This is a Design-Build Scope of Work for the construction of an emergency generator building at Retamal Dam in Hidalgo County, Texas, issued by the United States Section of the International Boundary and Water Commission (USIBWC) under Solicitation 191BWC26Rxxxx, dated February 24, 2026.
The project comprises two phases: a Design Phase and a Construction Phase, each with a separate Notice to Proceed. The Design Phase includes site investigation, surveying, geotechnical investigations, design development, and production of construction documents and reports. The Construction Phase encompasses site preparation, construction of a metal building with a new diesel emergency generator, concrete mounting pad, fuel tank with spill containment, electrical interconnections to an existing automatic transfer switch, perimeter security fencing, quality control testing, and commissioning. The Design-Builder must provide all labor, materials, equipment, and services to deliver a fully commissioned, turnkey facility. Work is restricted to USIBWC right-of-way and must comply with facility operating hours (7:30 am to 4:00 pm, Monday through Friday, excluding federal holidays). The Design-Builder is responsible for identifying and coordinating with existing utilities, obtaining all necessary permits (including SWPPP and TPDES permits), and managing environmental compliance including protection of migratory bird breeding seasons, water quality, and fuel tank secondary containment per Texas Administrative Code. All designs must be signed and sealed by Texas-licensed professional engineers. The project includes minimum warranty requirements of 5 years for the generator and automatic transfer switch, and 20 years for roofing systems. The Design-Builder must submit required premobilization submittals—including construction schedule, quality assurance plan, safety documentation, SWPP plan, and condition survey—for Government compliance confirmation before construction mobilization. The contract uses FAR Part 52.236-3 (Site Investigation and Conditions) and is subject to the Davis-Bacon Act wage requirements.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Front Cover
International Boundary and Water Commission United States and Mexico United States Section
Design-Build Scope of Work Retamal Dam Emergency Generator and Building Hidalgo County, Texas
Solicitation 191BWC26Rxxxx
February 24, 2026
International Boundary and Water Commission United States Section Construction Management Division El Paso, Texas
This Scope of Work may be reprinted after Contract award using the awarded Contract number instead of the Solicitation number currently shown. The reprint shall have all changes indicated incorporated.
Reissuance of the awarded Scope of Work with the Contract number will proceed without an amendment or modification.
Reissuance with the Contract number will NOT result in a new date being displayed on the Scope of Work.
PLEASE NOTE - Scope of Work should be printed double sided.
Please conserve paper and print double sided.
USIBWC Retamal Dam
February 24, 2026 Division 00 USIBWC Solicitation 191BWC26Rxxxx Procurement and Contracting Requirements-Page 1
International Boundary and Water Commission United States Section
SCOPE OF WORK
DIVISION 00
PROCUREMENT AND CONTRACTING
REQUIREMENTS
Emergency Generator and Building US International Boundary & Water Commission Retamal Dam
Procurement and Contracting Requirements Division 00 Division 00-Procurement and Contracting Requirements
Division 00 February 24, 2026 Procurement and Contracting Requirements-Page 2 USIBWC Solicitation 191BWC26Rxxxx
This page intentionally left blank for double sided printing.
February 24, 2026 Table of Contents Governing USIBWC Solicitation 191BWC26Rxxxx 00.01.10.01-Page 1
SECTION 00.01.10.01
TABLE OF CONTENTS GOVERNING
00.01.10.01 Table of Contents Governing 00.01.10.01-Table of Contents Governing
Table of Contents
DIVISIONS AND SECTIONS
Division 00-Procurement and Contracting Requirements 00.01.10.01-Table of Contents Governing 00.21.13.01-◊●◊●◊ Instructions to Bidders 00.23.00.01-◊●◊●◊ Design-Build Procurement Definitions 00.24.00.01-Procurement Scope 00.31.00.01-Project Information 00.31.13.01-◊●◊●◊ Project Time Constraints & Milestones 00.31.19.01-Existing Condition Information 00.31.24.01-Environmental Information 00.31.26.01-Existing Hazardous Material Information 00.31.43.01-Permit Application 00.60.00.01-◊●◊●◊ USIBWC Forms and Standard Documents 00.70.00.01-◊●◊●◊ Delivery of Data to USIBWC 00.70.13.01-◊●◊●◊ Project Data 00.72.00.01-General Conditions 00.73.63.01-Security Requirements 00.73.73.01-Requirements for Sensitive But Unclassified Information 00.90.00.01-◊●◊●◊ Revisions, Clarifications, and Modifications 00.91.16.01-Bid Revisions 8-13-2024
Division 01-General Requirements 01.20.00.01-◊●◊●◊ Measurement and Payment 01.29.00.01-◊●◊●◊ Payment Procedures 01.29.15.01-◊●◊●◊ Certified Payroll 01.31.00.01-◊●◊●◊ Project Coordination 01.31.19.01-◊●◊●◊ Project Meetings 01.32.16.01-◊●◊●◊ Progress Schedule 01.32.33.01-◊●◊●◊ Photographic Documentation 01.33.00.01-◊●◊●◊ Submittal Procedures 01.33.16.01-Design Submittals 01.33.33.01-◊●◊●◊ Document Requirements 01.35.23.01-◊●◊●◊ Safety 01.40.00.01-◊●◊●◊ Quality Requirements 01.41.00.01-Regulatory Requirements 01.42.00.01-References 01.43.26.01-◊●◊●◊ Testing and Inspection Agencies 01.51.00.01-Temporary Utilities 01.52.13.01-Field Offices and Sheds 01.55.00.01-Vehicular Access and Parking 01.57.00.01-◊●◊●◊ Temporary Controls for Work Areas 01.57.19.01-◊●◊●◊ Temporary Environmental Controls 01.58.00.01-Project Identification 01.61.00.01-Common Product Requirements 01.61.16.01-◊●◊●◊ Use of Recovered Materials and Biobased Products 01.64.00.01-Government Furnished Materials
Table of Contents Governing February 24, 2026 00.01.10.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx
01.71.13.01-Mobilization 01.74.19.01-◊●◊●◊ Construction Waste Management and Disposal 01.77.19.01-◊●◊●◊ Closeout Requirements 01.78.23.01-Operations and Maintenance Data 01.78.36.01-◊●◊●◊ Warranties 01.78.39.01-Record Drawings 01.79.00.01-Demonstration and Training 01.80.05.01-General Design Requirements 01.80.23.01-General Structural Requirements 01.80.26.01-General Concrete Requirements 01.81.19.01-General Accessibility Requirements 01.81.63.01-General Civil/Architectural Requirements 01.84.00.01-Interior Design Requirements 01.86.13.01-Fire Protection Requirements 01.86.16.01-Plumbing Requirements 9-27-2022 01.86.19.01-HVAC Requirements 01.86.29.01-Electrical Requirements 01.88.00.01-General Construction Requirements 01.88.59.01-General Geological Materials Requirements 01.89.16.01-Site Improvements Requirements 10-14-2022 01.91.13.01-General Commissioning Requirements
Division 02-Existing Conditions 02.01.00.01-◊●◊●◊ Existing Conditions & Facilities 02.21.00.01-◊●◊●◊ Surveys 02.21.13.01-◊●◊●◊ Cultural Resources Surveys 02.22.13.01-Existing Conditions Assessment 12-14-2023
Scope of Work Tables Table 3 - CLIN 001 (Design) Schedule of Values Table 4 - CLIN 002 (Construction) Schedule of Values Table 5 - CLIN 003 (Closeout) Schedule of Values Table 6 - Acceptable Methods of Access Table 7 - Required Minimum Biobased Content Table 8 - Required Minimum Recovered Content Table 9 - Minimum Warranties Table 10 - Warranty Priority Code A Table 11 - Warranty Priority Code B Table 12 - Warranty Priority Code C Table 13 - Warranty Priority Code D Table 14 - Minimum Space Requirements Table 13 - Overdesign to Meet Compressive Strength Requirements (1) Table 14 - Overdesign to Meet Compressive Strength Requirements (2) Table 15 - Duration of Curing
Scope of Work Figures Figure 1 - Fillable Form (not printed) Figure 2 - Printed Fillable Form Figure 3 - Site Access Methods by Angle Figure 4 - Design-Build QA Organizational Chart
February 24, 2026 Table of Contents Governing USIBWC Solicitation 191BWC26Rxxxx 00.01.10.01-Page 3
Figure 6 - Sample Project Sign Figure 7 - Equipment Tag Example
--End of Section--
Table of Contents Governing February 24, 2026 00.01.10.01-Page 4 USIBWC Solicitation 191BWC26Rxxxx
February 24, 2026 ◊●◊●◊ Instructions to Bidders USIBWC Solicitation 191BWC26Rxxxx 00.21.13.01-Page 1
SECTION 00.21.13.01
INSTRUCTIONS TO BIDDERS
00.21.13.01 ◊●◊●◊ Instructions to Bidders 00.21.13.01-◊●◊●◊ Instructions to Bidders
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Reference Standards
1.3. Measurement and Payment
1.4. Definitions
1.5. Duty to Inquire
1.6. Investigation of Site Conditions
1.7. Bid Items
1.8. Statement of Work
1.9. Bid Submission
Part 2 - Products (Not Used) Part 3 - Execution
3.1. Requests for Interpretation (Duty to Inquire)
--End of Section--
1.2. REFERENCE STANDARDS
1.2.A. Federal Acquisition Regulation (FAR)
1. FAR 52.236-3, Site Investigation and Conditions Affecting the Work
1.3. MEASUREMENT AND PAYMENT
The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.4. DEFINITIONS
1.4.A. Within this Section, the following terms are used interchangeably.
1. Bid - Offer - Proposal
2. Solicitation - Request for Proposal - RFP
3. Bidder - Offeror - Design-Builder
1.5. DUTY TO INQUIRE
1.5.A. Bidders shall review the full Solicitation and all Contract Documents including, but not limited to, Scope of Work, Contract Drawings, USIBWC provided data, referenced items, attachments, etc. to determine the full scope of work required.
1.5.B. If during review of these items, the Bidder finds discrepancies, omissions, conflicts, defects, errors, or ambiguities, they have a duty to inquire. The Bidder shall also inquire about items that are open to interpretation.
1.5.C. The Bidder shall inquire about items as soon as they are discovered, whether before deadline for submission of bidder questions, whether after deadline for submission of bidder questions, whether after submission of bids, or whether after Contract award.
◊●◊●◊ Instructions to Bidders February 24, 2026 00.21.13.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx
1.5.D. If the Bidder fails to inquire, they forfeit their right to any claim based upon said discrepancies, omissions, conflicts, defects, errors, ambiguities, or items that are open to interpretation. The Bidder shall be proceeding at their own risk based upon only their unilateral interpretation.
1.5.E. The Bidder shall take no advantage of any item of which they have a duty to inquire.
1.6. INVESTIGATION OF SITE CONDITIONS
1.6.A. The Bidder, as well as their subcontractors, is urged to visit the worksite and project area to become fully aware as to the existing conditions affecting the work to be performed under the Contract Documents. A site visit will be announced during the solicitation. Each Bidder shall attend at their own expense. The Government will not pay for any site visits. This visit is intended to provide the potential Bidders the opportunity to observe site conditions and incorporate into their proposal any required work based on site conditions. The Bidder will have the opportunity to walk around during the site visit. Unless otherwise noted, no other opportunity will exist for visits to the site.
1.6.B. The Bidder shall be responsible for ensuring that all of its suppliers, manufactures and subcontractors have reviewed all applicable Contract Documents relative to their work. The Bidder shall provide all labor, material, equipment, and services not provided by the Bidder’s suppliers, manufacturers, fabricators, and/or subcontractors but required for complete and operable facilities as described in the Contract Documents.
1.6.C. Bidder has the sole responsibility to make such independent investigation and examination as they deem necessary in order to satisfy themselves as to the conditions to be encountered in the performance of work and the quantities required to complete the work in accordance with the SOW.
1.6.D. The Government assumes no responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of the Bidder's officers or agents before the execution of this Contract, unless that understanding or representation is expressly stated in the Contract Documents.
1.6.E. Any failure of the Bidder to take the actions described and acknowledged in this Section will not relieve the Bidder from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work.
1.7. BID ITEMS
1.7.A. The Contract Line Item Numbers (CLIN) that shall be bid upon are identified in Section B (bid schedule) of the Solicitation.
1.7.B. The Bidder shall include all work related costs within its bid prices even if not specifically listed in the bid schedule.
1.7.C. If an error exists on the bid schedule between the CLIN total cost provided and the resultant value of the CLIN quantity multiplied by the bid unit price, the bid unit price provided shall govern.
1.8. STATEMENT OF WORK
1.8.A. The Government does not implicitly warrant performance specifications (SOW requirements) for complete accuracy or adequacy. Typical performance type requirements set forth an objective or standard to be achieved, and the successful Bidder is expected to exercise their ingenuity in achieving that objective or standard of performance, selecting the means and assuming a corresponding responsibility for that selection.
1.8.B. When a particular product or manufacturer is identified by name, but permits substitution of ‘an approved equal,’ such a requirement is ‘performance’ in nature and, as a result, carries no implied warranty.
February 24, 2026 ◊●◊●◊ Instructions to Bidders USIBWC Solicitation 191BWC26Rxxxx 00.21.13.01-Page 3
1.8.C. The Scope of Work is written in imperative and abbreviated form. This imperative language is directed at the Design-Builder, unless specifically noted otherwise. Incomplete sentences shall be completed by inserting "shall", "the Design-Builder shall", and "shall be" or similar mandatory phrases by inference.
The words "shall be" are to be placed by inference where a colon (:) is used within sentences or phrases.
Except as worded to the contrary, the Design-Builder shall fulfill (perform) all indicated requirements whether stated imperatively or otherwise.
1.8.D. All equipment and facilities shall be furnished, installed, and constructed by the Design-Builder to provide the Government with complete, ready to use components, systems, and facilities. All necessary materials and work required to accomplish this are the responsibility of the Design-Builder alone, whether or not specifically stated in the Scope of Work.
1.9. BID SUBMISSION
1.9.A. Submission of a bid shall be conclusive evidence that the Bidder has reviewed, investigated, and acknowledged all items detailed in FAR 52.236-3 and listed below.
1. Conditions bearing upon transportation, disposal, handling, and storage of materials.
2. The availability of labor, water, electric power, and roads.
3. Uncertainties of weather and similar physical conditions at the site.
4. The conformation and conditions of the ground.
5. The security and safety conditions at and around the site.
6. The character of equipment and facilities needed preliminary to and during work performance.
1.9.B. Submission of a bid shall be conclusive evidence that the Bidder has reviewed all Contract Documents.
1.9.C. Submission of a bid shall be conclusive evidence that the Bidder has investigated and is satisfied as to the conditions to be encountered, the character, quality, and scope of work to be performed, and the quantities of materials to be furnished.
1.9.D. Submission of a bid constitutes agreement that Bidder has provided written notice of all discrepancies, omissions, conflicts, defects, errors, ambiguities, or items that are open to interpretation discovered in the Contract Documents, that responses to these written notices are acceptable to Bidder, and that Contract Documents are sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing required work.
1.9.E. Bidder has the sole responsibility to make such independent investigation and examination as they deem necessary in order to satisfy themselves as to the conditions to be encountered in the performance of work and the quantities required to complete the work in a accordance with the Contract Documents. The Government will not award a modification or additional funds for conditions that were observable but not considered by Bidder.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
3.1. REQUESTS FOR INTERPRETATION (DUTY TO INQUIRE)
3.1.A. Bidder shall submit requests for interpretation, questions, and other concerns about the Solicitation and Contract Documents including, but not limited to, Scope of Work, Contract Drawings, USIBWC provided data, referenced items, attachments, etc. to the Contracting Officer identified on SF-1442.
3.1.B. Such requests shall be made even if the question and answer period identified in the Solicitation has passed.
◊●◊●◊ Instructions to Bidders February 24, 2026 00.21.13.01-Page 4 USIBWC Solicitation 191BWC26Rxxxx
3.1.C. Failure to request interpretation prior to providing a bid shall result in the Bidder being fully responsible for any cost or time impacts involved to perform the work required.
February 24, 2026 ◊●◊●◊ Design-Build Procurement Definitions USIBWC Solicitation 191BWC26Rxxxx 00.23.00.01-Page 1
SECTION 00.23.00.01
DESIGN-BUILD PROCUREMENT DEFINITIONS
00.23.00.01 ◊●◊●◊ Design-Build Procurement Definitions 00.23.00.01-◊●◊●◊ Design-Build Procurement Definitions
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Related Requirements
1.3. Reference Standards
1.4. Measurement and Payment
1.5. Design-Build Definitions
1.6. Other Project Definitions
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2. RELATED REQUIREMENTS
1.2.A. Section 01.42.00.01-References
1.3. REFERENCE STANDARDS
1.3.A. Federal Acquisition Regulations (FAR)
1.4. MEASUREMENT AND PAYMENT
The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.5. DESIGN-BUILD DEFINITIONS
Construction Contractor The subcontractor hired by the Design-Builder who is involved in the actual construction of the project.
Construction Drawings The drawings provided by the Design-Builder, usually through the Designer, to accomplish construction in concert with the Technical Specifications.
Contract Documents The Contract Documents include the Solicitation and eventual Contract, any documents provided by USIBWC identified in this Scope of Work, any documents provide with the Solicitation, all design documents produced by the Designer, all construction drawings, all Technical Specifications, and all submittals required by either the Scope of Work or the construction specifications.
Design-Builder The Design-Builder is the entity, firm, partnership, joint venture, or organization that Contracts with the United States Section of the International Boundary and Water Commission (USIBWC) to design and construct items meeting this Scope of Work The Design-Builder may be the Designer, the Construction Contractor, and/or the project manager.
The Design-Builder has full responsibility for completion of the Contract.
◊●◊●◊ Design-Build Procurement Definitions February 24, 2026 00.23.00.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx
Designer A subcontractor or in-house participant that leads the team furnishing the design for the project. The Designer must be registered to practice engineering in the state where the construction will occur.
Government The Government usually refers to the USIBWC or its representatives although it can also cover DHS or other entities associated with the project.
Government Representative The Government Representative refers to the Contracting Officer (CO) or the Contracting Officer’s Representative (COR). These individuals are designated by the USIBWC to act in the capacity as the "Government Representative" as defined by the Federal Acquisitions Regulations (FAR) and shall be the final interpreter of any project issues that may arise in the course of the Work. The USIBWC’s Government Representative shall be responsible for the Compliance Review of the Work.
Subcontractor Any supplier, distributor, vendors, individual, partnership, joint-venture, or corporation who performs work, provides services, or furnishes supplies for the Design-Builder under this Contract.
Supplier or Vendor Any individual, partnership, joint-venture, or corporation who only furnishes materials for work under this Contract. They provide no service nor perform any work onsite except for inspection of their products or training of personnel.
Technical Specifications The construction specifications provided by the Design-Builder, in concert with the Designer, to accomplish construction of this project by their Construction Contractor.
1.6. OTHER PROJECT DEFINITIONS
1.6.A. General terms, abbreviations, and definitions are shown in Section 01.42.00.01.
1.6.B. If terms are defined in both Section 01.42.00.01 and in this Section, the definition in this Section governs.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
(Not Used)
February 24, 2026 Procurement Scope USIBWC Solicitation 191BWC26Rxxxx 00.24.00.01-Page 1
SECTION 00.24.00.01
PROCUREMENT SCOPE
00.24.00.01 Procurement Scope 00.24.00.01-Procurement Scope
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Related Requirements
1.3. Reference Standards
1.4. Measurement and Payment
1.5. Project Goal
1.6. Work Elements
1.7. Sequence of Work/Time for Completion of Work
1.8. Work Under Other Contracts
1.9. Labor and Staffing
1.10. Project Location
1.11. Conflict Order of Precedence
Part 2 - Products
2.1. Government Furnished Materials
2.2. Products to be Furnished by the Design-Builder
Part 3 - Execution
3.1. Submittals Required Prior to Construction Mobilization
3.2. Use of Right-of-Way
3.3. Occupancy of Right-of-Way
3.4. Site Work Restrictions
--End of Section--
1.2. RELATED REQUIREMENTS
1.2.A. Section 01.33.16.01-Design Submittals
1.2.B. Section 00.31.43.01-Permit Application
1.2.C. Section 01.32.16.01-◊●◊●◊ Progress Schedule
1.2.D. Section 01.32.33.01-◊●◊●◊ Photographic Documentation
1.2.E. Section 01.33.00.01-◊●◊●◊ Submittal Procedures
1.2.F. Section 01.35.23.01-◊●◊●◊ Safety
1.2.G. Section 01.40.00.01-◊●◊●◊ Quality Requirements
1.2.H. Section 01.52.13.01-Field Offices and Sheds
1.2.I. Section 01.57.00.01-◊●◊●◊ Temporary Controls for Work Areas
1.2.J. Section 01.57.19.01-◊●◊●◊ Temporary Environmental Controls
1.2.K. Section 01.58.00.01-Project Identification
1.2.L. Section 01.61.00.01-Common Product Requirements
1.2.M. Section 01.61.16.01-◊●◊●◊ Use of Recovered Materials and Biobased Products
1.2.N. Section 01.64.00.01-Government Furnished Materials
Procurement Scope February 24, 2026 00.24.00.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx
1.2.O. Section 01.74.19.01-◊●◊●◊ Construction Waste Management and Disposal
1.2.P. Section 02.01.00.01-◊●◊●◊ Existing Conditions & Facilities
1.2.Q. Section 02.21.00.01-◊●◊●◊ Surveys
1.2.R. Section 02.22.13.01-Existing Conditions Assessment 12-14-2023
1.3. REFERENCE STANDARDS
1.3.A. Federal Emergency Management Agency (FEMA)
1. 44 CFR 65.10, Mapping of Areas Protected by Levee Systems
1.3.B. United States Code (USC)
1. Davis Bacon Act (DBA), 40 USC 3141-3148
1.4. MEASUREMENT AND PAYMENT
The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.5. PROJECT GOAL
The Retamal Dam is an existing hydraulic diversion structure located in Hidalgo County, Texas, approximately
2.5 miles east of the Donna Point International Port of Entry along the U.S.–Mexico boundary. The dam has a structural height of approximately 33 feet and a maximum bottom‑slab width of 200 feet. The superstructure consists of four interior piers and two abutment piers that collectively support three radial‑gate assemblies. The Retamal Dam Substation Building currently contains the non‑operational emergency generator. The objective of the project is to construct a new turnkey building adjacent to the existing substation to accommodate the installation of a new emergency generator.
1.1.A. The final product shall be capable of or shall meet these requirements:
1. The final design for this project shall provide a fully integrated, turnkey facility engineered to accommodate and support the installation, operation, and maintenance of a new emergency generator at Retamal Dam.
2. The installation and construction will feature the following items:
a. Metal Building with exhaust system and well ventilated
b. New Emergency Generator
c. Concrete mounting pad to accommodate metal building and fuel tank.
d. Fuel tank and spill containment basin
e. All electrical and electrical interconnection to an existing automatic transfer switch located at existing substation facility.
f. Parameter Security Fence
1.1.B. Upon conclusion of the project, the new turnkey metal building shall be a fully commissioned building able to operate for its intended use with all the electrical components, mechanical components, HVAC, etc.
1.1.C. Utilities It is the Design-Builder’s responsibility to identify all existing utilities within the project limits as well as coordinating any work associated with these utilities with the utility company.
1.1.D. Permits Refer to Section 00.31.43.01.
USIBWC Solicitation 191BWC26Rxxxx 00.24.00.01-Page 3
1.2. WORK ELEMENTS
1.2.A. The work shall include all planning, design work, coordination, permitting, labor, material, tools, equipment, construction, testing, inspection, commissioning, and all necessary general conditions, that may be reasonably inferred from the Contract Documents to provide for all work for the design and construction of a new turnkey metal building to accommodate a new emergency generator. The new metal building and generator will be installed adjacent to the existing Retamal Dam Substation, where the damaged generator is currently located. Retamal Dam is in Hidalgo County, Texas.
1.2.B. The work shall be broken out into 2 phases.
1. Phase 1 is the Design Phase.
The Design Phase includes, but is not limited to:
a. Site investigation
b. Site surveying
c. Any required geotechnical investigations, modeling, or testing.
d. Design
e. Production of construction documents (minimum of drawings and technical specifications)
f. Production of all project reports
g. Coordination with stakeholders
2. Phase 2 is the Construction Phase.
The Construction Phase includes, but is not limited to:
a. Site preparation
b. Construction
c. Disposal of debris and construction waste
d. Quality control testing
e. Commissioning
1.2.C. Each phase shall have a separate Notice to Proceed (NTP).
1.2.D. The final product shall be a 100% completed construction project (turnkey) in accordance with the Design-Build Contract, this Scope of Work, and the construction drawings and specifications.
1.3. SEQUENCE OF WORK/TIME FOR COMPLETION OF WORK
1.3.A. After receipt of the Notice to Proceed (NTP) the Design-Builder shall comply with all submittal requirements as covered under this Scope of Work.
1. No construction shall be started, until the Government compliance confirms the required premobilization submittals. Once the Government determines that construction may proceed, will mobilization be allowed.
2. The Government will not grant any time extension for any resubmittal required when, in the opinion of the CO, the initial submission failed to meet the minimum quality requirements as set forth in the Contract.
3. If the Government allows the Design-Builder to proceed with limited construction based on pending minor revisions to the reviewed submittals, no payment will be made for any in-place construction related to the pending revisions until they are completed, resubmitted and are satisfactory to the Government.
4. No payment will be made for any in-place construction until all submittals required for that portion of the work and/or required prior to the start of construction have been made, reviewed, and are satisfactory to the Government.
00.24.00.01-Page 4 USIBWC Solicitation 191BWC26Rxxxx
1.3.B. Unless otherwise agreed to with the COR, mobilization and sitework shall begin within 90 days of the issuance of the Construction Notice to Proceed (NTP).
1. Design-Builder and Construction Contractor shall expeditiously plan and prepare their premobilization submittals and any resubmittals as well as take into account the Government's review time to meet this requirement.
2. Surveying, photographing/videotaping site, and vibration condition survey do not constitute sitework for this requirement.
1.3.C. The work under this Contract shall be completed within the timeframe specified in the Contract Provisions. Time will only stop being counted once substantial completion is achieved (Section 01.78.36.01).
1.3.D. Where FAR 52.211-10 provides specific timeframes for completion of the design, construction, and revegetation, the following shall apply:
1. Design shall be completed within the timeframe noted in FAR 52.211-10.
2. If the design is completed prior to the timeframe noted in FAR 52.211-10, the remaining days shall be applied to the construction phase. For example, if the design is completed 20 days early, 20 days shall be added to the construction timeframe.
3. If the design is completed after the specified timeframe noted in FAR 52.211-10, then the Design-Builder is behind schedule and subject to any liquidated damages or other repercussions determined by the CO. The additional time required for completion of the design shall be subtracted from the allowed construction timeframe. For example, if the design is completed 20 days late, 20 days shall be subtracted from the construction timeframe.
4. Regardless of the design completion time and the construction completion time, the timeframe noted in FAR 52.211-10 for revegetation shall begin after substantial completion has been reached.
1.4. WORK UNDER OTHER CONTRACTS
No work is anticipated to be performed at the project site under separate Contract with other Contractors during the Design-Builder’s performance period.
1.5. LABOR AND STAFFING
1.5.A. The Design-Builder is responsible for determining the appropriate staffing necessary to perform the Contract work. The Design-Builder is also responsible for complying with the minimum wage and benefits requirements for each labor classification performing work on the Contract.
1.5.B. If a classification considered necessary by the Design-Builder for performance of the work is not listed on the applicable wage determination, the Design-Builder must initiate a request for approval of an additional classification along with the proposed wage and benefit rates for that classification.
1.5.C. The Contracting Officer will attach the appropriate Davis-Bacon wage determination to this Contract. The Design-Builder is responsible for all requirements of the Davis-Bacon Act.
1.6. PROJECT LOCATION
1.6.A. The work is within the United States Section of the International Boundary and Water Commission's (USIBWC) Retamal Dam, in Hidalgo County, Texas.
1.6.B. The work is located completely within the United States but is directly adjacent to the international border with Mexico.
USIBWC Solicitation 191BWC26Rxxxx 00.24.00.01-Page 5
1.7. CONFLICT ORDER OF PRECEDENCE
1.7.A. In any case where this Scope of Work conflicts with the Federal Acquisition Regulations (FAR), use the following rules of precedence.
1. In any case where FAR requirements are stricter or impose a higher standard than these Scope of
Work, FAR requirements will take precedence.
2. In any case where Scope of Work requirements are stricter or impose a higher standard than FAR, Scope of Work requirements will take precedence.
1.7.B. Upon acceptance of the construction specifications and drawings by USIBWC, those documents become part of the Contract. If the construction specifications and drawings differ from this Scope of Work, the more stringent requirement will govern.
PART 2 - PRODUCTS
2.1. GOVERNMENT FURNISHED MATERIALS
2.1.A. Automatic Transfer Switch (ATS) is located at the existing Retamal Dam substation facility where the old generator is housed.
1. The Government will provide one (1) ATS switch for the new emergency generator.
2.2. PRODUCTS TO BE FURNISHED BY THE DESIGN-BUILDER
2.2.A. The Design-Builder shall provide all labor, all equipment, and all products required to execute the project.
2.2.B. All materials provided by the Design-Builder for the project shall be new (or recycled if allowed elsewhere in this SOW), high grade, free from defects, meeting the specifications herein. The minimum quality of the work shall be in accordance with the specifications herein.
2.2.C. The Design-Builder's QSM will ensure compliance confirmation and the Design-Builder's testing company will ensure that materials, equipment and work quality strictly adhere to the requirements of the construction documents.
2.2.D. Materials, equipment, and work quality not conforming to the requirements of this SOW, the construction specifications, and/or the construction drawings shall be considered defective and will be subject to rejection. Defective work material, whether in place or not, or equipment shall be removed immediately from the site by the Design-Builder, at its expense, when so directed by the COR.
2.2.E. If the Design-Builder fails to replace any defective or damaged work, materials or equipment after receiving notice, the COR may cause such work or materials to be replaced by other forces. The replacement expense shall be deducted from the amount to be paid to the Design-Builder. Defective equipment will not be allowed in the performance of any work.
2.2.F. Water for All Construction Activities.
1. The water required for all construction activities including, but not limited to, dust control (Section
01.57.19.01) and vegetation establishment shall be considered as incidental and shall be provided from a metered source that is compliance confirmed by the USIBWC.
2. Water from the Rio Grande shall not be used by the Design-Builder at any time.
3. Water use must be in accordance with Texas water law.
00.24.00.01-Page 6 USIBWC Solicitation 191BWC26Rxxxx
PART 3 - EXECUTION
3.1. SUBMITTALS REQUIRED PRIOR TO CONSTRUCTION MOBILIZATION
3.1.A. Specific specifications detail submittal requirements. The list below are the submittals required to have compliance confirmation from the COR prior to full construction mobilization and prior to starting construction activities.
1. Construction Schedule (Section 01.32.16.01)
2. Scheduler Qualifications (Section 01.32.16.01)
3. Video and Photographs of Existing Conditions (Section 01.32.33.01)
4. Submittal Register (Section 01.33.00.01)
5. Construction Accident Prevention Plan (Section 01.35.23.01)
6. Applicable AHAs to start mobilization and construction (Section 01.35.23.01)
7. Site Safety and Health Officer Qualifications (Section 01.35.23.01)
8. Construction Contingency Evacuation Plan (Section 01.35.23.01)
9. Construction Employee First-Aid and CPR Training Records (Section 01.35.23.01)
10. Design-Builder Quality Assurance Plan (Section 01.40.00.01)
11. Design-Builder QC/QA Personnel Qualifications (Section 01.40.00.01)
12. Construction Staging Area/Haul Routes/Trailer Location/Storage (Sections 01.52.13.01 and
01.57.19.01)
13. Construction SWPP Plan (Section 01.57.00.01)
14. Construction SWPP NOI (Section 01.57.00.01)
15. Resource Conservation Construction Plan (Sections 01.61.00.01, 01.61.16.01, and 01.74.19.01)
16. Construction Flood Protection Plan (Section 02.01.00.01)
17. Construction Vibration Control Plan (Section 02.22.13.01)
18. Preconstruction Condition Survey (Section 02.22.13.01)
3.1.B. The design report, survey data/report, geotechnical report, construction drawings, GIS data, and construction specifications outlined in Section 01.33.16.01 Paragraph 1.6.A. shall have reached 100% and been accepted by USIBWC.
3.1.C. The construction specifications and construction drawings shall have been added to the Contract via a no-cost modification.
3.1.D. Once these required items are complete, the Design-Builder will be allowed to mobilize their Construction Contractor and begin work within USIBWC's right-of-way (ROW).
3.2. USE OF RIGHT-OF-WAY
3.2.A. Limits
1. Construction operations shall be confined to the USIBWC ROW.
3.2.B. It is the Design-Builder’s responsibility to locate and/or verify the areas required for construction beyond the USIBWC ROW, identify the owners of the affected properties, and acquire necessary easements, prior to commencement of construction, at no cost to the USIBWC.
3.2.C. Roads serving the right-of-way, identified as such or not, owned by the USIBWC or CBP shall be clear and available to these agencies.
USIBWC Solicitation 191BWC26Rxxxx 00.24.00.01-Page 7
3.3. OCCUPANCY OF RIGHT-OF-WAY
3.3.A. Partial Government Occupancy The Government may need to occupy the right-of-way during the entire construction period, with the exception of areas under construction. The Construction Contractor via the Design-Builder shall cooperate with the Government during construction operations to minimize conflicts and facilitate Government access. The Design-Builder needs to maintain existing access to the facility, unless otherwise indicated in the construction drawings. The Design-Builder shall provide not less than 72 hours' notice to the Government of construction activities that will affect any Government activities.
3.3.B. Government Occupancy of Completed Areas of Construction The Government reserves the right to occupy and to place and install equipment in completed areas of the facility, before Substantial Completion, provided such occupancy does not interfere with completion of the work. Such placement of equipment and partial occupancy shall not constitute acceptance of the total work.
3.4. SITE WORK RESTRICTIONS
3.4.A. Onsite Work Hours The Design-Builder’s attention is directed to the Contract Provisions.
3.4.B. Facility Office Hour
1. The working hours of the adjacent USIBWC facility are 07:30 am to 04:00 pm, Monday through
Friday. The Design-Builder, the Construction Contractor, and any subcontractors shall only work onsite during these proposed hours.
2. USIBWC facilities are closed during all Federal Holidays.
00.24.00.01-Page 8 USIBWC Solicitation 191BWC26Rxxxx
February 24, 2026 Project Information USIBWC Solicitation 191BWC26Rxxxx 00.31.00.01-Page 1
SECTION 00.31.00.01
PROJECT INFORMATION
00.31.00.01 Project Information 00.31.00.01-Project Information
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Related Requirements
1.3. Measurement and Payment
1.4. Information Provided by the USIBWC
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2. RELATED REQUIREMENTS
1.2.A. Section 00.60.00.01-◊●◊●◊ USIBWC Forms and Standard Documents
1.2.B. Section 00.73.73.01-Requirements for Sensitive But Unclassified Information
1.3. MEASUREMENT AND PAYMENT
The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.4. INFORMATION PROVIDED BY THE USIBWC
1.4.A. USIBWC shall provide the following project documents to the Design-Builder.
1. Contract Drawings for the existing Retamal Dam substation facility.
2. USIBWC's standard AutoCAD border (USIBWC's CAD files and Drawing and CAD Standards link on www.ibwc.gov/resources-info/)
3. USIBWC's AutoCAD ctb file (USIBWC's CAD files and Drawing and CAD Standards link on www.ibwc.gov/resources-info/)
4. IBWC's Drawing and CAD Standards (USIBWC's CAD files and Drawing and CAD Standards link on www.ibwc.gov/resources-info/)
5. USIBWC Standard Technical Specifications Boilerplate (USIBWC's Construction Specifications
Template link on www.ibwc.gov/resources-info/)
6. USIBWC shall provide the following CUI project documents to the Design-Builder after completion of a nondisclosure agreement (IBWC Form 358). See Section 00.73.73.01 for guidance on CUI data.
1.4.B. CUI items will be provided via a Sharepoint link to each Offeror requesting access to this data. The Offerors shall provide an email address along with IBWC Form 358 to the CO for this link.
1. No more than 2 Sharepoint links will be provided to each Bidder.
2. To use Sharepoint, a user must have a valid Microsoft account. If this method fails, data can be provided to the Offeror via a DVD, but there will be a delay in getting the DVD mailed to each Bidder.
3. All unsuccessful Offerors shall provide IBWC Form 358A to the CO within 7 days of being notified of their unsuccessful offer.
https://www.ibwc.gov/resources-info/ https://www.ibwc.gov/resources-info/ https://www.ibwc.gov/resources-info/
Project Information February 24, 2026 00.31.00.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx
1.4.C. See Section 00.60.00.01 for instructions on accessing data on USIBWC's website.
1.4.D. The Design-Builder is responsible for printing copies of items provided in electronic format for their own use.
1.4.E. Any hardcopy documents provided to the Design-Builder are the property of the USIBWC and shall be returned upon completion of this project.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
February 24, 2026 ◊●◊●◊ Project Time Constraints & Milestones USIBWC Solicitation 191BWC26Rxxxx 00.31.13.01-Page 1
SECTION 00.31.13.01
PROJECT TIME CONSTRAINTS & MILESTONES
00.31.13.01 ◊●◊●◊ Project Time Constraints & Milestones 00.31.13.01-◊●◊●◊ Project Time Constraints & Milestones
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Measurement and Payment
1.3. Design Milestones
1.4. Schedule Limitations
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2. MEASUREMENT AND PAYMENT
The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.3. DESIGN MILESTONES
1.3.A. Required submittals include:
1. Conceptual Layout and Floor Plan / Design Development Documents
2. 30% Design
3. 60% Design
4. 90% Design
5. Pre-100% Design
6. 100% Design
1.4. SCHEDULE LIMITATIONS
1.4.A. The complete period of performance shall include the design, including production of design and construction documents, and construction.
1.4.B. The Design-Builder shall submit the 30% design documents as stipulated under the design criteria.
1. The USIBWC shall provide comments within 28 calendar days of receipt of these deliverables and the Design-Builder shall incorporate the Government's comments prior to the next submittal.
1.4.C. The Design-Builder shall submit the 60% design documents as stipulated under the design criteria.
1. The USIBWC shall provide comments within 28 calendar days of receipt of these deliverables and the Design-Builder shall incorporate the Government's comments prior to the next submittal.
1.4.D. The Design-Builder shall submit the 90% design documents as stipulated under the design criteria.
1. The USIBWC shall provide comments within 28 calendar days of receipt of these deliverables and the Design-Builder shall incorporate the Government's comments prior to the next submittal.
1.4.E. The Design-Builder shall submit the 100% design documents of construction specifications, construction drawings, and Design Memorandum as stipulated under Design Work Requirements.
1. Initial 100% submittal shall be in electronic form only. This shall be known as the pre-100% submittal.
◊●◊●◊ Project Time Constraints & Milestones February 24, 2026 00.31.13.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx
2. The USIBWC shall provide additional comments on the 100% deliverables in the event that the Design-Builder failed to incorporate accordingly or adequately address all of the USIBWC’s 90% comments. Comments will be provided within 28 calendar days of receipt of these submittals.
3. After acceptance of the 100% submittal, then Design-Builder shall provide required hard and electronic copies of all 100% documents.
1.4.F. After completion of Phase 1, the Design-Builder shall construct the metal building.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
February 24, 2026 Existing Condition Information USIBWC Solicitation 191BWC26Rxxxx 00.31.19.01-Page 1
SECTION 00.31.19.01
EXISTING CONDITION INFORMATION
00.31.19.01 Existing Condition Information 00.31.19.01-Existing Condition Information
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Related Requirements
1.3. Measurement and Payment
1.4. General
1.5. Existing Structures
1.6. Existing Utilities
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2. RELATED REQUIREMENTS
1.2.A. Section 00.31.32.01-Geotechnical Data 5-8-2020
1.3. MEASUREMENT AND PAYMENT
The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.4. GENERAL
1.4.A. The final design shall take all existing conditions into account as well as information discovered during investigations under this Contract.
1.4.B. Geotechnical investigations were performed as noted in Section 00.31.32.01.
1.5. EXISTING STRUCTURES
Retamal Dam is an existing diversion structure located in Hidalgo County, Texas, approximately 2.5 miles east of the Donna Point International Port of Entry along the U.S.–Mexico border. The Retamal Dam Substation Building, shown in Figure 1 and circled in red, currently contains the non‑operational emergency generator.
Existing Condition Information February 24, 2026 00.31.19.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx
Figure 1
1.6. EXISTING UTILITIES
1.6.A. USIBWC's records for installed utilities are often incomplete. The Design-Builder is responsible for locating all utilities including, but not limited to, irrigation structures, buried communication, gas, water, and electrical lines.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
February 24, 2026 Environmental Information USIBWC Solicitation 191BWC26Rxxxx 00.31.24.01-Page 1
SECTION 00.31.24.01
ENVIRONMENTAL INFORMATION
00.31.24.01 Environmental Information 00.31.24.01-Environmental Information
PART 1 - GENERAL
1.1. SECTION INCLUDES
Part 1 - General
1.1. Section Includes
1.2. Related Requirements
1.3. Reference Standards
1.4. Measurement and Payment
1.5. General
1.6. Preservation of Cultural and Natural Resources and the Environment
1.7. Other Considerations
1.8. Use of Geologic Materials on a Federally Funded Project
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2. RELATED REQUIREMENTS
1.2.A. Section 01.57.00.01-◊●◊●◊ Temporary Controls for Work Areas
1.2.B. Section 01.57.19.01-◊●◊●◊ Temporary Environmental Controls
1.2.C. Section 02.21.13.01-◊●◊●◊ Cultural Resources Surveys
1.3. REFERENCE STANDARDS
1.3.A. United States Code (USC)
1. Clean Air Act, 42 USC 7401 et seq.
2. Clean Water Act (CWA), 33 USC 1251 et seq.
3. Endangered Species Act (ESA), 16 USC 1531 et seq.
4. Migratory Bird Treaty Act (MBTA), 16 USC 703 - 712
5. National Environmental Policy Act (NEPA), 42 USC 4321-4347
6. National Historic Preservation Act (NHPA), 54 USC 300101 et seq.
7. National Wildlife Refuge System Improvement Act of 1997, 16 USC 668dd
8. Native American Graves Protection and Repatriation Act (NAGPRA), 25 USC 3001 et. seq.
9. Refuge Recreation Act, 16 USC 460k - 460k-4
1.4. MEASUREMENT AND PAYMENT
The work performed by the Design-Builder under this Section shall not be paid for directly but shall be included in the various Bid Items under this Contract.
1.5. GENERAL
1.5.A. The project’s Environmental Assessment (EA), entitled "XXXXXX," dated XXXX, was prepared for
USIBWC by XXXX. The Design-Builder shall review and comply with the requirements provided in the EA document.
Environmental Information February 24, 2026 00.31.24.01-Page 2 USIBWC Solicitation 191BWC26Rxxxx
1.5.B. These documents lists environmentally and culturally sensitive areas that need to be protected from any disturbances of construction activities. The environmentally and culturally sensitive areas that were identified on the document are identified below.
1. Environmentally Sensitive Areas
a. USIBWC will be responsible for compliance with National Environmental Policy Act (NEPA).
USIBWC may prepare NEPA documentation concurrent with this contract and/or solicitation. The Contractor must incorporate any environmental protection measures identified in the NEPA document
2. Culturally Sensitive Areas
a. Although this area has not been previously surveyed nor cleared archeologically, USIBWC has determined that the construction of a new building on this location would not result in adverse effects on cultural properties as no historic properties will be affected.
3. Biological Resources Work should be scheduled to occur outside of the bird breeding season whenever possible.
Migratory birds may be present within the project area; birds, nests, and eggs are to be protected and avoided during construction. The breeding and nesting season is identified in Section 01.57.19.01. If work continues into the bird breeding/nesting season the areas proposed for disturbance shall be surveyed in order to avoid the inadvertent destruction of nests and eggs.
4. Natural Resources Equipment cannot be parked, staged, or used under large, mature trees. Keeping equipment away from the large, mature trees will prevent incidental damage to the tree and prevent compression of the root ball.
5. Water Quality
a. The Contractor must ensure that construction will not adversely impact on the water quality of the Rio Grande during construction (per 01.57.19.01 Part 1.9.).
6. Fuel Tanks
a. Fuel storage tanks must comply with Texas Administrative Code (TAC) 30 TAC Chapter 334 Subchapter F for aboveground storage tanks, including secondary containment.
1.5.C. Further details of environmental requirements are in Sections 01.57.00.01 and 01.57.19.01.
1.6. PRESERVATION OF CULTURAL AND NATURAL RESOURCES AND THE ENVIRONMENT
1.6.A. If the Design-Builder initiates changes to the Contract and USIBWC approves the changes, the Design-Builder is responsible for obtaining clearances and coordinating with the appropriate regulatory agencies.
1.6.B. Culturally Sensitive Areas If a site, building, or location of historical, archaeological, educational, or scientific interest is discovered within the right of way, cease all work immediately, secure the site from further disturbance and possible vandalism, and notify USIBWC. The site, building, or location will be investigated and evaluated by
USIBWC.
1.7. OTHER CONSIDERATIONS
The Design-Builder is required to ensure that all Environmental Permits, Issues, and Comments (EPIC), which are included within the Contract Documents are followed and implemented to ensure potential impacts are avoided.
February 24, 2026 Environmental Information USIBWC Solicitation 191BWC26Rxxxx 00.31.24.01-Page 3
1.8. USE OF GEOLOGIC MATERIALS ON A FEDERALLY FUNDED PROJECT
1.8.A. To ensure preservation of historical and archaeological data, prior to use of any soil, rock, or gravel including aggregate in concrete, the source must first be compliance confirmed by the COR to ensure compliance with Section 106 of the National Historic Preservation Act (NHPA).
1.8.B. Take no action to use or alter the proposed location until written approval for site use is received from the
COR.
1.8.C. If the quarry or borrow site already provides materials for TxDOT, USACE, or other governmental agency, a copy of the environmental approvals from said agencies may be provided to the COR.
1.8.D. Include permission for Government access to any geological source locations.
1.8.E. Full details of requirements for geological materials are in Section 02.21.13.01.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
Environmental Information February 24, 2026 00.31.24.01-Page 4 USIBWC Solicitation 191BWC26Rxxxx
February 24, 2026 Existing Hazardous Material Information USIBWC Solicitation 191BWC26Rxxxx 00.31.26.01-Page 1
SECTION 00.31.26.01
EXISTING HAZARDOUS MATERIAL INFORMATION
00.31.26.01 Existing Hazardous Material Information 00.31.26.01-Existing Hazardous Material Information
PART 1 - GENERAL
1.1…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .