191BWC26R0005 0001.pdf

PDF 474 KB Posted

Attached to
Retamal Dam Building and Generator
Solicitation number
191BWC26R0005
Issued by

About this file

This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) for the International Boundary and Water Commission (IBWC), a federal agency. The solicitation number is 191BWC26R0005, issued June 15, 2026, with an effective date of June 1, 2026. This is Amendment 0001, dated July 15, 2026, extending the receipt deadline for proposals. The requisition number is FY264221003.

The solicitation is for design-build services for a Retamal Dam Emergency Generator and Building project located in Mercedes, Texas (Hidalgo County). The work consists of three contract line items (CLINs): Design, Construction (Labor, Equipment, and Material), and Closeout/Drawing Record/O&M Manuals, all with firm fixed-price contracts. The project delivery date is May 8, 2026. The contract type is design-build under FAR Subpart 36.3 (Two-Phase Design-Build Selection Procedures). Site access is coordinated with the COR and restricted to weekdays 7:00 a.m. to 3:30 p.m.; the facility is closed during federal holidays. The project requires compliance with OSHA standards (29 CFR 1926) and the U.S. Army Corps of Engineers Safety Manual (EM 385-1-1). Performance and payment bonds equal to 100% of contract price are required within 10 days of award. Liquidated damages are set at $1,349.49 daily for construction and $403.64 daily for closeout, with a completion timeframe of 485 calendar days plus 120 days for closeout. The contractor must perform at least 50% of the work with its own organization. Small business subcontracting plan goals include 23% small business, 5% women-owned, 5% socially disadvantaged, 3% service-disabled veteran-owned, and 3% HUBZone small businesses. Proposals must be submitted electronically via SharePoint by August 4, 2026, at 3:00 p.m. MST in three separate volumes (Business, Technical, and Pricing), with technical proposals limited to 40 pages. Award will be made to the responsible offeror whose proposal best demonstrates technical qualifications and capability to perform under two-phase evaluation procedures, with technical factors and past performance weighted approximately equal to cost.

View the file

Other files

Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Document Number: 191BWC26R0005 DRAFT Page 1 of 63

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE RATING

2. AMENDMENT/MODIFICATION NUMBER

3. EFFECTIVE DATE

06/01/2026

4. REQUISITION/PURCHASE REQ. NUMBER

FY264221003

5. PROJECT NUMBER (If applicable)

IBWC_CODE

International Boundary and Water Commission (IBWC)

USIBWC - ACQUISITIONS DIV

4191 NORTH MESA ST

EL PASO, TX 79902-1441

US

Adrian I Knights

NAME

(915)832-4723

TEL.

knightsai@state.gov

EMAIL

6. ISSUED BY CODE7. ADMINISTERED BY (If other than Item 6)

9A. AMENDMENT OF SOLICITATION NUMBER

191BWC26R0005

CODE FACILITY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, country, state and ZIP Code) (X)

X 9B. DATED (SEE ITEM 11)

07/15/2026

10A. MODIFICATION OF CONTRACT/ORDER

NUMBER

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X XThe above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended, Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning ____copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

ORDER NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Add Section J/list of attachments posted to SAM.gov.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Philip Johnson

(Signature of person authorized to sign)

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED

By (Signature of Contracting Officer)

16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

07/03/2026

NSN 7540-01-152-8070

Previous edition unusable

STANDARD FORM 30 (REV.

11/2016) Prescribed by GSA FAR (48 CFR) 53.243

CGFS // CGFS

Document Number: 191BWC26R0005 DRAFT Page 2 of 63

Table of Contents

Section Description Page Number

B Supplies or Services and Prices/Costs C Descriptions/Specifications/Statement of Work

C.01 Descriptions/Specifications/Statement of Work D Packaging and Marking

D.02 Marking E Inspection and Acceptance

52.246-12 Inspection of Construction (Aug 1996) F Deliveries or Performance

52.211-13 Time Extensions (Sept 2000) 52.242-14 Suspension of Work (Apr 1984) 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) 52.211-12 Liquidated Damages-Construction (Sept 2000)

G Contract Administration Data IBWC 242-70 Designation of Contracting Officer IBWC 242-71 Contractor's Officer Representative IBWC 242-73 Contractor's Payment Personnel IBWC 242-74 Contracting Officer

INV-IPP ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS AND INSTRUCTIONS

TO IMPLEMENT USAGE OF THE INVOICE PROCESSING PLATFORM (IPP)

G.05 Notification of Government Delays

H Special Contract Requirements IBWC.01 Performance and Payment Bonds (DEC 2015) IBWC.02 Compensation and Liability Insurance (DEC 2015) IBWC.03 Builders Risk Insurance (DEC 2015) IBWC.04 Brand Name or Equal (DEC 2015) IBWC.05 Technical Data Submittal Requirements (DEC 2015) IBWC.06 Accident Prevention and Pre-Planning (DEC 2015) IBWC.07 Construction Program (DEC 2015) IBWC.08 Construction Safety Standards (DEC 2015) IBWC.09 Cultural Resources (DEC 2015) IBWC.10 Contract Work Schedule (DEC 2015) IBWC.11 Utility and Telephone Services (DEC 2015) IBWC.12 Administration of Default (Fixed-Price Construction) (DEC 2015) IBWC.13 Time Extensions for Unusually Severe Weather (DEC 2015) IBWC.14 Change Orders and Contract Modifications: Limitations on Markups (DEC 2015) IBWC.15 Damage from the Elements - Diversion of Water (DEC 2015) IBWC.16 Contract Closeout Procedures (DEC 2015) IBWC.17 Extended Warranties IBWC.18 DESIGN-BUILD CONTRACT - Order of Precedence (DEC 2015) IBWC.19 DESIGN-BUILD CONTRACT - Incorporation of Designer of Record Final Design (DEC 2015)

I Contract Clauses 52.252-2 Clauses Incorporated by Reference (Feb 1998) 52.202-1 Definitions (Jun 2020) 52.203-3 Gratuities (Apr 1984) 52.203-5 Covenant Against Contingent Fees (May 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (Jun 2020) 52.203-7 Anti-Kickback Procedures (Jun 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) 52.203-12 Limitation On Payments to Influence Certain Federal Transactions (Jun 2020) 52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021) 52.203-17 Contractor Employee Whistleblower Rights (Nov 2023) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017)

Document Number: 191BWC26R0005 DRAFT Page 3 of 63

52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011) (DEVIATION) 52.204-13 System for Award Management-Maintenance (DEVIATION JAN 2026) 52.204-14 Service Contract Reporting Requirements (DEVIATION JAN 2026) 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (DEVIATION JAN 2026) 52.210-1 Market Research (DEVIATION JUN 2025) 52.215-2 Audit and Records-Negotiation (DEVIATION FEB 2026) 52.215-8 Order of Precedence - Uniform Contract Format (DEVIATION FEB 2026) 52.219-8 Utilization of Small Business Concerns (DEVIATION FEB 2026) 52.219-9 Alt II Small Business Subcontracting Plan (DEVIATION FEB 2026) - Alternate II (FEB 2026) 52.219-16 Liquidated Damages-Subcontracting Plan (DEVIATION FEB 2026) 52.222-3 Convict Labor (DEVIATION FEB 2026) 52.222-4 Contract Work Hours and Safety Standards--Overtime Compensation (DEVIATION FEB 2026) 52.222-6 Construction Wage Rate Requirements (DEVIATION FEB 2026) 52.222-7 Withholding of Funds (DEVIATION FEB 2026) 52.222-8 Payrolls and Basic Records (DEVIATION FEB 2026) 52.222-9 Apprentices and Trainees (DEVIATION FEB 2026) 52.222-10 Compliance with Copeland Act Requirements (DEVIATION FEB 2026) 52.222-11 Subcontracts (Labor Standards) (DEVIATION FEB 2026) 52.222-12 Contract Termination-Debarment (MAY 2014)(DEVIATION FEB 2025) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (DEVIATION FEB 2026) 52.222-15 Certification of Eligibility (May 2014) 52.222-16 Approval of Wage Rates (DEVIATION FEB 2026) 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment (DEVIATION FEB 2026)..

52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method) (DEVIATION

FEB 2026)

52.222-35 Equal Opportunity for Veterans (DEVIATION FEB 2026) 52.222-36 Equal Opportunity for Workers with Disabilities (DEVIATION FEB 2026) 52.222-37 Employment Reports on Veterans (DEVIATION FEB 2026) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEVIATION

FEB 2026)

52.222-50 Combating Trafficking in Persons (DEVIATION FEB 2026) 52.222-54 Employment Eligibility Verification (DEVIATION FEB 2026) 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026 (DEVIATION FEB 2026) 52.222-62 Paid Sick Leave Under Executive Order 13706 (DEVIATION FEB 2026) 52.223-5 Pollution Prevention and Right-to-Know Information (May 2024) 52.223-20 Aerosols (May 2024) 52.223-21 Foams (May 2024) 52.224-1 Privacy Act Notification (Apr 1984) 52.224-2 Privacy Act (Apr 1984) 52.224-3 Privacy Training (JAN 2017)(DEVIATION) 52.227-4 Patent Indemnity-Construction Contracts (Dec 2007) 52.227-17 Rights in Data - Special Works (Dec 2007) 52.228-2 Additional Bond Security (Oct 1997) 52.228-5 Insurance-Work on a Government Installation (Jan 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (Dec 2022) 52.228-14 Irrevocable Letter of Credit (Nov 2014) 52.228-15 Performance and Payment Bonds-Construction (Jun 2020)

Document Number: 191BWC26R0005 DRAFT Page 4 of 63

52.229-3 Federal, State and Local Taxes (Feb 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-10 Payments under Fixed-Price Architect-Engineer Contracts (Apr 2010) 52.232-17 Interest (May 2014) 52.232-18 Availability of Funds (Apr 1984) 52.232-23 Assignment of Claims (May 2014) 52.232-24 Prohibition of Assignment of Claims (May 2014) 52.232-25 Prompt Payment (Jan 2017) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct 2018) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.233-4 Applicable Law for Breach of Contract Claim (DEVIATION JAN 2026) 52.236-2 Differing Site Conditions (DEVIATION AUG 2025) 52.236-3 Site Investigation and Conditions Affecting the Work (DEVIATION AUG 2025) 52.236-5 Material and Workmanship (DEVIATION AUG 2025) 52.236-6 Superintendence by the Contractor (DEVIATION AUG 2025) 52.236-7 Permits and Responsibilities (DEVIATION AUG 2025) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(DEVIATION AUG 2025)

52.236-10 Operations and Storage Areas (DEVIATION AUG 2025) 52.236-11 Use and Possession Prior to Completion (DEVIATION AUG 2025) 52.236-12 Cleaning Up (DEVIATION AUG 2025) 52.236-13 Accident Prevention (DEVIATION AUG 2025) 52.236-23 Responsibility of the Architect-Engineer Contractor (DEVIATION AUG 2025) 52.236-24 Work Oversight in Architect-Engineer Contracts (Apr 1984) 52.236-25 Requirements for Registration of Designers (June 2003) 52.236-26 Preconstruction Conference (Feb 1995) 52.237-2 Protection of Government Buildings, Equipment, and Vegetation (Apr 1984) 52.237-3 Continuity of Services (Jan 1991) 52.243-1 Alt III Changes-Fixed-Price (DEVIATION JUL 2025) - Alternate III (JUL 2025) 52.244-4 Subcontractors and Outside Associates and Consultants (Architect-Engineer Services) (Aug 1998) 52.244-5 Competition in Subcontracting (Aug 2024) 52.244-6 Subcontracts for Commercial Products and Commercial Services (DEVIATION JAN 2026) 52.245-1 Government Property (Sep 2021) 52.245-1 Alt I Government Property (Sep 2021) - Alternate I (Apr 2012) 52.246-21 Warranty of Construction (Mar 1994) 52.246-23 Limitation of Liability (Feb 1997) 52.249-2 Alt I Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - Alternate I (Sept 1996) 52.249-7 Termination (Fixed-Price Architect-Engineer) (Apr 1984) 52.249-10 Alt I Default (Fixed-Price Construction) (Apr 1984) - Alternate I (Apr 1984) 52.203-14 Display of Hotline Poster(s) (Nov 2021) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (DEVIATION JAN 2026) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (DEVIATION JAN 2026) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (DEVIATION

JAN 2026)

52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data-Modifications (DEVIATION FEB 2026) 52.215-23 Limitations on Pass-Through Charges (DEVIATION FEB 2026) 52.222-44 Fair Labor Standards Act and Service Contract Labor Standards-Price Adjustment

(DEVIATION FEB 2026)

52.225-9 Buy American-Construction Materials (DEVIATION FEB 2026) 52.225-10 Notice of Buy American Requirement-Construction Materials (May 2014) 52.232-26 Prompt Payment for Fixed-Price Architect-Engineer Contracts (Jan 2017) 52.233-1 Alt I Disputes - Alternate I (DEVIATION JAN 2026) 52.236-1 Performance of Work by the Contractor (Apr 1984)

Document Number: 191BWC26R0005 DRAFT Page 5 of 63

52.236-4 Physical Data (Apr 1984) 52.248-3 Value Engineering-Construction (Oct 2025) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (Apr 2012) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.253-1 Computer Generated Forms (DEVIATION FEB 2026)

J List of Attachments J.01 List of Attachments

K Representations, Certifications, and Other Statements of Offerors or Respondents 52.204-8 Annual Representations and Certifications (Mar 2026) 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021)

L Instructions, Conditions, and Notices to Offerors and Respondents 52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998) 52.215-1 Instructions to Offerors-Competitive Acquisition (DEVIATION FEB 2026) 52.215-20 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data (DEVIATION FEB 2026) 52.215-22 Limitations on Pass-Through Charges-Identification of Subcontract Effort (DEVIATION

FEB 2026)

52.216-1 Type of Contract (DEVIATION FEB 2026) 52.233-2 Service of Protest (DEVIATION JAN 2026) 52.236-27 Alt I Site Visit (Construction) (Feb 1995) - Alternate I (Feb 1995) L.01 Pre-Bid Conference and Site Visit L.02 General Proposal Instructions L.03 Business Proposal Offeror Statements Instruction L.05 Technical Proposal Instructions L.06 Pricing Proposal Instructions L.07 Professional Behavior L.08 Contractor's Contract Administration

M Evaluation Factors for Award M.01 Evaluation Factors For Phase One M.02 Basis For Award M.03 Phase Two Evaluation Factors For Award M.04 Phase Two Offer Evaluation M.05 Scoring Adjectives and Definitions

Document Number: 191BWC26R0005 DRAFT Page 6 of 63

Section B - Supplies or Services and Prices/Costs

Line Item Summary

Solicitation Number:

191BWC26R0005

Contract Number: Title:

Retamal Dam Emergency Generator and Building

Date of Solicitation:

07/27/2026

Number Supplies or Services Qty Unit Unit Price Total (Inc. disc., tax, and fees)

PSC: Y1JZ

PSC Description: CONSTRUCTION OF

MISCELLANEOUS BUILDINGS

Type of Contract Pricing: Firm Fixed Price

Original: 1.0

Change: 0.0

Current: 1.0

EA Original: $0.00

Change: $0.00

Current: $0.00

Original: $0.00

Change: $0.00

Current: $0.00

Delivery Schedule:

Delivery Number Delivery Date Quantity FOB Point 1 05/08/2026 1.000000 Destination

Description: Design

Reference Line: FY264221003 - 001

Number Supplies or Services Qty Unit Unit Price Total (Inc. disc., tax, and fees)

PSC: Y1JZ

PSC Description: CONSTRUCTION OF

MISCELLANEOUS BUILDINGS

Type of Contract Pricing: Firm Fixed Price

Original: 1.0

Change: 0.0

Current: 1.0

EA Original: $0.00

Change: $0.00

Current: $0.00

Original: $0.00

Change: $0.00

Current: $0.00

Delivery Schedule:

Delivery Number Delivery Date Quantity FOB Point 1 05/08/2026 1.000000 Destination

Description: Construction-Labor, Equipment and Material

Reference Line: FY264221003 - 002

Number Supplies or Services Qty Unit Unit Price Total (Inc. disc., tax, and fees)

PSC: Y1JZ

PSC Description: CONSTRUCTION OF

MISCELLANEOUS BUILDINGS

Type of Contract Pricing: Firm Fixed Price

Original: 1.0

Change: 0.0

Current: 1.0

EA Original: $0.00

Change: $0.00

Current: $0.00

Original: $0.00

Change: $0.00

Current: $0.00

Delivery Schedule:

Delivery Number Delivery Date Quantity FOB Point 1 05/08/2026 1.000000 Destination

Description: Closeout, Drawing Record, and O M Manuals

Reference Line: FY264221003 - 003

Invoices to be uploaded to Invoice Processing Platform at http://www.ipp.gov

Document Number: 191BWC26R0005 DRAFT Page 7 of 63

CLIN Funding: Cost:

Base Totals: Original: $0.00

Change: $0.00

Current: $0.00

Original: $0.00

Change: $0.00

Current: $0.00

Exercised Options Totals: Original: $0.00

Change: $0.00

Current: $0.00

Original: $0.00

Change: $0.00

Current: $0.00

Unexercised Options Totals: Original: $0.00

Change: $0.00

Current: $0.00

Original: $0.00

Change: $0.00

Current: $0.00

Base and Options Totals: Original: $0.00

Change: $0.00

Current: $0.00

Original: $0.00

Change: $0.00

Current: $0.00

Section C - Descriptions/Specifications/Statement of Work

Clause C.01 Descriptions/Specifications/Statement of Work was deleted.

C.02 - Description of Work Location

1. The site access shall be coordinated with COR Heriberto Cantu. The working hours of the USIBWC facility are 7:00 am to 3:30 pm, Monday through Friday. The Contractor and any subcontractors shall only work on site during these proposed hours. USIBWC facilities, including the dam, are closed during all Federal Holidays. Workers must pass through USIBWC levees to access Retamal Dam. Border Patrol are present in the area. Contractor and subcontractor shall have identifying vehicular when working in the area. US Fish and Wildlife own land adjacent to Retamal Dam.

Contractor shall stay clear of US Fish and Wildlife Property.

2. City: Mercedes

3. County: Hidalgo

4. State: Texas

5. Latitude : 26 03'4.684"N

6. Longitude: 98 02'5.811"W

Clause C.01 Descriptions/Specifications/Statement of Work was added or modified.

C.01 - Descriptions/Specifications/Statement of Work

The Specifications for this solicitation 191BWC26R00005 are referenced in Section J and included as attachments to this document.

Section D - Packaging and Marking

Document Number: 191BWC26R0005 DRAFT Page 8 of 63

D.02 - Marking

All information submitted to the CO or the COR shall be clearly marked to show the Name of the Contractor and the Contract Number.

Section E - Inspection and Acceptance

Clause Title Fill-ins

52.246-12 Inspection of Construction (Aug 1996)

Section F - Deliveries or Performance

Clause Title Fill-ins

52.211-13 Time Extensions (Sept 2000)

52.242-14 Suspension of Work (Apr 1984)

52.211-10 - Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within 10 [Contracting Officer insert number] calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than four hundred and eight five (485) calendar days. All closeout documents and final paperowrk shall be provided within one hundred and twenty (120) calendar days.* The time stated for completion shall include final cleanup of the premises.

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

(End of clause)

52.211-12 - Liquidated Damages-Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,349.49 daily for construction and $403.64 for closeout [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

Section G - Contract Administration Data

IBWC 242-70 - Designation of Contracting Officer

The Contracting Officer for this contract is:

Name: Philip Johnson Address: 4191 N Mesa St El Paso TX 79902

Document Number: 191BWC26R0005 DRAFT Page 9 of 63

(end of clause)

IBWC 242-71 - Contractor's Officer Representative

The Contracting Officer shall designate a technical representative to act for the contracting Officer during the contract period. The Contracting Officer's Representative (COR) will act for the Contracting Officer only in technical matters and will not be authorized to commit the Government on any contract terms, conditions, or changes in unit price, total contract price, quantity, or quality, or delivery schedule. Any changes to the contract in unit price, total contract price, quantity, quality, or delivery schedule will be made only by the Contracting Officer by executed modification to the contract. The Contracting Officer's Representative will be located at the .

The Contracting Officer's Representative will be appointed in writing after contract award.

(end of clause)

IBWC 242-73 - Contractor's Payment Personnel

Offerors are requested to designate the person who may be contacted for bank account and-or payment information.

IBWC 242-74 - Contracting Officer

"Contracting Officer" means a person with the authority to enter into, administer, and-or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the Contracting Officer within the limits of their authority as delegated by the Contracting Officer.

(end of clause)

INV-IPP - ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS AND INSTRUCTIONS TO IMPLEMENT

USAGE OF THE INVOICE PROCESSING PLATFORM (IPP).

(a) Definitions. As used in these instructions

(1)”Payment request” means a bill, voucher, invoice, or request for contract financing payment with associated supporting documentation. The payment request must comply with the requirements identified in FAR 32.905(b), “Payment documentation and process” and the applicable Payment clause included in this contract.

(b) Except as provided in paragraph (c) of these instructions, the Contractor shall submit payment requests electronically using the Invoice Processing Platform (IPP) at www.ipp.gov. Information regarding IPP is available on the Internet at www.ipp.gov. Assistance with the IPP application can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866)973-3131. The Contractor shall ensure that its supporting documentation conforms to IPP requirements. IPP accommodates up to 25 supporting attachments per invoice, individual attachment file size may not exceed ten megabytes (10mb). If the Contractor assesses that their supporting documentation will not reasonably conform to IPP requirements, the Contractor shall contact the Contracting Officer to explore possible alternatives. In addition, the IPP only allows certain characters to be used as the invoice number. The invoice number shall conform to the IPP convention and the attachments (if used) shall match exactly the invoice number allowed. The allowed characters in the IPP are “abcdefghijklmnopqrstuvwxyzABCDEFGHIJKLMNOPQRSTUVWXYZ0123456789-_”

Document Number: 191BWC26R0005 DRAFT Page 10 of 63

(c) If the Contractor wishes to be paid via a foreign bank account, the contractor must properly fill out form GFS-FO-CLM-089 and attach it to each invoice in the IPP where payment to a foreign bank account is requested. The form can obtained by e-mailing CGFSIPPITSForm@state.gov.

(d) The Contractor may submit payment requests using other than IPP only when the Contracting Officer authorizes alternate procedures in writing.

(e) If alternate payment procedures are authorized, the Contractor shall include a copy of the Contracting Officer’s written authorization with each payment request.

[End of instructions]

G.01 - USIBWC's Small Business Subcontracting Plan Goals

Small Business: At least 23% of contract dollars must go to small businesses.

Women-Owned Small Businesses: 5% of contract dollars Socially Disadvantaged Small Businesses: 5% of contract dollars Service-Disabled Veteran-Owned Small Businesses: 3% of contract dollars HUBZone Small Businesses: 3% of contract dollars

G.05 - Notification of Government Delays

In the event the contractor encouters difficulty in meeting performance requirements, or anticipates difficulty in compying with the contract delivery schedule or dates, or whenever the Contractor has knowledge that any actual or potential situation is delaying or threatens to delay the timely performance of this contract, the Contractor shall immediately notify the Contracting Officer and the COR in writing, giving pertinent details.

NOTE: This data shall not be construed as a waiver by the Government of any delivery schedule or dates or of any rights or remedies provided by law or under this Contract.

Section H - Special Contract Requirements

IBWC.01 - Performance and Payment Bonds (DEC 2015)

H.01.A. For contracts that exceed $150,000.00 the Contractor shall, within 10 calendar days after award of contract, furnish to the Government bonds as follows:

H.01.A.1. SF 25, Performance Bond. Performance bond with a surety or sureties approved by the Contracting Officer, securing performance and fulfillment of the Contractor's obligations under this contract, with a penal amount of not less than 100% of the price of the contract at the time of award.

H.01.A.2. SF 25A, Payment Bond. Payment bond with a surety or sureties approved by the Contracting Officer, assuring payment as required by law to all persons supplying labor or materials in the prosecution of the work provided for in the contract with a penal amount of not less than 100% of the price of the contract at the time of award.

H.01.B. Costs. All costs of furnishing performance and payment bonds shall be included in the total bid in the schedule.

H.01.C. Requirements for execution of surety bonds. Each surety company bond (performance or payment), that purports to have been executed by an agent or attorney in fact for the corporate surety, is required to have submitted with it a power of attorney to the signatory agency or attorney in fact, and (1) be executed by the corporate surety upon a date

Document Number: 191BWC26R0005 DRAFT Page 11 of 63 reasonably proximate to the date of the bond, or (2) the power of attorney shall be accompanied by a certification of the surety to the effect that the power of attorney was in full force and effect upon a date reasonable proximate to the date of the bond.

H.01.D. Individual Sureties.

H.01.D.1. If individual surety bonds are furnished for payment and performance bonds, the individual sureties must submit with their bonds proof of ownership and value of the assets which they claim in their net worth. The Government's preferred method of proof is to have a statement of net worth prepared by a certified public accountant in accordance with generally accepted accounting principles. The statement of net worth on the SF 28, Affidavit of Individual Surety is not in itself sufficient and will not be accepted absent of additional proof of value and ownership.

H.01.D.2. Bidders are also cautioned that individual sureties must provide complete and detailed information in block 10 of the SF 28 concerning other contracts on which they have provided bonds. This information should include contract number, contract location, amount and type of bond, email address, and telephone number of the involved contracting officer.

H.01.D.3. Failure to provide the proof and information requested above will cause delays to the start of construction for which the contractor must bear the responsibility and may result in termination of contract for failure to provide adequate bonds.

[End of Clause]

IBWC.02 - Compensation and Liability Insurance (DEC 2015)

H.02.A. The Contractor shall within ten (10) calendar days after award of contract provide and maintain minimum insurance as follows:

H.02.A.1. General Liability Insurance. General Liability Insurance for bodily injury and property damage with minimum limits $500,000 each occurrence with an aggregate of $1,000,000.

H.02.A.2. Automobile Liability. Automobile Liability for bodily injury and property damage with minimum of $250,000 for injury to or death of any one (1) person, $500,000 each accident or occurrence for bodily injury, and $100,000 for each accident or occurrence for property damage liability.

H.02.A.3. Worker's Compensation Insurance. Worker's Compensation Insurance for all labor employed on the project who may come within the protection of workers' compensation laws and Employers General Liability with minimum limits of $100,000 each accident, bodily injury by disease $100,000 each employee, $500,000 aggregate. In every case the insurance coverage shall amount to at least the limits stated above. However, where the Financial Responsibility Compulsory Insurance Law of the State in which the project is located requires higher limits, the Automobile Liability Insurance Policy shall provide coverage of at least those limits required by State law. The insurance obtained by the Contractor must (1) be effective for the term of the contract and (2) must name both the United States of America by and through the United States Section of the International Boundary and Water Commission as additionally insured. The requirement for naming the United States of America as an additional insured does not apply to Worker's Compensation Insurance. Before commencing work under this contract, the Contractor shall certify to the Contracting Officer in writing that the required insurance has been obtained.

H.02.B. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (1) for such period as the laws of the State in which this contract is to be performed prescribe or (2) until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer. The Contractor's written certification shall be accompanied by either a Certificate issued by the insurer or photocopies of the insurance policies which reflect that the cancellation/change provisions of this contract have been met.

H.02.C. The Contractor shall insert the substance of this clause including this paragraph in subparagraphs under this contract and shall require subcontractors to provide and maintain the same limits. At least 5 days prior to each such

Document Number: 191BWC26R0005 DRAFT Page 12 of 63 subcontractor's personnel commencing work on this project, the Contractor shall furnish (or ensure that there has been furnished) to the Contracting Officer a current Certificate of Insurance meeting the requirements as stated above.

[End of Clause]

IBWC.03 - Builders Risk Insurance (DEC 2015)

H.03.A. The Contractor is responsible for losses suffered prior to Government acceptance of the work. Therefore, the Contractor is responsible for protection of the work and repair of damages. For the protection of the Contractor and the Government, the Contractor is required to obtain Builder's Risk Insurance with the maximum level of coverage available in the project locality and no less than 100% of the contract price.

H.03.B. The Contractor shall not commence work under this contract until he has obtained all the insurance required and such insurance has been approved by the Contracting Officer, nor shall the Contractor allow any subcontractor to commence work on their subcontract until the insurance required of the subcontractor has been so obtained and approved.

H.03.C. The Contractor shall procure within 10 calendar days after award of contract, and maintain during the life of this contract, Builder's Risk Insurance based on 100% of the completed value of the insurable portion of the project.

H.03.D. The Contractor shall furnish the Contracting Officer with certificates showing the type, amount, class of operations covered, effective dates, and dates of expiration. Such certificates shall also contain substantially the following statement: "The insurance covered by this certificate will not be canceled or materially altered, except after thirty (30) calendar days written notice has been received by the Contracting Officer."

H.03.E. The insurance obtained by the Contractor must (1) be effective for the term of the contract and (2) must name the United States of America by and through the United States Section of the International Boundary and Water Commission as an additional insured.

[End of Clause]

IBWC.04 - Brand Name or Equal (DEC 2015)

If items called for by this Solicitation have been identified in the specifications by a "Brand Name or Equal" description, such identification is intended to be descriptive, but not restrictive, and is to indicate the quality and characteristics of products that will be satisfactory (Reference Section I, FAR Clause 52.236-5 entitled Material and Workmanship). The determination as to equality of a product shall be the responsibility of the Government and will be based on information furnished during the submittal process (Reference Technical Specification Section 01.33.00-Submittals). As used in this clause, the term "brand name" includes identification of products by manufacturer, make, and/or model.

[End of Clause]

IBWC.05 - Technical Data Submittal Requirements (DEC 2015)

H.05.A. Technical data required to be provided to the government are described in the paragraph entitled "Submittal Requirements" in the Technical Specifications Section 01.33.00-Submittals.

H.05.B. If the Contractor fails to provide required technical data within the time(s) specified in this contract, or any extension, such failures shall be considered to demonstrate unsatisfactory progress and:

H.05.B.1. There shall be retained from the progress or other payments under this contract such amount(s) as the Contracting Officer considers adequate protection to the Government, therefore.

H.05.B.2. The Contractor and its sureties shall be liable to and assessed by the Government for all damages caused by such failure.

H.05.B.3. The Contractor’s right to proceed with the work that has been delayed may be terminated for default.

Document Number: 191BWC26R0005 DRAFT Page 13 of 63

H.05.C. In the event the Contractor provides submittals prior to Notice to Proceed, the Government may review the submittals prior to the Notice to Proceed. The Contractor shall not seek compensation for efforts spent on the preparation of submittal documents submitted prior to the Notice to Proceed.

H.05.D. The rights and remedies of the Government in this clause are in addition to any other rights and remedies provided by law or under this contract.

H.05.E. The Government may expedite the review of submittals. Expedite is defined as any review time less than the allotted time specified for the review of the submittal in Section 01.33.00. However, the Government reserves the right to require up to the amount of time specified in Section 01.33.00 for review of submittals or resubmittals.

[End of Clause]

IBWC.06 - Accident Prevention and Pre-Planning (DEC 2015)

H.06.A. With reference to the requirements of Contract Clause 52.236-13 (Alternate I) for an overall safety program, the Contractor shall:

H.06.A.1. Submit a detailed plan for performing each major phase of work.

H.06.A.2. Require Subcontractors to submit their plan of operations showing methods they propose to use in accomplishing major phases of work.

H.06.A.3. Be prepared to discuss the plans in conferences convened by the Contracting Officer or Contracting Officer’s Representative prior to starting work on each major phase of work. Plans shall include all pertinent information, such as methods of providing safety measures for personnel performing required work. The plan for accomplishing work shall be submitted prior to commencing operations.

[End of Clause]

IBWC.07 - Construction Program (DEC 2015)

H.07.A. The Contractor shall submit a progress schedule of construction in accordance with the requirements set forth in the Technical Specifications Section 01.32.16-Construction Progress Schedule. The initial compliance confirmed progress schedule under Section 01.32.16 shall serve as a baseline for the project. The Contractor's progress schedule shall account for the assigned workday calendar, seasonal weather conditions, and other constraints considered in the planning and scheduling of all work to ensure the completion within the allotted contract time. The progress schedule shall be of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a progress schedule within the time prescribed, the Contracting Officer (CO) may withhold approval of progress payments until the Contractor submits the required progress schedule. Until such time as the submitted progress schedule is compliance confirmed as the official schedule of the project, the CO may withhold approval of progress payments.

H.07.B. If, in the opinion of the CO, the Contractor falls behind the compliance confirmed progress schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the CO, without additional cost to the Government. In this circumstance, the CO may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the CO deems necessary to demonstrate how the approved rate of progress will be regained.

H.07.C. Failure of the Contractor to comply with the requirements of the CO under this clause shall be grounds for a determination by the CO that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the CO may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.

[End of Clause]

Document Number: 191BWC26R0005 DRAFT Page 14 of 63

IBWC.08 - Construction Safety Standards (DEC 2015)

H.08.A. Offerors shall obtain and review the current Construction Industry "OSHA Safety and Health Standards (29 CFR 1926)" and the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, dated March 15, 2024 (see Specification Section 01.35.23-Safety), prior to submitting offers and preparing required safety program. Offerors shall utilize these standards in preparing required safety programs.

H.08.B. The Contractor shall comply with all pertinent provisions of the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, dated March 15, 2024. This manual is available from:

www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE%2015March2024.pdf.

H.08.C. In the event there is a conflict between the requirements contained in OSHA Safety and Health Standards (29 CFR 1926), U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1), specifications paragraphs, Contractor's approved safety program, or referenced safety and health standards, the more stringent requirement will prevail.

[End of Clause]

IBWC.09 - Cultural Resources (DEC 2015)

H.09.A. In accordance with the National Historic Preservation Act of 1966 (16 U.S.C. 470), the following procedures are implemented to ensure historic preservation and fair compensation to the Contractor for delays attendant to cultural resources investigations. In the event potential historical, architectural, archaeological, or cultural resources (herein after cultural resources) are discovered during subsurface excavations at the site of construction, the following procedures shall be instituted:

H.09.A.1. The Contractor shall immediately cease work in that area, secure the location from further disturbance and possible vandalism, and immediately notify the Contracting Officer and the Contracting Officer’s Representative.

H.09.A.2. The Contracting Officer shall issue a "Suspension of Work" directing the Contractor to cease all construction operations at the location of such potential cultural resources find.

H.09.A.3. Such "Suspension of Work" shall be effective until such time as a qualified archaeologist can be called to assess the value of these potential cultural resources and make recommendations to the State Historical Preservation Officer. Any "Suspension of Work" shall contain the following:

H.09.A.3.a. A clear description of the work to be suspended;

H.09.A.3.b. Any instructions regarding issuance of further orders by the Contractor for material services;

H.09.A.3.c. Guidance as to action to be taken on subcontracts;

H.09.A.3.d. Any suggestions to the Contractor as to minimization of costs;

H.09.A.3.e. Estimated duration of the temporary suspension.

H.09.B. If the archaeologist determines that the potential find is a bona fide cultural resource, at the direction of the State Historical Preservation Officer, the Contracting Officer shall extend the duration of the "Suspension of Work" in writing, and the Contractor shall suspend work at the location of the find. Equitable adjustment of the construction contract shall be made in the following manner:

H.09.B.1. Time Extension. If the work temporarily suspended is on the "critical path," the total number of days for which the suspension is in effect shall be added to the number of allowable contract days. If a portion of work at the time of such suspension is not on the "critical path," but subsequently becomes work on the critical path, the allowable contract time will be computed from the date such work is classified as on the critical path.

H.09.B.2. Additional Compensation. If, as a result of a suspension of the work, the Contractor sustains a loss which could not have been avoided by judicious handling of forces, equipment, and (plant) or redirection of forces or equipment to perform other work on the contract, there shall be paid to the Contractor an amount as determined by the Contracting Officer to be fair and reasonable compensation for the Contractor’s actual loss in accordance with the following:

H.09.B.2.a. Idle Time of Equipment. Compensation for equipment idle time will be determined on a force account (time and materials) basis and shall include the cost of extra moving of equipment and rental loss.

Document Number: 191BWC26R0005 DRAFT Page 15 of 63

H.09.B.2.b. Idle Time of Labor. Compensation for idle time of workers will be determined by the Contracting Officer as "Labor" less any actual productivity factor of this portion of the work force.

H.09.B.2.c. Increased Costs of Labor and Materials. Increased costs of labor and materials will be compensated only to the extent such increase was in fact caused by the suspension as determined by the Contracting Officer.

H.09.C. Compensation for actual loss due to idle time of either equipment or labor shall not include markup for profit.

The hours for which compensation will be paid will be the actual normal working time during which such delay condition exists but will in no case exceed eight hours in any one day. The days for which compensation will be paid shall be full or partial calendar days, excluding Saturdays, Sundays, Federal and State holidays, during the existence of such delay.

H.09.D. Applicable State Historical Preservation Officer. The Texas Historical Commission is located at 1511 Colorado St., Austin, TX 78701. The Texas Historical Commission may be reached by email at thc@thc.state.tx.us, by telephone at (512) 463-6100, or by mail at: Mailing Address: PO Box 12276, Austin, TX 78711.

[End of Clause]

IBWC.10 - Contract Work Schedule (DEC 2015)

H.10.A. Normal working hours for the Contractor shall not be earlier than 6:00 am nor later than 5:30 pm, Monday through Friday, excluding Federal Holidays. If the Contractor wishes to work during periods other than that above or in excess of 40 hours per week, additional Government inspection forces will be required. The Contractor shall notify the Contracting Officer's Representative (COR) 3 business days in advance of their desire to work during other periods to allow the determination if additional inspection forces are reasonably available. If such forces are reasonably available, the Contracting Officer or COR may authorize the Contractor to perform work during periods other than normal duty hours/days or in excess of 40 hours per week; however, if additional inspection forces are required to perform in excess of their normal duty hours/days, the actual cost of the overtime inspection at overtime rates will be charged to the Contractor and will be deducted from the final payment of the Contract amount.

H.10.B. Consistent with Section 6103(a) of Title 5 of the United States Code the following are legal public holidays:

H.10.B.1. New Year’s Day, January 1.

H.10.B.2. Birthday of Martin Luther King, Jr., the third Monday in January.

H.10.B.3. Washington’s Birthday, the third Monday in February.

H.10.B.4. Memorial Day, the last Monday in May.

H.10.B.5. Juneteenth National Independence Day, June 19.

H.10.B.6. Independence Day, July 4.

H.10.B.7. Labor Day, the first Monday in September.

H.10.B.8. Columbus Day, the second Monday in October.

H.10.B.9. Veterans Day, November 11.

H.10.B.10. Thanksgiving Day, the fourth Thursday in November.

H.10.B.11. Christmas Day, December 25.

H.10.C. A listing of Federal Holidays are available at the following link:

www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/ For Holidays that fall on a Saturday, for Federal employees, the preceding Friday will be treated as a holiday for pay and leave purposes (See 5 U.S.C. 6103(b)). For Holidays that fall on a Sunday, for Federal employees, the following Monday will be treated as a holiday for pay and leave purposes (See section 3(a) of Executive order 11582, February 11, 1971).

H.10.D. If the above holidays are a paid holiday and results in works hours in excess of 40 hours in any workweek, laborers and mechanics shall be paid at least 1 and 1/2 times the basic rate of pay for each hour worked over 40 hours consistent with FAR Clause 52.222-4.

Document Number: 191BWC26R0005 DRAFT Page 16 of 63

IBWC.11 - Utility and Telephone Services (DEC 2015)

The U.S. Section, International Boundary and Water Commission will not provide utility (water, internet, gas, and electricity) and telephone services to the Contractor. The Contractor shall, at their own expense and in a workmanlike manner satisfactory to the Contracting Officer, install and maintain all necessary temporary connections and distribution lines, and shall remove the same prior to final acceptance of the work by the Government.

[End of Clause]

IBWC.12 - Administration of Default (Fixed-Price Construction) (DEC 2015)

H.12.A. Notwithstanding Paragraph (b)(1)(xi) of Contract Clause 52.249-10, Default (Fixed-Price Construction), the Contractor shall not be excused for delays, and shall be liable for any excess costs for failure to perform, if the subcontracted or purchased supplies or services were obtainable from other sources in sufficient time for the Contractor to meet the required delivery schedule or other performance requirements.

H.12.B. Unusually severe weather, as used in Paragraph (b)(1) of Contract Clause 52.249-10, Default (Fixed-Price Construction), means adverse weather which at the time of the year in which it occurred, was unusual for the place in which it occurred. No matter how severe or destructive, if the weather is not unusual for the particular time and place, or if a Contractor could have reasonably foreseen it, the Contractor is not entitled to an extension in contract time.

Climatological records are available for the Contractor's information online from the National Weather Service. The Government shall not be responsible for any interpretation or a conclusion drawn from the data or information by the Contractor.

H.12.C. Upon acknowledgment of the Notice to Proceed and continuing throughout the contract on a monthly basis, adverse weather will be recorded on a calendar day basis (including weekends and holidays). The COR will examine these records each month and determine whether the Contractor is entitled to a time extension.

H.12.D. Adverse weather must prevent work for 50% or more of the Contractor's work during any workday and delay work critical to the timely completion of the project.

[End of Clause]

IBWC.13 - Time Extensions for Unusually Severe Weather (DEC 2015)

H.13.A. This provision specifies the procedures for the determination of time extensions for unusually severe weather in accordance with the Contract Clause, 52.249-10, Default (Fixed-Price Construction). The listing below defines the monthly anticipated adverse weather for the contract period and is based on NOAA or similar data for the geographical location of the project. The weather conditions for this contract is based upon the weather station at McAllen, TX COOP (415701) .

H.13.B. Monthly Anticipated Adverse Weather Calendar Days

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual

2 1 1 0 0 0 4 4 2 0 0 2 16

H.13.B. Determination:

H.13.B.1. The above schedule of anticipated adverse weather will…

This is the start of the file's text. The full file is on GovTribe.