Attachment__4_-_Price_Schedule_(06_18_2024)_0004.xlsx

XLSX spreadsheet 24 KB Posted

Attached to
SEKI 326438 KNP Hazard Tree Removal
Solicitation number
140PS124R0003
Issued by

About this file

This document is a Price Schedule Template for Task Order 140PS124R0003 under the National Park Service (NPS) - ConOps Strategic Solicitation. The solicitation is for a project to mitigate tree hazards at Sequoia and Kings Canyon National Parks (SEKI) following the 2021 KNP Complex Wildfire. The Price Schedule details the various line items for tree felling, limbing, topping, slash disposal, and other related services, with estimated quantities and units of measure. Offerors are required to submit pricing for all base and option line items. The project location is Parkwide, and the PMIS number is SEKI 326438. Pricing is requested for tasks such as tree removal by diameter class, slash disposal, bole manipulation, existing stump treatment, silt fence installation, ditch repair, hydraulic mulching, and offsite disposal. Totals are to be rounded to the nearest whole dollar.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Schedule Template

Task Order Price Schedule
National Park Service (NPS) - ConOps Strategic
Solicitation Number:140PS124R0003
PARK - PMIS:SEKI 326438
Location:Parkwide
Project Title:Mitigate Tree Hazards, KNP Complex Wildfire
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all
option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced
line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related
item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts
govern. Round totals and extended prices to whole dollars.
Contract Line Item (CLIN)PWSItem TitleEstimated QuantityUnit of MeasureUnit PriceTotal Price
01011.1, 1.2Mobilization1Lump Sum$0.00
01021.3Tree, fell, limb & top, 4-11" DBH978Each$0.00
01031.3Tree, fell, limb & top, 12-19" DBH2,791Each$0.00
01041.3Tree, fell, limb & top, 20-25" DBH1,685Each$0.00
01051.3Tree, fell, limb & top, 26-29" DBH834Each$0.00
01061.3Tree, fell, limb & top, 30-41" DBH1,154Each$0.00
01071.3Tree, fell, limb & top, 42+" DBH733Each$0.00
01081.4, 2.2Slash and stem: chip, pile or lop & scatter, 4-11" DBH tree978Each$0.00
01091.4, 2.2Slash: chip, pile or lop & scatter, 12-19" DBH tree2,791Each$0.00
01101.4, 2.2Slash: chip, pile or lop & scatter, 20-25" DBH tree1,685Each$0.00
01111.4, 2.2Slash: chip, pile or lop & scatter, 26-29" DBH tree834Each$0.00
01121.4, 2.2Slash: chip, pile or lop & scatter, 30-41" DBH tree1,154Each$0.00
01131.4, 2.2Slash: chip, pile or lop & scatter, 42+" DBH tree733Each$0.00
0114Slash, Red Fir Spray Field, masticate or chip & spread1LPSM$0.00
01151.5, 1.8, 2.3Bole, buck and load, 12-19" DBH1,271Each$0.00
01161.5, 1.8, 2.3Bole, buck and load, 20-25" DBH703Each$0.00
01171.5, 1.8, 2.3Bole, buck and load, 26-29" DBH667Each$0.00
01181.5, 1.8, 2.3Bole, buck and load, 30-41" DBH486Each$0.00
01191.5, 1.8, 2.3Bole, buck and load, 42-60" DBH261Each$0.00
01202.2Bole, manipulate to disperse, 12-19" DBH823Each$0.00
01212.2Bole, manipulate to disperse, 20-25" DBH216Each$0.00
01222.2Bole, manipulate to disperse, 26-29" DBH349Each$0.00
01232.2Bole, manipulate to disperse, 30-41" DBH100Each$0.00
01242.2Bole, manipulate to disperse, 42-60" DBH14Each$0.00
01252.4Existing high stump, flush-cut1,500Each$0.00
01261.7Existing felled tree, limb, top, lop & scatter/chip slash, 12-19" DBH500Each$0.00
01271.7Existing felled tree, limb, top, lop & scatter/chip slash, 20-25" DBH tree400Each$0.00
01281.7Existing felled tree, limb, top, lop & scatter/chip slash, 26-29" DBH400Each$0.00
01291.7Existing felled tree, limb, top, lop & scatter/chip slash, 30-41" DBH100Each$0.00
01301.7Existing felled tree, limb, top, lop & scatter/chip slash, 42-60" DBH100Each$0.00
01311.8Existing felled tree, manipulate bole to disperse, 12-19" DBH250Each$0.00
01321.8Existing felled tree, manipulate bole to disperse, 20-25" DBH tree150Each$0.00
01331.8Existing felled tree, manipulate bole to disperse, 26-29" DBH50Each$0.00
01341.8Existing felled tree, manipulate bole to disperse, 30-41" DBH30Each$0.00
01351.8Existing felled tree, manipulate bole to disperse, 42-60" DBH20Each$0.00
01362.7Silt fence, install5,000Linear Foot$0.00
01372.8Ditch, repair incidental damage1Lump Sum$0.00
01382.9Hydraulic mulching, ditch repair areas10Acre$0.00
01392.10Culvert inlet, cleanout, incidental30Each$0.00
01402.11Traffic control1Lump Sum$0.00
01412.11Traffic control, supervisor1Lump Sum$0.00
01421.14Offsite Disposal9,160Ton$0.00
Total Evaluated Price - (CLIN 0101 through 0142)$0.00

File details come from the government source that posted it. Updated .