19-PA2045 RFQ.pdf

PDF 409 KB Posted

Attached to
Terminal F Phase 2 Ticketing, Processing, Garage, & Roadways
Solicitation number
PA2045
Issued by
Dallas County, Texas

About this file

This is a Request for Qualifications (RFQ) for a Design-Build contract issued by the Dallas/Fort Worth International Airport Board for the Terminal F Phase 2 Ticketing, Processing, Garage & Roadways project. The solicitation seeks qualified design-build firms to provide comprehensive design, construction, delivery, and operational readiness testing of a new terminal ticketing and processing building with an integrated parking garage and associated roadways. The facility will span approximately 2,983,000 square feet across seven levels and will include passenger drop-off and pick-up areas, self-parking, baggage claim zones, ground transportation options, and a skyway bridge connector to Terminal F. The RFQ was released on January 15, 2026, with a pre-SOQ conference scheduled for January 22, 2026. Statements of Qualifications are due February 23, 2026, at 2:00 PM Central Time, with shortlisted firms (up to five) to be notified by March 3, 2026. Additional information submissions are due March 27, 2026, and interviews are scheduled for April 14-16, 2026, with final design-builder selection on April 17, 2026. The contract term extends four years through June 15, 2030, with an estimated Notice to Proceed date of June 15, 2026. Design is scheduled to commence June 15, 2026, with substantial completion milestones of February 2029 for core and shell ticketing and baggage handling areas and March 15, 2030, for the garage and roadways, with final completion 90 days thereafter.

The estimated project budget is $650,000,000, inclusive of design, permits, mobilization, pre-construction services, construction, and demolition costs. Small Business Enterprise (SBE) participation goals are set at 26% for design services and 18% for construction services, with required SBE certifications and compliance documentation to be submitted with the Statement of Qualifications. The project is federally grant-funded and subject to federal procurement procedures and regulations, which take precedence over state or local procedures in case of conflict. Evaluation of respondents will occur in two phases: Phase One assesses Statements of Qualifications based on relevant design-build experience, project complexity understanding, technical qualifications, schedule and budget delivery ability, management track record, and safety/quality performance; Phase Two requests proposals from shortlisted firms addressing project approach, schedule innovation, costing methodology, and SBE participation. The Design-Builder will be required to self-perform all major concrete operations except precast elements to ensure single-point responsibility and contract continuity. An early completion incentive of $1,000,000 per month is available if substantial completion occurs up to three months ahead of schedule, not to exceed $3,000,000 total. General Requirements and General Conditions costs are capped at 15% of direct construction costs and are fixed and non-negotiable.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR

STATEMENT OF

QUALIFICATIONS

Terminal F Phase 2 Ticketing, Processing Garage and Roadways

1-15-2026

CONTENTS

ADVERTISEMENT

1. SOLICITATION SCHEDULE

2. NOTICE TO DESIGN-BUILD FIRMS (INSTRUCTIONS TO

RESPONDENTS)

3. PROJECT DESCRIPTION / SCOPE OF WORK

4. ENVIRONMENTAL

5. DESIGN REQUIREMENTS

6. SELECTION PROCEDURES

Phase One – Statement of Qualifications (SOQ)

SOQ Evaluation Criteria Phase Two – Request for Proposals (RFP)

RFP Evaluation Criteria Post Selection Steps

ADVERTISEMENT

The Dallas/Fort Worth International Airport Board will receive Statement of Qualifications (SOQ) for the indicated Solicitation according to the following estimated schedule:

SOLICITATION: PA2045, Terminal F Phase 2 Ticketing, Processing, Garage & Roadways - Design-Build

RFQ Release Date: January 15, 2026

PRE-SOQ CONFERENCE: January 22, 2026, 10:00 AM (Central Time), via In-Person & Virtual

SOQ DUE DATE AND TIME: February 23, 2026, at 2:00 PM (Central Time)

SHORTLIST OF (UP TO FIVE) FIRMS: March 3, 2026

ADDITIONAL INFORMATION DUE: March 27, 2026, at 2:00 PM (Central Time)

INTERVIEW DATES: April 14-16, 2026 (if necessary)

SELECTION OF DESIGN BUILDER (DB): April 17, 2026

BUDGET: $650,000,000

SMALL BUSINESS ENTERPRISE (SBE) GOAL: 26% Design

SMALL BUSINESS ENTERPRISE (SBE) GOAL: 18% Construction

POINT OF CONTACT: Contract Administrator, James Legerme Tel: (972) 973-1735;

Email: jlegerme@dfwairport.com

1. SOLICITATION SCHEDULE

Solicitation Schedule

TERMINAL F PHASE 2 TICKETING, PROCESSING, GARAGE & ROADWAYS

CONTRACT NO. PA2045

Advertisement Publication Date January 14, 2026

Request for Qualifications available on website January 15, 2026

Pre-Qualifications Conference – Microsoft Teams https://teams.microsoft.com/meet/27010950640293?p=g t1anPxTZYEzos9C3d You can also dial in using your phone. (United

States) +1 469-965-2569, 899096283#

January 22, 2026, 2:00 p.m. Central Time

Deadline for Questions February 3, 2026, 4:00 p.m. Central Time

Issue Addenda (if applicable) February 11, 2026

Statement of Qualifications Due February 26, 2026, 2:00 p.m. Central Time

Committee Review February 26 to March 6, 2026

Notification to Shortlisted Firms and Requests for Proposal

March 9, 2026

Proposal Preparation by Firms March 10 to March 25, 2026

Request for Additional Information Due March 25, 2026, 2:00 PM Central Time

Committee Review March 25 – April 7, 2026

Interviews (if requested) March 31 – April 7, 2026

Notification of Selected Responder April 8, 2026

Contract Negotiations with selected Respondent April 8 – April 20, 2026

Airport Board Action May 7, 2026

Estimated Notice to Proceed June 15, 2026

Contract Term (Duration through Construction) 4 Years – June 15, 2030 https://teams.microsoft.com/meet/27010950640293?p=gt1anPxTZYEzos9C3d https://teams.microsoft.com/meet/27010950640293?p=gt1anPxTZYEzos9C3d

2. NOTICE TO DESIGN-BUILD FIRMS (INSTRUCTIONS TO

RESPONDENTS)

DFW Airport requests Statements (SOQ) from qualified respondents seeking to enter a contract with DFW to design and construction of the Terminal F Phase 2 Ticketing, Processing, Garage & Roadways, located at Dallas/Fort Worth International Airport (DFW), Texas. SOQ documents are required to be uploaded and submitted via solicitation portal, Euna Procurement, by the due date and time indicated in the solicitation schedule in the Events schedule of the Euna Procurement project page for the opportunity. Additional information related to this solicitation is available on the Euna Procurement page for this opportunity.

The resulting contract from this RFQ is United States Federally grant-funded and therefore subject to grant requirements. If there is a conflict between Federal or State procurement procedures, laws and/or regulations, Federal procedures, laws and/or regulations shall prevail.

A pre-submittal conference will be held at 2:00 p.m. CST on January 22, 2026, via Microsoft Teams. The deadline for questions from prospective Design-Builders will be 4:00 p.m. (Central Time) on February 3, 2026. The pre-submittal conference is non-mandatory. Respondent representation at this meeting should include a representative of any proposed partner, subcontractor/subconsultant, and the person/people who will be completing the SBE program response and response forms.

Any questions, concerns and/or requests for modification to the subject solicitation documents, including the Plans, Specifications, Agreement and Provision Terms, must be submitted in writing via Euna Procurement Vendor Discussions prior to the solicitation deadline for questions. If selected as the preferred firm, any attempts to negotiate these items after selection may be grounds for declaring an impasse and ceasing negotiations. Q for questions. Questions will not be accepted if submitted through any other method or if submitted after the deadline for questions.

All questions and responses will be posted on the Euna Procurement project page for this opportunity.

DFW will conduct a two-phase process to first shortlist the best qualified design-build firms then select the design-build firm that offers the most advantageous technical and costing methodology proposal and other factors included.

Phase One: After evaluating the Statements of Qualification (SOQ) submitted in response to this Request for Qualifications (RFQ), DFW will shortlist the best qualified design-build firms. A maximum of five (5) selected shortlisted firms will be notified to then submit supplemental information, through a Request for Proposal (RFP) for the design and construction of the project as defined through this RFQ and associated attachments.

Phase Two: DFW will request proposals (the RFP) from the shortlisted firms from Phase One.

The RFP will include, among other things, a design criteria package, instructions for preparing the technical and costing proposal and the items to be included, complete contract documents, and the weighting of the technical and costing methodology by which the proposals will be evaluated and ranked. DFW reserves the right to interview those firms for question and answer follow up as needed.

After selecting the design-build firm that offers the most advantageous proposal in Phase Two, DFW will first attempt to negotiate a contract with the selected Respondent. If DFW is unable to negotiate a contract with the selected Respondent, DFW will, formally and in writing, end negotiations with that Respondent and proceed to the next Respondent in the order of the selection ranking until a contract is reached or all proposals are rejected. The Board will seek to have a settled agreement with the most preferred firm prior to requesting Airport Board approval.

This will include due diligence in design rate, overhead, caps and level of effort (hours) proposed and other cost validation practices.

Addenda and Interpretations – Requests for interpretation of the RFQ must be received in accordance with the Solicitation Event Schedule. Only substantive items, as determined by the Board, will be addressed in the form of written addenda, which, if issued, will be posted on the DFW Airport Euna Procurement Solicitation website. Failure of any Contractor to retrieve and review any such addendum shall not relieve such Contractor from any obligations under its Proposal as submitted. All addenda issued shall become part of the Contract Documents. The Board may elect to not respond to all inquiries in this manner.

Small Business Enterprise Goals The DFW Airport, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252, 42 U.S.C. §§ 2000d to 2000d-4) and the Regulations, hereby notifies all DBs or Responders that it will affirmatively ensure that any contract entered into pursuant to this advertisement, small business enterprises will be afforded full and fair opportunity to submit bids in response to this invitation.

The Small Business Enterprise (SBE) goal for this solicitation/contract is established at 18% for the construction services (subcontractors, suppliers, etc.) and the Small Business Enterprise (SBE) goal for this solicitation/contract is established at 26% for professional design services (architect, engineer, consultants, etc.). Small Business Enterprise certifications and associated compliance documentation are required to be submitted with the Statement of Qualifications. Prior to being considered for evaluation by the selection committee, the Respondent’s SOQ shall be reviewed for compliance with DFW’s Business Development Department (BDD) Noncompliance will result in the SOQ being declared non-responsive and shall receive no further consideration.

The DFW Board may disqualify a Responder submitting a qualification statement, either as a prime or a subconsultant, as non-responsible and its Proposal shall not be considered for reasons including, but not limited to, the following:

I. Where the Prime Firm, or any subconsultant (or subcontractor or supplier) thereof, is in litigation with the DFW Board, or with either the cities of Dallas or Fort Worth, or where such litigation is contemplated or imminent, in the sole opinion of the DFW Board. The Prime Firm, as used in this solicitation is the single entity that holds direct contract with the Owner.

II. The Prime Firm, or any subconsultant thereof, being in arrears on any existing contract, change order, delivery order, and/or other contract action with DFW or any other publicly known contract or project.

III. The Prime Firm, or any subconsultant thereof, having defaulted on a previous contract.

IV. Uncompleted work that, in the judgment of the DFW Board, will prevent or hinder the prompt completion of additional work if awarded.

V. Where the Prime Firm, or any subconsultant thereof, in the judgment of the DFW Board, has failed to perform in a satisfactory manner on a previous contract.

VI. Where a Prime Firm, or any subconsultant thereof, has failed to disclose a potential conflict of interest or is discovered to have a conflict of interest in accordance with the DFW Board’s Code of Business Ethics.

VII. Where a Prime Firm, or any subconsultant thereof, or individual officer/principal of the firm or subcontractor is under criminal indictment or been convicted of a criminal offense.

Contracting Prohibitions

a) Bid/Proposal Rejection: Board will reject any Bid/Proposal from a Bidder/Proponent that:

i) boycotts Israel;

ii) contracts with or provides supplies or services to a foreign terrorist organization;

iii) engages in certain scrutinized business operations in Sudan, Iran or with a designated foreign terrorist organization; or

iv) has been complicit in the Darfur genocide during any preceding 20-month period.2

b) “Boycott Israel” Defined: “Boycott Israel” means refusing to deal with, terminating business activities with, or otherwise taking any action that is intended to penalize, inflict economic harm on, or limit commercial relations specifically with Israel, or with a person or entity doing business in Israel or in an Israeli-controlled territory, but does not include an action made for ordinary business purposes.

c) Verification: Each Bidder/Proponent must execute and submit with its submittal the Verification of Contracting Prohibitions. That verification will: [i] form a material part of its Bid/Proposal; and [ii] will be incorporated into any awarded contract.

d) Pursuant to Section 2274.002, Texas Government Code, enacted by SB 13 in the 2021 Regular Session, the Contractor hereby represents that it

(i) does not boycott energy companies; and

(ii) will not boycott energy companies.

e) Pursuant to Section 2274.002, Texas Government Code, as enacted by SB 19 in the 2021 Regular Session, the Contractor hereby represents that it (i) does not have a practice, policy, guidance, or directive that discriminates against a firearm entity or firearm trade association; and (ii) will not discriminate during the term of the contract against a firearm entity or firearm trade association.

See Texas Government Code; Chapter 2252; Subchapter F; Prohibition on Contracts with Certain Companies (including Sections 2252.152 and 2252.153); Chapter 2270; Prohibition on Contracts with Companies Boycotting Israel; and Chapter 2270; Prohibition on Investing Public Money in Certain Investments (including Sections 2270.0001, 2270.0052, 2270.0102 and 2270.0152).

Cone of Silence - To ensure a proper and fair evaluation, the DFW International Airport has established a cone of silence applicable to all Competitive Selection Processes, including RFQs, RFPs and RFBs. The cone of silence is designed to protect the integrity of the procurement process by shielding it from undue influences. The cone of silence will be imposed on all Competitive Selection Processes beginning with advertisement for the same and ending with the Board’s selection for RFQs, RFPs or the Board’s award for a RFB. The Cone of Silence begins when the solicitation is advertised/released and ends after the contract/purchase order is awarded, noting that release of some information is restricted by law. Potential bidders/proposers shall not discuss any aspect of a released solicitation with Airport personnel with exception to the contract administrator/ buyer listed in the solicitation.

3. PROJECT DESCRIPTION / SCOPE OF WORK

DFW seeks a Design-Builder (DB) with demonstrated ability to deliver highly integrated aviation facilities combining terminal functions, structured parking, elevated roadway systems, and bridge structures, while maintaining uninterrupted airport operations. The project will include the design, construction, delivery, and operational readiness testing of a new DFW Terminal F Ticketing, Processing & Garage Building with associated roadways. Design builder as used in this solicitation means the single entity contracted by the Owner to provide both design and construction of the project, integrating its consultants and contractors and has single-point responsibility.

The Terminal F Ticketing, Processing & Garage Building is a comprehensive, passenger-focused garage and ticketing building that consolidates essential landside functions under one roof.

Designed to enhance the travel experience, the facility will serve both departing and arriving passengers with a full suite of services. Departing travelers will benefit from streamlined curbside drop-off, efficient check-in areas, and convenient access to self-parking. Arriving passengers will be supported by intuitive baggage claim zones and a wide range of ground transportation options, including rideshare services (e.g. Uber and Lyft), limousine, and buses. This overall project will provide a new parking ramp building and associated infrastructure for the Terminal F site. The new building will include 7 levels providing a total of about 2,983,000 square feet including parking areas, passenger drop-off and pickup curbsides, access helices, access roads, connector bridge ramps and skyway bridge to Terminal F. The square footage is an approximation and is for information purposes only.

The Ticketing, Processing & Garage Building will connect to the Terminal F Concourse via a skyway bridge connector which is included in the scope of this project. The Ticketing, Processing & Garage Building scope includes the Core and Shell implementation, the relocation and provision of necessary utilities and support infrastructure for the buildings to be operational. Once building occupancy is permitted, other contractors will complete fit out tasks including infrastructure such as airline ticketing, processing and baggage handling systems. The Design Criteria Package (DCP) set forth in section 1.2.2 of the Design Criteria Package (DCP) provides a detailed Responsibility Matrix that splits responsibilities between the various entities.

The project scope includes the design, construction, delivery, and operational readiness testing of a new DFW Terminal F Ticketing, Processing and Garage building that will be constructed in the International Parkway median between Terminal E and Terminal F.

DCP Section 1.2.2 provides a responsibility matrix for features that are to be constructed under this contract. After core and shell fit out other features will be completed by airline partners, TSA, and other entities.

The DB is required to coordinate with other projects and the Board with respect to access the project site.

The NTP date for the design phase of the Terminal F Phase 2 Ticketing, Processing, Garage & Roadways will be contract execution date.

The Terminal F Phase 2 Ticketing, Processing, Garage & Roadways project will be designed with adherence to DFW Guidelines i.e. the DFW Design Criteria Manual (January 2026 version), IATA and all other applicable requirements. Refer to the DCP (section1.2.2) for Core & Shell, Fit-Out and User Fit-Out responsibilities, coordination, and approvals. Core and Shell items listed in the DCP are required scope of this project. Fit-Out and User Fit-outs require coordination and approvals with others.

The scope shall include (as referenced in the Design Criteria Package, included as part of this solicitation) but is not limited to: Architectural, Structural, Civil, Mechanical, Heating, Ventilation and Air-Conditioning (HVAC), Electrical, Plumbing, Life Safety, sanitary sewage and grease, drainage, storm water modification and site lighting, as well as roadway/frontage improvements, Natural Gas, Build Automation system, IT/Data, Low Voltage and Airport Systems, Fire & Life Safety, Security, Airport Systems, Security/CCTV, Access Control, Preconditioned Air units (PCAs), Parking Guidance Systems (PGS), Parking Access Revenue Control Systems (PARCS), Glycol Systems, Jet Fueling System, Fueling System, Conveyances, Roofing, Environmental (NEPA), Dynamic Glazing, Restrooms, Signage, Wayfinding, Graphics, Concessions, Interior Finishes, and Cellular Network systems.

The DB’s responsibilities will include continuous coordination with other DFW program teams working in the vicinity as listed below, but not limited to:

• Terminal F Expansion Program

• International Parkway (IP) Right Program – o Coordination with the IP Right Program team will be required to schedule the demolition of the Terminal E flyover.

o Construction and alteration that impacts the International Parkway.

The DB will share and coordinate construction schedules with other teams performing adjacent work to ensure synchronized completion and access to meet the established project completion date and milestones, to ensure gate availability and terminal operability at each stage of the project, per DFW and stakeholder requirements.

The DB will coordinate with all stakeholders including, but not limited to, ETAM, EAD, Operations, DPS (Aviation Security, Police and Fire), ITS, CX, Concessions, Innovation, Planning, Transportation Business Unit, Design, Code & Construction (DCC), Aviation Real Estate, DFW’s Fueling Operator and American Airlines.

Design and construction by the DB will include complete documents for construction and implementation for the following:

• Terminal F Ticketing, Processing, & Garage areas

• Skyway Bridge Connection to Terminal F.

• Associated roads, bridges and other facilities impacted by this project.

The scope of work includes developing phasing plans for the overall delivery of the Terminal F Ticketing, Processing & Garage Building and associated roads, bridges, and other facilities in coordination with other consultant teams.

The DB will develop and propose details of the overall project strategy, and the DB will need to undertake early detailed coordination with the previously referenced project(s) design consultant(s) and contractor(s) to align the new Terminal F Phase 2 Ticketing, Processing, Garage & Roadways utilities tie-ins as well as capacities and load requirements for the new building.

Coordination will be required with the other project teams to ensure dual feed communications network and main power are achieved to maintain full facility functionality during power outage events. Coordination will also be required with utilities for tie-in to new supply points where applicable.

The DB must be cognizant of the numerous tie-ins, and integration with the range of building systems, including many that serve live airport areas, and areas of other terminal refurbishment projects. The DB must demonstrate design, construction, testing, commissioning, and operational readiness capabilities for achieving system ties ins, both without disruptions to the airport operations, while also ensuring safe occupancy of the premises for all persons.

Portion of the Work may be inside the Airport’s secure Air Operations Area (AOA); however, the DB will be required to propose construction phasing to create non-AOA project construction areas when and where this provides construction and operational efficiency and must also plan for just in-time delivery due to laydown area size and constraints. The DB will be required to adhere to all FAA and DFW requirements working within the secure side of airport operations including AOA access and badging requirements.

The Project shall always maintain during construction the optimum level of service to passengers, tenants, and stakeholders, per DFW customer satisfaction standards. The DB shall establish a detailed phasing plan demonstrating continuity of operations while maintaining customer satisfaction. As applicable, the DB may need to provide necessary information to all stakeholders.

The Project should achieve, at a minimum, DFW Green Building Standards available at the following link:

https://assets.ctfassets.net/m2p70vmwc019/HUlt4QAG5SlGX8msKDnVC/b493cac9c1fe401c52 be5a0c0a2d04a4/DFW_Sustainability_DFW_Green_Building_Standards.pdf

- Provide a Building Information Modeling (BIM) protocol to achieve a Level of Development (LOD) 500 with complete building report attributes to be used for estimating and maintenance purposes.

- The DCP will serve as the basis of design for the project, further design evolution is the responsibility of the DB.

Budget: The estimated budget is $650,000,000 (including all costs; design, applicable permits, mobilization, pre-construction services, construction, abatement and demolition of existing facilities, general conditions, etc.) This is an estimate for informational purposes only. The intent is to award a single contract to a single DB for the entire work scope; however, the project may be divided and awarded to multiple contracts, as deemed appropriate by the DFW Board.

If the DB achieves Substantial Completion three (3) months prior to the Contract Substantial Completion Date, (in the instance that the DB contracts with DFW for the whole scope) and such early completion is not the result of scope reduction, deferred work, or Owner-directed changes, the Contractor shall be eligible for a pro-rated early completion incentive.

The incentive shall be earned at a rate of One Million Dollars ($1,000,000) per calendar month of early completion up to three (3)-month threshold and only if there is at least one month https://assets.ctfassets.net/m2p70vmwc019/HUlt4QAG5SlGX8msKDnVC/b493cac9c1fe401c52be5a0c0a2d04a4/DFW_Sustainability_DFW_Green_Building_Standards.pdf https://assets.ctfassets.net/m2p70vmwc019/HUlt4QAG5SlGX8msKDnVC/b493cac9c1fe401c52be5a0c0a2d04a4/DFW_Sustainability_DFW_Green_Building_Standards.pdf improvement on the substantial completion date. The maximum early completion incentive shall not exceed Three Million Dollars ($3,000,000).

Schedule: The tentative schedule for the project is:

Design Start: June 15, 2026 Preconstruction Services: June 15, 2026 Substantial Completion

a. Core & Shell Ticketing, Processing and Baggage Handling Areas including Sky bridge for baggage transport: February 2029

b. Garage: March 15, 2030

c. Roadways: March 15, 2030

Final Completion 90 days after Substantial Completion: June 15, 2030

4. ENVIRONMENTAL

The DB shall be responsible for coordination with DFW DCC and Environmental Affairs Department (EAD), for all governing NEPA and environmental requirements for the project including all applicable laws and regulations. This includes identification of hazardous materials to be abated, removed and disposed of per local and governing guidelines.

DFW will provide the DB with copies of available hazardous material assessment reports for the facilities to be demolished and or renovated. The DB shall be responsible for identifying the presence of any additional hazardous materials by testing, and if identified, coordinate with DFW EAD to develop an acceptable abatement plan. The DB shall be responsible for the abatement and disposal of the hazardous material.

The DB shall submit all (electrical, communication, plumbing, etc.) pathway drawings as deliverables at 35% design stage for DFW to review for impacts to any known existing hazardous material.

5. DESIGN REQUIREMENTS

The DB shall develop the packaging strategy and milestones as indicated below. DFW envisages an NTP for each package:

• Mutually agreeable packages to accommodate the overall project schedule. Each package will require permitting, and DFW review before proceeding with construction.

• The Design Builder is to provide Issued for Permit (IFP) packages for review and approval by DFW’s Authority Having Jurisdiction (AHJ). The Design Builder may break out the design into separate Issued for Permit (IFP) to meet an expedited schedule.

Construction can only commence after obtaining necessary permits including, but not limited to NEPA approval, the delivery of the Issued for Construction (IFC) document, construction permit(s), FAA Airspace, SWPPP, etc. This requires a prior design submission for DFW, followed by incorporation of comments and development of a permit design package. The Design Builder will provide the information necessary to the DFW for NEPA permit submissions.

6. SELECTION PROCEDURES

PHASE ONE – STATEMENT OF QUALIFICATIONS (SOQ)

The intent of the Request for Qualifications (RFQ) process is to identify the most highly qualified Design-Builder capable of delivering a complex, multi-level aviation facility that integrates structured parking, elevated roadways, bridge structures, passenger processing areas, and baggage systems, while maintaining continuous airport operations. Interested Respondents will submit their Statements of Qualification (SOQ) that will include an introductory letter, executive summary, business information and history, office locations, list of comparable projects, professional qualifications, ability to meet schedules, familiarity of applicable rules and regulations, safety record, and other pertinent information.

DFW will evaluate all Responders’ SOQ submissions pursuant to the provisions of Texas Government Code 2269.307 to select the preferred DB. Evaluation and ranking will be per the criteria set forth in Table 1 below. After evaluating SOQs, DFW will shortlist to up five of the most qualified Respondents.

Table 1 Evaluation Criteria SOQ Weighting %

SOQ

1 Relevant Design Build Experience in a minimum of three (3) and not more than twelve (12) Previous Projects for the past 10 years

A. Relevant Design-Build Experience Parking Garages and Airport Processors

20%

B. Relevant Design-Build Experience Bridge, Roadway, Complex Structural

20%

2 Understanding of Project Complexity and Approach 20%

3 Technical Qualifications and Experience of Key Project Team Members 10%

4 Ability to Deliver within Project Schedule, Budget and Scope 10%

5 Proven, Successful Track Record of Management of Partners, Logistics, Procurement and Controls

10%

6 Safety program, Quality Control and Past Safety Record. 10%

SOQ Total 100%

Contents – A Qualifications Statements will consist of 1 submittal.

Identification – A Qualifications Statements must clearly identify the name of the project:

Request for Qualifications Statements for Contract No. PA2045 Terminal F Phase 2 Ticketing, Processing, Garage, and Roadways, and the name and address of Respondent.

Organization – The Qualifications Statement should have each information category clearly identified and/or separated by label or cover page (not counted against page limit) and organized in accordance with subject matter sequence set forth in this RFQS.

Submittals – The following submittals must be completed and submitted with each Qualifications Statement. This table is included for Respondent’s convenience and may be used to track the preparation and submittal of certain required information with its Qualifications Statement.

Item # Required Qualifications Statement Submittal - Check Sheet Check (√)

1. SBE Contract Provisions and Forms

• Commitment to SBE Participation Form

• Final Schedule of Subcontractors

• Intent to Perform Contract as a SBE Subcontractor

• Good Faith Effort (if applicable)

• Draft Joint Venture Agreement (if applicable)

• SBE Certificates

Additional Forms

• Business Disclosure Form

• Verification of Contracting Prohibitions

• Statement of Disclosure

The Statement of Qualifications (SOQ) are limited to 30 pages, 10 to 12-point font. The SOQ may be submitted single or double sided, each printed side of any page will count as a numbered page. 11” x 17” paper may be used for large exhibits only; each printed side of an 11” x 17” page will count as two (2) numbered pages. Resumes and forms (including attachments to such forms prepared by DBs) do not count toward applicable page limits.

Each Volume 1 SOQ shall contain the following identified tabs with the corresponding tab number and title indicated below:

Cover Letter & Executive Summary The cover letter must accompany the executive summary and include:

A. DB’s name, address, telephone number and email address signed by a person authorized to act on behalf of DB.

B. The name, title, address, e-mail address, and telephone number of the person signing the letter and to whom all future correspondence and/or communications may be directed by DFW Board concerning this solicitation.

C. The type of business entity that proposes to enter into a Contract with DFW Board and the identity of any other business entities that will comprise DB.

Executive Summary The purpose of the Executive Summary is to provide an overview of the DBs and their subconsultants/subcontractors’ qualifications to perform the services outlined in this RFQ.

At a minimum, the Executive Summary must contain the following information:

A. DB’s name, address, telephone number and fax number, signed by a person authorized to act on behalf of DB.

B. Complete legal name of DB and the name of the legal entities that comprise DB.

C. DB must provide the domicile where each entity comprising it is organized, including entity name, brief history of the entity (including services provided), managing and corporate office locations(s) (principal and joint venture firm), number of years in business (individually and joint venture with submitted firm(s)), contact name, address, phone number, email address, as well as the legal structure of the entity and a listing of major satellite offices.

D. DB must discuss how the team was formed and how the team will function as an integrated unit in providing work to DFW Board.

E. Each professional and consulting services firm must certify that it was selected based on demonstrated competence and qualifications, in the manner provided by Texas Government Code Section 2254.004

F. Provide a description of the general and specific capabilities and experience of DB’s team members, including Subconsultants/Subcontractors, concerning the construction and renovation of terminals, parking garages, roads, bridges, and design-build projects.

G. Identify examples where team members have worked together to complete a similar project and discuss how the team was formed and how the team will function as an integrated unit in providing services to DFW.

SOQ EVALUATION CRITERIA

Relevant Experience on Previous Projects At a minimum the Experience, Qualifications and Previous Performance must contain the following information:

A. Parking Garages and Airport Processor Facilities.

Provide the team’s experience delivering projects of similar size, scope, complexity, and operational sensitivity that included

i. Design-Build delivery of large, multi-level parking garages

ii. Terminal-adjacent or landside aviation facilities at active commercial airports

iii. Facilities incorporating passenger processing areas (ticketing, baggage claim)

iv. Integration of buildings with roadway and bridge infrastructure

v. Experience delivering projects under active traffic and passenger operations

B. Bridge, and Roadway Experience, Complex Structural Responder teams must submit their experience delivering complex structural and transportation infrastructure elements, which are critical to the success of this Project.

Evaluation factors include:

i. Design and construction of elevated roadways and viaducts

ii. Modification, widening, or rehabilitation of existing bridge structures under traffic

iii. Helical ramps (helixes) for parking or vehicular circulation

iv. Long-span structural systems

v. Integration of roadway geometry, structural systems, and architectural requirements

Teams demonstrating successful integration of building and bridge systems under a single Design-Build contract will be rated more favorably.

Responder must provide a list of minimum of three (3) and no more than six (6) projects from the past 10 years for items A and B above in reverse chronological order beginning with the most recent and include project description, project initial budget, project completed cost, project initial schedule, planned vs actual project duration, facility size

(gross square feet), construction duration, and references with names and telephone numbers.

A. Provide a list a minimum of three (3) and no more than five projects for each of items

A and B in the last Ten (10) years that DB and/or its team members have successfully completed, that best demonstrate the ability to apply innovative construction techniques and new use of materials.

B. For each project listed, describe each team member’s specific contribution.

C. Provide a description of the procedures/processes DB used on previous projects to manage the overall work including, budget, schedule, and function. Include a description of any metrics used to measure performance concerning budget and schedule as well as to ensure quality.

Understanding of Project Complexity and Approach The Proposer will demonstrate their understanding of the Project’s complexity and its proposed high-level approach to delivering the Project. The purpose of this section is to assess the Proposer’s awareness of the unique technical, operational, and coordination challenges associated with the Project and its ability to articulate a thoughtful, realistic, and integrated approach to addressing those challenges.

This narrative is not intended to solicit a design solution or cost proposal, but rather to evaluate the Proposer’s comprehension of the Project and its ability to successfully perform the Work.

The DB team will provide the following:

A. An understanding of the Project’s role as a gateway facility to Terminal F and its importance to the overall airport experience.

B. DFW has established a budget of $650,000,000. The respondent will describe the feasibility of designing and constructing to budget based on the costing methodology definition.

C. Provide written observations based upon previous experiences in similar projects, addressing any anticipated problems and propose solutions.

D. Discuss staging of equipment and materials and coordination with terminal management adherence to limited work hours and ensuring completion and departure within work hours to allow airport and airline operations to commence every day as scheduled. This will include seasonal traffic volume changes, such as during Christmas, Thanksgiving, Spring Break etc.

Discuss means of maintaining traffic during construction operations, such as construction entrances, contractor employee parking, crane pad or tower placements, managing large loads within the tight working space without causing any disruptions to traffic flow at the airport. The respondents will also address management of traffic during seasonal increases during moratorium periods such as for Christmas, Thanksgiving, Spring Break etc., to ensure unimpeded passenger flow.

Discuss the phasing approach. Detail how Terminal E access/egress traffic operations will be managed. Discuss how anticipated construction operations and durations have set the design schedule and the DB’s proposed design packaging.

E. Discuss construction sequencing in areas within the project limits to demonstrate the approach to multiple work operations in near proximity such as shoring, utilities, CUP Tunnel access(es), building foundations, storm water, jet fuel lines and access to AOA.

F. Discuss conceptual engineering design. Propose design packages and their timing of completion to procure materials and construct project elements to meet the overall project schedule. Indicate items that may require advanced procurement schedules such as steel bridge girders. Discuss the engineering processes and schedule integration to meet the overall project schedule. Proposers are encouraged to discuss innovations that they propose to use in the project delivery and how they would impact the efficiency of project delivery.

G. Potential project risks should be identified, discussed and potential solutions provided.

H. Provide narrative and graphics showing proposed concepts and approach to designing to budget and meet or better the schedule.

Proposals that demonstrate a clear, realistic, and well-reasoned understanding of the Project’s complexity, supported by relevant experience and a logical delivery approach, will be rated more favorably.

Technical Qualifications & Experience Of Key Project Team Members At a minimum, the Technical Qualifications & Experience of Key Project Team Members must contain the following information:

A. Describe the professional qualifications and experience of key personnel in executing design-build projects utilizing prefabrication techniques. Key personnel (project senior management) must have a minimum of 5 years’ experience in design-build or similar aviation projects. The DB must provide details of all key personnel employed by major subs. At a minimum the submission must provide details for the following roles for DFW’s evaluation:

i. Design-Build Project Manager

ii. Design Manager / Architect of Record

iii. Construction Superintendent

iv. Structural / Bridge Engineering Lead

v. Roadway and Traffic Engineering Lead

vi. Aviation Fire/Life Safety Specialist

vii. Quality Control Administrator

B. Describe the Organizational Structure/Staffing Plan. DB’s Organizational Structure

Section of the Qualifications Statement should introduce the proposed DB team (including Subconsultants/Subcontractors) by:

i. Providing DB's Management Organizational Chart both graphically and in narrative format. The Organizational chart and narrative should provide a description of DB's views on how it will organizationally provide the Services, as well as depict the relationship of its key personnel roles to that of the Project Executive and other key members of the management team.

ii. Describing how this organizational structure will facilitate managing the Services requested and how an efficient flow of information will be realized from the organizational structure.

iii. Describing how the organizational structure will incorporate the role of Subconsultants/Subcontractors in a well thought out approach to providing the Services.

C. Provide the names of proposed candidates for each function on the Management Organizational Chart with Current Capacity and Workload Backlog. Indicate architects and/or engineers licensed to practice in the State of Texas.

i. Describe the DB’s (including joint venture firms’) ability to meet schedules and commit resources based on current and projected workload.

ii. Describe additional resources to be utilized, in the event they are needed.

Candidates named in the organization structure should be those that will work on the project. Substitution of key personnel will not be allowed unless approved by DFW.

D. Key Personnel resume format:

i. Identify and provide resumes for the individuals that the DB (including

Subconsultants/Subcontractors) will use to provide the Services.

ii. Resumes should be organized as follows:

Name and Title.

Professional Background.

Current and Past Relevant Employment.

Education.

Certifications.

Licenses.

Relevant Knowledge.

Ability To Deliver Within Project Schedule, Budget and Scope DFW will evaluate the Proposer’s demonstrated ability to deliver the Project in accordance with the required schedule, budget, and overall Project objectives, while managing the technical, operational, and coordination risks associated with a complex, active airport environment.

Evaluation will consider the extent to which the Proposal demonstrates:

A. A clear and realistic understanding of the Project schedule, including critical path activities and sequencing of major work elements such as helixes, elevated roadways, bridge structures, passenger bridges, and baggage bridges.

B. A credible approach to meeting key milestones, interim access requirements, and phased turnover requirements while maintaining continuous airport operations.

C. Provide a schedule for preconstruction services, construction and close-out demonstrating understanding of the phasing requirements of Terminal F Phase 2 Ticketing, Processing, Garage & Roadways project regarding staging, access, traffic, and adjacent airport operations. Discuss the ability to meet or exceed the project schedule.

D. Discuss approach using methods for schedule recovery, and its philosophy regarding establishment and use of total float on the Project to achieve the desired substantial completion date.

E. Provide a narrative regarding the project budget. The selected DB will commit to designing to and adhering to the agreed stipulated sum negotiated with the selected preferred design-build firm. This narrative will also provide value engineering strategies to remain within the budget in accordance with the costing methodology definition. Discuss innovative solutions and techniques from previous, relevant projects that resulted in increased efficiency, schedule, and cost savings.

F. A demonstrated ability to manage cost and control budget through effective estimating, cost monitoring, value management, and change management practices.

G. Alignment of the proposed delivery approach with the Authority’s project objectives, including safety, quality, operational continuity, passenger experience, and long-term asset value.

H. Firms must provide Evidence from five (5) past projects in the last Ten (10) years of the Proposer’s ability to successfully deliver complex aviation, transportation, or infrastructure projects on time and within budget. Use the Table 2 format below for reference.

I. Identification of schedule and cost risks specific to the Project, along with practical mitigation strategies.

Proven, successful Track Record of Management of Partners, Logistics, Procurement and Controls

DFW seeks Design-Build Firms that can directly and effectively manage complex networks of designers, subconsultants, specialty contractors, suppliers, and third-party stakeholders while delivering work within an active airport environment with significant logistical constraints.

A. Subconsultant and Trade Partner Management

Proposers shall demonstrate their ability to:

i. Lead and coordinate multi-disciplinary design teams and construction trade partners with clearly defined roles, responsibilities, and decision-making authority.

ii. Due to the criticality of the concrete operations to contract and due to the intent maintaining single point of contact and responsibility, the DB prime shall be required to self-perform all concrete operations except for precast elements.

For all major concrete operations under this Contract — including but not limited to Portland cement concrete pavement (P-501), structural concrete (P-610), taxiways, runways, aprons, airfield shoulders, roadway pavements, bridges, abutments, foundations, and other significant civil or all super and sub-structural components — the DB prime shall be solely and directly responsible for procuring, contracting for, and maintaining all contracts directly with suppliers of ready-mix concrete, cementitious materials, and related admixtures. Subcontractors shall not be permitted to enter into separate or direct contracts with concrete suppliers for these major scopes. The intent of this requirement is to ensure continuity of supply, uniformity and consistency of quality, accountability for schedule performance, strict compliance with FAA AC 150/5370-10H, DFW Airport Construction Standards and all other applicable laws and regulations, and to eliminate disputes that could jeopardize schedule, safety, or regulatory compliance.

For minor concrete operations of limited scope — such as sidewalks, small pads, duct bank encasements, and similar incidental work — this requirement may be

Table 2: Past Project Deadlines and Construction Cost Within the Past Ten (10) Years Project Name Engineer’s

Estimate Bid Price Actual

Price Contracted Days

Actual Days Change Order Percentage modified or waived on a case-by-case basis only with the prior written approval of the Owner. The applicability of this clause to such smaller operations shall be determined and documented in the relevant subcontract package for each Project.

Regardless of any such modification or waiver, the DB shall remain fully responsible for all concrete material quality, testing, documentation, placement, and compliance with the requirements of the Contract.

The DB shall coordinate, control, and supervise all ordering, scheduling, delivery, QA/QC testing, and payment for all concrete materials under its direct supply contracts for major operations. This includes responsibility for ensuring that all quality assurance and acceptance testing (including, without limitation, flexural strength testing, compressive strength correlations, maturity meter validation, PWL acceptance testing, etc.) are properly scheduled and documented to support Owner review and audit and compliance with all applicable standards.

Failure of the DB to comply with this requirement will deem the bid as non-responsive and subject to rejection. Any subsequent unauthorized delegation of concrete procurement responsibilities to subcontractors shall constitute a material breach of contract. The Owner, in its sole discretion, may withhold payments, issue non-conformance directives/reports, or undertake corrective measures at the DB’s expense as necessary to maintain compliance with these provisions. The DB shall not be entitled to any extension of time, additional compensation, or claim of delay resulting from enforcement of this requirement by the Owner.

iii. Manage performance, quality, and schedule across multiple subconsultants and subcontractors

iv. Integrate design and construction activities to minimize rework and interface conflicts

v. Address underperformance through proactive corrective action

vi. Confirm in the Qualifications that all firms in the Design Builder’s team have the resources (fiscal and manpower) to perform the work they are tasked in line with the project schedule and budget.

vii. Provide a detailed narrative that demonstrates Respondent’s (including joint venture firms’) capacity to provide services according to applicable schedules and budgets. Describe the Respondent’s (including joint venture firms’) ability to meet schedules and commit resources based on current and projected workload.

Describe additional resources to be utilized, in the event they are needed.

Include specific examples from comparable projects where the Proposer directly managed subconsultant or trade partner performance.

B. Logistics Planning and Execution

Proposers shall describe their approach to:

i. Site management, access planning within constrained and secure environments

ii. Phased construction sequencing to maintain operations

iii. Material staging and laydown planning

iv. Traffic control and maintenance of traffic

v. Coordination of deliveries within restricted time windows

vi. Interface management with ongoing airport operations

C. Procurement Strategy and Supply Chain Management

Numeric pricing, unit costs, or cost estimates shall not be included. Proposers shall describe their approach to:

i. Their approach to early procurement of long-lead items

ii. Supplier qualification and vetting processes

iii. Integration of procurement planning with design development

iv. Risk mitigation strategies for material availability, escalation, and delivery delays

v. Experience managing specialized or proprietary systems relevant to airport facilities

D. Documentation and Controls Describe tools and systems used for:

i. Procurement tracking

ii. Subconsultant and supplier performance monitoring

iii. Logistics coordination and reporting

iv. Issue escalation and resolution

Safety and Quality Program and Past Records DFW will evaluate the proposer’s Safety Program and provide details of its Quality Control (QC) approach to demonstrate the Proposer’s ability to plan, manage, and execute the Work safely within an active airport environment That meets or exceeds the requirements for safety, performance, durability, and long-term asset value.

The Evaluation will consider the extent to which the Proposal demonstrates:

A. Project-Specific Safety Approach

i. A clear understanding of the unique safety challenges associated with this Project, including:

a. Construction of elevated roadways, bridges, and helixes

b. Work over and adjacent to active vehicular traffic

c. Interfaces with passengers, airport staff, and the traveling public

d. Coordination with airport operations, emergency services, and security personnel

ii. Strategies for maintaining safe pedestrian and vehicular circulation throughout construction.

iii. Procedures for managing work in constrained areas and at height.

iv. Coordination of safety…