This is a Site Demolition specification document for the Salt Lake School District's Nibley Park Elementary School project. The specification outlines the complete scope of demolition work required within designated demolition limit lines, including removal of sidewalks, curbs, paving, concrete slabs, utility lines and meters, fencing, building structures, trees and stumps, underground structures such as septic tanks and basements, and paint obliteration. The contractor must submit a proposed demolition schedule and methods for review prior to work commencement, coordinate utility shut-offs and capping, and obtain a Demolition Permit and Utility Disconnection Permits from the City and utility companies. A mandatory pre-bid site visit is scheduled for Tuesday, May 26, 2026 at 9:00 A.M. at Nibley Park Elementary School located at 2785 South 800 East, Salt Lake City, Utah 84106, with contractors required to attend and meet in the northeast parking lot; failure to attend on time will result in bid disqualification.
The specification prohibits the use of explosives and requires contractors to implement pollution controls through water sprinkling and temporary enclosures to minimize dust and debris while complying with environmental protection regulations. Contractors must conduct operations to ensure safe passage around the demolition area, prevent injury to adjacent buildings and structures, promptly repair any damage caused by demolition operations, and avoid interrupting existing utilities serving occupied facilities without written authorization. All excavated areas associated with substructure removal must be backfilled with well-graded granular material not exceeding 2 inches in size with no more than 15 percent passing a #200 sieve, placed in maximum 8-inch loose lifts and compacted to 95 percent of Maximum Laboratory Density per ASTM D 1557-78. The contractor is responsible for removing all debris and disposing of demolished materials in a legal manner, with overhead utility line removal and relocation to be performed by the respective utility companies at the Owner's expense.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Salt Lake School District – Nibley Park School
024119 - 1 Site Demolition
SECTION 024119 – SITE DEMOLITION
PART 1 - GENERAL
0.1 SUMMARY:
A. Section includes requirement for demolition work.
1. Verify existing utilities to be removed as well as site features to be demolished with owner and engineer.
B. Demolition includes, but is not limited to, the removal of the following items within the demolition limit lines:
1. Sidewalks
2. Curbwalls
3. Curb and Gutter
4. Paving
5. Concrete Slabs
6. Water Lines and Meters
7. Gas Lines
8. Fencing
9. Building Structures (below and above grade)
10. Unmarked Trees and all their Roots
11. Tree Stumps and all their Roots
12. Minor Overhead Utility Lines and Poles
13. Sod, Lawn and all irrigated wet soils
14. Shrubs and all their Roots
15. Underground Structures including Septic Tanks, vaults, Basements
16. Paint Obliteration
C. Related Sections
1. Refer to Section 02300 for earthwork requirements.
D. Drawings and general provisions of contract, including general and supplementary
Conditions and site clearing specifications apply to work in this section.
0.2 SUBMITTALS:
A. Schedule: Submit proposed methods and operations of demolition to review prior to start of work. Include in schedule coordination for shut-off, capping, and continuation of utility services as required.
B. Explosives: The use of explosives is not permitted.
C. Traffic: Conduct demolition operations and removal of debris to ensure minimum interference with roads, streets, walks, and other adjacent occupied or used facilities.
1. Do not close or obstruct streets, walks or other occupied or used facilities without permission from authorities having jurisdiction. Provide alternate routes around closed or obstructed traffic ways if required by governing regulation.
024119 - 2 Site Demolition
D. Protections: Ensure safe passage of persons around area of demolition. Conduct operations to prevent injury to adjacent buildings, structures, other facilities, and persons.
1. Erect temporary covered passageways as required by authorities having jurisdiction.
2. Provide interior and exterior shoring, bracing, or support to prevent movement, settlement or collapse of structures to be demolished and adjacent facilities to remain.
E. Damage: Promptly repair damage caused to adjacent facilities by demolition operations.
1. Do not interrupt existing utilities serving occupied or used facilities, except when authorized in writing by authorities having jurisdiction. Provide temporary services during interruptions to existing utilities, as acceptable to governing authorities.
F. Hazardous Materials Removal:
1. When hazardous materials are encountered, notify the Owner immediately.
PART 1 - PRODUCTS
Not used.
PART 2 - EXECUTION
A. Demolition:
1. Pollution Controls: Use water sprinkling, temporary enclosures, and other suitable methods to limit dust and dirt rising and scattering in air to lowest practical level.
Comply with governing regulations pertaining to environmental protection.
a. Do not use water when it may create hazardous or objectionable conditions such as ice, flooding, and pollution.
b. Clean adjacent structures and improvements of dust, dirt, and debris caused by demolition operations, as directed by Architect or governing authorities. Return adjacent areas to condition existing prior to start of work.
B. Cutting Asphalt, Concrete and Concrete Block: Saw cut asphalt paving, concrete slabs and concrete block walls with approved saws at lines and levels indicated on drawings. Saw cut concrete walks and curbs only if they cannot be removed to an existing control joint.
C. Capping and Abandonment: Cap all abandoned lines and conduits and drains in accordance with requirements of Utility Companies having jurisdiction. Remove abandoned lines, unless otherwise noted.
D. Overhead Utility Lines: The Utility companies that own or otherwise control the overhead utility lines, will remove and relocate their poles and overhead utility lines at the Owner's expense. The Contractor shall coordinate these utility changes with the proper utility companies.
E. Permits: Contractor is required to obtain a Demolition Permit and Utility Disconnection
Permits from the City and utility companies.
1. Record on Record Document location and extent of all capped and abandoned lines below grade.
F. Relocation: Relocate utilities as indicated. Work performed for relocation of utilities to conform to new utility line construction.
024119 - 3 Site Demolition
2.1 DISPOSAL OF DEMOLISHED MATERIALS:
A. General: remove from site debris, rubbish, and other materials resulting from demolition operations and dispose in a legal manner.
2.2 BACKFILL
A. Excavated areas associated with the removal of all substructures should be backfilled with a well-graded granular material having a maximum size of 2 inches and not more than 15 percent passing a #200 sieve. All earth materials placed in excavated areas should be placed in maximum eight inch loose lifts and densified to an in-place unit weight equal to 95% of the Maximum Laboratory Density as determined by ASTM D 1557-78.
1. Refer to section 02300 for placement and compaction requirements.
END OF SECTION 024119