This is Amendment #2 to the bidding documents for the Library Renovation to the Blue Bell Branch Library General Construction project issued by the Wissahickon Valley Public Library in Pennsylvania. The project involves general demolition and reconstruction of interior partitions and finishes, construction of a new entrance feature, and selected additions of doors and windows. The owner anticipates work will begin in late October or early November 2026 with a completion timeline of 6 to 9 months. The bid submission deadline was 10:00 A.M. on Thursday, September 15, 2026, with the question submission period closing on Friday, September 11, 2026. A pre-bid conference was conducted with an attendance list included in the amendment. The contract is structured as a single prime bid contract administered through PennBid, with monthly invoicing using AIA forms.
The estimated project cost ranges from $1.5 to $2 million, with no formal budget estimate prepared. A 10% bid bond is required, with AIA Bid Bond forms acceptable. Performance bonds and labor and materials bonds of 100% are required, along with a 25% maintenance bond. Monthly retainage is set at 10% of invoiced amounts, with an option for the owner to reduce retainage after 50% completion. The owner is a separate private corporation, not a governmental entity, and no public funds are being used for this project. No liquidated damages or bonus provisions apply. Additional work including signage, fire alarm systems, camera and security installations will be executed under separate contracts. Sprinkler system modifications must comply with NFPA-13 standards, and employee clearances are not required.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT #2 2026-09.08
B RESPONSES TO QUESTIONS
1 Bidders list is attached
2 Insurance requirements are attached
3 Contract is a Single Prime Bid Contract. There are no public funds being used for this project and the Owner is a separate private corporation not a governmental entity. Regarding the question pertaining to the
Acknowledgement Form, Bid Form Spec Section 00 4116 item 8, on page 3 of 3 lists the items for Corporate Bidders. This form is sufficient.
4 There are no liquidated damages on this project. There are no “bonus provisions” either. The Owner is prepared to execute a contract to allow work to begin in late October or early November with the anticipation that it will take 6 to 9 months to complete.
5 Bid Bond At the Pre-Bid conference it was stated that the requirement would be a 10% Bid Bond. Use of the AIA Bid Bond form is acceptable.
6 Budget—no Estimate has been prepared for this project. It is believed that the cost will be in the range of $1.5 to $2 million.
7 Asbestos—to the best of the Owner’s knowledge and experience, there is no Asbestos in this building. If any is encountered, it will be addressed and remediated by the Owner.
8 Supplementary Instructions to Bidders Section 1.5 F—Delete references to preferred electrical and roofing subcontractors. Bidder will be required to perform connection work for roofing as shown on the drawings. There is no preferred electrical contractor associated with this project.
9 The Owner and the Project Team have no knowledge of a Responsible
Contractors’ Ordnance that applies to this project
10 Final Addendum will be posted after the closing of the Question and
Answer period
11 Employee clearances WILL NOT be required for this work. There will be no occupancy by the Library during construction.
12 Monthly invoices will be made using the specified AIA form. The retainage will be 10% of the invoiced amount. At 50% completion, the progress will be reviewed with the option of the Owner to reduce the retainage for the remaining invoices
AMENDMENT #2 2026-09.08
13 Signage will be executed under a separate contract. Contractor will be required to coordinate with that contract when the point in the work is reached to install signage.
14 Fire Alarm, Camera and Security work scope will be executed under separate contract. Locations are shown on the drawings for Information
Purposes Only. Work scope in this contract includes only the conduits/ raceways that are imbedded in the floor.
15 Fire Sprinklers: The building is currently equipped with an automatic sprinkler system per NFPA Standard 13. The scope of work for this contract will involve the following:
A Installation of a Dry Sprinkler system to protect the new construction at the entrance canopy. This shall include the operating features (valve, alarm activation and inspection test)
B The scope of work does not anticipate the need for a Pre-Action
System. The only area that requires a special system is the entrance are noted in item 8A above.
C Modifications to the existing system to conform with the revised layout and construction of new walls. In some rooms it will require the addition of one or two sprinkler heads to achieve the NFPA 13 level of coverage. It is not anticipated that hydraulic calculations will be necessary for this work.
C. At completion of work, sprinkler system shall comply with NFPA-13
END OF ADDENDUM 001
ATTACHMENTS INCLUDED IN THIS ADENDUM:
ATTENDANCE LIST FROM PRE-BID CONFERENCE (2 pages)
INSURANCE REQUIREMENTS (5 pages)