This is a Pre-Bid Conference document for the Navajo-Gallup Water Supply Project (NGWSP) Block 2-3 Horizontal Directional Drilling (HDD) segment. The project is part of a larger $2.2 billion water infrastructure initiative involving approximately 300 miles of pipelines, two water treatment plants, and 19 pumping plants. The specific Block 2-3 HDD project involves approximately 1.8 miles of pipeline crossing four critical areas: San Juan River, Nenahnezad Bluff, Shumway Arroyo, and Chaco River, with pipeline diameters ranging from 36" to 42" and significant engineering challenges at each crossing.

The procurement timeline includes a bid due date of February 25, 2026 at 1 pm MT, with bid evaluation in March 2026 and contract award planned for May 20, 2026. The project's construction is scheduled for completion by September 21, 2027. Key technical challenges include managing elevation differences between entry and exit points (up to 240 feet), navigating difficult geological conditions like cobbles, boulders, and dipping bedrock, and maintaining careful environmental and cultural compliance. The Bureau of Reclamation is managing the solicitation, with Ashton Jones (Contracting Officer) and supporting contracting specialists as the primary points of contact.

View the file

Other files

File Type Posted
140R4026R0002_Attachment_1_3_33_05_22_-_Horizontal_Directional_Drilling_(HDD)_0005.pdf PDF
Sol_140R4026R0002_Amd_0005.pdf PDF
Sol_140R4026R0002_Amd_0004.pdf PDF
Questions___Answers_-_Round_3_0004.pdf PDF
Sol_140R4026R0002_Amd_0003.pdf PDF
Questions___Answers_-_Round_2_0003.pdf PDF
140R4026R0002_Attachment_2_2_00_00_02_Drawings_01162026_0003.pdf PDF
140R4026R0002_Attachment_1_2_00_00_01_Specifications_01162026_0003.pdf PDF
140R4026R0002_Attachment_2_1_00_00_02_-_Drawings_12102025_0002.PDF PDF
140R4026R0002_Attachment_1_1_00_00_01_-_Specifications_12102025_0002.pdf PDF
Sol_140R4026R0002_Amd_0002.pdf PDF
Questions___Answers_-_Round_1_0002.pdf PDF
Sol_140R4026R0002_Amd_0001.pdf PDF
Site_Tour_Sign-in_Sheet_0001.pdf PDF
Sol_140R4026R0002.pdf PDF
140R4026R0002_Attachment_9_-_Construction_Contract_Administration.pdf PDF
140R4026R0002_Attachment_2_-_00_00_02_Dwgs-B_NGWSP-Block2-3HDD_11x17_20251027.pdf PDF
140R4026R0002_Attachment_4_-_WD_NM20250040_Heavy_-_San_Juan_County__NM.pdf PDF
140R4026R0002_Attachment_1_-_00_00_01_NGWSP-BLK2-3-HDD_Specifications_10272025.pdf PDF
140R4026R0002_NGWSP_Block_2-3_HDD_17NOV25.pdf PDF
140R4026R0002_Attachment_6_-_Past_Performance_Questionnaire.pdf PDF
140R4026R0002_Attachment_3_-_00_00_02A_GeologyDwgsAndLogs_NGWSP-BLK2-3-HDD_11x17_20251027.pdf PDF
140R4026R0002_Attachment_5_-_WD_NM20250046_Building_-_San_Juan_County__NM.pdf PDF
140R4026R0002_Attachment_8_-_Key_Personnel_Form.docx DOCX document
140R4026R0002_Attachment_7_-_Experience_Form.docx DOCX document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Navajo-Gallup Water Supply Project (NGWSP)

December 2, 2025

Block 2-3 HDD Pre-Bid Conference

Agenda

• Overview Presentation

• Introductions

• NGWSP Overview

• Block 2-3 HDD Project Overview

• Challenges

• Acquisition Overview

• Safety

• Questions

• Travel to the site (10:45 to 11:00)

• Tour the site starts at 11:00

• Adjourn

NGWSP Background

March 30, 2009

NGWSP Background

• Description

• Currently estimated at $2.2 Billion

• 2 Main Laterals (Cutter and San Juan) totaling 300 miles of Pipelines (20”-48”)

• 2 Conventional Water Treatment Plants with ultimate capacity of 5 & 38 MGD

• 19 Pumping Plants -- raw and finished water

• Numerous Storage Tanks

• Construction began – June 2012

• Complexities

• Cultural Resources and Environmental Compliance

• Land Acquisitions

• Bringing power to remote area

• Coordination with various Stakeholders and Jurisdictions

• Various Studies

Cutter Lateral

San Juan Lateral

Operational Completed Under Construction In Design (As of March 2025)

Project Status

4A/4B Pipeline Completion: Dec. 2025

San Juan Lateral WTP Const. Completion: Dec. 2028

Lybrook Completion: 2027

BBN9 Lateral Completion: 2028

Pumping Plants 2 & 3 Completion: Jan. 2026

Block 2-3 HDD

Presenter Notes Presentation Notes Lybrook Dates

Project Overview Map Cutter Lateral

San Juan Lateral

Operational Completed Under Construction In Design (As of February 2024)

FCWR

WTP

SJL Intake & River Pumping System

42” Line to Reservoir

Intake and River Pumping Plant

Block 2-3 Pipeline – (not the HDD)

• 42” to 48” Pipeline ~12 miles

• Pipeline Appurtenances

• Jack and Bore Crossings

• Two (2) - 240,000-Gallon Raw Water Concrete Storage Tanks

• SCADA

• Cathodic Protection

Not part of the HDD project– Award ETA September 2026

Block 2-3 Pipeline -- (not the HDD)

SJLWTP

Reach 3 ~8.1 Miles

Reach 2 ~3.8 Miles

SJLWTP Regulating Tanks~4.0 Miles

~4 .1 Miles

~1.0 Miles ~0.2 Miles

~1.1 Miles ~1.5 Miles

Block 2-3 Horizontal Directional Drilling

SJLWTP

Reach 3 ~8.1 Miles

Reach 2 ~3.8 Miles

SJLWTP

Reg. Tanks

~4.0 Miles

~4 .1 Miles

~1.0 Miles

~0.2 Miles

~1.1 Miles ~1.5 Miles

- Block 2-3 HDD

Block 2-3

FCWR

SJLWTP

SJLWTP Regulating Tanks

Approximately a Total of 1.8 miles

HDD CROSSINGS

Item # HDD Crossing Name Length

(feet) Elevation

Difference (feet)

Pipe Diameter

(inch)

Reamed Diameter (inch)

Pipe Material

1 Reach 2 -- San Juan River 2,400 65 36 48 Steel 2 Reach 2 -- Nenahnezad Bluff 3,300 241 42 54 Steel

3 Reach 2 -- Shumway Arroyo 2,000 / 1,100 23 36 48

Steel /

HDPE /

PVC

4 Reach 3 -- Chaco River 2,080 3 36 48 Steel

Reach 2 HDD

Shumway HDD

~2,000 LF

San Juan River HDD

~2,100 LF

Nenahnezad Hill HDD

~3,300 LF

Reach 3 HDD

Chaco River HDD

~2,000 LF

Pumping Plant 1

• Metal Building ~13,000 SQFT

• Six (6) 700-horsepower Vertical Turbine Pumps

• Q = 71 CFS and TDH = 315 Feet

• Steel Manifold Piping

• 4 Air Chambers (2-2)

• Electrical System

• Precast Concrete Manholes & Vaults

• SCADA System

• Access Road improvements

Contact Awarded to Ames Construction on November 10, 2025

Close Coordination and Cooperation is required

FCWR

Reach 2

Block 2-3 HDD Schedule

• Bids Due Date – February 25, 2026 at 1 pm MT

• Bids Evaluation Completion – March 2026

• Award Date – May 20, 2026

• Construction Completion Date – September 21, 2027

Shumway Arroyo Challenges

• Conductor casings may be needed at for the alluvium (cobbles and boulders) that could be encountered

• Crossing existing Farmers Mutual Irrigation Siphon (very old and fragile)

• 2 Material options – Metallic or Plastic

• 23-foot elevation difference between entry and exit

San Juan River Challenges

• Conductor casings are required on both entry and exit sides

• Requires that pilot bore uses an intersection method (drilling from both sides)

• Cobbles and boulders are expected in alluvium, based on geology data

• Mid-pull Weld will be required due to limited ROW

• ~1,900 feet is available to laydown at a time

• 65-foot elevation difference between entry and exit

• Unpaved ditch located at the HDD Exit

Nenahnezad Bluff Challenges

• There is an elevation difference of 240-feet between the entry and exit pits

• Conductor casings are not required but may be used.

• Entry HDD is located in uncontrolled manmade fill.

• Nenahnezad Hill Road location and steepness.

Chaco River Challenges

• Approximately 5.5 miles of access road will be required, includes:

• Stripping, clearing, and grubbing

• Repairs and maintenance to new and existing roadways

• Final grading, inspection, clean-up, and restoration of access roads

• Available laydown on both sides of HDD to allow contractor flexibility.

• Dipping bedrock needs to be drilled through

Acquisition Overview

• ACQUISITION OVERVIEW

• PRINCIPAL CONSTRUCTION COMPONENTS

• ENVIRONMENTAL AND CULTURAL REQUIREMENTS

• SAFETY REQUIREMENTS

• NOTICE OF BUY AMERICAN REQUIREMENTS

• PREFACE

• SOLICITATION POINTS OF CONTACT AND COMMUNICATION

• BIDS DUE DATE/TIME – Bid must be submitted no later than February 25, 2026, 1:00 pm MST

Safety

Questions

a. Contracting Officer (Ashton Jones, 801-524-3621, ajones@usbr.gov)

b. Contracting Specialists (Amy Loveless, 801-524-3790, aloveless@usbr.gov;

Tyler Spencer, 801-524-3653, tspencer@usbr.gov)

c. are the official points of contact.

mailto:ajones@usbr.gov mailto:aloveless@usbr.gov

Navajo-Gallup Water Supply Project (NGWSP)
Agenda
NGWSP Background
NGWSP Background
Project Status
Project Overview Map
SJL Intake & River Pumping System
Block 2-3 Pipeline – (not the HDD)
Block 2-3 Pipeline -- (not the HDD)
Block 2-3 Horizontal Directional Drilling
Block 2-3 Horizontal Directional Drilling
Block 2-3 Horizontal Directional Drilling
Pumping Plant 1
Pumping Plant 1
Block 2-3 HDD Schedule
Shumway Arroyo Challenges
San Juan River Challenges
Nenahnezad Bluff Challenges
Chaco River Challenges
Acquisition Overview
Safety
Safety
Safety
Questions
Slide Number 25