This sources sought notice is requesting capability statements for the construction of the Poplar Ancillary Healthcare Facility and renovation of the Vern E. Gibbs Health Center located on the Fort Peck Reservation in Poplar, Montana. The estimated value of construction is over $10 million to be awarded as a fixed-price contract by the Indian Health Service. Capability statements are due by March 12, 2019 with the anticipated period of performance from May 31, 2019 through 36 months after issuing the notice to proceed. The resulting contract is expected to be awarded on or about May 24, 2019. The solicitation is expected to be available for download on April 18, 2019 on FBO.gov with proposals due by May 17, 2019. The NAICS code is 236220 for Commercial and Institutional Building Construction with a size standard of $36.5 million.
Specification 26 27 13-Underground Electric Services
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNDERGROUND ELECTRIC SERVICE 26 27 13 - 1
SECTION 26 27 13 – UNDERGROUND ELECTRIC SERVICE
PART 1 - GENERAL
1.1 SUMMARY
A. Arrange with Montana Dakota Utilities Company for permanent electric service including all charges or fees levied by the serving utility company relative to this project. All service fees shall be paid by Owner.
B. Underground service entrance, items furnished by serving utility company:
1. Pad mounted transformer.
2. Current transformers.
3. Meter and meter conductors.
4. Primary cable and installation.
5. Secondary cable and installation to CT Cabinet.
1.2 WORK INCLUDED - SECONDARY
A. Items furnished by contractor (verify all requirements with Utility Company):
1. Secondary conduit from transformer to CT Cabinet.
2. Secondary conduits and conductors from CT Cabinet to Main Disconnect.
3. Primary conduits stubbed out past pad.
4. Meter base.
5. 1” Conduit from CT cabinet to the meter base.
6. Transformer pad and vault.
7. Padmount CT Cabinet and concrete pad.
1.3 SYSTEM DESCRIPTION
A. System voltage: 208Y/120 volts, three phase, four wire, 60 hertz.
1.4 QUALITY ASSURANCE
A. Utility company: Montana Dakota Utilities Company.
B. Install service entrance in accordance with Utility Company's rules and regulations.
Amendment 0005 to RFP 19-102-SOL-00026
UNDERGROUND ELECTRIC SERVICE 26 27 13 - 2
PART 2 - EXECUTION
2.1 INSTALLATION
A. Coordinate all work relative to the electrical service with the serving Utility Company prior to construction.
END OF SECTION 26 27 13
Amendment 0005 to RFP 19-102-SOL-00026
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Arrange with Montana Dakota Utilities Company for permanent electric service including all charges or fees levied by the serving utility company relative to this project. All service fees shall be paid by Owner. |
| B. Underground service entrance, items furnished by serving utility company: |
| 1.2 WORK INCLUDED � SECONDARY |
| A. Items furnished by contractor (verify all requirements with Utility Company): |
| 1.3 SYSTEM DESCRIPTION |
| A. System voltage: 208Y/120 volts, three phase, four wire, 60 hertz. |
| 1.4 QUALITY ASSURANCE |
| A. Utility company: Montana Dakota Utilities Company. |
| B. Install service entrance in accordance with Utility Company's rules and regulations. |
| PART 2 - EXECUTION |
| 2.1 INSTALLATION |
| A. Coordinate all work relative to the electrical service with the serving Utility Company prior to construction. |