140R4026R0002_Attachment_1_2_00_00_01_Specifications_01162026_0003.pdf
PDF 678 KB Posted
- Attached to
- NGWSP BLOCK 2-3 HDD
- Solicitation number
- 140R4026R0002
About this file
This document is a comprehensive Horizontal Directional Drilling (HDD) specification for the Navajo-Gallup Water Supply Project's San Juan Lateral Block 2-3 pipeline installation. The specification covers detailed technical requirements for installing water pipeline crossings using horizontal directional drilling methods at four specific locations: Shumway Arroyo, San Juan River, Nenahnezad Bluff, and Chaco River. The document provides extensive guidance on drilling procedures, equipment specifications, pipe materials (including steel, HDPE, PVC, and ductile iron), installation techniques, quality control testing, and environmental protection measures.
Key technical requirements include precise drilling tolerances, mandatory testing protocols, drilling fluid management, pipe installation procedures, and post-installation acceptance criteria. The specification allows for multiple pipe material options and requires contractors to have significant experience in HDD projects, with requirements such as a minimum 10-year track record, successful completion of at least three previous HDD projects, and specific qualifications for personnel including drilling fluid engineers, guidance technicians, and fusion joint operators. Contractors must also submit detailed work plans, contingency plans, and follow strict environmental and safety guidelines throughout the installation process.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Navajo-Gallup Water Supply Project Amendment No. 003 San Juan Lateral – Block 2-3 Horizontal Directional Drilling Solicitation No.
Revised Price Schedules
B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES
SAN JUAN LATERAL – BLOCK 2-3 HORIZONTAL DIRECTIONAL DRILLING
NAVAJO-GALLUP WATER SUPPLY PROJECT, NEW MEXICO
B.1 PRICE SCHEDULES
(a) Offers will be considered for award on the following Price Schedules, but no offer will be considered for award on only part of the Price Schedules. Offers are subject to the terms and conditions of this solicitation.
(b) Quantities in Price Schedules are estimated quantities for comparison of offers only.
Except as provided in contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against Government for overruns or underruns. Contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.
(c) See contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLINs 1-1 and 2-1.
(d) Definitions:
(1) CLIN – Contract Line Item Number
(e) Note: In accordance with Section 7-9-3.3 of New Mexico Statutes Annotated (NMSA) 1978 and Section 402 of Navajo Nation’s Business Activity Tax Statute, it is Contractor’s responsibility to ensure that all applicable New Mexico Gross Receipts Tax and Navajo Nation Gross Receipts Tax are included in their price proposal.
(f) In accordance with FAR 52.232-5 (Payments under Fixed-Price Construction Contracts) (b)(2), payment may be approved for materials delivered to Contractor at locations other than the site if Contractor obtains CO approval prior to making arrangements for obtaining the materials. Contractor shall also be required to complete a “Materials on Hand Certificate” which will certify:
(1) Materials described for use on identified contract.
(2) Materials are clearly marked to identify that they belong to contract cited.
(3) Full title for those materials vested in Prime Contractor sited.
(4) Materials are free of liens and encumbrances.
(5) Materials are properly stored, secured, and protected against loss or damage.
B - 2
PRICE SCHEDULE 1 (Reach 2)
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
1-1 WBR
1452.232-
Mobilization and Preparatory Work
For the lump sum of $
1-2 01 31 30 Contract Document Management System (CDMS)
For the lump sum of $
1-3 01 51 00 Construction Water Reach 2 9 Months $ $
1-4 01 56 15 Utility Crossing Investigations Reach 2
For the lump sum of $
1-5 01 78 30 As-built Drawings Reach 2 For the lump sum of $75,000
1-6 01 78 30 Final Drawings Reach 2 For the lump sum of $30,000
1-7 31 02 10 Water for Dust Abatement Reach 2
10,500 M (1,000) Gal
1-8 33 05 22 Shumway Arroyo Pilot Bore 2,000 lin ft $ $
1-9 33 05 22 Shumway Arroyo Horizonal Directional Drilling (HDD)
2,000 lin ft $ $
1-10 33 05 22 Shumway Arroyo Conductor Casing
290 lin ft $ $
1-11 33 05 22 San Juan River Pilot Bore 2,400 lin ft $ $
1-12 33 05 22 San Juan River Horizontal Direction Drilling (HDD)
2,400 lin ft $ $
1-13 33 05 22 San Juan River Conductor Casing (required)
310 lin ft $ $
1-14 33 05 22 Nenahnezad Bluff Pilot Bore 3,294 lin ft $ $
1-15 33 05 22 Nenahnezad Bluff Horizontal Directional Drilling (HDD)
3,294 lin ft $ $
1-16 33 05 22 Nenahnezad Bluff Conductor Casing (required)
120 70 lin ft $ $
TOTAL FOR PRICE SCHEDULE 1 (Reach 2) $_________________
B - 3
PRICE SCHEDULE 2 (Reach 3)
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
2-1 WBR
1452.232-
Mobilization and Preparatory Work
For the lump sum of $
2-2 01 51 00 Construction Water Reach 3 3 Months $ $
2-3 01 56 15 Utility Crossing Investigations Reach 3
For the lump sum of $
2-4 01 78 30 As-Built Drawings Reach 3 For the lump sum of $25,000
2-5 01 78 30 Final Drawings Reach 3 For the lump sum of $10,000
2-6 31 02 10 Water for Dust Abatement Reach 3
6,000 M (1,000) gal
2-7 33 05 22 Chaco River Pilot Bore 2,080 lin ft $ $
2-8 33 05 22 Chaco River Horizontal Directional Drilling (HDD)
2,080 lin ft $ $
2-9 33 05 22 Chaco River Conductor Casing
150 lin ft $ $
2-10 33 05 22 Chaco River Access Roads 29,300 lin ft $ $
TOTAL FOR PRICE SCHEDULE 2 (Reach 3) $_________________
END OF SUPPLIES OR SERVICES AND PRICES
B - 4
This page intentionally left blank.
Revised Coatings
09 96 20 - 1
SECTION 09 96 20
COATINGS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. ASTM International (ASTM)
1. ASTM A380-25 Cleaning, Descaling, Pickling and
Passivation of Stainless Steel Parts, Equipment, and Systems
2. ASTM C920-18(2024) Elastomeric Joint Sealants
3. ASTM D870-15(2020)e1 Testing Water Resistance of Coatings Using
Water Immersion
4. ASTM D2794-93(2024) Resistance of Organic Coatings to the
Effects of Rapid Deformation (Impact)
5. ASTM D3276-21 Guide for Painting Inspectors (Metal
Substrates)
6. ASTM D4060-25 Abrasion Resistance of Organic Coatings by the Taber Abraser
7. ASTM D4214-23 Evaluating the Degree of Chalking of
Exterior Paint Films
8. ASTM D4285-24 Indicating Oil or Water in Compressed Air
9. ASTM D4541-22 Pull-Off Strength of Coatings Using
Portable Adhesion Testers
10. ASTM G8-96(2019) Cathodic Disbonding of Coated Steel
B. American Water Works Associations (AWWA)
1. AWWA C 213-22 Fusion-Bonded Epoxy Coatings and Linings
For Steel Water Pipe and Fittings
2. AWWA C 216-22 Heat-Shrinkable Cross-Linked Polyolefin
Coatings For Steel Water Pipe and Fittings
09 96 20 - 2
C. International Organization for Standardization (ISO)
1. ISO 8502-3:2017 Assessment of dust on Steel Surface
Prepared for Painting (Pressure-Sensitive Tape Method)
D. The Society for Protective Coatings (SSPC)/NACE International (NACE)
1. SSPC-AB1-19 Mineral and Slag Abrasives
2. SSPC-AB2-16 Cleanliness of Recycled Ferrous Metallic
Abrasives
3. SSPC-AB3-17 Newly Manufactured or Re-Manufactured
Steel Abrasives
4. SSPC-Guide 15-20 Field Methods for Retrieval and Analysis of
Soluble Salts on Substrates and Other Nonporous Substrates
5. SSPC-PA1-16 Shop, Field, and Maintenance Painting of Steel
6. SSPC-PA2-22 Measurement of Dry Paint Thickness with Magnetic Gages
7. SSPC-QP1-19 Evaluating Painting Contractors (Field Application to Complex Industrial Structures)
8. SSPC-QP2-19 Evaluating Painting Contractors (Field Removal of Hazardous Coatings From Complex Industrial Structures)
9. SSPC-QP3-10/AISC 420 Evaluating the Qualification of Shop Painting Contractors
10. SSPC-SP1-16 Solvent Cleaning
11. SSPC-SP2-24 Hand Tool Cleaning
12. SSPC-SP3-24 Power Tool Cleaning
13. SSPC-SP5/NACE 1-07 White Metal Blast Cleaning
14. SSPC-SP10/NACE 2-24 Near-White Blast Cleaning
15. SSPC-SP11-20 Power Tool Cleaning to Bare Metal, Level 3 minimum requirement
16. SSPC-VIS1-12 Guide and Reference Photographs for Steel
Surfaces Prepared by Abrasive Blast Cleaning
17. SSPC-VIS3-07 Visual Standard for Power- and Hand-Tool Cleaned Steel
09 96 20 - 3
18. SSPC-VIS4/NACE-VIS7-01 Guide and Reference Photographs for Steel Surfaces Prepared by Waterjetting
19. SSPC-VIS5/NACE VIS9-01 Guide and Reference Photographs for Steel Surfaces Prepared by Wet Abrasive Blast Cleaning
20. SSPC Paint Manual Volume 1, Good Painting Practices, Fourth Edition 2002
21. NACE SP 0188-24 Discontinuity (Holiday) Testing of New Protective Coatings on Conductive Substrates
22. NACE SP 0274-11 High Voltage Electrical Inspection of Pipeline Coatings
23. NACE SP 0287-16 Field Measurement of Surface Profile of Abrasive Blast Cleaned Steel Surfaces Using a Replica Tape
24. NACE SP 0297-12 Maintenance Painting of Electrical Substation Apparatus Inducing Flow Coating of Transformer Radiators
25. NACE RP 0288-11 Recommended Practices for Inspection of Linings on Steel and Concrete.
26. NACE SP 0178-07 Detail, Finish, and Design Considerations for Immersion Service.
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 09 96 20-1, Approval Data:
1. For each coating material:
a. Manufacturer’s product data, application, and Safety Data Sheets (SDS) sheets.
b. Identification of “Items to be coated” including sub-letter and sub-number listed in Coating Tabulations.
2. For each caulk and filler:
a. Manufacturer’s product data, application, and SDS sheets.
b. Identification of areas of use including sub-letter and sub-number listed in
Coating Tabulations.
3. For each substituted coating material “equal” to specified product in Coating
Tabulation:
a. List of not less than 5 similar successful material applications:
09 96 20 - 4
1) Project name, location, type of structure, and application dates.
2) Owner’s name, address, and telephone number.
b. Certification that material meets or exceeds specified requirements:
1) Manufacturer’s certification including technical representative’s signature and date of signature.
2) Independent laboratory’s certified test reports.
C. RSN 09 96 20-2, Final Approval Data:
1. For each coating material:
a. Purchase orders including order number, date, manufacturer’s designated product name, batch number(s), and quantity purchased.
b. Supplier’s name, address, and phone number.
D. RSN 09 96 20-3, Qualifications:
1. Coating Contractor:
a. Current AMPP -QP1 or AMPP-QP3 certifications.
b. List not less than 5 comparable completed jobs for each coating type including owner’s name, address, and telephone numbers completed within the last five years.
2. Coating Applicators:
a. List of not less than 5 comparable jobs for each coating type including owner’s name, address, and telephone number.
b. Provide one of the options below indicating personnel are qualified with relevant knowledge of surface preparation, coating materials, mixing, thinning and application practices:
1) Statement from contractor.
2) Statement from coating or equipment supplier.
3. Coating inspector:
a. Current Level 2 certification for NACE/AMPP Certified Coatings
Inspector (CIP) or SSPC Protective Coatings Inspector (PCI).
b. List of not less than 5 years of comparable jobs including project description, location, and owner’s name, address, and telephone number
E. RSN 09 96 20-4, Quality Control Plan:
1. Quality Control Manager:
a. Name and title.
2. Quality Control Procedure:
09 96 20 - 5
a. Quality control plan.
1) Factory, shop, or field testing procedures shall be in accordance with these specifications, product manufacturer’s written instructions, and NACE RP 0288, and ASTM D3276.
b. Procedure for addressing identified non-conformities.
F. RSN 09 96 20-5, Contractor Quality Testing Report:
1. Comprehensive report of daily quality control test reports.
1.04 DELIVERY, STORAGE, HANDLING
A. Deliver materials to jobsite in original, undamaged, unopened containers labeled with manufacturer’s name, designated product name, batch number, date of manufacture, and any special instructions.
B. Deliver materials in containers not larger than 5 gallons as packaged by manufacturer unless suitable equipment is provided at jobsite to handle and thoroughly mix materials in larger containers.
C. Store coating materials and thinners in accordance with the manufacturer's recommendations, and as a minimum, store off the ground, under cover, and at 50- to 95-degrees Fahrenheit (F).
D. Do not use coating material which has exceeded manufacturer’s specified storage stability period (shelf life).
1.05 AMBIENT CONDITIONS
A. Maintain environmental conditions to meet coating manufacturer’s requirements during surface preparation, coating application, and curing period. Provide heating or cooling, and dehumidification as needed. Complete curing before placing the coating systems into service.
B. Coatings shall be applied when the substrate surface temperature is 5 degrees F or more above the dew point temperature and for at least 8 hours after application.
1.06 PROJECT CONDITIONS
A. Galvanic isolation of dissimilar metals shall be required. Coatings in this specification section shall not serve as the primary galvanic isolation.
B. Contractor shall comply with applicable Federal, State, and local air pollution and environmental control regulations for surface preparations, blast cleaning, disposal of spent materials and debris, and coatings application.
09 96 20 - 6
PART 2 PRODUCTS
2.01 EQUIPMENT
A. Surface preparation and spray application equipment:
1. Sized in accordance with coating manufacturer’s recommendations.
2. Provide:
a. Pressure gauges and pressure regulators.
b. Air supply lines free from oil and moisture.
2.02 ABRASIVES
A. Mineral and slag abrasives: Meets SSPC-AB1, type I (natural minerals) and type II (slags), class A.
B. SSPC-AB2 for recycled cleanliness.
C. SSPC-AB3 Class I (steel) or II (iron) for angular shaped grit. Shot abrasives are not acceptable.
D. Commercially available products or processes to render the hazardous waste stream non-hazardous and not exceeding toxicity threshold limits.
1. Additive stabilizers for leachable toxic metal wastes are allowed, except elemental iron is not permitted.
2.03 COATINGS
A. Specified in Coating Tabulations:
1. Apply only one coating system per option in Coating Tabulations.
2. Apply compatible products of same manufacturer for coating system components.
B. Volatile Organic Compounds (VOC): Do not exceed maximum permitted by Federal, State, and local air pollution control regulations as supplied in container or by addition of thinner material.
C. Factory color or tint only. Do not color or tint at jobsite.
D. Use manufacturer’s recommended thinners for coating materials.
E. Do not use accelerator products unless approved by COR.
2.04 FILLERS AND CAULKS
A. Caulks:
1. Coating manufacturer’s standard or compatible caulk material.
09 96 20 - 7
2. Polyurethane, silicone, or silicone acrylic caulk material: Meets or exceeds ASTM C920 type S or M, grade NS, class 25, suitable for water immersion service.
B. Fillers:
1. Apply compatible products of same manufacturer as coating system components.
2. Approved fillers:
a. Carboguard 501, as manufactured by Carboline, www.carboline.com.
3. Provide one of the above fillers, or equal with following essential characteristics:
a. Coating manufacturer’s standard filler material.
b. Approved use by manufacturer.
2.05 MISCELLANEOUS MATERIALS
A. Deionized Water.
B. Chlor-Rid as manufactured by Chlor-Rid, www.Chlorid.com, C. HoldTight 102 as manufactured by Holdtight Solutions, www.holdtight.com, D. Chlor-Gone, as manufactured by Aquron, https://aquron.com/
E. Provide one of the above salt removers, or equal with following essential characteristics:
1. Commercially available additive for soluble salt removal.
2. Water soluble.
3. Biodegradable.
4. Zero volatile organic compounds.
PART 3 EXECUTION
3.01 SHOP PAINTING
A. Shop coated and lined equipment shall be primed and finished in the shop and touched up in the field with identical coating materials after installation and in accordance with the coating’s manufacturers standard surface preparation and application instructions.
3.02 FIELD PAINTING
A. Follow specified information in the Coating Tabulations and/or coating manufacturer’s standard surface preparations and application instructions for field applied coatings.
3.03 GALVANIC AND DIELECTRIC ISOLATION
A. Galvanic isolation of dissimilar metals shall be required.
http://www.holdtight.com/ https://aquron.com/
09 96 20 - 8
B. Coatings shall not serve as the primary galvanic isolation.
3.04 PROTECTION OF ADJACENT SURFACES
A. Remove, mask, or otherwise protect items or surfaces not coated from contamination and damage during cleaning and coating operations.
B. Examples include protecting mating and machined surfaces, mechanical and electrical equipment (open or enclosed), instruction and similar plates, and wet and newly coated surfaces.
3.05 SURFACE PREPARATION
A. Remove or repair surface irregularities and impart profile as specified:
1. Welds:
a. Welds: Smooth and continuous.
b. Weld spatter, protrusions, laminations, slag, buckshot, and slivers.
Remove and grind smooth in accordance with NACE SP 0178.
c. Undercuts and porosity: Fill with weld material and grind smooth in accordance with NACE-SP 0178.
d. Projections, sharp edges, high points, fillets, and corners: Grind smooth to a radius of at least 1/16-inch.
2. Substrate defects:
a. Pitting, gouges, scratches, porosity, and similar:
1) Grind smooth.
2) Defects exceeding 20-percent reduction in wall thickness require weld repairs.
3. Grind full length of edges and corners smooth to a radius of at least 1/16-inch.
B. Surface preparation method:
1. See Coating Tabulations.
2. Compare prepared steel surfaces to following visual reference photographs for allowable visible contaminants and stains:
a. SSPC-VIS1 for abrasive blast cleaning.
b. SSPC-VIS3 for power and hand tool cleaning.
3. Assessment of dust contaminants:
a. Perform clear tape test method in accordance with ISO 8502-3.
b. Perform three tests per shift.
c. Acceptance Criteria: Degree of cleanliness shall meet Class 3.
09 96 20 - 9
C. Surface profile:
1. Prepare as specified in Coating Tabulations.
2. Where not specified, prepare in accordance with manufacturer’s instructions for metallic substrates or existing coating surfaces and service environment.
3. Where manufacturer’s instructions do not specify a surface profile, prepare blasted surfaces to following profile:
a. Atmospheric Service Environments: 1-mil or greater angular profile and less than specified millage of first applied coat.
b. Burial and Immersion Service Environments: Angular profile 2-mil or greater and less than specified millage of first applied coat.
4. Inspect surface profile in accordance with NACE SP 0287:
a. Use replica tape suitable for surface profile depth range.
b. Perform at least two tests per 1,000-square feet.
D. Soluble salts:
1. Measure concentration of chlorides, nitrates and sulfates in accordance with SSPC
Guide 15.
2. Perform at least two tests per 1,000-square feet of surface area. Include corrosion pit areas.
3. Acceptance criteria: Do not exceed 3-micrograms per square centimeter for chlorides and 5-micrograms per square centimeter for nitrates and sulfates.
E. Re-clean or perform additional surface preparation of contaminated surfaces before coating application.
3.06 COMPRESSED AIR EQUIPMENT
A. Keep air compressor and spray application equipment lines free of oil and moisture during work.
B. Compressed air quality:
1. Perform tests in accordance with ASTM D4285.
2. Perform test at the beginning of shift.
3.07 FILLERS AND CAULK APPLICATION
A. Caulk areas including crevices, gaps, plate seams, skip welds, and conduit penetrations.
B. Apply in a uniform texture, neatness, and color matched appearance.
C. Apply in accordance with manufacturer’s instructions and achieve tight bond to substrate or previous coats.
09 96 20 - 10
3.08 COATING APPLICATION
A. Coating shall be done in a workmanlike manner to produce an even film of uniform thickness. The finished surfaces shall be free from runs, drops, ridges, waves, laps, sags, curtains, brush marks, and variations in color, texture, and finish.
B. Shop coated and lined equipment shall be primed and finished in the shop and touched up in the field with identical coating materials after installation and in accordance with the coating manufacturer’s application instructions.
C. Follow specified systems in the Coating Tabulations and coating manufacturer’s application instructions for applied coatings. In event of a conflict, the more stringent requirement shall apply.
D. Stripe coat:
1. Brush apply stripe coat to each coat applied.
2. Apply stripe coat prior to spray application of the primer, when practical.
3. Apply to edges, corners, interior angles, pits, plate seams, crevices, rivets, nuts, threads, bolts, washers, welds, and similar features.
E. Apply number of coats and coating thickness specified in Coating Tabulations.
1. Alternate coat colors to differentiate between coats.
2. Apply in accordance with manufacturer’s instructions.
3. Apply in accordance with SSPC PA1.
F. Prevent overspray or dry spray. When such conditions occur, clean surfaces prior to application of subsequent coats.
G. Re-clean contaminated surfaces between coats.
H. Dry Film Thickness (DFT):
1. After each coat, inspect hardened coating system for DFT compliance in accordance with SSPC PA2.
2. Acceptance Criteria no single spot measurement less than 80 percent minimum or
120 percent maximum specified.
I. Discontinuity (Holiday) Testing:
1. Inspect in accordance with NACE SP 0188:
a. Use maximum test voltage for DFT as recommended by coating manufacturer to prevent coating damage.
2. Inspect pipeline coatings in accordance with NACE SP 0274:
09 96 20 - 11
a. Use maximum test voltage for any DFT as recommended by coating manufacturer to prevent coating damage.
J. Coating Adhesion:
1. Test in accordance with ASTM D4541 at the direction of the COR.
3.09 CONTRACTOR FIELD QUALITY TESTING
A. Inspection Equipment:
1. Calibrate inspection devices and equipment in accordance with the manufacturer’s instructions.
2. Verify calibration prior to every use.
B. Qualified personnel shall conduct tests and sign reports.
1. Perform tests in presence of the OGR:
2. Provide rigging for OGR to observe inspections.
C. Make daily reports for review by the COR, including:
1. Date of work.
2. Description of areas and work performed.
3. Environmental conditions.
4. Results from the following quality control tests:
a. Soluble salt.
b. Surface profile.
c. Visual comparison of prepared surfaces.
d. Assessment of dust contaminants.
e. Compressed air quality.
f. Dry film thickness (DFT).
g. Discontinuity (Holiday) testing.
h. Coating adhesion testing (when directed by the COR).
D. Final inspection will take place after repairs, but before placing into service.
3.10 REPAIR AND REMEDIAL WORK
A. Repair defective or damaged areas of coatings in accordance with coating manufacturer’s recommendations.
09 96 20 - 12
3.11 COATING TABULATIONS
Tabulation No. 01
Items to be coated – Ferrous pipe surfaces subjected to horizontal directional drilling:
a. Exterior surface of ferrous pipe used for HDD.
Notes:
1. Use compatible girth weld liquid applied coating.
2. Follow manufacturer’s surface preparation and application instructions for coating repairs.
Material - Option 1
Two Coat Fusion Bonded Epoxy System
Number and thickness of coats Surface preparation method
3M Scotchkote:
Base Coat of FBE, Scotchkote 6233 or 226.
Topcoat of FBE, Scotchkote 6352.
Axalta:
Base Coat of FBE, Nap- Gard 7-2500.
Topcoat of FBE, Nap-Guard 7-2610
Color and gloss:
manufacturer’s standard color
1 coat of FBE protective base coat apply at 8 to 16 mils DFT.
1 coat of FBE abrasion resistant topcoat apply at 15 to 35 mils
DFT
Total system excluding stripe coats:
23-mil DFT, minimum 51-mil DFT, maximum
SSPC SP-1 followed by:
For steel:
SSPC-SP5/NACE 1 or
SP10/NACE 2
2.5 to 4 mil surface profile
Follow manufacturer’s surface preparation and application instructions to apply subsequent coats.
Materials - Option 2 Fusion Bonded Epoxy/ Epoxy
ARO
Number and thickness of coats Surface preparation method
Denso:
Base Coat of FBE – Topcoat of ARO, Protal
ARO
1 coat of FBE protective base coat apply at 8 to 16 mils DFT.
1 coat of ARO abrasion resistant topcoat apply at 30 to 60 mils DFT.
Total system excluding stripe coats:
38-mil DFT, minimum 76-mil DFT, maximum
SP10/NACE 2
2.5 to 4 mil surface profile
Follow manufacturer’s surface preparation and application instructions to apply subsequent coats.
Materials - Option 3 Epoxy/ Epoxy ARO
Number and thickness of coats Surface preparation method
Barry CPGSeal For Life: 1 or more base coats apply 30- 40 mils DFT.
09 96 20 - 13
Base Coat - Powercrete R60 Topcoat - Powercrete DD
Carboline:
Base Coat - SP-2888 RG Topcoat - SP-2888 RG
Denso:
Base coat - Protal 7200 Topcoat - Protal ARO
1 or more abrasion resistant coats apply 30-60 mils DFT
Total system excluding stripe coats:
60 mils DFT, minimum 100 mils DFT, maximum
For steel:
SSPC-SP5/NACE 1 or
SP10/NACE 2
2.5 to 4 mil surface profile
Follow manufacturer’s surface preparation and application instructions to apply subsequent coats
Tab BE-02B.DOCX
09 96 20 - 14
Tabulation No. 02 Items to be coated - Shop or field applied interior linings for immersion exposure:
a. Interior surface of ferrous pipe used for HDD Notes:
1. Use compatible girth weld liquid applied coating.
2. Follow manufacturer’s surface preparation and application instructions for coating repairs.
LINING OPTIONS
OPTION 1 – Fusion Bonded Epoxy in accordance with either AWWA C213 interior and exterior of steel pipe and/or fittings or AWWA C116 interior and exterior of ductile iron or grey-iron pipe and/or fittings.
OPTION 2 - 100% Solids Epoxy
Number and thickness of coats
Surface preparation method
Carboline:
Plasite 4500 S
Duromar:
HPL-2510
International Paint:
Enviroline 230
Raven Linings:
AquataPoxy A6
Sherwin Williams:
Sherplate PW Epoxy or Dura-plate UHS
Tnemec:
Series 22 Epoxoline or Series Epoxoline FC
Color and gloss:
manufacturer’s standard color and gloss
1 or more base coats apply at 20 to 40 mils DFT per coat, plus stripe coats.
Total base coat system:
20-mil DFT, minimum 40-mil DFT, maximum
2.5-4 mil surface profile
Follow manufacturer’s surface preparation and application instructions to apply subsequent coats
OPTION 3 - Epoxy Number and thickness of coats
Surface preparation method
09 96 20 - 15
Carboline:
Carboguard 891
PPG:
Amerlock 2 or 400 or Amercoat 235
Sherwin Williams:
Duraplate 235
Tnemec:
Epoxoline Series N69 or V69
Color and gloss: see color schedule
3 or more base coats, apply at 4 to 8 mils DFT per coat, plus stripe coats.
Total base coat system excluding stripe coats:
12-mil DFT, minimum 24-mil DFT, maximum
Follow manufacturer’s surface preparation and application instructions to apply subsequent coats
PERFORMANCE REQUIREMENTS
Testing Protocol Acceptance Criteria Fresh/deionized water immersion test, ASTM D870:
passes, 2 years test with water at ambient temperature, no blisters on scribed or unscribed sides.
Dilute Harrison immersion test, Modified
ASTM D870:
passes, 2 years test with water at ambient temperature, no blisters on scribed or unscribed sides.
Abrasion resistance, ASTM D4060, CS-17 wheel, 1,000 cycles, 1-kg load:
Epoxy: 100 milligram loss or less
Direct impact, ASTM D2794: 30 inch-pounds Pulloff adhesion, ASTM D4541, annex A2, type II tester:
1000 psi or greater
Cyclic testing salt fog/UV, ASTM D5894: 1/4 inch or less undercutting at 3000 hrs Cathodic disbondment, ASTM G8: 1/4 inch or less disbondment 120-day test Tab IE-01.DOCX
Tabulation No. 03
Items to be coated – Ferrous pipe surfaces subjected to horizontal directional drilling:
a. Exterior surface of ferrous HDD pipe at mid-pull weld.
Notes:
1. Follow manufacturer’s surface preparation and application instructions for coating repairs.
Materials - Option 3 Epoxy/ Epoxy ARO
Number and thickness of coats Surface preparation method
Denso:
Protal 7125
1 or more coats apply 20-40 mils DFT.
09 96 20 - 16
Seal For Life:
Powercrete DD 410
Total system:
30 mils DFT, minimum 40 mils DFT, maximum
SSPC-SP/NACE 1 or
SP10/NACE 2
2.5 to 4 mil surface profile
Follow manufacturer’s surface preparation and application instructions to apply subsequent coats
Tab BE-02B.DOCX
Tabulation No. 04 Items to be coated - Shop or field applied interior linings for immersion exposure:
a. Interior surface of ferrous HDD pipe at mid-pull weld.
Notes:
1. Can be applied after pipe has been installed.
2. Follow manufacturer’s surface preparation and application instructions for coating repairs.
LINING OPTIONS
09 96 20 - 17
OPTION 1 - 100% Solids Epoxy
Number and thickness of coats
Surface preparation method
Carboline:
Plasite 4500 S
Duromar:
HPL-2510
International Paint:
Enviroline 230
Raven Linings:
AquataPoxy A6
Sherwin Williams:
Sherplate PW Epoxy or Dura-plate UHS
Tnemec:
Series 22 Epoxoline or Series Epoxoline FC
Color and gloss:
manufacturer’s standard color and gloss
1 or more coats apply at 20 to 40 mils DFT per coat, plus stripe coats.
Total base coat system:
20-mil DFT, minimum 40-mil DFT, maximum
SSPC-SP10/NACE 2 or
SP10/NACE 2
Or
SSPC-SP-11
When abrasive blasting not practical surface preparation and application instructions to apply subsequent coats
OPTION 2 - Epoxy Number and thickness of coats
Surface preparation method
09 96 20 - 18
Carboline:
Carboguard 891
PPG:
Amerlock 2 or 400 or Amercoat 235
Sherwin Williams:
Duraplate 235
Tnemec:
Epoxoline Series N69 or V69
Color and gloss: see color schedule
2 or more coats, apply at 5 to 8 mils DFT per coat.
Total system:
10-mil DFT, minimum 16-mil DFT, maximum
SP10/NACE 2
Or
SSPC-SP-11
surface preparation and application instructions to apply subsequent coats
OPTION 3 – Surface Tolerant Epoxy
Number and thickness of coats
Surface preparation method
Sherwin Williams:
Epoxy Mastic II
International:
Interzone 954
PPG:
Sigmashield 880 ALU
1 or more coats in accordance with manufacturer standards.
Total system:
12-mils DFT, minimum 20-mils DFT, maximum
SP10/NACE 2
Or
SSPC-SP-11
surface preparation and application instructions to apply subsequent coats
09 96 20 - 19
PERFORMANCE REQUIREMENTS
Testing Protocol Acceptance Criteria Fresh/deionized water immersion test, ASTM D870:
passes, 2 years test with water at ambient temperature, no blisters on scribed or unscribed sides.
Dilute Harrison immersion test, Modified
ASTM D870:
passes, 2 years test with water at ambient temperature, no blisters on scribed or unscribed sides.
Abrasion resistance, ASTM D4060, CS-17 wheel, 1,000 cycles, 1-kg load:
Epoxy: 100 milligram loss or less
Direct impact, ASTM D2794: 30 inch-pounds Pulloff adhesion, ASTM D4541, annex A2, type II tester:
1000 psi or greater
Cyclic testing salt fog/UV, ASTM D5894: 1/4 inch or less undercutting at 3000 hrs Cathodic disbondment, ASTM G8: 1/4 inch or less disbondment 120-day test Tab IE-01.DOCX
09 96 20 - 20
3.12 COLOR SCHEDULE
A. Colors and glosses of finished coats:
1. To be selected and approved by OGR.
END OF SECTION
Revised Horizontal Directional Drilling 33 05 22 - 1
SECTION 33 05 22
HORIZONTAL DIRECTIONAL DRILLING (HDD)
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Shumway Arroyo Pilot Bore:
1. Measurement: Horizontally along pipe centerline, without allowance for slope, between ends of pipe in place.
1. Payment: Linear foot prices offered in the Price Schedule 1 (Reach 2).
a. Contractor to select plastic or steel pipe. Linear foot price depends on selected pipe material.
B. Shumway Arroyo Horizontal Directional Drilling (HDD):
1. Measurement: Horizontally along pipe centerline, without allowance for slope, between ends of pipe in place.
2. Payment: Linear foot prices offered in the Price Schedule 1 (Reach 2):
a. Includes:
1) Preparation of drilling site (entry/exit points) and pullback areas, topsoil segregation, grading, filling, annular backfill, gravel, geofabric, final grading, inspection, clean-up, and restoration of construction site.
2) Mobilization and demobilization of HDD drilling and support equipment.
3) Hole reaming, cleaning, and completing the drilled hole to specified diameter.
4) Hauling and disposal of drilling fluid, byproducts, and cuttings.
5) Furnishing specified HDD Pipe (product pipe).
6) Contractor to select plastic or steel pipe. Linear foot price depends on selected pipe material.
7) Pre- and post-pullback testing of pipe.
8) Costs for providing:
a) Sacrificial length of HDD pipe at each end that shall be long enough to prevent settlement and strain recovery effects of HDD Pipe from retracting pipe ends below ground surface.
b) Design and fabrication of shielded bundled pulling head.
33 05 22 - 2
c) Two temporary end caps or blind flanges, one at each end, of HDD Pipe to prevent contamination or other debris from entering HDD Pipe before connection to Line Pipe (by others).
9) Pipe that is damaged beyond repair during installation, as determined by OGR, or is not retrieved from an unsuccessful pullback installation, is at expense of Contractor.
b. Does not include:
a) Pilot bore drilling at the site.
b) Conductor casing and installation.
c) Water needed for filling and testing pipe. See Section 01 51 00 –
Temporary Utilities, for measurement and payment of water for construction.
C. Shumway Arroyo Conductor Casing:
1. Measurement: Installed length along pilot bore.
2. Payment: Linear foot prices offered in the Price Schedule 1 (Reach 2).
D. San Juan River Pilot Bore:
1. Measurement: Horizontally along pipe centerline, without allowance for slope, between ends of pipe in place.
2. Payment: Linear foot prices offered in the Price Schedule 1 (Reach 2).
E. San Juan River Horizontal Directional Drilling (HDD):
1. Measurement: Horizontally along pipe centerline, without allowance for slope, between ends of pipe in place.
2. Payment: Linear foot prices offered in the Price Schedule 1 (Reach 2):
a. Includes:
1) Preparation of drilling site (entry/exit points) and pullback areas, topsoil segregation, grading/filling, annular backfill, gravel, geofabric, final grading, inspection, clean-up, restoration of construction site.
2) Mobilization and demobilization of HDD drilling and support equipment.
3) Hole reaming, cleaning and completing the drilled hole to specified diameter.
4) Hauling and disposal of drilling fluid, byproducts, and cuttings.
5) Furnishing specified HDD Pipe (product pipe).
6) Pre- and post-pullback testing of pipe.
7) Costs for providing:
33 05 22 - 3
a) Sacrificial length of HDD pipe at each end that shall be long enough to prevent settlement, and strain recovery effects of HDD Pipe from retracting pipe ends below ground surface.
b) Design and fabrication of shielded bundled pulling head.
c) Two temporary end caps or blind flanges, one at each end, of HDD
Pipe to prevent contamination or other debris from entering HDD Pipe before connection to Line Pipe (by others).
8) Pipe that is damaged beyond repair during installation, as determined by OGR, or is not retrieved from an unsuccessful pullback installation, is at expense of Contractor.
b. Does not include:
1) Pilot bore drilling at the site.
2) Conductor casing and installation.
3) Water needed for filling and testing pipe. See Section 01 51 00 –
Temporary Utilities, for measurement and payment of water for construction.
F. San Juan River Conductor Casing:
1. Measurement: Installed length along pilot bore.
2. Payment: Linear foot prices offered in the Price Schedule 1 (Reach 2).
G. Nenahnezad Bluff Pilot Bore:
1. Measurement: Horizontally along pipe centerline, without allowance for slope, between ends of pipe in place.
2. Payment: Linear foot prices offered in the Price Schedule 1 (Reach 2).
H. Nenahnezad Bluff Horizontal Directional Drilling (HDD):
1. Measurement: Horizontally along pipe centerline, without allowance for slope, between ends of pipe in place.
2. Payment: Linear foot prices offered in the Price Schedule 1 (Reach 2):
a. Includes:
1) Preparation of drilling site (entry/exit points) and pullback areas, topsoil segregation, grading/filling, annular backfill, gravel, geofabric, final grading, inspection, clean-up, restoration of construction site.
2) Mobilization and demobilization of HDD drilling and support equipment.
3) Hole reaming, cleaning, and completing the drilled hole to specified diameter.
4) Hauling and disposal of drilling fluid, byproducts, and cuttings.
33 05 22 - 4
5) Furnishing specified HDD Pipe (product pipe).
6) Pre- and post-pullback testing of pipe.
7) Costs for providing:
a) Sacrificial length of HDD pipe at each end that shall be long enough to prevent settlement and strain recovery effects of HDD Pipe from retracting pipe ends below ground surface.
b) Design and fabrication of shielded bundled pulling head.
c) Two temporary end caps or blind flanges, one at each end, of HDD
Pipe to prevent contamination or other debris from entering HDD Pipe before connection to Line Pipe (by others).
8) Pipe that is damaged beyond repair during installation, as determined by OGR, or is not retrieved from an unsuccessful pullback installation, is at expense of Contractor.
b. Does not include:
1) Pilot bore drilling at the site.
2) Conductor casing and installation.
3) Water needed for filling and testing pipe. See Section 01 51 00 –
Temporary Utilities, for measurement and payment of water for construction.
I. Nenahnezad Bluff Conductor Casing:
1. Measurement: Installed length along pilot bore.
2. Payment: Linear foot prices offered in the Price Schedule 1 (Reach 2).
J. Chaco River Pilot Bore:
1. Measurement: Horizontally along pipe centerline, without allowance for slope, between ends of pipe in place.
2. Payment: Linear foot prices offered in the Price Schedule 2 (Reach 3).
K. Chaco River Horizontal Directional Drilling (HDD):
1. Measurement: Horizontally along pipe centerline, without allowance for slope, between ends of pipe in place.
2. Payment: Linear foot prices offered in the Price Schedule 2 (Reach 3):
a. Includes:
1) Preparation of drilling site (entry/exit points) and pullback areas, excavation for entry and exit pits, topsoil segregation, grading/filling, annular backfill, gravel, geofabric, final grading, inspection, clean-up, restoration of construction site.
33 05 22 - 5
2) Mobilization and demobilization of HDD drilling and support equipment.
3) Hole reaming, cleaning, and completing the drilled hole to specified diameter.
4) Hauling and disposal of drilling fluid, byproducts, and cuttings.
5) Furnishing specified HDD Pipe (product pipe).
6) Pre- and post-pullback testing of pipe.
7) Costs for providing:
a) Sacrificial length of HDD pipe at each end that shall be long enough to prevent settlement and strain recovery effects of HDD Pipe from retracting pipe ends below ground surface.
b) Design and fabrication of shielded bundled pulling head.
c) Two temporary end caps or blind flanges, one at each end, of HDD
Pipe to prevent contamination or other debris from entering HDD Pipe before connection to Line Pipe (by others).
8) Pipe that is damaged beyond repair during installation as determined by OGR, or is not retrieved from an unsuccessful pullback installation, is at expense of Contractor.
b. Does not include:
1) Pilot bore drilling at the site.
2) Conductor casing and installation.
3) Chaco River access roads.
4) Water needed for filling and testing pipe. See Section 01 51 00 –
Temporary Utilities, for measurement and payment of water for construction.
L. Chaco River Conductor Casing:
1. Measurement: Installed length along pilot bore.
2. Payment: Linear foot prices offered in the Price Schedule 2 (Reach 3).
M. Chaco River Access Roads:
1. Measurement: Horizontally along road centerline, without allowance for slope.
2. Payment: Linear foot prices offered in the Price Schedule 2 (Reach 3).
a. Includes:
1) Stripping, clearing, and grubbing of area.
2) Repairs and maintenance to new and existing roadways.
3) Final grading, inspection, clean-up, and restoration of area.
33 05 22 - 6
1.02 DEFINITIONS
A. Horizontal Directional Drilling (HDD): Steerable trenchless technology method of installing underground utilities in a shallow recurve arc along prescribed bore path by using a surface-launched drilling rig. Consists of furnishing materials, equipment, and labor associated with installing underground utilities under obstacles such as river crossings and steep terrain. A surface-to-surface pipeline installation technique used to install pipelines or conduits along pre-determined straight and curved alignments in soil or rock formations. The installation technique is comprised of four primary stages including pilot bore drilling, reaming pass(es), swab pass, and product pipe installation. Drilling fluids, comprised of a mixture of water, bentonite, or polymers are continuously pumped into the bore during all stages to facilitate the installation process and stabilize the bore. Tracking of the drilling string is achieved using downhole wireline survey tools that may be augmented with an energized wire grid at the ground surface or by using a gyroscopic survey tool.
B. Pilot Bore: First stage of installation process whereby a guided and steerable pilot bore is drilled along a planned alignment from an entry location to an exit location.
C. Drilling Fluid/Mud: Mixture of water, bentonite, or polymers specially designed for HDD operations within the anticipated geotechnical conditions and continuously pumped through the drilling equipment to facilitate the installation process and stabilize the bore.
D. Cutting Shoe: Steel bands welded to leading edge of pipe to increase stiffness and impact loads of advancing edge of pipe. Cutting shoe may consist of both an exterior and interior band.
E. Product Pipe Installation: Stage of the installation process whereby product pipe is installed within the bore. Also noted as HDD Carrier Pipe or HDD Pipe.
F. Pipe sizes and classes: HDD Carrier Pipe is designated on plan and profile drawings by an alphanumeric symbol:
1. Symbol identifies pipe diameter, cover class and hydraulic transient head as follows:
a. First number in symbol indicates nominal diameter in inches.
b. Second number in symbol is maximum hydraulic transient head measured to centerline of pipe.
c. A symbol of 36HDD500 means pipe is 36-inches in diameter with a hydraulic transient head of 500-feet at centerline of pipe.
2. Unless specific reference is made to outside or inside diameter of pipe, pipe diameters shown on drawings and used in this section are nominal pipe diameters.
3. Pipe working class pressures as shown in Table 33 05 22A – Working Class Pressures
33 05 22 - 7
Table 33 05 22A – Working Class Pressures
HDD Crossing Designated Pipe Class Maximum Working Pressure (psi)
Shumway Arroyo (Metallic)
36HDD375 108
Shumway Arroyo (Plastic) 36HDD350 98
San Juan River (Metallic Only)
36HDD525 130
Nenahnezad Bluff (Metallic Only)
42HDD600 217
Chaco River (Metallic Only)
36HDD550 235
G. Reaming Pass: Second stage of installation process whereby a reamer is used to increase the diameter of the bore to its final diameter. This shall include multiple reaming passes/diameters if necessary.
H. Swab Pass: Third stage of installation process whereby the reamed hole is prepared for product pipe installation by making a pass through the hole with the tooling to collect residual cuttings and loose materials in the hole that may impede pipe installation. Swab pass is completed after the entire bore has been reamed to its final diameter and before product pipe installation begins.
I. Installation Load: Tensile load or force that is applied to the drill string and product pipe that is required to install the product pipe.
J. Obstruction: Object lying completely or partially within the bore path that prevents forward advancement of the drill pipe, reamer, or product pipe along the proposed alignment, after all reasonable efforts by the Contractor to advance past or around the object have failed.
K. Annular Space Grout: Grout that is injected into the annular space between the installed product pipe and the excavated bore following completion of the product pipe installation phase of the HDD installation process.
33 05 22 - 8
1.03 REFERENCE STANDARDS
A. American Petroleum Institute (API)
1. API RP 13B-1 Field Testing Water-based Drilling Fluids
2. API RP 7G-2 Inspection and Classification of Used Drill Stem
Elements, Second Edition
B. ASTM International (ASTM)
1. ASTM A139/A139M-22 Electric-Fusion (Arc) – Welded Steel Pipe (NPS 4 and Over)
2. ASTM D2241-24 Poly (Vinyl Chloride) (PVC) Plastic Pipe (SDR-
PR).
3. ASTM F1962-25 Use of Maxi-Horizontal Directional Drilling for
Placement of Polyethylene Pipe or Conduit Under Obstacles, Including River Crossings
4. ASTM F2160-22a Solid Wall High Density Polyethylene (HDPE) Conduit Based on Controlled Outside Diameter
5. ASTM F2164-21 Field Leak Testing of Polyethylene (PE) and Crosslinked Polyethylene (PEX) Pressure Piping Systems Using Hydrostatic Pressure
6. ASTM F2620-24 Heat Fusion Joining of Polyethylene Pipe and Fittings
7. ASTM E165 Liquid Penetrant Testing for General Industry
8. ASTM D2513-24 Polyethylene (PE) Gas Pressure Pipe, Tubbing, and
Fittings
9. ASTM F2634-15(2021) Laboratory Testing of Polyethylene (PE) Butt
Fusion Joints using Tensile-Impact Method
10. ASTM E18-24 Rockwell Hardness of Metallic Materials
11. ASTM A519/A519M-24a Seamless Carbon and Alloy Steel Mechanical
Tubing
12. ASTM D3350-24 Polyethylene Plastics Pipe and Fittings Materials
13. ASTM D1784-20 Rigid Poly (Vinyl Chloride) (PVC) Compounds and
Chlorinated Poly (Vinyl Chloride) (CPVC) Compounds
14. ASTM E2700-20 Contact Ultrasonic Testing of Welds Using Phased Arrays
C. American Welding Society, Inc. (AWS)
33 05 22 - 9
1. AWS D1.1/D1.1M-25 Structural Welding Code – Steel
D. American Water Works Association (AWWA):
1. AWWA C110-21 Ductile-Iron and Gray-Iron Fittings for Water
2. AWWA C151/A21.51-23 Ductile-Iron Pipe, Centrifugally Cast, for Water or
Other Liquids
3. AWWA C206-23 Field Welding of Steel Water Pipe
4. AWWA C900-16 Polyvinyl Chloride (PVC) Pressure Pipe and
Fabricated Fitting, 4-In through 60-In.
5. AWWA C906-21 Polyethylene (PE) Pressure Pipe and Fittings, 4-In.
through 65-In. (100 mm through 1,6500 mm), for Waterworks
6. AWWA M11 Steel Pipe: A Guide for Design and Installation, Fifth Edition
7. AWWA C605-21 Underground Installation of Polyvinyl Chloride (PVC) and Molecularly Oriented Polyvinyl Chloride (PVCO) Pressure Pipe and Fittings
8. AWWA C600-23 Installation of Ductile-Iron Mains and Their Appurtenances
9. AWWA C604 Installation of Buried Steel Water Pipe – 4 In. (100 Mm) And Larger
E. International Organization for Standardization
1. ISO 9001:2015 Quality Management Systems - Requirements
F. North American Society for Trenchless Technology (NASTT)
1. ISBN 978-1-928984-10-8 HDD Good Practices Guidelines, 5th Ed. 2024
G. National Sanitation Foundation (NSF)
1. NSF/ANSI 61-16 Drinking Water System Components – Health
Effects
H. Pipeline Research Council International
1. PR-277-144507-Z01 Installation of Pipelines by Horizontal
Directional Drilling, “An Engineering Design Guide” (2015).
I. Plastic Pipe Institute
1. Handbook of Polyethylene Pipe 2nd Edition, Chapter 12, Horizontal
Directional Drilling
33 05 22 - 10
2. TR-33-2012 Generic Butt Fusion Joint Procedure for Field Joint of Polyethylene Pipe
1.04 REQUIREMENTS
A. Furnish labor, equipment, supplies and materials necessary to use horizontal directional drilling (HDD) construction practices to install water pipeline crossings as shown on the drawings and specified herein.
B. Develop a drilling and reaming installation strategy that minimizes the volume of drilling fluids lost to the environment by maximizing drilling fluid returns to the drill rig location.
C. Develop a pipeline installation strategy for pulling the product pipe from the exit point to the entry point.
1.05 SUBMITTALS
A. Submit the following in accordance Section 01 33 00 – Submittals.
B. Submit RSN 33 05 22-1, Key Personnel Resumes and RSN 33 05 22-2, General Work Plan for all HDD Crossings prior to remaining submittals. For subsequent submittals, submit no more than one full HDD package within a 21-day period.
1. If additional full HDD packages are submitted within 21 days, Government will require an additional 21 days for review of each additional package.
a. One full HDD package includes submittals for Drilling Plan and Calculations for one specific crossing.
C. RSN 33 05 22-1, Key Personnel Resumes:
1. Includes at a minimum:
a. HDD Contractor:
1) In accordance with 33 05 22 Section 1.06 – Qualifications and include corporate resume.
b. Project Engineer registered as a Professional Engineer in the State of New
Mexico.
c. Drilling Fluid (mud) Engineer.
d. Drilling Fluid (mud) Technician.
e. HDD rig operator(s).
f. Annular Grout Contractor, if subcontracted.
g. Intersection Surveyor or Guidance Technician, for intersection method HDDs.
1) If subcontracted, provide corporate resume of subcontractor.
2. Submit personnel changes with a minimum notice of 48-hours to COR:
33 05 22 - 11
a. Changes shall be approved by COR prior to work being performed by new personnel.
D. RSN 33 05 22-2, General Work Plan for all HDD Crossings:
1. Submit a work plan complete with drawings, sketches, schedules, written descriptions, manufacturer’s information, and other documents defining the Contractor’s plans and procedures for completing the HDD components of the work for each site. Identify the details of the proposed method of construction and the sequence of operations during construction. Field verify dimensions, elevations, potential alignment obstructions, and installation criteria prior to preparing the General Work Plan.
2. Include:
a. Drawings for each site showing:
1) Contractor proposed bore path revisions (Plan and Profile), including entry and exit locations, based on field verified conditions or for Contractor convenience.
2) Equipment setup and laydown areas shown within the allowable working limits for construction. Include any required grading.
3) Excavations, including:
a) Surface dimensions and depths of slurry return/mud recycling pits,
b) Entry and exit pits,
c) Unwatering, if used,
d) Shoring, if used.
4) Entry, exit, and smallest bend radius for pipe during pullback.
5) Pipe laydown areas, as shown on drawings, for joining/welding and testing prior to pullback. Include calculations for pipe stress in laydown area prior to pull back.
6) Drill rig anchor system, if needed.
b. Schedule shall include:
1) Hours of operation proposed and length of work week (work plans shall be subject to compliance with applicable regulatory requirements for construction activities, and any offsite impacts).
2) Site preparation.
3) Conductor casing installations; where applicable. Include a means of fluid containment (e.g. packer, seal, backflow of conductor casing).
4) Entry and exit pit excavations/preparation.
5) Equipment mobilization.
6) Pilot bore drilling, reaming, swab pass, and product pipe installation.
33 05 22 - 12
7) Fusion welding and testing of plastic pipe or welding and testing of metallic pipe.
8) Casing weld tests appropriate for pipe material.
9) Pressure testing of HDD Pipe prior to and following installation.
10) Annular space grouting.
11) Mandrel/pig testing.
12) Cleanup and backfilling of excavations.
13) Surface restoration.
14) Demobilization.
c. Submit photographs and details of proposed downhole tooling, including alternate tooling.
d. Certificate of inspection for drill rods and tooling joints shall be in accordance with API RP 7G-2 and provided within 30 days of transporting.
e. Disposal location permit status and authorization to dispose fluid, cuttings, and other waste products.
E. RSN 33 05…
This is the start of the file's text. The full file is on GovTribe.