19-Appendix H Draft Contract F.pdf
PDF 1 MB Posted
- Attached to
- CP2600617-Carlsbad State Veterans Cemetery
- Solicitation number
- 70-350-26-08806
- Issued by
- Doña Ana County, New Mexico
About this file
This is a Draft Contract document for the State of New Mexico's General Services Department relating to construction and site work for a new Carlsbad State Veterans Cemetery. The project encompasses construction of a new approximately 2,810 gross square foot administration and maintenance building, cemetery structures including a committal shelter with ceiling fan and storage room, and precast columbarium units with cut limestone caps. Site work will be performed on a 15-acre tract with less than 4.9 acres of actual disturbance and will include paved asphalt roads, concrete curbs, subsurface stormwater cells for drainage, two setback frontage gates, and perimeter fencing consisting of ornamental metal paneling along street-facing areas transitioning to six-foot chain-link fencing along boundaries. Site development for burial areas will incorporate pre-placed in-ground crypts, cremains areas, drought-tolerant xeriscaping, and targeted irrigation systems. Add Alternate No. 1 includes interior improvements to the administration and maintenance building comprising a public information center, director's office, honor guard areas, restrooms, and equipment service bays, along with all associated plumbing, mechanical, fire suppression, and electrical systems including Dark Sky-compliant site lighting. The contractor, Nine Degrees Architecture & Design Inc., is responsible for field-measuring the site and accounting for all materials, hardware, and labor required for complete installation, with specific clarification that Veterans Administration-provided items include physical pre-placed crypt units, information kiosk equipment, and standard VA niche covers, while the contractor must furnish all mounting hardware, bronze military service seals, and memorial plaques.
The contract sum is listed as $500.00, which represents a placeholder figure in this draft document pending final negotiation and pricing. The contractor must submit a detailed Baseline CPM Schedule within 10 days of contract award using MS Project, Primavera P6, or other Owner-approved scheduling software, with activity durations not exceeding 28 calendar days unless approved by the Owner. Change order pricing follows a Fixed Price method with itemized breakdowns of direct costs including labor, equipment, and materials, with allowable overhead and profit markups varying based on the percentage of contract value affected and whether work is self-performed or subcontracted. The contractor is required to maintain detailed books and records for three years from final payment, subject to Owner audit. Time extensions and associated costs must be submitted separately following approval, and any schedule update showing project completion more than 15 calendar days beyond the contract completion date requires submission of either a recovery schedule demonstrating completion within contract duration at no additional cost or written justification for a time extension. The document includes provisions for recovery schedules, revised baseline schedules, time impact analyses, and detailed requirements for CPM periodic progress schedules to be submitted with each pay application.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Enter Contract Number
Enter or "Pending"
Funding Contract ID
Complete Name of Contractor Legal Entity
Name of Individual Signing Contract (See Note below
Title of Individual Signing Contract
Physical Address of Contractor
Mailing Address of Contractor
City, State. Zip of Contractor
Juanito Maes Telephone of Contractor juanito.maes@gsd.nm.gov Email Address of Contractor for Notice; Article 5.6 Notices, Part A
Carlsbad State Veterans Cemetery
NINE DEGREES ARCHITECTURE & DESIGN INC.
NINE DEGREES ARCHITECTURE & DESIGN INC.
101 MAGUEY CT, SUITE 2
101 MAGUEY CT, SUITE 2
MICHAELB@NINE-DEGREES.COM
915 533 8482
Draf t C on tra ct
THIS LIST IS NOT ALL INCLUSIVE - REFER TO THE DRAWINGS FOR FULL DETAILS OF WORK. CONSTRUCTION AND SITE WORK FOR A NEW VETERAN'S
CEMETERY AT CARLSBAD, NM.
NEW APPROX. 2,810 GSF ADMINISTRATION AND MAINTENANCE BUILDING. NEW CEMETERY STRUCTURES INCLUDING A COMMITTAL SHELTER (FEATURING A LARGE CEILING FAN AND STORAGE ROOM) AND PRECAST COLUMBARIUM UNITS WITH CUT LIMESTONE CAPS.
SITE WORK ON A 15-ACRE TRACT (UNDER 4.9 DISTURBED) TO INCLUDE PAVED ASPHALT ROADS, CONCRETE CURBS, SUBSURFACE STORMWATER CELLS FOR DRAINAGE, AND TWO SET-BACK FRONTAGE GATES. SITE FENCING TO INCLUDE ORNAMENTAL METAL ALONG THE ROAD FRONTAGE
TRANSITIONING TO CHAIN-LINK FOR THE BOUNDARIES.
SITE DEVELOPMENT FOR BURIAL AREAS INCLUDING PRE-PLACED IN-GROUND CRYPTS AND CREMAINS, COMPREHENSIVE DROUGHT-TOLERANT
XERISCAPING, AND TARGETED IRRIGATION.
LTERNATE #1 INTERIOR IMPROVEMENTS FOR THE ADMINISTRATION AND MAINTENANCE BUILDING TO INCLUDE A PUBLIC INFORMATION CENTER, DIRECTOR'S OFFICE, HONOR GUARD AREAS, RESTROOMS, AND EQUIPMENT SERVICE BAYS AS INDICATED ON THE DRAWINGS. ALL
ASSOCIATED PLUMBING, MECHANICAL, FIRE SUPPRESSION, AND ELECTRICAL SYSTEMS (INCLUDING DARK SKY COMPLIANT SITE LIGHTING) FOR
FULLY FUNCTIONING FACILITIES.
Draf t C on
Five Hundred Dolars and 00/100
$ 500.00
Enter the full amount of the Contract Sum written out in words
$ 0.00
$ 0.00
Enter Brief Alt Description or N/A $ 0.00
Enter Brief Alt Description or N/A $ 0.00
Enter Brief Alt Description or N/A $ 0.00
Enter Brief Alt Description or N/A $ 0.00
Enter Brief Alt Description or N/A $ 0.00
Enter Brief Alt Description or N/A $ 0.00
$ 0.00
0.0000% $ 0.00
$ 0.00
$ 0.00
$ 0.00
Draf t C on
Draf t C on
Unique ID (Date/ Author/ Version...) - Upload Below - Must have a minimum of a Vicinity Map Map
Unique ID (Date/ Author/ Version...) - Upload below
Unique ID (Date/ Author/ Version...) - Upload & Requirements below
Revision Dated 24 Jan 2024
Draf t C on
Obtain from Contractor
Obtain from Contractor Obtain from Capital Outlay/ Pl
Draf t C on
Signature: _________________________________________________________
Printed Name: ________________________________________________________
Title: ______________________________________________________________
Date: _______________________________________________________________
Signature: ___________________________________________________________
Printed : ________________________________________________________
Title: _______________________________________________________________
Date: _______________________________________________________________
Signature: _________________________________________________________
Printed Name: ______________________________________________________
Title: _____________________________________________________________
Date: _____________________________________________________________
END OF SIGNATURE PAGE FOR PART A
Enter Contract Number
Draf t C on
Contents
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
This space intentionally left blank
Draf t C on
CPM output and ancillary requirements shall substantially conform to Exhibit D – CPM Schedule Standards.
: Contractor shall use the following CPM Software to create and maintain the Project CPM Construction Schedule:
MS Project or Primavera P6 or Other CPM software approved by Owner and the Design Professional
(Only required for Projects with a Contract Sum greater than $2,000,000)
The Contractor shall provide a Scheduler who has verifiable training and credentials in preparing and maintaining a computerized CPM Construction Schedule using the latest version of Primavera scheduling software (or other software approved by the State).
Within 5 days of being awarded the Contract and before the first payment application the Contractor shall submit the Project Scheduler’s showing the Project Scheduler’s work on previous similar types of projects. The Owner reserves the right to reject the proposed cheduler based on the lack of qualifications as defined in this Section.
The Owner, at its sole discretion, may retain a Scheduler to review all submitted schedule related contract documents. The Contractor shall respond to all issues raised by the Scheduler in writing to the Design Professional and Owner’s satisfaction.
Initial Project Plan Within 10 days of being awarded the Contract, Contractor shall furnish an electronic copy of the Baseline CPM Schedule and Summary Schedule for review and approval by the Design Professional and Owner.
The Contractor shall provide any and all reports in electronic form, including the native CPM Schedule Software files.
A Baseline CPM Schedule showing a completion date after the Substantial Completion Date is cause for rejection.
The Baseline CPM Schedule shall show a single critical path.
Each Baseline CPM Schedule activity shall include (in detail) all activities’ ID numbers, WBS breakdowns, descriptions, predecessors, successors, start/finish dates, calendars, duration, remaining duration, physical percent complete, actual dates, constraints, and other grouping codes such as location and responsibility.
No progress shall be shown in the initial Baseline Schedule.
The Baseline CPM Schedule shall not show any negative float.
Each electronic schedule file submission shall be given a file name that will enable it to be uniquely and readily identified.
The Contractor shall prepare and submit a narrative along with the Baseline CPM Schedule. The baseline narrative shall include the schedule methodology, rain day calculation, productivity considerations, high risk activities, critical path and nearly critical path description, and other general comments.
Total float or slack is defined as the minimum amount of time between the early start date and the late start date, or the early finish date and the late finish date, for any activity in the Schedule. Float or slack is not time for the exclusive use of or benefit of either the Owner or the Contractor but is a resource available to both parties on a first-needed basis and at no change in contract price. Extensions of time will not be granted unless the excusable delays affect the critical path in the Schedule as required by the Contract Terms and after all available float or slack has been used.
Use of Project float suppression techniques shall be cause for rejection of any schedule submittal. Float suppression techniques include, but are not limited to, Preferential sequencing (arranging critical path through activities more susceptible to Owner-caused delay), Special lead/lag logic restraints, Zero total or free float constraints, Extended activity durations, Imposing of constraint dates other than required by Contract, and Modifying the work calendar in a way that does not reflect when the work will take place.
Enter Contract Number
Draf t C on
1. The schedule shall include proper logic and adequate durations for all activities including but not limited to mobilization, submittals, review/approval, fabrication/delivery, installation, system shutdowns, key milestones, cleanup, remedial and restoration work, testing and start-up, submittal of closeout documentation, and demobilization.
2. Activities should be assigned clear descriptions that reflect the work being performed and substantially correspond to an item in Exhibit C - Schedule of Values. Each activity may be subdivided into sub-activities as required for planning and monitoring progress.
3. As a minimum, each Baseline CPM Schedule activity shall include (in detail) all activities’:
a. ID numbers,
b. WBS breakdowns,
c. Descriptions,
d. Predecessors,
e. Successors,
f. Start/finish dates,
g. Calendars,
h. Duration,
i. Remaining duration,
j. Physical percent complete,
k. Actual dates,
l. Constraints, and
m. Other grouping codes as required such as location and responsibility.
4. Activity durations shall not exceed 28 calendar days unless it is approved by the Owner.
5. Long Lead Items – Material, equipment other such items of the Work where an acquisition delay impacts the performance of the work must be included.
6. A Schedule Activity hierarchy that substantially reflects Exhibit C - Schedule of Values hierarchy facilitating the generation of summary schedules and cost checking Pay Applications.
7. Milestones indicators that represent significant Project Milestones such as:
a. Project Start,
b. Project Complete,
c. Substantial Completion, Enter Contract Number
This space intentionally left blank
Draf t C on
d. Final Payment, and
e. Must include any Critical Inspection Points identified by the Design Professional.
8. Activities are to be delineated by individual parties and specific work areas. No activity should be assigned more than one responsible party or one specific area.
9. Unless required by the Owner or Design Professional, Resource Loading will not be required.
10. Unless required by the Owner or Design Professional, Budget Tracking or Cost Loading will not be required.
11. No lags on finish-to-start relationships shall be used. Also, no lags that exceed the predecessor’s duration shall be used. Both circumstances create gaps between the activities. Instead, these lags need to be either removed, or converted into the activities that they are intended to represent.
12. Negative lags shall not be used.
g. CPM Periodic Progress Schedule:
1. The Contractor shall prepare a Periodic Progress Schedule prior to processing of a corresponding Pay Application that updates the Baseline CPM Schedule during the Work.
The Periodic Progress Schedule must reflect progress up to the payment application period, forecast finish for in-progress activities and re-forecast early dates for activities planned in the next update period.
2. Data dates for schedule updates must be the day after the progress period closes. Failure to make corrections to the schedule update is cause for rejection of the schedule update and will delay processing of the Pay Application. The Monthly Progress Schedule must include the following:
a. Actual start and finish dates for completed activities;
b. Actual start dates, percentage complete, actual and remaining quantities, and remaining duration for activities in progress;
c. Projected sequences of activities for future Work;
d. Planned start and finish dates for future activities; and
e. Progress for the current invoice submittal for Project activities
f. Any other output as defined in Exhibit D – CPM Schedule Standards.
3. Pending change orders shall not be incorporated into the Project Schedule unless pre-approved by the Owner. Only after a Change Order has been approved can the changes to the schedule be made and coded as such.
4. If, at any point, a schedule update shows a late Project completion by more than 15 calendar days of the contract completion date, the Contractor shall provide a separate schedule file consisting of either:
a. A recovery schedule that shows how the Contractor will complete the project within the contract duration, at no additional cost to the Owner, or;
b. Justification for granting a Time extension as defined in Contract Terms
h. Recovery Schedule:
1. Unless otherwise directed in writing by the Owner, if the Owner’s review of the Monthly
Progress Schedule indicates a late completion of the Work, or should Critical Path items shown on the Monthly Progress Schedule Submittal slip by fifteen (15) or more calendar days beyond any milestone, Contractor shall prepare a Recovery Schedule that demonstrates how Contractor intends to reschedule those activities to regain compliance with the milestones and the Contract at no additional cost to the Owner.
2. Whenever a Recovery Schedule is required, Contractor shall prepare and include the following information with the Recovery Schedule:
a. Transmittal letter;
b. Electronic copy of the file used for the proposed Recovery Schedule; and
Enter Contract Number
Draf t C on
c. Narrative describing any proposed changes to the Project Schedule, in detail, with justification for the changes, including the following:
• Changes to activity original durations;
• Changes to activity relationships and/or schedule logic;
• Cause of schedule slippage and actions taken to recover schedule within the shortest reasonable time (e.g., hiring of additional labor, use of additional construction equipment, and expediting of deliveries);
• Identification of activities that have been added, deleted, or modified; and/or
• Changes to the Project Schedule’s Critical Path.
3. Contractor is not required to prepare a Recovery Schedule if Contractor is awarded a Time Extension under the terms of Paragraph 8.3 Delays and Extension of Time a Recovery Schedule is not required at that time.
4. If the Owner or Design Professional rejects a Recovery Schedule, Contractor shall prepare a revised Recovery Schedule that incorporates the Owner’s and Design Professional’s comments.
5. When the Owner accepts Contractor’s Recovery Schedule, Contractor shall prepare an updated Project Schedule that incorporates such Recovery Schedule and becomes the Revised Baseline Schedule. Contractor must proceed in accordance with the approved Recovery Schedule.
i. Revised Baseline Schedule:
1. If Contractor is awarded a Time Extension under the terms of Article 8 – Time a Revised
Baseline Schedule is required at that time.
2. When the Owner accepts Contractor’s time extension, Contractor shall prepare an updated Project Schedule that incorporates authorized time extension and becomes the Revised Baseline Schedule.
Enter Contract Number
This space intentionally left blank
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on a) b) c)
Enter Contract Number
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
METHODS FOR CHANGES IN THE WORK PRICING
7.3.1 Fixed Price- Allowable Costs and Fees: Unless specifically authorized by additional terms and conditions of this Agreement, the Parties agree and bind themselves to the following method of calculating Change Order costs by Fixed Price or by utilizing the terms and conditions of the original funding Contract.
Time extension cost proposals will be submitted separately per 7.3.4 after the time extension has been approved per the contract terms and conditions. With each Proposal for a cost Change Order, the Contractor shall submit an itemized breakdown of any change in the Cost that shall include at least the following itemized accounting detail in the general order listed unless otherwise provided in the terms and conditions of this Agreement. For Contractor’s Direct Costs of Work, use the following:
7.3.1.1 Contractor’s Direct Costs of Work
A list of Tasks (Cost Codes) required to complete the proposed Work that shall detail the Direct Costs for the proposed Work.
Each Task shall be subdivided into the typical Cost Types required to perform the proposed Work.
Typical Cost Types may include the following or any other requisite Cost Types:
Worked performed by forces directly employed, owned or rented by Contractor
Labor: Hours and burdened rates for employees directly employed in the Change in the Work (identified with related items of material to be placed or operation to be performed) and labor burden (FICA, FUTA, SUTA, Pension, Workman’s Compensation Insurance, General Liability & Group Insurance, if any). Burdens shall not include retirement plans qualified by minimum employment time, organizational fees or dues, legal or related expenses, information technology training and the like.
Equipment: Quantities and unit utilization or rental costs of machinery and equipment, exclusive of hand tools, whether rented from the Contractor, Subcontractor or others;
Utilization costs shall be based on the life expectancy of the equipment and the purchase price of the equipment.
Materials: List of materials to be installed.
required to complete the proposed work.
This would include Subcontractors and Vendor’s quotes. Those quotes shall be itemized by labor, materials, equipment as well as allowable overhead and profit markup shown in the schedule below.
7.3.1.2 Contractor, Subcontractor and Subsubcontractors’s Allowable Markups for Overhead and Profit on the Work (See Allowable Overhead and Profit Schedule ) The costs for each category below shall be subtotaled and the markup applied.
Indirect Overhead and Profit may include, but is not limited to, project management costs including software, timekeeping, project accounting, main office expenses, processing of documents, computers, cell phones, and incidentals. These are not to be included in the ‘cost of Work’ because they are part of the markup agreed to and indicated in the schedule below.
Overhead and profit for both additive and deductive changes in the Work (other than changes covered by unit prices) shall be paid by applying the specified percentage markups only on the net cost of the changed Work (i.e. difference in cost between original and changed Work excluding overhead and profit) Said percentages for overhead and profit shall reasonably approximate the Contractor’s overhead and profit, but shall not exceed the percentages on the below schedule.
7.3.1.3 Other Allowable Costs
Enter Contract Number
Draf t C on
Permits: Quantities and unit premiums for any permit fees requited for the proposed Work.
Insurance: Maximum of 1% mark-up for Insurances applied to the sum of Contractor’s Direct Cost and Allowable Markups.
Charges: Quantities and unit costs of any “use charges” or similar fees related to proposed Work.
Bonds: Maximum of 2% mark-up for Bonds applied to the sum of Contractor’s Direct Cost and Allowable Markups. At the Owner's request, the Contractor shall provide proof of his notification to the Surety of the proposed Work and of the Surety's agreement to include such change in its coverage.
Gross Receipts Tax: New Mexico Gross Receipts Tax (GRT) as required by statute for Contractor only.
Allowable Overhead and Profit Schedule for Direct Work Costs Amount of Change in The Work
Category of Work < 5% 0f Contract
5% of Contract
1 Contractor for Self Performed Work by forces directly employed by Contractor
10% Negotiable but < 5%
2 Contractor for Work performed by Subcontractor or Vendor
5% Negotiable but < 5%
3 Subcontractor For Self Performed Work 10% Negotiable but < 5% 4 Subcontractor for Work performed by
Subsubcontractor 5% Negotiable but < 5%
7.3.2 Time and Material: Only if specifically provided in the terms and conditions of this Agreement, the following Time and Material method of pricing may be used to price a Change in the Work subjects to the terms and conditions authorizing such pricing.
7.3.3 Unit Price: Only if specifically provided in the terms and conditions of this Agreement, the following Time and Material method of pricing may be used to price a Change in the Work subjects to the terms and conditions authorizing such pricing.
7.3.4 Time Extension Costs: Changes in the Work that extend the Contract Duration must be approved, as specifically provided in the terms and conditions of this Agreement. The costs below shall not be marked up for indirect overhead and profit unless there is no additional Work involved. Labor costs below have a definition the same as in 7.3.1.1.2(a)i above. The Contractor shall submit a separate Proposal for Change Order providing a detailed accounting of General Conditions which are Allowable Direct Site and Project Costs including the following:
Project Management Fully Burdened Labor Costs- prorated time of Project Manager(s), Project Engineer(s) and Project Scheduler Site Superintendence- Fully Burdened Labor Costs Project General Labor- Fully Burdened Labor Hourly Costs Project Company Vehicle(s) for Superintendent(s) Project Temporary Office, Supplies and Equipment Project Temporary Fencing Project Site Storage Project Temporary Utilities Project Temporary Waste Control
Enter Contract Number
Draf t C on
7.3.5 Audit: The Owner shall be entitled to audit the books and records of a Contractor or Subcontractor for any time-and-material or negotiated cost to the extent that such books and records relate to the proposal or performance of such Work. Such books and records shall be maintained by the Contractor and Subcontractor for a period of three years from the date of final payment under their respective Contracts, unless a shorter period is otherwise authorized in writing (13-1-16 , NMSA 1978).
7.3.6 Change Orders
10. Project Sanitation Requirements
11. Project Safety Requirements
12. Project SWPPP Requirements
13. Other Project Specific Direct Site Temporary Costs
These costs shall be subtotaled and calculated to a daily rate and multiplied by the number of days of the approved Time Extension. If there is no Work involved for a period of time, then overhead and profit in the amount of 5% may be added to the inactivity period. Finally, insurance, bond and NMGRT costs may be added to reach the total value of the Time Extension cost.
Enter Contract Number
Draf t C on
Draf t C on
8.3.2 Time Impact Analysis (TIA): Contractor shall submit a Time Impact Analysis (TIA) for any change that effects overall cost and schedule within 14 calendar days of when the delay event began. The TIA shall illustrate the impact of each change or delay on the Contract Substantial Completion Date or milestones. In addition to the limitation of delay damages provided in the Contract, the Contractor shall not be granted any time extensions or delay damages paid unless a delay occurs which consumes all available Project float, extending the projected finish beyond the Contract Completion Date. Each time impact analysis must include a fragnet demonstrating the following information:
a. How Contractor proposes to incorporate the extension of time;
b. How the change impacts the Project Schedule;
c. The sequence of new and/or existing activity revisions that are proposed to be added to the Project Schedule that is in effect when the change or delay is encountered; and
d. The proposed method for incorporating the delay and its impact to the Project Schedule.
e.
The TIA shall be a separate schedule file to be reviewed separately from the Pay Application that the Contractor must follow for providing a TIA schedule are as follows:
The modeled delay event shall be inserted into the appropriate pre-impacted schedule.
The pre-impacted schedule shall be the approved schedule of record immediately preceding the start of the delay event.
No time extension request will be considered unless all available float has been used and the impact event delayed the completion date beyond the contract date.
Enter Contract Number
Draf t C on intentionally left black
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on
Draf t C on intentionally left blank
Draf t C on
Draf t C on
SITE WORK AND PERIMETER FENCING WHILE THE PROJECT SITE ENCOMPASSES A 15-ACRE TRACT, BIDDERS SHOULD NOTE THAT THE ACTUAL DISTURBED ACREAGE FOR EARTHWORK AND CIVIL SITE DEVELOPMENT IS STRICTLY LESS THAN 4.9 ACRES.
THE ENTIRE 15-ACRE PROPERTY PERIMETER MUST BE FULLY ENCLOSED BY A CONTINUOUS FENCE LINE. THE FENCING DESIGN REQUIRES ORNAMENTAL PANELIZED TUBE STEEL FENCING ALONG ALL STREET-FACING AREAS, WHICH MUST RETURN 50 FEET INTO THE PROPERTY AT BOTH ENDS FROM THE STREET FRONTAGE. THE REMAINDER OF THE BOUNDARY, BORDERING NEIGHBORING LOTS (BACK-OF-HOUSE AREAS), WILL BE SECURED WITH 6-FOOT HIGH CHAIN-LINK FENCING. PLEASE BE ADVISED THAT ANY FENCING DIMENSIONS PROVIDED IN THE CONSTRUCTION DRAWINGS ARE APPROXIMATE. THE CONTRACTOR HOLDS FULL RESPONSIBILITY FOR FIELD-MEASURING THE SITE AND ACCOUNTING FOR ALL MATERIALS, HARDWARE, AND LABOR REQUIRED TO ASSEMBLE AND INSTALL
THE COMPLETE PERIMETER ENCLOSURE.
OWNER-PROVIDED VS. CONTRACTOR-PROVIDED ELEMENTS TO ENSURE ACCURATE BIDDING, THE FOLLOWING CLARIFICATIONS ARE MADE REGARDING EQUIPMENT AND MATERIALS PROVIDED BY THE VETERANS ADMINISTRATION (VA) VERSUS THOSE REQUIRED TO BE FURNISHED BY THE CONTRACTOR. THE PHYSICAL PRE-PLACED CRYPT UNITS ARE VA-PROVIDED AND SHOULD NOT BE INCLUDED IN THE CONTRACTOR'S MATERIAL PRICING. HOWEVER, THE CONTRACTOR'S BID MUST INCLUDE THE COST OF ALL ASSOCIATED
EARTHWORK, CIVIL SITE PREPARATION, AND THE PHYSICAL INSTALLATION OF THE CRYPTS.
THE INFORMATION KIOSK (GRAVE LOCATOR) EQUIPMENT WILL ALSO BE PROVIDED BY THE VA. THE CONTRACTOR'S SCOPE OF WORK INCLUDES THE COMPLETE INSTALLATION OF THIS EQUIPMENT AND ALL RELATED SITE PREPARATION IN THE BASE BID.
FOR THE COLUMBARIA, STANDARD VA NICHE COVERS WILL BE PROVIDED BY THE OWNER. THE CONTRACTOR IS REQUIRED TO FURNISH ALL ASSOCIATED MOUNTING HARDWARE AND PERFORM THE FINAL INSTALLATION. AS A SPECIAL REQUIREMENT, PRIOR TO FULL INSTALLATION, THE CONTRACTOR MUST INSTALL A MOCKUP CONSISTING OF THREE (3) COLUMNS AND FIVE (5) ROWS OF NICHE COVERS TO ALLOW STATE REPRESENTATIVES TO REVIEW AND FORMALLY SIGN OFF ON THE ALIGNMENT TOLERANCES.
FINALLY, PLEASE NOTE THAT ALL BRONZE MILITARY SERVICE SEALS AND MEMORIAL PLAQUES DEPICTED IN THE CONSTRUCTION DOCUMENTS ARE STRICTLY PART OF THE BASE CONTRACT. THEY ARE NOT OWNER-PROVIDED AND MUST BE FURNISHED AND
INSTALLED BY THE CONTRACTOR.
ADD ALTERNATE NO. 1 SCOPE DEFINITION THE PROJECT INCLUDES ONE SPECIFIC ADD ALTERNATE THAT MUST BE PRICED COMPLETELY SEPARATE FROM THE BASE BID. THIS ALTERNATE ENCOMPASSES TWO MAIN COMPONENTS: THE COLUMBARIUM
ADDITION AND THE ADMINISTRATION BUILDING INTERIOR BUILD-OUT.
THE COLUMBARIUM ADDITION INCLUDES THE CONSTRUCTION AND INSTALLATION OF ONE (1) NEW COLUMBARIUM UNIT CONTAINING
Draf t C on
NONE
This space intentionally left blank
Draf t C on intentionally left blank
Draf t C on
Complete Name of Contractor Legal Entity Carlsbad State Veterans Cemetery
Name of Individual Signing Contract (See Note below
CP2600617
Enter Contract Number
Title of Individual Signing Contract Reference # (SPA Contract...)
Physical Address of Contractor Enter or "Pending"
Obtain from Capital Outlay/ Planning
Mailing Address of Contractor $ 0.00
City, State. Zip of Contractor
Telephone of Contractor
Email Address of Contractor for Notice; Article 5.6 Notices, Part A
Name of Individual Signing Contract (See Note below
Draf t C on
Draf t C on
File details come from the government source that posted it. Updated .