This is a Quality Assurance Surveillance Plan (QASP) for contract N0060426P4XXX (TBD), a U.S. Indo-Pacific Command Access Control Support Services contract to be awarded to a contractor yet to be determined. The QASP establishes systematic methods for evaluating contractor performance through monitoring, documentation, and quality control assessments. The document specifies that the Contracting Officer is Rachel Tamashiro at NAVSUP FLC Pearl Harbor Regional Contracting Office, with assigned CORs Ryan Crider (Master Diver) and Luke Berger (EODGRU1 Deputy N41). The QASP is designated as a "living document" subject to regular review and revision in coordination with the contractor, with changes communicated to all implementing parties.
The performance standards matrix requires 100% compliance across numerous technical maintenance and service tasks, including maintenance at NAVSEA-certified facilities, compressed gas cylinder refills (HeO2, O2, and O2N2), calibration of pressure gauges and relief valves, maintenance of oxygen transfer pump assemblies (OTPAs), air compressor servicing, transportable recompression chamber (TRC) maintenance, Standard Navy Double Lock (SNDL) system repairs, FADS III system servicing, ORCA system calibration, hydrostatic testing of SCUBA cylinders and relief valves, and calibration of portable gauges. Specific requirements include a 25-calendar-day turnaround time for hydrostatic testing, oxygen cleaning performed in a Class 100,000 cleanroom per MIL-STD-1330D, certification requirements for technicians, and monthly documentation of all contractor labor hours (including subcontractors) via a secure data collection site for EXPLOSIVE ORDNANCE DISPOSAL GROUP ONE. Surveillance methods include periodic inspection, user surveys, and 100% inspection, with performance rated on a five-tier scale (Exceptional, Very Good, Satisfactory, Marginal, Unsatisfactory). Unacceptable performance triggers issuance of a Contract Discrepancy Report (CDR) requiring written corrective action plans, which may support contract payment deductions or other government remedies.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2.03 26Q4023_Amd1_Att8_QandA.pdf | ||
| 2.07 26Q4023_Att1_Comb SS.pdf | ||
| 2.07a 26Q4023_Att4_FAR_DFARS.pdf | ||
| 2.07a 26Q4023_Att6_QASP_Log.xlsx | XLSX spreadsheet | |
| 2.07a 26Q4023_Att2_PWS.pdf | ||
| 2.07a 26Q4023_Att7_PricingWksht.xlsx | XLSX spreadsheet | |
| 2.07a 26Q4023_Att3_PWS_Att1_Service List.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUALITY ASSURANCE SURVEILLANCE PLAN
Contract Number: N0060426P4XXX (TBD) Contract Description: U.S. Indo-Pacific Command Access Control Support Services
Contractor’s Name: TBD (hereafter referred to as the contractor).
1. PURPOSE.
This Quality Assurance Surveillance Plan (QASP) provides a systematic method to evaluate performance for the stated contract. This QASP explains the following:
• What will be monitored.
• How monitoring will take place.
• Who will conduct the monitoring.
• How monitoring efforts and results will be documented.
This QASP does not detail how the contractor accomplishes the work. Rather, the QASP is created with the premise that the contractor is responsible for management and quality control actions to meet the terms of the contract. It is the Government’s responsibility to be objective, fair, and consistent in evaluating performance. In addition, the QASP should recognize that unforeseen and uncontrollable situations may occur.
This QASP is a “living document” and the Government may review and revise it on a regular basis. However, the Government shall coordinate changes with the contractor. Updates shall ensure that the QASP remains a valid, useful, and enforceable document. Copies of the original QASP and revisions shall be provided to the contractor and Government officials implementing surveillance activities.
The following FAR clauses may apply depending on contract type:
52.212-4 Contract Terms and Conditions – Commercial Items
2. GOVERNMENT ROLES AND RESPONSIBILITIES.
The following personnel shall oversee and coordinate surveillance activities.
a. Contracting Officer (KO) - The KO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The KO shall also assure that the contractor receives impartial, fair, and equitable treatment under this contract. The KO is ultimately responsible for the final determination of the adequacy of the contractor’s performance.
Assigned KO: Rachel Tamashiro Organization or Agency: NAVSUP FLC Pearl Harbor Regional Contracting Office Telephone: 808-603-5214 Email: rachel.m.tamashiro.civ@us.navy.mil
b. Contract Specialist (CS) – The CS works in conjunction with the Contacting Officer to assist with contract administration functions and serves as the liaison between the contracting office and Requiring Activity. The Contract Specialist is not authorized to bind the Government into any legally contractual instrument.
Assigned CS: Rachel Tamashiro Organization or Agency: NAVSUP FLC Pearl Harbor Regional Contracting Office Telephone: 808-603-5214 Email: rachel.m.tamashiro.civ@us.navy.mil
c. Contracting Officer’s Representative (COR) - The COR will act as the Contracting Officer’s representative for technical matters, providing technical direction and discussion as necessary with respect to the specifications or statement of work, and monitoring the progress and quality of contractor performance. The COR is not an administrative Contracting Officer and does not have authority to direct the accomplishment of effort outside the existing scope of the contract.
Assigned Primary COR: Ryan Crider, Master Diver Telephone: (619) 522-2874 Email: ryan.l.crider.mil@us.navy.mil
Tentative Assigned Primary COR: Luke Berger, EODGRU1 Deputy N41 Telephone: (619) 316-2736 Email: lucas.r.berger.civ@us.navy.mil
3. PERFORMANCE STANDARDS.
Performance standards define desired services. The Government performs surveillance to determine if the contractor exceeds, meets or does not meet these standards.
The Performance Requirements Summary Matrix, Section 5.0, in the Performance Work Statement (PWS) includes performance standards. The Government shall use these standards to determine contractor performance and shall compare contractor performance to the Acceptable Quality Level (AQL).
PWS
SECTION PERFORMANCE STANDARD
ACCEPTABLE
QUALITY LEVEL
(AQL)
SURVEILLANCE METHOD
3.1 Any maintenance (excluding work on non-
transportable compressors and air systems) shall be completed at a Naval Sea Systems Command (NAVSEA) certified facility. Any equipment that fails to test must be returned to the customer (EODGRU1) with documentation stating all reasons for failure within three (3) business days upon maintenance service completion.
EODGRU1 will determine the likelihood of repairing any equipment that fails testing or is otherwise unable to be repaired and will notify the contractor via email or telephone of their decision immediately.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.2.1 Provide a total of 50 HeO2 88/12% compressed
gas cylinder refills, to be delivered on an as-needed basis upon cylinder drop-off during each annual period of performance.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.2.2 Provide a total of 30 O2 100% compressed gas
cylinder refills, to be delivered on an as-needed basis upon cylinder drop-off during each annual period of performance.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.2.3 Provide a total of 20 O2N2 60/40% compressed
gas cylinder refills, to be delivered on an as-needed basis upon cylinder drop-off during each annual period of performance.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.3.1 Calibrate three (3) oxygen outlet pressure
gauges (part number (p/n) OHP-G201) for each of the three (3) OTPAs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.3.2 Replace three (3) pump assembly air cycling
valve O-rings and bumpers for each of the three
(3) OTPAs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.3.2.1 Provide three (3) air cycling valve kits (p/n
17329) for each of the three (3) OTPAs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.3.3 Test OTPA relief valves of three (3) oxygen
transfer pumps for each of the three (3) OTPAs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.3.4 Inspect two (2) oxygen in-line filters for each of
the three (3) oxygen transfer pumps, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.3.5 The Contractor shall overhaul three (3) OTPAs.
Upon successful completion of the maintenance, the owning unit shall retrieve and take custody of the serviced OTPAs.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.4.1 Replace three (3) cartridges (i.e., A-2 air
purifier (SECURUS) cartridge, drying filter cartridge, and CO filter cartridge) for each of the four (4) compressors, once a year.
Contractor Monthly Report to
COR.
3.4.1.1 Provide two (2) drying filter cartridges (p/n
058825A) for each of the four (4) compressors, once a year.
Contractor Monthly Report to
COR.
3.4.1.2 Provide one (1) Securus filter cartridge (p/n
060037A) for each of the four (4) compressors, once a year.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.4.1.3 Provide three (3) O-rings (p/n N04735) for
each of the four (4) compressors, once a year.
Contractor Monthly Report to
COR.
3.4.1.4 Provide three (3) backup rings (p/n N04736)
for each of the four (4) compressors, once a year.
Contractor Monthly Report to
COR.
3.4.1.5 Provide one (1) air intake filter (p/n N25886)
for each of the four (4) compressors, once a
Contractor Monthly Report to
COR.
3.4.2 Calibrate diver’s portable gauges for each of the
four (4) compressors, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.4.3 Disassemble, clean, inspect, and reassemble
sintered metal filter of helical insert Bauer oil and water separator element of four (4) compressors, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.4.3.1 Provide one (1) sintered filter element (p/n
061860) for each of the four (4) compressors, for each scheduled service.
Contractor Monthly Report to
COR.
3.4.4 Conduct two (2) oil changes and replacements
of the oil tube/filter for each of the four (4) compressors, for each scheduled service.
3.4.4.1 Provide one (1) oil filter (p/n N25326) for each
of the four (4) compressors, for each scheduled service.
Contractor Monthly Report to
COR.
3.4.4.2 Provide one (1) gasket (p/n 077774) for each of
the four (4) compressors, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.4.4.3 Provide one (1) O-ring (p/n N04058) for each
of the four (4) compressors, for each
Contractor Monthly Report to
COR.
3.4.4.4 Provide one (1) O-ring (p/n N25327) for each of
the four (4) compressors, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.4.4.5 Provide two (2) units of compressor oil (p/n
OIL-0024) for each of the four (4) compressors, for each scheduled service.
Contractor Monthly Report to
COR.
3.4.5 Replace Bauer air compressor pressure
maintaining valve (PMV) and inlet/outlet check valves two (2) times for each of the four (4) compressors, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.4.5.1 Provide two (2) check valves (p/n VAL-0007)
for each of the four (4) compressors, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.4.5.2 Provide one (1) pressure maintaining valve
(p/n VAL-0053) for each of the four (4) compressors, for each scheduled service.
Contractor Monthly Report to
COR.
3.4.6 Test relief valves removed from the system for
four (4) compressors, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.5.1 Replace one (1) A-10 Bauer air purifier element
for each of the five (5) compressors, once a
Contractor Monthly Report to
COR.
3.5.1.1 Provide one (1) air purifier element (p/n
058821A) for each of the five (5) compressors, once a year.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.5.1.2 Provide one (1) O-ring (p/n N04735) for each of
the five (5) compressors, once a year.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.5.1.3 Provide one (1) backup ring (p/n N04736) for
each of the five (5) compressors, once a year.
100% Compliance TPOC inspection/acceptance.
Summary of work included in
3.5.1.4 Change one (1) A-11 CO/Moisture indicator
element for each of the five (5) compressors, once a year.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.5.1.5 Provide one (1) moisture indicator element (p/n
ELM-0056) for each of the five (5) compressors, once a year.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.5.2 Calibrate two (2) diver's portable gauges for
each of the five (5) compressors, for scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.5.3 Test two (2) relief valves removed from each of
the five (5) compressors, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.1 Conduct onsite calibration of 24 DLSS-installed
gauges for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.1.1 TRCS calibration may take up to an estimated
18 labor hours per TRCS, for each scheduled service, as the complete process involves the removal of the relief valve, system line-ups, and joint testing.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.1.2 3.6.1.2 Provide six (6) AS3581-111 O-rings that are cleaned IAW MIL STD 1330D (for TRCS relief valve removal) for each of the three
(3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.1.3 Provide one (1) AS3581-010 O-rings that are
cleaned IAW MIL STD 1330D (for TRCS med-lock gauge) for each TRCS per scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.2 Perform a visual inspection of five (5) acrylic
windows of each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.3 Conduct onsite testing of eight (8) relief valves
that are removed from each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.3.1 TRCS testing may take up to an estimated six
(6) labor hours per TRCS, as the complete process involves the removal of the relief valve, system line-ups, and joint testing.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.3.2 Provide six (6) AS3581-111 O-rings that are
cleaned IAW MIL STD 1330D (for TRCS relief valve removal) for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.4 Clean and inspect transportable recompression
chamber (TRC) T-filter elements and housings for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.4.1 Provide five (5) Swagelok filter elements (p/n
M-8F-K4-15) for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in
3.6.4.2 Provide five (5) Swagelok filter gaskets (p/n SS-
8TF-K2) for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.4.3 Clean filter elements and gaskets of three (3)
TRCSs IAW MIL STD 1330E per scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.5 Clean and inspect transfer lock (TL) T-filter
elements and housings for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.5.1 Provide four (4) Swagelok filter elements (p/n
M-8F-K4-15) for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.5.2 Provide four (4) Swagelok filter gaskets (p/n SS-
8TF-K2) for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.5.3 Clean filter elements and gaskets of three (3)
TRCs IAW MIL STD 1330E per scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.6 Conduct external and internal inspections, hydrostatic testing and rupture disc replacement for 12 DOT .93 carbon fiber flask(s) for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.6.1 This service may take up to an estimated 12
labor hours for each of the three (3) TRCSs, for each scheduled service, as it includes the disassembly and reassembly of a total of four (4) flask racks annually, while maintaining cleanliness levels IAW MIL STD 1330E, and filling flasks for 24-hour joint-tightness drop tests.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.6.2 Provide 12 rupture discs (p/n 20Z) that are
cleaned IAW MIL STD1330E for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.6.3 Provide 12 M83248/2-916 O-rings that are
cleaned IAW MIL STD 1330E for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.6.4 Provide 12 M83248/2-010 O-rings that are
cleaned IAW MIL STD 1330E for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.6.5 Provide one (1) unit of diver’s air gas (i.e., O2
for O2 racks, air for air racks) required for flask rack joint tightness test for each of the three (3) TRCSs, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.7 Hydrostatically test one (1) TRCS fire
extinguisher per TRCS (three (3) total), for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in
3.6.8 Hydrostatically test U-2 hoses for each of the
three (3) TRCSs, once a year.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.9 Clean and inspect U-3 interlock poppet and
NATO flange bearings for each of the three (3) TRCSs, once a year.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.10 Clean, inspect, and reinstall air supply and
exhaust diffusers/silencers for each of the three
(3) TRCSs, once a year.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.6.11 Compile and submit a Re-Entry Control (REC)
and Objective Quality Evidence (OQE) documentation package for each TRCS upon completion of this service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.1 Test and inspect the air supply rack assembly
(ASRA) check valve (p/n AHP-V445) for one
(1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.2 Calibrate 22 DLSS installed gauges for one (1)
SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.3 Inspect one (1) SNDL recompression chamber
system (RCS) high pressure (HP) in-line air reducing station filter element for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.3.1 Provide two (2) filter elements (p/n U-10007)
for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.3.2 Clean two (2) filter elements for one (1) SNDL
IAW MIL STD 1622B, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.3.3 Provide two (2) M83248/2-906 O-rings for one
(1) SNDL that are cleaned IAW MIL STD 1622B, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.3.4 Provide two (2) M83248/2-914 O-rings for one
(1) SNDL that are cleaned IAW MIL STD 1622B, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.3.5 Provide two (2) M83248/2-015 O-rings for one
(1) SNDL that are cleaned IAW MIL STD 1622B, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.3.6 Provide four (4) M83248/2-908 O-rings for one
(1) SNDL that are cleaned IAW MIL STD 1622B, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.4 Clean, inspect, and test SNDL HP oxygen
reducing station piping and valves for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in
3.7.4.1 The inspection portion of this service may take
up to an estimated four (4) labor hours for each scheduled service, as it includes panel removal, piping removal and reinstallation, panel reinstallation, and joint testing.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.4.2 Conduct one (1) visual inspection of the primary
HP oxygen supply regulator OHP-R206 and secondary HP oxygen supply regulator OHP- R205 inlet screens for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.4.3 Conduct one (1) visual inspection of the primary
oxygen supply valve OHP-V201 and secondary oxygen supply value OHP-V203 outlet for one
(1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.4.4 Overhaul primary oxygen supply valve (p/n
OHP-V201) and secondary oxygen supply valve (p/n OHP-V203) outlets for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.4.5 Provide one (1) valve repair kit (p/n T-9K-6N)
for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.4.6 Clean two (2) valve repair kits for one (1) SNDL
IAW MIL STD 1330E, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.4.7 Perform a valve seat tightness test on each the
primary oxygen supply valve (p/n OHP-V201) and secondary oxygen supply valve (p/n OHP- V203) for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.5 Conduct tests of seven (7) relief valves that are
removed from one (1) SNDL system, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.6 Clean and inspect three (3) Standard Navy
Double Lock (SNDL) T-filter elements and housings for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.6.1 Provide three (3) Swagelok filter elements (p/n
M-8F-K4-15) for one (1) SNDL, for each scheduled service
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.6.2 Provide three (3) Swagelok filter gaskets (p/n
SS-8TF-K2) for one (1) SNDL, for each
Contractor Monthly Report to
COR.
3.7.6.3 Clean three (3) filters and three (3) gaskets IAW
MIL STD 1330E for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.7 Clean and inspect Standard Navy Double Lock
(SNDL) low pressure (LP) in-line filter element for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in
3.7.7.1 Provide two (2) Norman filter elements (p/n
416G-20VN) for one (1) SNDL, for each
Contractor Monthly Report to
COR.
3.7.7.2 Clean two (2) filter elements IAW MIL STD
1622B for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.7.3 Provide four (4) M83248/2-924 O-rings that are
cleaned IAW MIL STD 1622B for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.7.4 Provide a total of four (4) M83248/2-912 O-
rings that are cleaned IAW MIL STD 1622B for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.7.5 Provide eight (8) M83248/2-021 O-rings that are
cleaned IAW MIL STD 1622B for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.8 Remove, clean, inspect, and reuse SNDL charge
port and HP regulator filters of the Air Supply Rack Assembly (ASRA), oxygen supply rack assembly (OSRA), helium-oxygen supply rack assembly (HOSRA), and self-contained underwater breathing apparatus (SCUBA) for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.8.1 Provide two (2) filter elements (p/n U-10007)
for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.8.2 Clean two (2) filter elements IAW MIL STD
1622B for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.8.3 Provide four (4) M83248/2-012 O-rings that are
cleaned IAW MIL STD 1622B for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.8.4 Provide four (4) M83248/2-906 O-rings that are
cleaned IAW MIL STD 1622B for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.8.5 Provide two (2) M83248/2-914 O-rings that are
cleaned IAW MIL STD 1622B for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.9 Conduct external and internal inspections, hydrostatic testing and rupture disc replacements for nine (9) DOT 3.15 carbon fiber flasks, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.9.1 This service may take up to an estimated total of
16 labor hours for each fiber flask, as it includes disassembly, removal, reassembly, and reinstallation of flasks while maintaining cleanliness, including filling flasks for 24-hour joint tightness drop tests.
100% Compliance TPOC inspection/acceptance.
Summary of work included in
3.7.9.2 Provide nine (9) rupture discs (p/n 128450XX)
for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.9.3 Clean nine (9) rupture discs IAW MIL STD
1622B for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.9.4 Provide 15 M83248/2-111 O-rings that are
cleaned IAW MIL STD 1330D for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.9.5 Provide 18 M83248/2-910 O-rings that are
cleaned IAW MIL STD 1330D for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.9.6 Provide 17 M83248/2-010 O-rings that are
cleaned IAW MIL STD 1330D for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.9.7 Provide one (1) unit of diver’s air gas that is
required for joint tightness/24-hour drop test for each scheduled service. The Contractor shall leave flasks full and provide current satisfactory air samples from diver’s air source for the flask rack joint tightness tests.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.10 Hydrostatically Test U-2 Hose of one (1) SNDL
per scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.11 Repair and conduct tightness tests of two (2) U-
4 ASRA check valves (p/n AHP-V445) for one
(1) SDNL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.11.1 Provide one (1) Swagelok check valve (p/n SS-
CHVCO8-5) for one (1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.12 Clean, inspect and reinstall two (2) U-5 air
supply and exhaust diffuser(s)/silencers for one
(1) SNDL, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.7.13 Compile and submit a Re-Entry Control (REC)
and Objective Quality Evidence (OQE) documentation package upon completion of this service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.1 Perform onsite calibration of 12 DLSS-installed
gauges for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.2 Clean and inspect Control Console Assembly
(CCA) HP in-line air filter elements for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.2.1 Provide a total of one (1) filter element (p/n U-
10007) for one (1) FADS III, for each scheduled service.
3.8.2.2 Clean a total of four (4) filter elements IAW
MIL STD 1622B for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.2.3 Provide six (6) M83248/2-906 O-rings that are
cleaned IAW MIL STD 1622B for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.2.4 Provide one (1) M83248/2-914 O-ring that is
cleaned IAW MIL STD 1622B for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.2.5 Provide two (2) M83248/2-111 O-rings that are
cleaned IAW MIL STD 1622B for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.3 Conduct onsite testing of four (4) relief valves
removed from one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.4 Remove, clean, inspect, and reuse charge port
and HP regulator filters of the ASRA, OSRA, HOSRA, and SCUBA for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.4.1 Provide one (1) filter element (p/n U-10007)
for one (1) FADS III, for each scheduled service.
Contractor Monthly Report to
COR.
3.8.4.2 Clean four (4) filter elements IAW MIL STD
1622B for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.4.3 Provide two (2) M83248/2-012 O-rings that are
cleaned IAW MIL STD 1622B for one (1) FADS III, for each scheduled service.
Contractor Monthly Report to
COR.
3.8.4.4 Provide one (1) M83248/2-906 O-ring that is
Contractor Monthly Report to
COR.
3.8.4.5 Provide one (1) M83248/2-914 O-ring that is
Contractor Monthly Report to
COR.
3.8.5 Conduct external and internal inspections, conduct hydrostatic testing and replace rupture disc for nine (9) DOT 3.15 carbon fiber flasks, for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.5.1 This service may take up to an estimated total of
16 labor hours for each fiber flask, as it includes disassembly, removal, reassembly, and reinstallation of flasks while maintaining cleanliness, including filling flasks for 24-hour joint tightness drop tests.
100% Compliance TPOC inspection/acceptance.
Summary of work included in
3.8.5.2 Provide nine (9) rupture discs (p/n 128450XX)
for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.5.3 Clean nine (9) rupture discs IAW MIL STD
1622B for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.5.4 Provide 15 M83248/2-111 O-rings that are
cleaned IAW MIL STD 1330D for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.5.5 Provide 18 M83248/2-910 O-rings that are
cleaned IAW MIL STD 1330D for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.5.6 Provide 17 M83248/2-010 O-rings that are
cleaned IAW MIL STD 1330D for one (1) FADS III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.5.7 Provide diver’s air gas (i.e., O2, air) that is
required for joint tightness/24-hour drop test for one (1) FADS III, for each scheduled service.
The Contractor shall leave flasks full and provide current satisfactory air samples from diver’s air source for the flask rack joint tightness tests.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.6 Hydrostatically test U-2 hoses for one (1) FADS
III, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.8.7 Compile and submit a Re-Entry Control (REC)
and Objective Quality Evidence (OQE) documentation package upon completion of this service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.9.1 Calibrate two (2) DLSS-installed gauges onsite
for one (1) ORCA system, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.9.2 Test one (1) relief valve removed from the
system of one (1) ORCA system, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.9.3 Clean and inspect ORCA I & II in-line filter
elements of one (1) ORCA system, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.9.4 Hydrostatically test U-2 hoses of one (1) ORCA
system per scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.9.5 Compile and submit a Re-Entry Control (REC)
and Objective Quality Evidence (OQE) documentation package upon completion of this service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.10 The Contractor shall conduct onsite testing of a
total of 200 relief valves removed from the
DLSS system 200 times each for each scheduled service.
Contractor Monthly Report to
COR.
3.11 The Contractor shall conduct hydrostatic testing
of 300 SCUBA cylinders 300 times each for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.12.1 Calibrate 400 6R DLSS portable gauges 400
times each, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.12.2 Calibrate 400 DLSS installed gauges 400 times
each, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.13.1 Calibrate test two (2) panel gauges and relief
valves and conduct comparison accuracy (CCA) test for flowmeters and pocket flowmeters two
(2) times, for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.13.2 Deliver pressure vessels to an authorized activity
for hydrostatic testing two times for each scheduled service.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.14.1 All hydrostatic testing shall have a 25-calendar
day turnaround time upon the Contractor’s receipt of gas flask or bottle.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.14.2 Scheduled maintenance of the Haskel oxygen
booster pumps manifold and the oxygen transfer pump assemblies shall be accomplished by a certified Haskel technician qualified on both the MK-23 MOD-0 and MOD-1 models.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.14.3 Scheduled maintenance of the Transportable
Recompression Chambers shall be accomplished by a certified technician knowledgeable of Navy Divers Life Support and American Society of Mechanical Engineers (ASME) Pressure Vessels for Human Occupancy requirements.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.14.4 Oxygen cleaning shall be performed in a Class
100,000 cleanroom with daily particle counting in accordance with MIL-STD-1330D
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.14.5 The Contractor shall provide evidence of
NAVSEA Quality Assurance (QA) Audit relative to US Navy Diving Systems
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.15 The Contractor shall perform maintenance
services of Government-provided DLSS equipment at Contractor facilities and/or on-base EODGRU1 worksite. For equipment serviced at the Contractor’s facility, the Contractor shall drop off or schedule pick up of equipment to the EODGRU1 facility within three (3) calendar days upon maintenance service completion.
100% Compliance TPOC inspection/acceptance.
Summary of work included in Contractor Monthly Report to
COR.
3.16 The Contractor shall document the efforts
performed in the completion of each task in a detailed Monthly Status Report.
100% Compliance TPOC inspection/acceptance.
Summary of work included in
3.17 The Contractor shall report all contractor labor
hours (including subcontractor labor hours) required for performance of services provided under this contract for the EXPLOSIVE ORDNANCE DISPOSAL GROUP ONE via a secure data collection site.
100% Compliance TPOC inspection/acceptance.
Summary of work included in
5. METHODS OF QA SURVEILLANCE.
Various methods exist to monitor performance. The COR shall use the surveillance methods listed, in the administration of this QASP.
Regardless of the surveillance method, the COR shall always contact the KO when a defect is identified and inform the KO of the specifics of the problem. The COR, shall be responsible for monitoring the contractor’s performance in meeting a specific performance standard/AQL.
a. PERIODIC INSPECTION. (Uses a comprehensive evaluation of selected outputs. Inspections may be scheduled monthly or unscheduled, as required.)
b. USER SURVEY. (Combines elements of validated user complaints and random sampling. Random survey is conducted to solicit user satisfaction. Appropriate for high quantity activities that have historically been satisfactory. May also generate periodic and 100% inspections.)
c. 100% INSPECTION. (Evaluates all outputs. Most applicable to small quantity, but highly important services.
May be used where there are written deliverables and stringent requirements such as tasks required by law, safety, or security.)
Surveillance results may be used as the basis for actions (to include payment deductions) against the contractor. In such cases, the commercial clause in the Contract becomes the basis for the KO’s actions.
8. RATINGS.
For each performance standard and the respective AQL identified in the PWS, the COR will assign an adjectival rating from the table below and document the results on the Quality Assurance Surveillance Log. In addition, each contract will be assigned an overall evaluation rating.
RATING DEFINITION NOTE
Exceptional Performance meets contractual requirements and exceeds many to the Government’s benefit.
The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
To justify an Exceptional rating, identify multiple significant events and state how they were of benefit to the Government. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
Very Good Performance meets contractual requirements and exceeds some to the Government’s benefit.
The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
To justify a Very Good rating, identify a significant event and state how it was a benefit to the Government. There should have been no significant weaknesses identified.
Satisfactory Performance meets contractual requirements.
The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
To justify a Satisfactory rating, there should have been only minor problems, or major problems the contractor recovered from without impact to the contract/order. There should have been NO significant weaknesses identified. A fundamental principle of assigning ratings is that contractors will not be evaluated with a rating lower than Satisfactory solely for not performing beyond the requirements of the contract/order.
Marginal Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being evaluated reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.
To justify Marginal performance, identify a significant event in each category that the contractor had trouble overcoming and state how it impacted the Government. A Marginal rating should be supported by referencing the management tool that notified the contractor of the contractual deficiency (e.g., management, quality, safety, or environmental deficiency report or letter).
Unsatisfactory Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
To justify an Unsatisfactory rating, identify multiple significant events in each category that the contractor had trouble overcoming and state how it impacted the Government. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating An Unsatisfactory rating should be supported by referencing the management tools used to notify the contractor of the contractual deficiencies (e.g., management, quality, safety, or environmental deficiency reports, or letters).
9. DOCUMENTING PERFORMANCE.
a. UNACCEPTABLE PERFORMANCE.
When unacceptable performance occurs, the COR shall inform the KO. This will normally be in writing unless circumstances necessitate verbal communication. In any case the KO shall document the discussion and place it in the contract file.
If necessary the KO shall prepare a Contract Discrepancy Report (CDR) (Enclosure 1), and present it to the contractor or on-site representative. A CDR template is enclosed to this QASP.
The contractor shall acknowledge receipt of the CDR in writing. The CDR will specify if the contractor is required to prepare a corrective action plan to document how the contractor shall correct the unacceptable performance and avoid a recurrence. The CDR will also state how long after receipt the contractor has to present this corrective action plan to the KO and COR. The Government shall review the contractor's corrective action plan to determine acceptability.
Any CDRs may become a part of the supporting documentation for contract payment deductions, or other actions deemed necessary by the KO.
Enclosure (1)
CONTRACT DISCREPANCY REPORT (CDR)
1. Contract Number: N0060426P4XXX (TBD)
2. TO: (Contractor Task Manager or on-site representative) <insert name>
3. FROM: Contracting Officer
4. Date and time observed discrepancy:
5. DISCREPANCY OR PROBLEM:
<Describe in detail. Identify any attachments.>
5. Corrective action plan:
A written corrective action plan < is / is not > required.
< If a written corrective action plan is required include the following. > The written Corrective Action Plan will be provided to the undersigned not later than < # days after receipt of this
CDR. >
Prepared by: Contracting Officer
Signature – Contracting Officer Date
Received by:
Signature - Contractor Task Manager or on-site representative Date
| Various methods exist to monitor performance. The COR shall use the surveillance methods listed, in the administration of this QASP. |
| Regardless of the surveillance method, the COR shall always contact the KO when a defect is identified and inform the KO of the specifics of the problem. The COR, shall be responsible for monitoring the contractor’s performance in meeting a specific ... |