This is an Identify Need Statement prepared for the Harris County Flood Control District in Texas, documenting the project scope for professional architectural and/or engineering services related to the South Mayde Creek Bypass Channel and Stormwater Detention Basin. The project aims to reduce flooding along South Mayde Creek by lowering peak flows and water surface elevations, minimizing sedimentation and erosion, and improving hydraulic conveyance without creating adverse downstream impacts. The scope encompasses design, bidding, and construction phase services for two primary components: a bypass channel between Greenhouse and Barker Cypress Road, and sedimentation basins located upstream of Greenhouse Road. These improvements are part of Alternative 2, Scenario 2 from the 2020 Preliminary Engineering Report and represent the finalized recommended alternative for Lower South Mayde Creek improvements.

The project is anticipated to produce significant flood mitigation benefits, including average water surface elevation reductions of 0.9 to 2.3 feet for the 10% annual exceedance probability event and 0.8 to 2.3 feet for the 1% annual exceedance probability event between Fry and Greenhouse Road. The improvements are projected to remove 32 structures from the 10% annual exceedance probability event inundation and 1,203 structures from 1% annual exceedance probability event inundation. The statement does not specify contract pricing, funding sources, award dates, or contract term details, indicating that such information would be contained in the related request for services documentation.

View the file

Other files

File Type Posted
8-Attachment V – MWBE Trucking Procedure Compliance Packet.pdf PDF
4-Attachment I - Minimum Insurance Requirements for Flood Control District.pdf PDF
20-Attachment Y - General Scope of Basic Services – Appendix B.pdf PDF
17-Attachment CC - Preliminary Engineering Report.pdf PDF
15-Attachment X - General Scope of Basic Services – Appendix A.pdf PDF
13-Harris County Minimum Wage FAQs as of December 2025 - Final.pdf PDF
7-Attachment K - Required Contract Provisions.docx DOCX document
2-Attachment C - Statement of Offeror Qualifications.pdf PDF
9-Attachment F - Contractor Profile.pdf PDF
23-Federal Single Vendor RFQ General Requirements and Specifications.pdf PDF
21-Attachment EE - Final Build America, Buy America (BABA) Certification.pdf PDF
6-Attachment Q - Standard Form 330 Architect - Engineer Qualifications.pdf PDF
10-Attachment A - RFQ and Addenda Acknowledgement.pdf PDF
18-Attachment U – Non-HUB MWBE Goal Participation Information Packet.pdf PDF
22-Attachment DD - Texas Water Development Board Build America, Buy America Act Guidance.pdf PDF
16-Attachment BB - Project Boundary Map.pdf PDF
14-Attachment AA - Sample Exercise.pdf PDF
12-Attachment T – Non-HUB MWBE Utilization Plan Commitment Form.pdf PDF
5-Attachment J - Workers Compensation Insurance Coverage Rule 110.110.pdf PDF
1-Attachment B - Certification Regarding Lobbying.pdf PDF
3-Attachment E - References.pdf PDF
11-Attachment W - Harris County Minimum Wage Policy and Certification.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U101-01-00-E003

South Mayde Creek Bypass Channel and Stormwater Detention Basin

Identify Need Statement

The purpose of this project is to reduce flooding along South Mayde Creek by lowering peak flows and water surface elevations, reduce the potential for sedimentation and erosion along South Mayde Creek, and improve hydraulic conveyance without producing adverse impacts in the form of increases to water surface elevations or peak flow downstream. Additionally, it will finalize the recommended alternative – Alternative 2, Scenario 2, from the 2020 Preliminary Engineering Report, “Lower South Mayde Creek (U101-00-00) Bypass Channel and Channel Improvements Preliminary Engineering Report”. Alternative 2, Scenario 2 includes the (1) channel conveyance improvements between Fry and Greenhouse Road that consist of a benched trapezoidal widening of the channel,

(2) a regional detention basins between Morton and Fry Road, (3) a bypass channel between Greenhouse and Barker Cypress Road, and (4) Sedimentation basins located just upstream of Greenhouse Road.

This project includes design, bidding and construction phase services of improvements (3) and (4) as written above:

Bypass channel between Greenhouse and Barker Cypress Road Sedimentation basins located just upstream of Greenhouse Road

Alternative 2, Scenario 2 provides an average reduction of WSEL of 0.9-2.3 ft for the 10% AEP event between Fry and Greenhouse Road and 0.8-2.3 ft for the 1% AEP event. Additionally, 32 structures removed from the 10% AEP event and 1,203 structures removed from 1% AEP event inundation.

File details come from the government source that posted it. Updated .