B09_Amend_9_Attach_1_QandA_2024_11_27_0009.xlsx
XLSX spreadsheet 60 KB Posted
- Solicitation number
- 140P2025R0008
About this file
This is a Questions and Answers document containing 214 contractor questions and government responses regarding solicitation 140P2025R0008 for the rehabilitation of the El Portal Wastewater Treatment Facility (WWTF) and Administrative Camp at Yosemite National Park.
Key clarifications include: proposal due date extended to January 6, 2025; no Project Labor Agreement required; NPS will provide the Process Testing and Startup Manager; contractors must provide full propane tank after testing; leak detection cable not required on double containment piping; excess soils must remain on site; and NPS will provide 12 pneumatically actuated butterfly valves for the tertiary building. Technical clarifications address pipe materials, valve types, coating systems, electrical components, concrete specifications, and equipment requirements. The Q&A also confirms that reseeding/replanting is not part of the contractor's scope and that safety forms/insurance letters are excluded from the 20-page technical approach page limit.
View the file
Other files
Show 40 more
Latest 50 of 87 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| YOSE 196416 140P2025R0008 Questions and Answers | ||||
| Question | Solicitation Reference | Answer | Amendment | |
| 1 | In the summary of Work, Section 01 11 00 Part 1.12A it is noted that Onsite Work hours are to be during normal business hours of 6:30am to 4:30pm. Under A-4 (Same Section) it is noted that no construction material deliveries will be allowed during the hours of 8:00am through 2:00pm between May 15 and September 15.Due to limited winter access, the amount of work to be completed November through April will be very limited. With these unrealistic restrictions the NPS is only allowing necessary daily construction deliveries to take place from 6:30am to 8am every morning and 2pm through 4:30pm Monday through Friday. With limited storage and staging onsite, the critical ready mix concrete and reinforcing steel deliveries, installations, and placements would in essence be limited to 1.5 hours in the morning and 2.5 hours in the afternoon. When the placement of cast-in-place concrete for these structures start we cannot simply stop and pick it back up after 2pm. These delivery restrictions are not realistic for a project of this magnitude in a weather constricted remote location such as this. Please revisit and reconsider your delivery restrictions. | Section 01 11 00 Part 1.12A | Specification 01 11 11, Part 1.12A, REVISE Paragraph 4: Material deliveries are allowed within normal business working hours. | 6 |
| 2 | In the Solicitation Part II - Contract Clauses 52.236-7 states required permits are the contractors responsibility to obtain. Please provide a list of the required permits the contractor would be obligated to obtain for this project and which agencies they are to be obtained from. | Permit requirements are identified within Specification 013100. | 6 | |
| 3 | In the Administration Camp plan set on drawing G1.3 (Sheet 4 of 77) General Note No.3 states, the Contractor shall be responsible for locating all NPS and Non-NPS owned utilities. A General Contractor cannot be made responsible for locating utility owners utilities. Per USA guidelines, the excavator/contractor is required to provide proper notification prior to underground exploration and/or excavations (Dig Permits) and clearly mark and identify the areas to be excavated so that the utility owner can properly identify the location of their utilities. The excavator/contractor has an obligation to then verify the extend of the utility that may conflict with the proposed excavation to confirm its location. Please clarify if it is the NPS intent to have the contractor hire a 3rd party service on behalf of the NPS to perform Ground Penetrating Radar services for all utility locates prior to excavations or is this note in error and the NPS will be performing this service? | Administration Camp plan set on drawing G1.3 | Refer to section 01 73 40 3.2 and 01 11 00 1.12B for expectation of contractor responsibilities regarding existing utilities. Not dictating specific means and methods of examination/investigation of existing utilities. | 8 |
| 4 | In the Administration Camp Plan set on drawing C2.0 (Sheet 7 of 77) Note 7 state the contractor shall be fully responsible for all damage of utility lines, both above and below ground, resulting from construction operations. A General Contractor cannot be made responsible for unknown, or unidentified utilities that the utility owner failed to identify when the contractor/excavator obtained the necessary Dig Permit allowing the utility owner to properly mark/identify the location of their utilities. Please remove or correct this note in accordance with federal and state law governing utility owners obligations. | Administration Camp Plan set on drawing C2.0 | Refer to section 01 73 40 3.2 and 01 11 00 1.12B for expectation of contractor responsibilities regarding existing utilities. | 8 |
| 5 | The project documents provided for the El Portal Wastewater Treatment Facility note that various plan sheets call for the complete demolition of several structures, including the Chlorine Contact Basin, Storage Container Maintenance Area, Aeration Basins, Thickening Tank, Primary and Secondary Clarifiers, Generator, Operation and Maintenance Building, Digester Complex, Diesel Fuel Tank, and Dewatering System. However, in order to provide a comprehensive and accurate proposal, additional details regarding the demolition scope are required. Specifically, please provide structural drawings and utility details for these existing facilities. This information is critical for assessing the full extent of the demolition work, including potential challenges related to existing utilities, foundation removal, and other construction or electrical sequencing concerns. | Demolition | Submit a request to the Contracting Officer for as-built drawings. A Non-Disclosure Agreement (NDA) will need to be executed prior to releasing the documents.Please send a request to the CO & CS. We are no longer requiring an NDA. | 4 |
| 6 | Drawing 75A139 calls out Design Detail 0929-009 for details related to the metal framed walls. This detail cannot be found in the provided standard details. Can you please provide detail 0929-009? | Drawing 75A139 | Drawing 75A139 calls out incorrect detail number. Refer to Construction Detail 0929-101: Deflection Head. | 6 |
| 7 | What is the clear height required in the Tertiary PEMB? There is a reference in the architectural plans (Sheet 30A303) to refer to the structural plans, but there is not a dimension in the structural plans. In the alternative do we make the Tertiary canopy tall enough to accommodate the crane beams? | Structural Plans | On Drawing 30S302, the minimum vertical clear distance from top of concrete to the metal building structure is shown as 9'-0". | 4 |
| 8 | Equipment Parking (sheet 04S131)– Under IBC 2021, the building is too long to torsionally brace, Are portal frames at both side walls acceptable? Will this effect primary frame spacing? | Sheet 04S131 | Confirmed, portal frames occuring at both side walls is acceptable. Portal frames can be applied on each side in the easternmost bay and the column spacing in this bay should increase to 20'-0" to allow an adequate clear dimension between the columns for the portal frames. | 4 |
| 9 | Some PEMB canopies show metal liner panel on the ceilings. Liner is not called out for in the specifications (133419). Please confirm if liner panel is required, and if so, provide a basis of design. | Spec 13 34 19 | Soffit panels are required at Septage Receiving (Facility 11), Tertiary (Facility 30), and UV (Facility 35). Refer to the Color List and Exterior Finish Schedule on the Construction Drawings for each Facility. Provide the following soffit panels: C. Soffit Panels: |
1. Material:
a. ASTM A653/A653M or ASTM A792/A792M preformed ribbed steel panels, Grade 50, minimum.
b. Minimum 24 gauge galvanized steel with roll-formed corrugations for structural stiffness and appearance.
c. Exterior Finish: Factory-applied, 70 percent fluoropolymer coating, dry film thickness of 1.0 mil including primer, in color shown in the Exterior Finish Schedule as shown on the Drawings.
2. Sheet Metal Soffit Panel System: a. ASTM E1514 structural standing seam steel roof panel system.
b. Standing Seam: Formed with vertical ribs at panel edges and two intermediate stiffening striations symmetrically spaced between vertical ribs designed for sequential field installation by mechanically attaching panels to supports using concealed clips located under one side of panel and engaging opposite edge of adjacent panels and mechanically seaming panels together.
c. Panel Coverage: 36 inches.
d. Panel Height: 3 inches max.
e. Tested and certified to meet UL 580, Class 90 wind uplift rating.
f. Manufacturers and Products:
1) Basis of Design: Nucor; R-Panel.
| 2) Or equal. | 4 | ||||
| 10 | Is there any way that the bid date could be postponed for a couple of weeks? We would need the time to give you the most competitive bid. | Proposal Due Date | Due date extended to Januay 6, 2025 via Amendment 7 | 7 | |
| 11 | 44 43 30 Filter Media |
2.02.A.1.d. The specified media sphericity of >= 0.85 is not available from media suppliers in the domestic water treatment market. Please update specification to >=0.7 which is available and is appropriate for this application.
| 44 43 30 Filter Media | Media sphericiy of >=0.7 is acceptable. | 4 | ||
| 12 | Specification 09 29 00 - 3.09 discusses spray texture application methods and conditions on gypsum board. In addition, 3.08.D calls for a level 3 finish on surfaces indicated to have spray texture. The architectural finish schedules, among other drawings, do not call out any walls to have spray texture applied. Please confirm if any walls have texture, and if so, indicate the walls that should? | Spec 09 29 00, 3.09 | Provide spray texture on ALL GWB walls and ceilings. Provide level 3 gypsum wallboard finish prior to applying spray texture as noted in specification 09 29 00-3.08 & 3.09. | 4 |
| 13 | Interior finish schedule on sheet 75A601 notes a Ceiling Finish system of 106 for the Server Room, Janitor Room, Mechanical Room, and Sprinkler Riser Room. Specification section 09 90 00 - 3.08 does not contain information for this system. Please provide information for system 106. | Sheet 75A601 | System No. 106 Galvanized Metal: Surface Prep - In accordance with Paragraph Galvanized Metal, Copper, and Nonferrous Metal Alloy Surface Preparation. Paint Material - Manufacturer's Recommended Primer. Min. Coats, Cover - 1 coat, as recommended by manufacturer. Paint Material - Alkyd Enamel (Semigloss). Min. Coats, Cover - 2 coats, 4 MDFT. | 4 |
| 14 | The maximum w/cm for the Concrete Toppings mix has not been provided in section 03 30 00, 2.8 D of the Administrative Camp specifications. Please provide the maximum water-cement ratio for this mix. | Spec 03 30 00, 2.8 D | Maximum water-cement ratio for section 03 30 00 2.8 D "Concrete Toppings" shall be 0.5. | 4 |
| 15 | Do you have a flow schematic for the incoming and outfall on the wastewater treatment facility, including all the diversions inside the input and output? | Exisiting Conditions | Submit a request to the Contracting Officer for as-built drawings. A Non-Disclosure Agreement (NDA) will need to be executed prior to releasing the documents.Please send a request to the CO & CS. We are no longer requiring an NDA. | 4 |
| 16 | Do you have a sample or a most recent sampling of water coming in and going out in reference to hazardous waste E. coli , Covid, etc? | Exisiting Conditions | Influent and effluent wastewater is routinely sampled and tested for typical treatment proces related parameters. The Contractor may coordinate with Contracting Officer to take samples and perform any additional testing desired. | 4 |
| 17 | I saw a lot of asbestos basically everywhere and I’d like to know what asbestos testing has been done and what the results were so I know how to bid this work? | Exisiting Conditions | Refer to Specification 01 11 00 Part 1.15 & Volume 1B for the Hazardous Materials Investigation Report completed during the design phase. | 6 |
| 18 | Has there been any soil sampling done around the existing facility to establish a baseline for contaminants and also in the admin park Rv Park? | Exisiting Conditions | Refer to Specification 01 11 00 Part 1.15 & Volume 1B for the Hazardous Materials Investigation Report completed during the design phase. | 6 |
| 19 | We request acknowledgement that Pinnacle Prestress in Wasco, CA, formerly Bethlehem Construction, who is listed in the project specifications, is an approved Precast Concrete Manufacturer for The El Portal WWTP due to the name change at the Wasco location? | It is acknowledged that the previously pre-approved precast concrete manufacturer's name has changed, however it is assumed that the salient characterisitics of their products has not changed. | 4 | |
| 20 | Per Drawing 01G027 Pipe Schedule Sheet 2; Liquid Petroleum Gas service line states to refer to specification section 22 10 01.13 for further details. Spec section is not included in the bid documents. Please provide. | Spec 22 10 01.13 | Buried LPG pipe must be MDPE and exposed pipe must be carbon steel per Section 40 27 00.02. Detailed requirements for MDPE pipe will be provided by Addendum | 4 |
| 21 | Drawing 30R007 has a call out to Section A on 30R008, however Section A/30R008 shows the pipe demo along the Rapid Mixer wall. Please provide Section A, which is a section view of the pipe demo for the Tertiary Feed Pumps & Tertiary Polymer Pumps & Storage side. | Drawing 30R007 | A section view of the filter gallery wall is not provided (Section A). Contractor may use the photographs provided on drawings 30R502 and 30R503 for views of the area to supplement information shown on Drawing 30R007. | 4 |
| 22 | Throughout the project, various connections are required to be tied into HRW & LRW pipe, but neither pipe is on the pipe schedule or in the specs. Please provide what material these existing pipes are made of. | Exisiting Conditions | Exposed HRW and LRW pipes appear to be ductile iron. Record drawings do not list a pipe material, but indicate the pipes at each storage tank are steel. | 4 |
| 23 | Drawing 02C132, Sequence Step 2C & 2D, references DWG 05E815 for additional information on the Temporary New Plant Water Pump Station. Drawing 05E815 is not included in the drawings. Please provide. | Drawing 02C132 | Incorrect drawing reference. The additional information on the temporary power for the new plant water pump station can be found on 05E813. | 4 |
| 24 | Drawing 02C132 Sequence Step 5 calls for temp piping from the existing In-Plant Lift Station to the Return Flow Pump Station. Please provide detail drawings and/or description for the tie-ins for the temp piping at these locations. Also please confirm that the Return Flow Pump Station is new and not existing as stated on 02C132. | Drawing 02C132 | Confirmed, the Return Pump Flow Station is NEW. "EXST" was incorrectly written. Temporary flow control is described in Section 01 57 28 and is the Contractor's responsibility. Installation of temporary systems described therein shall not begin until the Contracting Officer has approved the plan. Drawings must be signed and signed and sealed by a professional engineer registered in the State of California. | 4 |
| 25 | Drawing 04R100 note 7 calls to provide a temporary connection of new plant water pump station discharge (W3) to existing HRW service, but the drawing shows the connection to the existing 6" LRW. Please confirm if the connection is meant to be to the 8" HRW line or the 6" LRW line. | Drawing 04R100 | The temporary connection is meant to be connected to the 8" HRW line from the new plant water pump station. | 4 |
| 26 | Drawing 11R130 calls for the equipment in and around channels to be demolished. In order to quantify this work, please clarify what equipment needs to be removed. Please provide equipment O&M submittal info if available. | Drawing 11R130 | Record drawings show the equipment located within the existing headworks facilities. The screening equipment located on the outside deck is not shown on the record drawings and should also be removed. | 4 |
| 27 | Drawing 04R100 calls to install new 16" HDPE FE piping from UV to existing Flow Measurement Structure, however the pipe schedule on sheet 01G027 calls for all FE pipe to be Ductile Iron. Please confirm which material is required for the new FE pipe. | Drawing 04R100 | FE pipe must follow what is listed on 01G027. The note indicating HDPE pipe on drawing 04R100 is incorrect. | 4 |
| 28 | Drawing 04R100 shows the new 8" FE discharge line tying into an unknown line just past the existing plant water pump station, please provide the line's size and material. | Drawing 04R100 | The 8" FE ties into the existing plant water pump station 8" LRW inlet line. | 4 |
| 29 | Specification Section 41 22 03.07 part 2.02 A2 provides the quantity and location of davit bases for the portable davits on the project (total - 19ea). The specifications do not mention the required quantity of portable davits that contractor needs to provide. Is it the intent of the owner to have the contractor provide same quantity on Portable Davits (19ea) as the fixed davit bases? | Spec 141 22 03.07 part 2.02A2 | Provide two (2) portable davit crane assemblies to include portable davit cranes, lifting winches, and wire ropes. | 4 |
| 30 | Drawing 04Y131 Yard Piping Plan 01 called out for ½” PACL (Polyaluminum Chloride) in 3” Conduit. PACL is not listed on the pipe schedule. Please provide pipe schedule information for the PACL pipe system. | Drawing 04Y131 | PACL must follow the same pipe/tubing requirements as Aluminum Sulfate listed in the Pipe Schedule. | 4 |
| 31 | Drawing 04Y131 Yard Piping Plan 01 shows 2” W3 Line running from Secondary Clarifier #2 connecting to the East side of the Tertiary building to a section of 6” W3 as shown on drawing 30D130. Please confirm that the 2" W3 piping on 04Y131 is the correct pipe size and confirm it will connect to the section of 6" W3 that stubs out of the building as shown on 30D130. | Exisiting Conditions | The pipe size shown is correct. Per Note 8 on 04Y131 | 4 |
| 32 | To supplement the description of the bypass work in specification 01 57 28, please provide the existing facility process flow diagrams. | Exisiting Conditions | ||
| 33 | A callout on Drawing 15S142 indicates "Grating Type 'A' with 'GS-1' Support All Around" for the grating that is east of gridline 4, and adjacent to the South Stair Tower. The callout does not indicate the type of material for the grating. Please provide the type of material required for the grating at this location. | Drawing 15S142 | Provide aluminum grating at this location. See Drawing 01G031 for the Material Selection Table for general guidelines. | 4 |
| 34 | Drawing 75A139 calls out Design Detail 0929-009 for details related to the metal framed walls. This detail cannot be found in the provided standard details. Can you please provide detail 0929-009? | Drawing 75A139 | Drawing 75A139 calls out incorrect detail number. Refer to Construction Detail 0929-101: Deflection Head. | 4 |
| 35 | With the current bid date is the first working day following the Thanksgiving Holiday. In order to allow adequate time to analyze the project and accommodate subs and suppliers' schedules, we are requesting a bid date extension to December 12th, 2024. | Proposal Due Date | Due date extended to Januay 6, 2025 via Amendment 7 | 7 |
| 36 | Drawing 30R170 calls for the demolition of "Damaged Grating" in the Process Room, but does not specify the grating material type or thickness. Drawing 30S120 includes a callout at this location indicating, "Replace Damaged Grating In Kind." Please provide the material type and thickness for the grating to be removed and replaced at this location. | Drawing 30R170 | Provide aluminum type 'A' grating at this location. See standard detail 0553-001 for grating thickness. | 4 |
| 37 | Process Mechanical Pipe Schedule on 01G026 has AHP Listed as 316SST, SCH 40S for IN/OUT Exposed use. Plumbing Piping Schedule found in specification section 22 10 01 has AHP listed as STL for all EXP/BUR use. Please clarify the AHP line material for plumbing drawings vs process drawings. | Process Mechanical Pipe Schedule | All AHP pipe materials must follow the requirements shown on Drawing 01G026. | 4 |
| 38 | Detail 2213-150 for Floor Drain FD-1 shows a 1/2" PW line for Trap Primers, plumbing piping schedule shown on 22 10 01 shows system TP for Trap Primer Lines, no trap primer lines nor trap primer panels are shown on the drawings. Please clarify if trap primers are to be installed. | Detail 2213-150 | Headworks facility 10 shall not require Traps or Trap primers for the installation of drainage to the chanel inside the facility. All other facilities require plumbing traps for the installation. Trap Seals shall be installed in lieu of trap primers at these locations. | 4 |
| 39 | Buildings 45,75,80 call for System S and SS within the plumbing drawings. Plumbing piping schedule shown within the specification section 22 10 01 does not include system S and SS. Please provide piping schedule information for the S and SS for plumbing. | Buildings 45,75,80 | System S and SS are designations to indicate tie-in to drain locations on the site. All piping shall match the requirements of plumbing drainage. Drains shall be the materials listed in the 22 10 01 Plumbing Piping Schedule Supplement in the specifications. | 4 |
| 40 | Drawing 04Y132 shows a line coming from the existing digester to the new sludge drying beds with no system callout or pipe size. Drawing 09R001 sheet notes 1, 2, 3 describe removing all piping and equipment and capping/sealing the digester structure to ensure it is protected. It appears this digester is decommissioned and non-operational, and therefore would not be tied into the new sludge drying beds. Please advise if this piping is required and if so provide the pipe size, material type, and tie in locations. | Drawing 04Y132 | No pipe is needed between the drying bed and the existing digester. Neglect line shown. | 4 |
| 41 | Drawing 04Y101 shows the existing drying beds being fed from existing DS piping. However, the temporary and new sludge drying beds do not have any sludge feed piping shown on the drawings. Please advise how sludge is conveyed into the temporary and new sludge drying beds. | Drawing 04Y101 | The temporary drying beds are for trucked-in waste only. No sludge from the El Portal WWTP will be conveyed to the temporary drying beds. | 4 |
| 42 | Drawing 02C132 shows a 48" precast pumping manhole connected to the temporary drying beds through a 6" PD pipe. Please confirm how flows are conveyed from this manhole into the plant process. If the contractor is responsible for conveying the flow into the plant, please provide a discharge location, anticipated flows, and frequency of how often the manhole will need to be drained. | Drawing 02C132 | Pump discharge may be routed to an active primary clarifier located adjacent to the temporary drying beds. Anticipated water volume for each trucked-in load is less than 200 gallons and can be pumped out at a rate of the Contractor's choice. It is anticipated there will be 1 to 4 truck loads per week. | 4 |
| 43 | Please advise if there will be a Project Labor Agreement (PLA) on this Project. | Solicitation | There will not be a PLA on this project, an approved exemption has been received. | 4 |
| 44 | Specification section 09 96 35 - 3.06.B instructs coating system CRC-1 to be used at facility 65 containment vault. Drawings do not appear to show any vault for area 65 and the Interior Finish Schedule does not reference a CRC-1 coating. Please advise location for this coating system. | Specification 09 96 35 - 3.06.B | The containment vault was moved to the adjacent structure 86 - Return Flow Pump Station, and is designated as Chemical Vault 1 & 2.. Refer to drawing 86S301 and 86S303 for the required extents of the CRC-1 coating system. | 4 |
| 45 | The technical approach section of the proposal directs the contractor to describe the approach to maintaining water, wastewater and power services during installation of new infrastructure. In order to provide a comprehensive and complete approach, and estimate the necessary temporary flow control measures required to keep the facility operational, please provide the current facility process flow diagrams, P&IDs, and as-builts. | current facility process flow diagrams, P&IDs, and as-builts. | Please send a request to the CO & CS. We are no longer requiring an NDA. | 8 |
| 46 | Spec 01 91 15, 1.07 states, "Process Testing and Startup Manager: Government provided agent responsible for overseeing, organizing, compiling, and administering all field testing for the overall work and managing the Process Testing Startup Team." Please confirm that NPS will provide the Process Testing and Startup Manger fulfilling all requirements of 1.07. Contractor will work closely with government provided agent and provide support craft and staff for equipment testing and facility startup | Spec 01 91 15, 1.07 | The Government will provide the Process Testing and Startup Manager that will oversee and coordinate the elements listed in 1.07.C. The manger will not perform those activities, only ensure that they are completed. | 4 |
| 47 | The TOC elevation for the slab of the Chemical Vault at the Return Flow Pump Station is called out as 1685.33 on Sheets 86S130 and 86S301, but is called out as 1684.33 in Section D on Sheet 86S303. |
Please clarify the TOC elevation for the slab on grade for the Chemical Vault.
| TOC elevation for the slab of the Chemical Vault | Elevation 1685.33 is the correct base slab elevation inside the Chemical Vault. | 4 |
| 48 | 1) Solicitation 140P2025R0008, 1452.228-70 LIABILITY INSURANCE (JUL 1996)(a) requires the United States of America be included on the liability insurance as a “named insured” rather than as an “additional insured”. The differences between the two types of insured states are significant as outlined below. Named insureds are normally tied to the First Named Insured (the entity shown on the declarations page) by sharing more than 50% common ownership. Additional Insureds are a third party that requires protection under the Named Insured’s policies as the Additional Insured has a business interest that may result in both parties being brought into a suit. |
Named Insured duties/rights include:
• Pay premiums
• Report claims
• Policy cancellation rights
• Administer and authorize changes to the policy Additional Insured duties/rights include:
• The policy provides indemnity and defense in the event of a covered claim
• Receive notices of cancellation
• No obligation to pay premiums
• No ability to make changes to the policy
For the reasons above, Contractor cannot add the United States of America as a Named Insured on its corporate insurance program. Further, the United States of America does not want or need the additional risk and responsibility for premium payment or changes to the Contractor’s liability insurance. Please confirm that the United States of America will accept “additional insured” status.
| Solicitation | NPS is only required to be "named insured". | 8 | ||
| 49 | Drawing C6.4 Water Service Table and Drawing C6.7 Detail A&B states to use HDPE CL200 DR-9 for the Water Service Line; but Administrative Camp Specification 33 12 13-2 states to use DR-11 (200psi). Please clarify the correct pipe material. | Drawing C6.4 and Drawing C6.7 | HDPE DR-9 shall be used for water service lines. Specifications will be updated to match drawings. | 4 |
| 50 | Drawing C7.5 Sewer Main Detail C states to use 4” SDR-26 for the Sewer Service Line, but Drawing C7.4 Sewer Service Table and Specification 33 31 11-2 states to use 4” SDR-35 PVC. Please clarify the correct pipe material. | Drawing C7.5 | 4" SDR-26 PVC shall be used for sewer service lines. C7.4 and Specifications shall be updated accordingly. | 4 |
| 51 | Drawing 40D405 shows valves FV 118, FV 128, FV 138 on the 2" DS line. The drawing and valve schedule call out these valves to be V400 eccentric plug valves. However, P&ID 08N400, 401, & 402 has them shown as butterfly valves. Please confirm if these valves are to be plug or butterfly valves. | Drawing 40D405 | Valves for FV 118, FV 128, and FV 138 should all be plug valves as shown on 40D405 and listed in Section 40 27 02, Supplement 2, Electric Actuated Valve Schedule. | 4 |
| 52 | P&ID 08N404 shows multiple ball valves on the 2" DS line before and after the dewatering feed pumps. Drawings for facility 40 show all the valves on the 2" DS line to be plug valves. Please confirm if these valves are to be ball or plug valves. | P&ID 08N404 | Valves on DS pipes must be plug valves as shown on the mechanical drawings and as listed in Section 40 27 02, Supplement 2, Electric Actuated Valve Schedule. | 4 |
| 53 | Drawing 45D302 shows a V610 check valve on a 4" WAS line. Assumed the same check valve for the 6" RAS line. However, V610 check valve is not listed in the specifications. Please provide specification information for a V610 valve. | Drawing 45D302 | Check valves on the discharge of the WAS pumps and discharge of the RAS pumps must be Type V634. | 4 |
| 54 | P&ID 08N650 shows MHO line to be double contained but the process mechanical drawings for facility 65 do not label any MHO to be double containment. Please confirm that the MHO piping within the Chem building will not be double contained. | P&ID 08N650 | Section B on 65D302 shows where the double containment piping begins near the magnesium hydroxide pumps. | 4 |
| 55 | Drawing 86D301 calls out for 3” RF buried pipe section to be HDPE. Pipe schedule states 3” RF buried pipe material to be Ceramic Epoxy Ductile Iron. Please confirm pipe material to be used. | Drawing 86D301 | Install 3" Schedule 80 PVC pipe in buried RF service. | 4 |
| 56 | Drawing 30D130 and 30D302 shows 1/2" PAC tubing within 3" containment. All drawings in facility 65 for chemical building shows 2" PACL within 6" containment. Please confirm if PAC and PACL are the same system. Also, Please provide pipe schedule information for both systems, since neither are on the pipe schedule. | Drawing 30D130 and 30D302 | PAC and PACL are the both Polyaluminum Chloride pipe service and must follow the same tubing and piping requirements listed as Aluminum Sulfate (ALUM) listed in the Pipe Schedule. Facility 65 shows 3" PACL in 6" containment pipe from the truck fill connection to the PACL Storage Tank. PACL from the metering pumps to Facility 30 are shown as (2) 1/2" tubing within a 3" containment pipe. | 4 |
| 57 | Drawing 04Y131 calls out to use 10” V134 TYP of 3 for the 10” RW bypass running between the Headworks Building to MH RW #7. Valve Type V134 is not listed in the specification/drawings. Please provide V134 valve type and specifications information. | Drawing 04Y131 | Type V134 must be an AWWA C509 iron body resilient seated gate valve with bronze stem and 2-inch stem nut, non-rising stem, mechanical joint ends, 200 psig working water pressure, full port, and fusion epoxy coated inside and outside per AWWA C550. | 4 |
| 58 | Spec Section 01 57 28 - 1.01A calls for the replacement of the isolation gate to Percolation Ponds No. 1, 2 & 3. However an existing isolation gate to the Percolation Ponds is not shown in the drawings, please provide additional details on the isolation gate as well as its location. | Spec Section 01 57 28 - 1.01A | Record drawings label the gates as flange mounted shear gates. They are installed in the same location as the new slide gates are shown. | 4 |
| 59 | Drawing 10P130 shows detail call out 2213-150, TYP for FD-2. Detail 2213-150 references a trap primer line that would be plumbed to the floor drain. General Drawing 01G021, under the "Plumbing Symbols" header, describes a naming convention for Floor Drains that includes a symbol "P" for floor drains that have primed traps. The FD-2 callout on 10P130 does not indicate that a trap primer is required for these floor drains. Please confirm that primed traps are not required for Floor Drains on this project. If required, please indicate which floor drain(s) require a trap primer and where the wall access panel(s) will be located that will house the trap primer(s). | Drawing 10P130 | Headworks facility 10 shall not require Traps or Trap primers for the installation of drainage to the chanel inside the facility. All other facilities require plumbing traps for the installation. Trap Seals shall be installed in lieu of trap primers at these locations. | 4 |
| 60 | Drawing 10D302 calls for a 4" V320 valve on a 4" GR line and P&ID 08N101 shows it as a pinch valve. However, V320 is not in the valve specifications. Please confirm that V320 is a pinch valve and provide specification information for this type of valve. | Drawing 10D302 | Provide a 4" Type V905 pinch valve. See Specification Section 40 27 02. | 4 |
| 61 | Drawing 30D303 calls out LIT 110 on a 12" TFI line and gives a 4091-411 standard detail. Detail 4091-411 is not found in the standard details section. Please provide the 4091-411 standard detail. | Drawing 30D303 | The correct standard detail for installation of LIT 110 is 4091-272. | 4 |
| 62 | 1.05.D. Requires the shop to hold a RTP-1 Certification. |
Would you be willing to accept Midwestern Fabricators as a manufacturer that can provide FRP Tanks that are designed, fabricated, inspected and documented per the ASME RTP-1 program but is not a certified facility?
If so, our recommendation would be to reword the statement found in 1.05-D with the following statement that has been widely accepted in other engineered FRP Tank specifications:
“The tanks should be designed, fabricated, inspected and documented per the ASME RTP-1 standards, but shop certification is not required”
| To further expand: Midwestern does not participate in the RTP-1 certification program. However, their in house engineering staff and full time QA/QC inspector are well versed in the ASME RTP-1 level 2 requirements and use this as their in house standard for the design, fabrication and testing of their manufactured FRP Tanks. They would be able to provide all the documentation and requirements associated with the standard. If this request was to be implemented you would receive all the same requirements sought after by having the ASME RTP-1 specified without the unnecessary inflated costs associated with it being a certified project. | 43 40 02 FRP Tank | FRP tanks should be proposed as specified. | 4 | ||
| 63 | Specification Section 26 05 26 states, "Install [Ground Rods] to 8 feet below local frost depth." Please confirm what the local frost depth is. | Section 26 05 26 | Local frost depth is 12-inches. | 6 | |
| 64 | Contract Drawing 02C132, Minimum Construction Sequence Step 2C states, "For additional information see DWG 05E815." DWG 05E815 has not been included in the Drawings provided. Please advise. | Drawing 02C132 | The drawing references in Step 2C and 2D to 05E815 are incorrect. The correct drawing reference is 05E813. | 4 | |
| 65 | Contract Drawing 02C132, Minimum Construction Sequence Step 7 states, "Remove and Replace Septage Receiving Station and perform Tank Rehabilitation." The New Septage Receiving Station is not supplied with permanent power or control until the electrical ductbanks are installed in Construction Phase 5 as shown on drawing 02C136. There are no current provisions within the plans to provide temporary power or control to the new septage receiving station between construction Phase 1 through Phase 5. Please confirm that the New Septage Receiving Station is intended to be non-operable between Construction Phase 1 through Construction Phase 5. | ||||
| Drawing 02C132 | Reuse the existing Septage Receiving Station power temporarily at MCC11 located in the exsting Headworks building, upper level. | 4 | |||
| 66 | Drawing 05E131 shows an empty ductbank ("DB-12") routed from MH-01S and MH-01PC to the existing Maintenance Complex Lift Station ("the Lift Station"). This duct bank appears to conflict with an existing buried electrical and communication line ("Elec & Comm") shown on Drawing 04Y101. Drawing 04Y101 General Note 2 states: “Existing yard piping to remain at the final stage of the project is shown in black. All other piping is to be removed or abandoned in place.” Approximately 80 feet southeast of the Lift Station, the color of the "Elec & Comm" line changes from black to gray, indicating that this section of the line is scheduled to be removed or abandoned. Please confirm whether this portion of the "Elec & Comm" line, which is shown to be removed or abandoned, is responsible for providing power and control to the Lift Station. If this line does indeed provide power and control to the Lift Station, please clarify how and/or if the Lift Station remains operational during the construction process given that the new ductbank is shown to be empty. | ||||
| Drawing 05E131 | Install New power and fiber conductors to the Maintenance Complex Lift Station (MCLS) via duct bank shown on Drawing 05E131 from Facility 40, 40-DP-01, shown on Drawings 40E602, 95E240, 95E241, 95N202, and 95N203. | ||||
| The MCLS must be temporarily powered if power can not be transferred from the existing power feed to the new power feed in a timely manner. Conduit and conductor sizes are to be 1 [2"C - 3#6, 1#10G] and 1 [2"C - FIBER]. | 6 | ||||
| 67 | Drawing 40A303 / Section B shows rigid insulation (R-15) on one side of the footing. Please confirm that the rigid insulation will only be placed on the side of gridline A (and not around the entire building). | ||||
| Drawing 40A303 | Perimeter rigid insulation is required for the entire facility except at Digester Walls. | 4 | |||
| 68 | Drawing 40S130 of the Operating Level shows vapor retarder below slab between gridlines 3 and 4. Section B (40S302) does not show any callouts for vapor retarder. Please confirm that there will be vapor retarder as outlined by the dashes on the plan view. | ||||
| Drawing 40S130 | Vapor Retarder is required under the containment area located at this callout. This is shown on Drawing 40A130 as well. | 4 | |||
| 69 | For Headworks, drawing 10A303 shows installation of Rigid Insulation R-15 around the building footing vertical faces. On drawing 10S302, it shows installation of premolded joint filler at horizontal joint between the headworks and EPS building. Please confirm that premolded joint filler will be installed on top of the R-15 rigid insulation. | ||||
| Drawing 10A303 | Perimeter rigid insulation is not required where the Headworks Effluent Pump Station abuts the Headworks footing. Perimeter rigid insulation is required around the remaining facility footing. | 4 | |||
| 70 | On drawing 10S302 Section B, it shows installation of premolded joint filler and 1" Sponge rubber joint filler on South side of the building footing. Please provide the extents for these joint fillers for installation. | ||||
| Drawing 10S302 | The joint filler is required for the full length of the Headworks EPS slab interface with the Headworks building foundation. This is shown as 51'-8" on Drawing 15S140. | 4 | |||
| 71 | Architectural section views on drawing 65A302 shows underslab vapor retarder. Drawing 65A130 shows underslab vapor retarder in the Polymer Storage room only. Structural section views on drawing 65S301 does not indicate any vapor retarder below grade. Please confirm the locations of vapor retarder, whether it is underneath the entire building or only in the Polymer Storage room. | ||||
| Drawing 65A302 | Underslab vapor retarder is required for the entire Chemical Building (facility 65). Paint system 21 on only required at the Polymer Storage Room (65102) as indicated on the plan and the Interior Finish Schedule on Construction Drawing 65A601. | 4 | |||
| 72 | Architectural section views on drawing 75A303 & 75A304 show underslab vapor retarder. The structural section views do no indicate any vapor retarder below grade. Please confirm whether the vapor retarder is underneath the entire slab of the building. | ||||
| Drawings 75A303 & 75A304 | Underslab vapor retarder is required for the entire Operations Building (facility 75). Refer to architectural sections for additional clarifications on extents | 6 | |||
| 73 | Could a second site vist be accomodated | Site Visit | A second site visit will be accomodated on November 20, 2024, at 9:00 AM Pacfic Time. Please see site visit attachment for details. | 6 | |
| 74 | We find no valve v134 as noted on the 10" RW around mhrw8. Will a spec be issued for this valve or should this be a v405? | 04Y131 | Type V134 must be an AWWA C509 iron body resilient seated gate valve with bronze stem and 2-inch stem nut, non-rising stem, mechanical joint ends, 200 psig working water pressure, full port, and fusion epoxy coated inside and outside per AWWA C550. | 4 | |
| 75 | MH RW8 Is Labeled As A 3305-711. Should MH RW8 Be A Metering Manhole In Accordance With Dwg 08n100? | 04Y131 | The correct standared detail to follow is 3305-666 | 4 | |
| 76 | No wall pipe is shown for the 10" RW structure penetration. Is one required? If not, what type of wall penetration is required? | 10D130 | Installl a wall pipe per Standard Detail 4027-601 | 4 | |
| 77 | We find no valve v320 as noted on the 4" grit line. Will a spec be issued for this valve, or should this be a v405? | 10D302 | Provide a 4" Type V905 pinch valve. See Specification Section 40 27 02. | 4 | |
| 78 | Should there be a wall pipe where the grit pd enters the flow channel? | 10D130 | Installl a wall pipe per Standard Detail 4027-605. Use Type 305 stainless steel wall pipe material. | 4 | |
| 79 | With no section view of the septage receiving screen, what are the equipment items between the rock trap and the screen? Can an elevation view be provided? | 11D130 | An actuated valve and flow meter, provided by the septage receiving system vendor, are located between the rock trap and the screen. See P&ID 08N110 | 4 | |
| 80 | Is a cam-lok coupling required on the septage receiving pipe? | 11D130 | Yes, provide 4" male camlock fitting for the septage receiving inlet connection. | 4 | |
| 81 | Should the 16" RW GV v-122 in the inf. Channel have an extension stem & guides up to the top slab with a floor box? | 15D130 | Provide a 16" Type V150 knife gate valve with extension stem and guides to within 16" of the top of concrete. Provide floor box, coated per System 4. | 4 | |
| 82 | Should the wall sleeves in wet basins be 316 SST rather than galvanized? | 15D130 | Pipe sleeve standard details include notes to coat the entire sleeve with specified paint system prior to concrete placement. | 4 | |
| 83 | The bends on most of the process pipelines appear to be drawn as long radius, but are not notes as such. Is this correct? | 15D304 | Refer to the pipe data sheets for bend radius requirements. Carbon steel and stainless steel pipes are required to have long radius bends unless otherwise stated. | 4 | |
| 84 | Should The 6" Alp Drops To The Sparger Rings Have Expansion Bellows Similar To The 4" Alp Shown On Dwg 15D303 Section C? | 15D131 | Expansion bellows are shown for the 6" ALP pipes in Section A (also see Note 9) on Drawing 15D301. | 4 | |
| 85 | Is there some reason the new 10" MLSS, 8" RAS & air lines which interconnect with the bioreactor are not shown as new on this yard pipe plan? | 04y131 | Piping in this area are shown and detailed on the mechanical drawings | 4 | |
| 86 | The PI&D dwg shows six (6) valves on the 8" RAS/WAS pump suction line whereas the 45 series drawings only show three (3). Which is correct? | 08N450/45D130/45D304 | Valves shown on the mechanical drawings are correct. | 4 | |
| 87 | We find no check vale designation for the RAS PMP discharge check valve. Will a V634 be acceptable? | 45 SERIES | Check valves on the discharge of the WAS pumps and discharge of the RAS pumps must be Type V634. | 4 | |
| 88 | We find no call out for the 4 RA Sas wall penetration. Is a 4027-607 acceptable? | 45D301 | Wall penetration per Standard Detail 4027-607 is acceptable. | 4 | |
| 89 | We find no v610 check valve in the spec for the was discharge line. Will a v634; be acceptable? | 45D302 | Check valves on the discharge of the WAS pumps and discharge of the RAS pumps must be Type V634. | 4 | |
| 90 | Was Pipe Section C Shows 4" FCV202 Plug Valve After the Meter. However This Valve Does Not Show Up On The Elec. Actuated Valve Schedule. This Valve Is Shown as Manual on The PI&D 08n451. Which Is Correct? | 45D302 | The valve should only have a manual actutor; the FCV 202 label is incorrect. | 4 | |
| 91 | The Butterfly Valves for the 6" Alp Are Shown as V500 Type Which Are For Water Service According To The Specification 40 27 02. Should These Be V514's? | 45D301 | The butterfly valves shown on 45D301 are mislabeled and should be provided as Type V514. | 4 | |
| 92 | Drawing 04C131 calls out a 6,500 gallon propane tank on a concrete slab. On specification section 23 13 00 Part 2.01B, the LPG storage tank described only has the capacity of 4,500 gallons. Please advise what is the correct capacity of the tank to be provided. | Drawing 04C131 | The propane tank must be 4,500 gallons as listed in Section 23 13 00. | 4 | |
| 93 | Drawings 35R120, 35R301, and 35S120 shows what looks to be additional under ground pipe penetrations on the west side of the UV Facility. Are these pipe penetration existing and if so, please provide additional drawings/details. | Drawings 35R120, 35R301, and 35S120 | These are above grade wall penetrations and are shown on Detail 1 on Darwing 35R301. There are no pipes connected to the pipe penetrations (blind flanged). | 4 | |
| 94 | All drawings in facility 65 for process mechanical label 2" PACL within 6" containment but drawing 65D307 labels it as 3" PACL within 6" containment at the fill connection. There is also a FV 301 valve at the fill connection, the valve schedule calls it to be a 3" valve size. Please confirm if the PACL line is to be 2" within 6" containment or 3" within 6" containment. | Facility Drawings | 3" PACL in a 6" containment pipe is required from the fill connection to the storage tank. 2" PACL is required in the trench between the storage tank and the metering pump skid, where it reduces to 1/2" for connection to the metering pump skid. | 4 | |
| 95 | Callout for Sequence Step 3 on Drawing 02C132 indicates constructing 2 temporary drying beds per Drawing 87S401. Drawing 87S401 calls for a steel truss frame structure covered with a fabric membrane. |
Is the intent for the temporary drying beds to have this truss and fabric cover? If so, are 2 of these structures to be included in the contract price? One for the temporary drying beds and another truss frame structure for the permanent drying beds?
| Drawing 02C132 | The requirements as shown on drawing 87S100 only apply to the permanent drying bed as shown. A steel fabricated structure is not required at temporary drying beds. | 4 |
| 96 | General Sheet Note 4 on Drawing 87S401 indicates Metallic Aggregate Topping and Armored Joint Treatment and Hardware are to be included in the slab concrete construction. |
Are these elements of the work required for the 2 temporary drying beds or just in the construction of the permanent work?
| Drawing 87S401 | The requirements as shown on drawing 87S100 only apply to permanent facility. Metallic aggregate topping and armored joints are not required on the temporary drying beds. | 4 |
| 97 | Section 2.02 A.1.a of Specification 03 35 00, lists two Metallic Aggregate Topping Mix products, but neither appears to be available by the listed product names. Euclid Chemical Co. makes a product called "Diamond-Plate" which can be applied either as a dry shake to wet concrete, or as a screedable formulation. Master Builders has been purchased by SIKA Corporation and all the Master Builder products have been re-branded under SIKA product names. Anvil-Top 300 has been re-branded as "Sikafloor MetalTop-300", which is described as a "Metallic dry-shake surface hardener". |
Please clarify if Diamond-Plate and Sikafloor MetalTop-300 are the appropriate, currently available replacements to the listed products, and whether the application of the Metallic Aggregate Topping must be as wet mixture and not a dry-shake.
| Specification 03 35 0 | All products that meet the salient characteristics requirements of Specification Section 03 35 00 are appropriate for use. | 4 |
| 98 | The Flow pumps that are basis of design in section 44 42 56.03 The motor data sheet on page 15 of this section calls for the Cascade mixed flow pump motors to have a CISD-TEFC enclosure. When we reference Low-Voltage AC Induction Motors Section 26 20 00 – 2.15.B.15 it lists 2 different service factors based on the Ambient Temperature rating of the motor(see snipet below). The motor manufactures are asking for us to provide clarity on what temperature rating the motors need to be designed to, 40 Degrees C or 65 Degrees C. We don't anticipate the Yosemite valley ever experiencing prolonged temperatures that would require a 65 Degree C motor rating, but wanted to confirm. |
From Page 26 20 00-9
15. Service Factor:
a. At 40 Degrees C Ambient: 1.15
b. At 65 Degrees C Ambient: 1.00.
| Motor Data sheet | Provide 40 Degrees C Ambient: 1.15 | 6 |
| 99 | Section 3.08 of Specification 03 10 00 says, "Provide form liner manufacturer’s representative at Site for installation assistance, and inspection." |
Please indicate whether the intent is for the representative to be on site for the complete duration of form liner installation on the project, or on some other limited basis. If the intent is the latter, please provide duration parameters.
| Specification 03 10 00 | Continuous site presence from form liner representative is not required. The representative shall be on site for initial form liner application for assistance and inspection with additional site visits as needed based on additional quality control need or requests from the field. | 6 | ||
| 100 | Several significant existing structures are to be demolished per the drawings/specifications. The current contract documents do not provide sufficient information to accurately estimate the amount of work required to complete the demolition scope. Please provide record drawings / As-Builts for all structures that are to be demolished. | Demolition | See responses above | 6 |
| 101 | Please confirm the plant will drain and flush existing chemical lines and process piping prior to demolition of existing structures. If not, please confirm any leftover grit, sludge, etc. can be pumped back into the existing headworks. Also, please consider providing an allowance for this work as quantities are unknown. | Demolition | Contractor should assume to provide all flushing, draining, and pumping required to move wastewater fluids from the existing plant to the new treatment system. | 6 |
| 102 | Facility 11 Drawings indicate the existing Septage Receiving Tanks 1 and 2 must be cleaned. |
What amount of material/sludge/grit should the contractor assume will need to be removed from these existing tanks? Can this material be pumped back into the plant process, or will it need to be hauled offisite?
| Facility Drawings | Contractor should assume that each septage receiving tanks are appoximately 1/3 full of solids, with heavy compaction in the south tank. Material can be disposed of in the temporary drying beds. | 6 | ||
| 103 | On the polymer feed system, plans show two liquid polymer feed systems downstream of dry polymer makeup systems for both the tertiary system – building 40 and the dewatering system – building 65. Please reference tags 040-P-540/550 and 065-P-440/450. There do not appear to be any technical specifications for these qty (4) systems. Please address if these systems are necessary and if so please provide a technical specification. | Polymer Feed System |