This document is a pre-proposal site visit presentation for the YOSE 196416 Rehabilitate El Portal Wastewater Treatment Facility and Administrative Camp project in Yosemite National Park, California.
The project will rehabilitate the 45-year-old, 1.0 MGD El Portal wastewater treatment facility, including constructing new headworks, secondary treatment, and aerobic digestion processes, as well as rehabilitating the existing tertiary and dewatering systems and upgrading the electrical systems and SCADA. It will also rehabilitate the former El Portal Trailer Village to serve as RV sites for construction workforce housing and a contractor staging area. The solicitation will be posted in October 2024, with award expected in the first quarter of 2025. The contract will be a single firm-fixed price award with a 1,460 calendar day period of performance. Questions should be directed to the National Park Service's Denver Service Center contracting personnel.
View the file
Other files
Show 40 more
Latest 50 of 87 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NPS ● 2024
PRE-PROPOSAL SITE VISIT
FOR
REHABILITATE EL PORTAL WASTEWATER
TREATMENT
FACILITY AND ADMIN CAMP
YOSEMITE NATIONAL PARK
Notice ID: 140P2025R0008
NPS PMIS #: YOSE 196416
October 23, 2024
THIS MEETING WILL BE NOT RECORDED
AGENDA
• CONFERENCE ROOM 8:00-8:45 am
• INTRODUCTIONS and WELCOME - (Mike Luecker & Paula Teague)
• Yosemite Staff, Jacobs Engineering (Dan Robillard) & DSC (Patrick Naulty & Evan Yates)
• PURPOSE, PROJECT OVERVIEW & TIMELINE (Mike Luecker& Paula Teague)
• BREAK 8:45-9:00 am
• WALK THROUGH EL PORTAL WWTF 9:00-10:30 am
• BREAK/TRAVEL 10:30am-11:00am
• WALK THROUGH ADMIN CAMP AREA 11:00am-12:00pm
• Closing remarks at the conclusion of admin camp walk through.
• Attendees List, presentation & handouts will be included as an Amendment to the Solicitation
2 YOSE 196416 EL PORTAL WWTF & ADMIN CAMP PRE-PROPOSAL SITE VISIT
PURPOSE
• Visual orientation for contractors and subcontractors who are interested in the project
• Opportunity to visit the site
• Provide questions in writing to Contracting
Ground Rules
• Site Access is not permitted beyond Pre-Proposal site visit
• Pictures are allowed during Pre-Proposal site visit
• Stay with group during site visit
• Please leave no trace
• Park/drive on paved surfaces at Admin Camp
• No restrooms or potable water available at Admin Camp
• Information provided or responses to questions that may be stated during the Pre-Proposal site visit may not be reflected in the solicitation. Interested parties must review the requirements as posted in the solicitation and amendments as issued.
YOSE 196416 EL PORTAL WWTF & ADMIN CAMP PRE-PROPOSAL SITE VISIT
YOSE - 196416 El Portal WWTF and Admin Camp
• Location: Yosemite National Park, California
• Magnitude of Construction: Greater Than $150M
• Design & Construction Method: Design – Bid – Build
• EP WWTP and Admin Camp are connected; One firm fixed contract with a single period of performance
• Procurement Method: Full & Open
• Key Dates:
• Sources Sought Posting: January 2024
• Solicitation: Posted October 4, 2024
• Award: Expected 1st quarter 2025 (Jan-March)
• Solicitation #: 140P2025R0008
• NAICS: 237990
• Period of Performance: 1,460 Calendar Days
• Construction Management Representative
Services: Procurement via General Services Administration (GSA) Task Order
4 YOSE 196416 EL PORTAL WWTF & ADMIN CAMP PRE-PROPOSAL SITE VISIT
El Portal WWTF This project will rehabilitate the 45-year-old WWTF to improve treatment efficiency & meet current standards. Project Scope includes:
• The wastewater processes will be designed for a nominal capacity of 1.0 MGD.
• New treatment processes constructed at the existing plant site including headworks, secondary treatment, and aerobic digestion.
• Rehabilitation of the existing tertiary and dewatering processes.
• Replacement and upgrade of the electrical systems throughout the treatment plant.
• New operations and maintenance facilities.
• The new facilities will be constructed on the existing site, while maintaining operation of the existing treatment processes.
• Upgrade SCADA for El Portal WWTF and wastewater lift stations within the El Portal service area.
• Demolition of the old treatment process facilities.
5 YOSE 196416 EL PORTAL WWTF & ADMIN CAMP PRE-PROPOSAL SITE VISIT
Admin Camp - Improvements The existing El Portal Trailer Village will be rehabilitated for use as a contractor camp for the duration of the El Portal WWTF project. Project Scope includes:
• Development and rehabilitation of 30 RV camping sites
• Improvement of existing roadways and paved areas
• Rehabilitation and/or replacement of existing utilities
(water, sewer and electrical)
• Removal of existing structures & clean up
• Temporary RV Sites outside limits of construction
• Does not include rehabilitation/replacement of the existing laundry, restroom and shower facility.
6 YOSE 196416 EL PORTAL WWTF & ADMIN CAMP PRE-PROPOSAL SITE VISIT
Questions
•Direct all questions to the DSC Contracting Office
• Contracting Officer: Paula_Teague@NPS.gov
• Contracting Specialist: Patrick_Naulty@NPS.gov
•Attendees List, presentation & handouts will be included as an Amendment to the Solicitation
• Information provided or responses to questions that may be stated during the Pre- Proposal site visit may not be reflected in the solicitation. Interested parties must review the requirements as posted in the solicitation and amendments as issued.
YOSE 196416 EL PORTAL WWTF & ADMIN CAMP PRE-PROPOSAL SITE VISIT
WWTF Tour Route
8 YOSE 196416 EL PORTAL WWTF & ADMIN CAMP PRE-PROPOSAL SITE VISIT
Admin Camp Tour Route
Pre-Proposal Site Visit Parking
Meet at Laundry Bldg
NOTICE:
Please leave no trace Park/drive on paved surfaces only Do not enter structures No restrooms available No potable water available
YOSE 196416 EL PORTAL WWTF & ADMIN CAMP PRE-PROPOSAL SITE VISIT
Lift Station Route
Thank you
10 YOSE 196416 EL PORTAL WWTF & ADMIN CAMP PRE-PROPOSAL SITE VISIT
Information provided or responses to questions that may be stated during the Pre-Proposal site visit may not be reflected in the solicitation. Interested parties must review the requirements as posted in the solicitation.
| PRE-PROPOSAL SITE VISIT�FOR� Rehabilitate El Portal Wastewater Treatment�Facility and Admin Camp�YOSEMITE National Park |
| AGENDA |
| PURPOSE |
| YOSE - 196416 El Portal WWTF and Admin Camp |
| El Portal WWTF |
| Admin Camp - Improvements |
| Questions |
| WWTF Tour Route |
| Admin Camp Tour Route |
| 10 |
File details come from the government source that posted it. Updated .