transmission is completed. The system must be capable of repeating this process at least once every 5 minutes. This capability may be integrated into AOS.

4.2.4 Dialer software will operate automatically whenever AOS requests a network connection as needed, without human intervention.

4.2.5 Dialer software will be configured to attempt transmissions only when sufficient signal strength is present. (Note: based on preliminary testing, we consider minimum signal strength as 2 out of 5 bars as seen on the Iridium phone.)

4.2.6 Software will include an Iridium satellite signal strength meter displayed within the windows GUI.

4.2.7 Must be able to transmit 1-2kb text files generated by AOS using File Transfer Protocol (FTP).

4.2.8 The drivers cannot interfere with AOS’s operation and the user must be able to simultaneously view incoming information on AOS while it is sending the observation (i.e., it must be a background operation.).

5.0 NOTES

5.1 Reference Documents

Document No. Title

AFMAN 15-111 Surface weather Observations FMH-1 Federal Meteorological Handbook No. 1, Surface Weather Observations and Reports AFPD 33-2 C4 Systems Security AFI 21-116 Maintenance Management Of Communications Electronics AFI 31-101V1 The Physical Security Program AFI 31-209 The Air Force Resource Protection Program AFI 31-401 Managing the Information Security Program AFJMAN 24-204 Preparing Hazardous Materials For Military Air Shipments AFSSI 5001 System Security Policy Generation AFSSI 5017 Deployable Computer Systems Security MIL-STD-1472D Human Engineering Design Criteria for Military Systems, Equipment, and Facilities

5.2 Abbreviations and Acronyms

Abbreviation or Acronym Meaning

AC Alternating Current AETC Air Education and Training Command AF Air Force AFI Air Force Instruction AFJMAN Air Force Joint Manual AFMAN Air Force Manual AFMC Air Force Materiel Command AFPD Air Force Policy Directive

AFSSI Air Force System Security Instruction AFW Air Force Weather AFWA Air Force Weather Agency AGL Above Ground Level ALDT Administrative Logistics Delay Time avg average BIT Built-in Test BITE Built-in Test Equipment C Celsius CONOPS Concept of Operations COTS Commercial Off-the-Shelf DC Direct Current deg degrees DISN Defense Information Systems Network DoD Department of Defense EMP Electromagnetic Pulse ft feet GFE Government Furnished Equipment GT Greater Than GTE Greater Than or Equal to HQ Headquarters hr hour HSI Human Systems Integration IAW In Accordance With ILS Integrated Logistics Support ILSP Integrated Logistics Support Plan in inch JET Joint Environmental Toolkit km kilometers kt knot LRU Line Replaceable Unit LSP Logistics Support Plan LT Less Than LTE Less Than or Equal to m meters MAJCOM Major Command mb millibar METAR Meteorological Aviation Report min minute nm Nautical Mile MTBCF Mean Time Between Critical Failure MRT Mean Repair Time NBC Nuclear, Biological, and Chemical OJT On-the-job Training ORD Operational Requirements Document OT Operational Test RCM Requirements Correlation Matrix RH Relative Humidity

SE Support Equipment TMOS Tactical Meteorological Observing System TBD To Be Determined TO Technical Order UPS Uninterruptable Power Supply USAF United States Air Force UTR Up-Time Ratio WSSC Weather Systems Support Cadre

Attachment 1

QTR101 Basic Sensor Transit Case:

QTR102 Basic Tripod Transit Case:

QTR103 Spares and Tool Kit Transit Case:

QTR104 Ceilometer Transit Case:

QTR105 Enhanced Power Supply Transit Case:

REQUIREMENTS CORRELATION MATRIX

Atch 1-1

SYSTEM CHARACTERISTICS THRESHOLD REQUIREMENTS REFERENCES

1. Accuracy and Range

a. Surface Pressure (paragraph 3.1.1)

(1) Accuracy +/- 0.6 mb

(2) Range 640 mb to 1080 mb

(3) Reported/Displayed Altimeter setting (selectable, inches of mercury or millibars), Pressure altitude, Density altitude, 3 hour pressure trend/tendency, and surface pressure

IAW AFMAN 15-111

b. Winds (paragraph 3.1.2)

(1) Speed

(a) Accuracy +/- 1 kt (0 to 24 kts); +/- 2 kts (25 to 70 kts)

(b) Reported/Displayed IAW AFMAN 15-111

(c) Gusts (Speed, Squalls) IAW AFMAN 15-111

(2) Direction

(a) Accuracy +/- 5 deg

(b) Reported/Displayed IAW AFMAN 15-111

(3) Measurement Height 6 ft to 12 ft

c. Temperature (paragraph 3.1.3)

(1) Accuracy +/- 1.0 deg C

(2) Range -40 deg C to +50 deg C

(3) Reported/Displayed to nearest whole deg C/F IAW AFMAN 15-111

d. Dewpoint (paragraph 3.1.4)

(1) Accuracy +/- 2.0 deg C

(2) Range -20 deg C to +30 deg C

(3) Reported/Displayed to nearest whole deg C/F IAW AFMAN 15-111

e. Relative Humidity (paragraph 3.1.5)

(1) Accuracy +/- 5%

(2) Range 5% - 100%

(3) Reported/Displayed to nearest whole %

f. Liquid Precipitation (paragraph 3.1.6)

(1) Accuracy +/- 0.1 inch

(2) Range 0.01 to 3.0 inches/hr

(3) Reported/Displayed total precip for past 24 hrs to nearest 0.1 inch

IAW AFMAN 15-111

j. Clouds Base Height/Coverage/Vertical Visibility (paragraph 3.3.1)

(1) Coverage CLR, FEW, SCT, BKN, OVC IAW AFMAN 15-111

(2) Heights (Bases) 100 ft to 10,000 ft

(a) Accuracy +/- 50 ft to 5,000 ft, +/- 75 ft above 5,000 ft

(b) Layers will detect all layers of clouds visible up to five

(3) Reported/Displayed IAW AFMAN 15-111

k. Surface Visibility (paragraph 3.3.2)

(1) Accuracy +/- 10%

(2) Range 0.0 km to 10 km

(3) Intervals Measured 0.1 km (0.0 km to 5.0 km)

1.0 km (5.0 km to 10.0 km)

Atch 1-2

(4) Reported/Displayed Kilometers, nautical miles, or statute miles, user selectable

IAW AFMAN 15-111

l. Present Weather(paragraph 3.3.3)

(1) Identification Fog, haze, or precipitation (rain, drizzle, snow, freezing rain, freezing drizzle)

(a) Accuracy 90%

(2) Reported/Displayed IAW AFMAN 15-111

m. Precipitation Detection

(1) Identification liquid, solid, freezing

(a) Accuracy 90%

(2) Precipitation Rate 0.1 in/hr

(a) Accuracy +/- 10%

(3) Precipitation Amounts 0.01 in

(a) Accuracy +/- 10%

(4) Total Precipitation Amount 10 in/6 hr

(5) Accumulation Reporting Hourly, 3, 6, 24 hr (liquid equivalent of solid)

(6) Intensity reporting Light, moderate, and heavy IAW AFMAN 15-111

(7) Reported/Displayed IAW AFMAN 15-111

n. Lightning Detection (paragraph 3.3.5)

(1) Type of System Passive

(2) Types of Lightning Detected Cloud-to-ground

(3) Range of Detection 30 nm radius

(4) Ranging Accuracy +/- 0.5 nm

(5) Directional Accuracy +/- 10 deg

(6) Reported/Displayed direction in degrees, distance in nm This will be reported in remarks of the METAR observation

o. Hand Held Display (paragraph 3.5.1)

(1) Readout value for each sensor on system

(2) Easily Readable Under all light conditions

(3) Standard Units of Measure US and Metric

p. Software Module (paragraph 3.5.2)

(1) The software will operate on:

(a) Computer based forecast systems Display METAR observation on forecast systems

IAW FMH-1 and AFMAN 15-111

(b) Component Processing Unit Disseminate METAR observation IAW FMH-1 and AFMAN 15-111

(2) Prepare data as METAR observation IAW FMH-1 and AFMAN 15-111

(3) Allow editing of METAR observation

(4) Accept data from multiple TMOS Minimum of 3 different systems

(5) Daily archive Save daily observations to temporary storage media and hard disk

2. Employment

a. Set Up and Tear Down (paragraph 3.6.1)

(2) full Chemical Protection Clothing LTE 60 min

3. Communications

a. Hardwire (paragraph 3.8.1) 200 ft

b. Radio Frequency (paragraph 3.8.2) 5 nm

4. Physical Characteristics

Atch 1-3

c. Configuration (paragraph 3.9.1.3)

(1) Weight LTE 200 lbs

(2) Max component weight Two-person portable, LTE 84 lbs

(3) Volume 1/8 pallet (standard 463L)

5. Logistics and Readiness (paragraph 3.10)

a. Mission Reliability GTE 95% for 30 days

b. Mean Time Between Critical Failure (MTBCF) 3200 hours

c. Availability (Up-Time Ratio) GTE 98%

d. Mean Repair Time (MRT) LTE 30 min

e. Preventive Maintenance LTE 120 min per 30

f. Deployability After Dormancy (Up to 1 year) Operate for 30 days

6. Critical System Characteristics (paragraph 3.10)

a. Environmental Conditions

(1) Operating Conditions

(a) Temperature -40 deg C to +50 deg C

(b) Humidity 5% to 100%

(c) Wind 0 kts to 70 kts

(d) Altitude -50 ft to 12,000 ft MSL

(2) Outside Storage Conditions

(a) Temperature -40 deg C to +60 deg C

(b) Humidity 0% to 100%

b. Power

(1) Voltage 110-120, 220-240 VAC, 50/60Hz

(2) Internal Power Supply Duration 24 hours limited

File details come from the government source that posted it. Updated .