NGWSP_-_Block_2-3_HDD_Site_Tour_-_2_DECEMBER_2025_0001.pdf
PDF 6 MB Posted
- Attached to
- NGWSP BLOCK 2-3 HDD
- Solicitation number
- 140R4026R0002
About this file
This is a Pre-Bid Conference document for the Navajo-Gallup Water Supply Project (NGWSP) Block 2-3 Horizontal Directional Drilling (HDD) segment. The project is part of a larger $2.2 billion water infrastructure initiative involving approximately 300 miles of pipelines, two water treatment plants, and 19 pumping plants. The specific Block 2-3 HDD project involves approximately 1.8 miles of pipeline crossing four critical areas: San Juan River, Nenahnezad Bluff, Shumway Arroyo, and Chaco River, with pipeline diameters ranging from 36" to 42" and significant engineering challenges at each crossing.
The procurement timeline includes a bid due date of February 25, 2026 at 1 pm MT, with bid evaluation in March 2026 and contract award planned for May 20, 2026. The project's construction is scheduled for completion by September 21, 2027. Key technical challenges include managing elevation differences between entry and exit points (up to 240 feet), navigating difficult geological conditions like cobbles, boulders, and dipping bedrock, and maintaining careful environmental and cultural compliance. The Bureau of Reclamation is managing the solicitation, with Ashton Jones (Contracting Officer) and supporting contracting specialists as the primary points of contact.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Navajo-Gallup Water Supply Project (NGWSP)
December 2, 2025
Block 2-3 HDD Pre-Bid Conference
Agenda
• Overview Presentation
• Introductions
• NGWSP Overview
• Block 2-3 HDD Project Overview
• Challenges
• Acquisition Overview
• Safety
• Questions
• Travel to the site (10:45 to 11:00)
• Tour the site starts at 11:00
• Adjourn
NGWSP Background
March 30, 2009
NGWSP Background
• Description
• Currently estimated at $2.2 Billion
• 2 Main Laterals (Cutter and San Juan) totaling 300 miles of Pipelines (20”-48”)
• 2 Conventional Water Treatment Plants with ultimate capacity of 5 & 38 MGD
• 19 Pumping Plants -- raw and finished water
• Numerous Storage Tanks
• Construction began – June 2012
• Complexities
• Cultural Resources and Environmental Compliance
• Land Acquisitions
• Bringing power to remote area
• Coordination with various Stakeholders and Jurisdictions
• Various Studies
Cutter Lateral
San Juan Lateral
Operational Completed Under Construction In Design (As of March 2025)
Project Status
4A/4B Pipeline Completion: Dec. 2025
San Juan Lateral WTP Const. Completion: Dec. 2028
Lybrook Completion: 2027
BBN9 Lateral Completion: 2028
Pumping Plants 2 & 3 Completion: Jan. 2026
Block 2-3 HDD
Presenter Notes Presentation Notes Lybrook Dates
Project Overview Map Cutter Lateral
San Juan Lateral
Operational Completed Under Construction In Design (As of February 2024)
FCWR
WTP
SJL Intake & River Pumping System
42” Line to Reservoir
Intake and River Pumping Plant
Block 2-3 Pipeline – (not the HDD)
• 42” to 48” Pipeline ~12 miles
• Pipeline Appurtenances
• Jack and Bore Crossings
• Two (2) - 240,000-Gallon Raw Water Concrete Storage Tanks
• SCADA
• Cathodic Protection
Not part of the HDD project– Award ETA September 2026
Block 2-3 Pipeline -- (not the HDD)
SJLWTP
Reach 3 ~8.1 Miles
Reach 2 ~3.8 Miles
SJLWTP Regulating Tanks~4.0 Miles
~4 .1 Miles
~1.0 Miles ~0.2 Miles
~1.1 Miles ~1.5 Miles
Block 2-3 Horizontal Directional Drilling
SJLWTP
Reach 3 ~8.1 Miles
Reach 2 ~3.8 Miles
SJLWTP
Reg. Tanks
~4.0 Miles
~4 .1 Miles
~1.0 Miles
~0.2 Miles
~1.1 Miles ~1.5 Miles
- Block 2-3 HDD
Block 2-3
FCWR
SJLWTP
SJLWTP Regulating Tanks
Approximately a Total of 1.8 miles
HDD CROSSINGS
Item # HDD Crossing Name Length
(feet) Elevation
Difference (feet)
Pipe Diameter
(inch)
Reamed Diameter (inch)
Pipe Material
1 Reach 2 -- San Juan River 2,400 65 36 48 Steel 2 Reach 2 -- Nenahnezad Bluff 3,300 241 42 54 Steel
3 Reach 2 -- Shumway Arroyo 2,000 / 1,100 23 36 48
Steel /
HDPE /
PVC
4 Reach 3 -- Chaco River 2,080 3 36 48 Steel
Reach 2 HDD
Shumway HDD
~2,000 LF
San Juan River HDD
~2,100 LF
Nenahnezad Hill HDD
~3,300 LF
Reach 3 HDD
Chaco River HDD
~2,000 LF
Pumping Plant 1
• Metal Building ~13,000 SQFT
• Six (6) 700-horsepower Vertical Turbine Pumps
• Q = 71 CFS and TDH = 315 Feet
• Steel Manifold Piping
• 4 Air Chambers (2-2)
• Electrical System
• Precast Concrete Manholes & Vaults
• SCADA System
• Access Road improvements
Contact Awarded to Ames Construction on November 10, 2025
Close Coordination and Cooperation is required
FCWR
Reach 2
Block 2-3 HDD Schedule
• Bids Due Date – February 25, 2026 at 1 pm MT
• Bids Evaluation Completion – March 2026
• Award Date – May 20, 2026
• Construction Completion Date – September 21, 2027
Shumway Arroyo Challenges
• Conductor casings may be needed at for the alluvium (cobbles and boulders) that could be encountered
• Crossing existing Farmers Mutual Irrigation Siphon (very old and fragile)
• 2 Material options – Metallic or Plastic
• 23-foot elevation difference between entry and exit
San Juan River Challenges
• Conductor casings are required on both entry and exit sides
• Requires that pilot bore uses an intersection method (drilling from both sides)
• Cobbles and boulders are expected in alluvium, based on geology data
• Mid-pull Weld will be required due to limited ROW
• ~1,900 feet is available to laydown at a time
• 65-foot elevation difference between entry and exit
• Unpaved ditch located at the HDD Exit
Nenahnezad Bluff Challenges
• There is an elevation difference of 240-feet between the entry and exit pits
• Conductor casings are not required but may be used.
• Entry HDD is located in uncontrolled manmade fill.
• Nenahnezad Hill Road location and steepness.
Chaco River Challenges
• Approximately 5.5 miles of access road will be required, includes:
• Stripping, clearing, and grubbing
• Repairs and maintenance to new and existing roadways
• Final grading, inspection, clean-up, and restoration of access roads
• Available laydown on both sides of HDD to allow contractor flexibility.
• Dipping bedrock needs to be drilled through
Acquisition Overview
• ACQUISITION OVERVIEW
• PRINCIPAL CONSTRUCTION COMPONENTS
• ENVIRONMENTAL AND CULTURAL REQUIREMENTS
• SAFETY REQUIREMENTS
• NOTICE OF BUY AMERICAN REQUIREMENTS
• PREFACE
• SOLICITATION POINTS OF CONTACT AND COMMUNICATION
• BIDS DUE DATE/TIME – Bid must be submitted no later than February 25, 2026, 1:00 pm MST
Safety
Questions
a. Contracting Officer (Ashton Jones, 801-524-3621, ajones@usbr.gov)
b. Contracting Specialists (Amy Loveless, 801-524-3790, aloveless@usbr.gov;
Tyler Spencer, 801-524-3653, tspencer@usbr.gov)
c. are the official points of contact.
mailto:ajones@usbr.gov mailto:aloveless@usbr.gov
| Navajo-Gallup Water Supply Project (NGWSP) |
| Agenda |
| NGWSP Background |
| NGWSP Background |
| Project Status |
| Project Overview Map |
| SJL Intake & River Pumping System |
| Block 2-3 Pipeline – (not the HDD) |
| Block 2-3 Pipeline -- (not the HDD) |
| Block 2-3 Horizontal Directional Drilling |
| Block 2-3 Horizontal Directional Drilling |
| Block 2-3 Horizontal Directional Drilling |
| Pumping Plant 1 |
| Pumping Plant 1 |
| Block 2-3 HDD Schedule |
| Shumway Arroyo Challenges |
| San Juan River Challenges |
| Nenahnezad Bluff Challenges |
| Chaco River Challenges |
| Acquisition Overview |
| Safety |
| Safety |
| Safety |
| Questions |
| Slide Number 25 |