This is a specification document for construction dewatering work at Nibley Park School, prepared by Salt Lake School District. The dewatering section outlines comprehensive requirements for designing, furnishing, installing, testing, operating, monitoring, and maintaining a dewatering system capable of controlling hydrostatic pressures and removing groundwater to permit excavation and construction on dry, stable subgrades. The contractor must provide delegated design services including comprehensive engineering analysis by a qualified professional engineer, continuous monitoring and maintenance to ensure erosion control and stability, prevention of surface water infiltration through grading and dikes, and system removal upon completion. The specification requires submission of shop drawings detailing well and well point arrangements, riser and header locations, filter specifications, pump equipment, power units, discharge lines, sediment control measures, water disposal methods, piezometer layouts, flow-measuring devices, and a written dewatering operations plan with control procedures. Additionally, the contractor must provide delegation-design submittals signed and sealed by the responsible engineer, qualification data for the installer, field quality-control reports, and pre-installation photographs or videotape documenting existing site conditions.
The specification mandates that the contractor engage an experienced installer specialized in dewatering systems and comply with all EPA notification regulations and applicable hauling and disposal regulations before commencing work. A preinstallation conference must be conducted at the project site to review methods, procedures, geotechnical reports, site conditions, existing utilities, construction schedules, and equipment availability. The contractor must maintain piezometric water levels a minimum of 12 inches below excavation surfaces, provide standby equipment on site for continuous operation, and repair any damages to adjacent facilities caused by dewatering operations at no additional expense to the owner. All observation wells must be maintained with daily recordings of groundwater and piezometric water levels, with repairs or replacements required within 24 hours if wells become inactive or damaged. Water disposal must occur in a manner that protects public health and property, with sumps and sedimentation tanks provided as required by authorities having jurisdiction.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Salt Lake School District – Nibley Park School
312319 - 1 Dewatering
SECTION 312319 DEWATERING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes construction dewatering.
B. Related Sections:
1. Division 01 Section "Construction Progress Documentation and Photographic Documentation" for recording preexisting conditions and dewatering system progress.
2. Division 31 Section "Earth Moving" for excavating, backfilling, site grading, and for site utilities.
3. Division 31 Section "Excavation Support and Protection" for shoring, bracing, and sheet piling of excavations.
4. Division 33 Section "Subdrainage" for permanent foundation wall, underfloor, and footing drainage.
1.3 PERFORMANCE REQUIREMENTS
A. Dewatering Performance: Design, furnish, install, test, operate, monitor, and maintain dewatering system of sufficient scope, size, and capacity to control hydrostatic pressures and to lower, control, remove, and dispose of ground water and permit excavation and construction to proceed on dry, stable subgrades.
1. Delegated Design: Design dewatering system, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated.
2. Continuously monitor and maintain dewatering operations to ensure erosion control, stability of excavations and constructed slopes, that excavation does not flood, and that damage to subgrades and permanent structures is prevented.
3. Prevent surface water from entering excavations by grading, dikes, or other means.
4. Accomplish dewatering without damaging existing buildings, structures, and site improvements adjacent to excavation.
5. Remove dewatering system when no longer required for construction.
1.4 SUBMITTALS
A. Shop Drawings: For dewatering system. Show arrangement, locations, and details of wells and well points; locations of risers, headers, filters, pumps, power units, and discharge lines; and means of discharge, control of sediment, and disposal of water.
312319 - 2 Dewatering
1. Include layouts of piezometers and flow-measuring devices for monitoring performance of dewatering system.
2. Include a written plan for dewatering operations including control procedures to be adopted if dewatering problems arise.
B. Delegated-Design Submittal: For dewatering system indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.
C. Qualification Data: For qualified Installer.
D. Field quality-control reports.
E. Other Informational Submittals:
1. Photographs or Videotape: Show existing conditions of adjoining construction and site improvements that might be misconstrued as damage caused by dewatering operations.
1.5 QUALITY ASSURANCE
A. Installer Qualifications: An experienced installer that has specialized in dewatering systems and dewatering work.
B. Regulatory Requirements: Comply with governing EPA notification regulations before beginning dewatering. Comply with hauling and disposal regulations of authorities having jurisdiction.
C. Preinstallation Conference: Conduct conference at Project site.
1. Review methods and procedures related to dewatering including, but not limited to, the following:
a. Inspection and discussion of condition of site to be dewatered including coordination with temporary erosion control measures and temporary controls and protections.
b. Geotechnical report.
c. Proposed site clearing and excavations.
d. Existing utilities and subsurface conditions.
e. Coordination for interruption, shutoff, capping, and continuation of utility services.
f. Construction schedule. Verify availability of Installer's personnel, equipment, and facilities needed to make progress and avoid delays.
g. Testing and monitoring of dewatering system.
h. Other agenda items.
1.6 PROJECT CONDITIONS
A. Interruption of Existing Utilities: Do not interrupt any utility serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility according to requirements indicated:
1. Notify Architect no fewer than two days in advance of proposed interruption of utility.
2. Do not proceed with interruption of utility without Architect's, Construction Manager's, and
Owner's written permission.
312319 - 3 Dewatering
B. Project-Site Information: A geotechnical report has been prepared for this Project and is available for information only. The opinions expressed in this report are those of geotechnical engineer and represent interpretations of subsoil conditions, tests, and results of analyses conducted by geotechnical engineer. Owner will not be responsible for interpretations or conclusions drawn from this data.
1. Make additional test borings and conduct other exploratory operations necessary for dewatering.
2. The geotechnical report is referenced in the Project Manual.
C. Survey Work: Engage a qualified land surveyor or professional engineer to survey adjacent existing buildings, structures, and site improvements, establishing exact elevations at fixed points to act as benchmarks. Clearly identify benchmarks and record existing elevations.
1. During dewatering, regularly resurvey benchmarks, maintaining an accurate log of surveyed elevations for comparison with original elevations. Promptly notify Architect if changes in elevations occur or if cracks, sags, or other damage is evident in adjacent construction.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by dewatering operations.
1. Prevent surface water and subsurface or ground water from entering excavations, from ponding on prepared subgrades, and from flooding site and surrounding area.
2. Protect subgrades and foundation soils from softening and damage by rain or water accumulation.
B. Install dewatering system to ensure minimum interference with roads, streets, walks, and other adjacent occupied and used facilities.
1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction. Provide alternate routes around closed or obstructed traffic ways if required by authorities having jurisdiction.
C. Provide temporary grading to facilitate dewatering and control of surface water.
D. Monitor dewatering systems continuously.
E. Promptly repair damages to adjacent facilities caused by dewatering.
F. Protect and maintain temporary erosion and sedimentation controls, which are specified in Division 01 Section "Temporary Facilities and Controls" and Division 31 Section "Site Clearing" during dewatering operations.
312319 - 4 Dewatering
3.2 INSTALLATION
A. Install dewatering system utilizing wells, well points, or similar methods complete with pump equipment, standby power and pumps, filter material gradation, valves, appurtenances, water disposal, and surface-water controls.
1. Space well points or wells at intervals required to provide sufficient dewatering.
2. Use filters or other means to prevent pumping of fine sands or silts from the subsurface.
B. Before excavating below ground-water level, place system into operation to lower water to specified levels. Operate system continuously until drains, sewers, and structures have been constructed and fill materials have been placed or until dewatering is no longer required.
C. Provide an adequate system to lower and control ground water to permit excavation, construction of structures, and placement of fill materials on dry subgrades. Install sufficient dewatering equipment to drain water-bearing strata above and below bottom of foundations, drains, sewers, and other excavations.
1. Do not permit open-sump pumping that leads to loss of fines, soil piping, subgrade softening, and slope instability.
D. Reduce hydrostatic head in water-bearing strata below subgrade elevations of foundations, drains, sewers, and other excavations.
1. Maintain piezometric water level a minimum of 12 inches below surface of excavation.
E. Dispose of water removed by dewatering in a manner that avoids endangering public health, property, and portions of work under construction or completed. Dispose of water and sediment in a manner that avoids inconvenience to others. Provide sumps, sedimentation tanks, and other flow-control devices as required by authorities having jurisdiction.
F. Provide standby equipment on site, installed and available for immediate operation, to maintain dewatering on continuous basis if any part of system becomes inadequate or fails. If dewatering requirements are not satisfied due to inadequacy or failure of dewatering system, restore damaged structures and foundation soils at no additional expense to Owner.
1. Remove dewatering system from Project site on completion of dewatering. Plug or fill well holes with sand or cut off and cap wells a minimum of 36 inches below overlying construction.
G. Damages: Promptly repair damages to adjacent facilities caused by dewatering operations.
3.3 FIELD QUALITY CONTROL
A. Observation Wells: Provide, take measurements, and maintain at least the minimum number of observation wells or piezometers indicated; additional observation wells may be required by authorities having jurisdiction.
1. Observe and record daily elevation of ground water and piezometric water levels in observation wells.
2. Repair or replace, within 24 hours, observation wells that become inactive, damaged, or destroyed. In areas where observation wells are not functioning properly, suspend construction activities until reliable observations can be made. Add or remove water from observation-well risers to demonstrate that observation wells are functioning properly.
312319 - 5 Dewatering
3. Fill observation wells, remove piezometers, and fill holes when dewatering is completed.
B. Provide continual observation to ensure that subsurface soils are not being removed by the dewatering operation.
END OF SECTION 312319
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. |
| 1.2 SUMMARY |
| A. Section includes construction dewatering. |
| B. Related Sections: |
| 1. Division 01 Section "Construction Progress Documentation and Photographic Documentation" for recording preexisting conditions and dewatering system progress. |
| 2. Division 31 Section "Earth Moving" for excavating, backfilling, site grading, and for site utilities. |
| 3. Division 31 Section "Excavation Support and Protection" for shoring, bracing, and sheet piling of excavations. |
| 4. Division 33 Section "Subdrainage" for permanent foundation wall, underfloor, and footing drainage. |
| 1.3 PERFORMANCE REQUIREMENTS |
| A. Dewatering Performance: Design, furnish, install, test, operate, monitor, and maintain dewatering system of sufficient scope, size, and capacity to control hydrostatic pressures and to lower, control, remove, and dispose of ground water and permit... |
| 1. Delegated Design: Design dewatering system, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated. |
| 2. Continuously monitor and maintain dewatering operations to ensure erosion control, stability of excavations and constructed slopes, that excavation does not flood, and that damage to subgrades and permanent structures is prevented. |
| 3. Prevent surface water from entering excavations by grading, dikes, or other means. |
| 4. Accomplish dewatering without damaging existing buildings, structures, and site improvements adjacent to excavation. |
| 5. Remove dewatering system when no longer required for construction. |
| 1.4 SUBMITTALS |
| A. Shop Drawings: For dewatering system. Show arrangement, locations, and details of wells and well points; locations of risers, headers, filters, pumps, power units, and discharge lines; and means of discharge, control of sediment, and disposal of ... |
| 1. Include layouts of piezometers and flow-measuring devices for monitoring performance of dewatering system. |
| 2. Include a written plan for dewatering operations including control procedures to be adopted if dewatering problems arise. |
| B. Delegated-Design Submittal: For dewatering system indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation. |
| C. Qualification Data: For qualified Installer. |
| D. Field quality-control reports. |
| E. Other Informational Submittals: |
| 1. Photographs or Videotape: Show existing conditions of adjoining construction and site improvements that might be misconstrued as damage caused by dewatering operations. |
| 1.5 QUALITY ASSURANCE |
| A. Installer Qualifications: An experienced installer that has specialized in dewatering systems and dewatering work. |
| B. Regulatory Requirements: Comply with governing EPA notification regulations before beginning dewatering. Comply with hauling and disposal regulations of authorities having jurisdiction. |
| C. Preinstallation Conference: Conduct conference at Project site. |
| 1. Review methods and procedures related to dewatering including, but not limited to, the following: |
| a. Inspection and discussion of condition of site to be dewatered including coordination with temporary erosion control measures and temporary controls and protections. |
| b. Geotechnical report. |
| c. Proposed site clearing and excavations. |
| d. Existing utilities and subsurface conditions. |
| e. Coordination for interruption, shutoff, capping, and continuation of utility services. |
| f. Construction schedule. Verify availability of Installer's personnel, equipment, and facilities needed to make progress and avoid delays. |
| g. Testing and monitoring of dewatering system. |
| h. Other agenda items. |
| 1.6 PROJECT CONDITIONS |
| A. Interruption of Existing Utilities: Do not interrupt any utility serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility according to requirements in... |
| 1. Notify Architect no fewer than two days in advance of proposed interruption of utility. |
| 2. Do not proceed with interruption of utility without Architect's, Construction Manager's, and Owner's written permission. |
| B. Project-Site Information: A geotechnical report has been prepared for this Project and is available for information only. The opinions expressed in this report are those of geotechnical engineer and represent interpretations of subsoil conditions... |
| 1. Make additional test borings and conduct other exploratory operations necessary for dewatering. |
| 2. The geotechnical report is referenced in the Project Manual. |
| C. Survey Work: Engage a qualified land surveyor or professional engineer to survey adjacent existing buildings, structures, and site improvements, establishing exact elevations at fixed points to act as benchmarks. Clearly identify benchmarks and r... |
| 1. During dewatering, regularly resurvey benchmarks, maintaining an accurate log of surveyed elevations for comparison with original elevations. Promptly notify Architect if changes in elevations occur or if cracks, sags, or other damage is evident i... |
| PART 2 - PRODUCTS (Not Used) |
| PART 3 - EXECUTION |
| 3.1 PREPARATION |
| A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by dewatering operations. |
| 1. Prevent surface water and subsurface or ground water from entering excavations, from ponding on prepared subgrades, and from flooding site and surrounding area. |
| 2. Protect subgrades and foundation soils from softening and damage by rain or water accumulation. |
| B. Install dewatering system to ensure minimum interference with roads, streets, walks, and other adjacent occupied and used facilities. |
| 1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction. Provide alternate routes around closed or obstructed traffic ways if required by authorities ... |
| C. Provide temporary grading to facilitate dewatering and control of surface water. |
| D. Monitor dewatering systems continuously. |
| E. Promptly repair damages to adjacent facilities caused by dewatering. |
| F. Protect and maintain temporary erosion and sedimentation controls, which are specified in Division 01 Section "Temporary Facilities and Controls" and Division 31 Section "Site Clearing" during dewatering operations. |
| 3.2 INSTALLATION |
| A. Install dewatering system utilizing wells, well points, or similar methods complete with pump equipment, standby power and pumps, filter material gradation, valves, appurtenances, water disposal, and surface-water controls. |
| 1. Space well points or wells at intervals required to provide sufficient dewatering. |
| 2. Use filters or other means to prevent pumping of fine sands or silts from the subsurface. |
| B. Before excavating below ground-water level, place system into operation to lower water to specified levels. Operate system continuously until drains, sewers, and structures have been constructed and fill materials have been placed or until dewater... |
| C. Provide an adequate system to lower and control ground water to permit excavation, construction of structures, and placement of fill materials on dry subgrades. Install sufficient dewatering equipment to drain water-bearing strata above and below ... |
| 1. Do not permit open-sump pumping that leads to loss of fines, soil piping, subgrade softening, and slope instability. |
| D. Reduce hydrostatic head in water-bearing strata below subgrade elevations of foundations, drains, sewers, and other excavations. |
| 1. Maintain piezometric water level a minimum of 12 inches below surface of excavation. |
| E. Dispose of water removed by dewatering in a manner that avoids endangering public health, property, and portions of work under construction or completed. Dispose of water and sediment in a manner that avoids inconvenience to others. Provide sumps... |
| F. Provide standby equipment on site, installed and available for immediate operation, to maintain dewatering on continuous basis if any part of system becomes inadequate or fails. If dewatering requirements are not satisfied due to inadequacy or fai... |
| 1. Remove dewatering system from Project site on completion of dewatering. Plug or fill well holes with sand or cut off and cap wells a minimum of 36 inches below overlying construction. |
G. Damages: Promptly repair damages to adjacent facilities caused by dewatering operations.
| 3.3 FIELD QUALITY CONTROL |
| A. Observation Wells: Provide, take measurements, and maintain at least the minimum number of observation wells or piezometers indicated; additional observation wells may be required by authorities having jurisdiction. |
| 1. Observe and record daily elevation of ground water and piezometric water levels in observation wells. |
| 2. Repair or replace, within 24 hours, observation wells that become inactive, damaged, or destroyed. In areas where observation wells are not functioning properly, suspend construction activities until reliable observations can be made. Add or remo... |
| 3. Fill observation wells, remove piezometers, and fill holes when dewatering is completed. |
B. Provide continual observation to ensure that subsurface soils are not being removed by the dewatering operation.