B09_BICY_229154_Questions_Responses_Spreadsheet_Amend05_0005.xlsx
XLSX spreadsheet 25 KB Posted
- Attached to
- BICY 229154
- Solicitation number
- 140P2024R0084
About this file
This is a Questions and Answers document containing 41 contractor questions and government responses regarding the construction of a Fire Station at Big Cypress National Preserve Headquarters Complex. Key clarifications include: no fire alarm/suppression systems are required, naturally vented port-a-johns are acceptable, the contractor is only responsible for providing construction documentation for green building certification, no extensions are automatically granted for long-lead items, and the Period of Performance is 12 months (though partial Notice to Proceed may be issued for long-lead items).
Notable technical specifications addressed include: wall panel requirements (R-19.5 composite value minimum, 2" minimum thickness), road crossing repair details (4" depth asphalt), utility responsibilities (LCEC to provide poles and overhead wire, contractor to provide underground conduits), and clarification that irrigation is not required though water access will be provided for grass establishment. The government confirmed they are not providing fill dirt, all government permits will be provided before Notice to Proceed, and the bid due date is January 10th.
View the file
Other files
Show 40 more
Latest 50 of 56 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI's
| PARK: | BICY |
| PMIS #: | 229154 |
| Project Name / Description | Construct Fire Station |
| Amendment | P0005 |
| Question # | Question: | Date Rec'd | Answer: |
| 1 | Could you please help us locate the complete specifications for Wall (MP-1) and Wainscot (MP-2) as shown on Sheet #23 (Sub A2.01)? |
| We were able to find the roof specifications but are having trouble finding the details for the Wall and Wainscot. | 13-Sep | This is in Specification Section 13 3419 Metal Building Systems part 2.4. | |
| 2 | FILL DIRT |
Additionally, during the site visit on September 24, CRANK Representative Eric Lien noted that there was mention of fill dirt being provided by Big Cypress for this project. Given our expectation of a 24/7 pump requirement to manage water on-site during construction, it would be extremely helpful to confirm the provision of fill dirt so we can better control our costs.
If the fill dirt will indeed be supplied, could you please provide this confirmation in writing? Alternatively, would it be necessary to administer an amendment for this? 14-Oct NPS is not furnishing any fill dirt for the BICY project.
| 3 | Will the Government provide the sign in sheets for all site visits that have occurred for this project? | 24-Oct | The sign in sheet for Site Visit #1 was uploaded to the solicitation at Sam.gov on 9/26/24. The sign in sheet for the second site visit will also be uploaded. |
| 4 | Will the Government provide a copy of all RFIs with responses that have been submitted for this project? | 24-Oct | Yes. Questions and RFI responses will be uploaded at Sam.gov. |
| 5 | Will the Government confirm that fire alarm and suppression systems for the fire station building is not required? | 24-Oct | Confirmed |
| 6 | Will the Government confirm that natural ventilation port-a-johns are acceptable? | 24-Oct | Yes, naturally vented port-a-johns are acceptable. |
| 7 | The RFP lists Green Building, Green Seal, and LEED standards for the procurement of materials with the possible intent of certification at the end of the project. Will the Government confirm that the contractor is only responsible for providing construction documentation to the DOR and that the DOR is responsible for all certification actions? | 24-Oct | Confirmed |
| 8 | Certain long lead items, like the generator, may take longer than the specified period of performance. Will the Government clarify how time of time extension will be handled due to procurement issues beyond the contractor’s control? | 24-Oct | No extensions to the required Period of Performance are included in the contract for long-lead items. Period of Performance extensions must be requested with justification by the Contractor and approved by the Contracting Office on a case-by-case basis. |
| 9 | Will the Government provide the expected turnaround duration for RFI responses? | 24-Oct | RFI response times vary depending on the nature of the request. The Government makes every attempt to answer RFI's expeditiously. |
| 10 | Will the Government provide a copy of all Government furnished permits for the project? | 24-Oct | The required Government Furnished permits and statuses are as follows: |
1. FDEP Wastewater Extension Notification - in hand and uploaded to solicitation as part of Amendment 3
2. SFWMD Environmental Resource Permit - pending SFWMD approval
3. USACE Nationwide Permit Application - pending SFWMD permit and USACE approval
4. FDEP NOI - in hand and uploaded to solicitation as part of Amendment 3
All government furnished permits will be finalized and provided to the contractor prior to issuance of Notice to Proceed.
| 11 | Will the Government provide a list of permits, not including the NPDES permit for SWPPP from FDEP, that are required for this project? | 24-Oct | See Specifications Section 01 31 00, Paragraph 1.9 for information regarding government (owner) furnished and contractor furnished permits. |
| 12 | The provide drawings show no utilities or underground structures in the project limits. Will the Government confirm that anything encountered will be covered by unforeseen conditions? | 24-Oct | See Solicitation for Federal Acquisition Regulation 52.236-2 Differing Site Conditions. |
| 13 | Will the Government confirm if any GFGI or OFOI equipment will be installed prior to project completion? | 24-Oct | The contractor shall assume that all equipment indicated to be government furnished, contractor installed will be provided for installation prior to project completion, and in accordance with Specification Section 01 10 00, Paragraph 1.4. |
| 14 | Will the Government confirm the project site is in an industrial area for acceptable sound levels determination during the workday? | 24-Oct | See Specification Section 01 57 19.12 "NOISE AND ACOUSTICS MANAGEMENT", Paragraph 3.1 for acceptable noise levels. Correct, the area falls under Commercial/Industrial receiving area. |
| 15 | Will the Government clarify how many personnel are required to fulfill the Site Superintendent, QCM, and SSHO functions? | 24-Oct | The Superintendent shall have no other duties. The Qaulity Control Manager and Safety Officer duties may be combined for an appropriately qualified person. See revised Spec Section 01 40 00 as part of Amendment 3. |
| 16 | Will the Government confirm the Contracting Officer's temporary site tailer does not require temporary water and sewer tank capabilities? | 24-Oct | The restrooms in the temporary site trailer(s) should have water and sewer. |
The intent is for the construction trailer to be the type that comes with a water tank and sewer tank, with water refill and sewer pumping on a regular schedule.
| 17 | Will the Government accept a virtual preconstruction meeting? | 24-Oct | The Preconstruction Conference shall be conducted on site. |
| 18 | The RFP states that the Government will provide water access for the grass maintenance period until the irrigation system is operational. However, an irrigation system is not shown in the scope of work or drawings. Will the confirm water access will be provided until the grass is established? | 24-Oct | Irrigation is not required. See revised Specification 03 92 00 issued as part of Amendment 3. The Park allow access to water for purposes of establishing grass. |
| 19 | Will the Government confirm that the soil within the project limits is not contaminated for disposal purposed? | 24-Oct |
The soils were not tested for contamination. There are no reports of contamination. If the removed soil is suspected of contamination, notify the Government.
| 20 | Will the Government clarify if observations wells are required for this project? | 24-Oct | If Dewatering is required, then observation wells shall be utlized as required by Specification Section 31 2319. |
| 21 | Specification 09 91 13 calls for a mockup of exterior paint that may remain as part of the work . Specification 13 34 19 requires that metal panels arrive finished at the factory to the greatest extent possible. Will the Government confirm that mockups are not required for this project? | 24-Oct | Field painting does not include the prefinished metal panels. Field painted items are limited in quantity and would be things like the hollow metal doors. Due to the small scope of work, the mock up requirement has been removed. See revised 09 91 13 spec as part of amendment 3. |
| 22 | Specifications 13 34 19 calls for standing seam wall panels in section 2.4 A. Wall panels do not come with standing seams because the seaming machine is only designed for use on a roof and could damage the wall panel during installation. Will the Government clarify the panels are to be fabricated with the industry standard (tongue and groove style connect with concealed screws) instead of using standing seams? | 28-Oct | Standing seam language was a mistatement of the product. The design intent is for a vertically oriented wide rib profile for the upper panels and a horizontally oriented narrower rib profile for the lower panels. NuCor CF Flute is an example of a vertically oriented wide rib profile. NuCor CF Mesa is an example of a horizontally oriented narrower rib profile. See revised specification 13 34 19 as part of amendment 3. |
| 23 | Specification 13 34 19 section 2.1 O calls for wall panels to have a combined R-19.5 rating. Section 2.4 calls for R-17.5 rating. Will the Government clarify the required R rating of the wall panels? | 28-Oct | The overall wall composition R value of 19.5 is a minimum composite value. The continuous insulation (ci) requirement for the wall panel is R-17.5. See revised specification 13 34 19 as part of amendment 3. |
| 24 | Specification 13 34 19 calls for a 2” thick panel. This type of panel is typically used for architectural items and may not meet building code. Will the Government clarify if 2.5” thick panel is what should be used? | 28-Oct | 2" is a minimum. A 2.5" thick panel is acceptable. Performance values of wall panels vary by manufacturer. If 2.5" is required to meet the loads indicated with the selected manufacturer, then use that. |
| 25 | Specification 13 34 19 section 2.1 B says to follow Metal Building Systems Manual (MBSM) standards and then provides structural performance standards shown in exceeds the MDMA standards. These change will increase the cost of construction. Will the Government clarify if MDMA serviceability limits or provided serviceability limits should be used? | 28-Oct | Use the loads and limits per Spec Section 13 3419, Paragraph 2.1.B.1 and 2.1.B.2 |
| 26 | Is builder’s risk required on this project? | Refer to solicitation clause 1452.228-70 Liability Insurance (JUL 1996) for what the contractor is required to procure in regards to this project | |
| 27 | Is there an irrigation system required for this project? | Irrigation is not required. See revised Specification 03 92 00 issued as part of Amendment 3. The Park allow access to water for purposes of establishing grass. | |
| 28 | Please provide details of the handrail outside the building. | See Specification section 05 5213 Pipe and Tube Railings 2.1. The handrails attachments are a delegated design item and will be provided by the handrail supplier. | |
| 29 | Please provide acoustical ceiling tile type specification. | See spec 09 5100 Acoustical Ceilings | |
| 30 | Is the exterior signage by Owner? If not, can you give us the material & size for this? | If this is the accessible parking sign, the dimensions are on C 1.04. SIGN FTP-20-06 mentioned in detail is .080 aluminum treated with Alodine. | |
| 31 | Is the appliance by Owner or GC’s will be supplying it? | See specialty equipment schedule on A6.02 for list of equipment/appliance and what is furnished by government. | |
| 32 | For Option 3, please give us details on how to attach the solar panels to the roof panels. | See Specification section 26 3100 Photovoltaic Collectors. Attachment details are a delegated design and will be provided by the manufacturer. | |
| 33 | Drawing C1.06 shows a road crossing repair for the installation of the new force main from the new lift station. This road crossing is shown to have a minimum of 10’ section removed and replaced. Confirm this road is asphalt and if so, what is the thickness of the pavement? | The road where the force main crosses is 4" depth asphalt. | |
| 34 | Are there any specific permits required for the lift station? Confirm this permit will be by NPS if one is required. | The lift station was permitted with FDEP. | |
| 35 | It was stated at the site visit the retention area is going to be revised. What is the timeframe as to when the new layout will be provided? | Any revisions to the site layout will be provided no less than 10-business days prior to the proposal due date. | |
| 36 | E0.03 shows new utility poles, overhead wire, and underground duct bank to be provided. Please confirm these all to be provided by LCEC. | Proposed utility poles and overhead wire will be installed by LCEC. Underground conduits from utility pole to transformer will be provided by Contractor (Refer to Special Note #3). Special Notes #1 and #2 indicate additional work by Contractor and LCEC per LCEC requirements handbook. | |
| 37 | E0.03, note 9 states details on E5.01 for the duct bank. E5.01 does not show any details with 3 conduits. Details 5 and 6 show one conduit in each with 5 showing open cut and 6 under pavement. Confirm there are no spacers required between the conduits, and no concrete is required to encase the conduit. | Detail is generic and intended to show depth and fill requirments. Provide 7-1/2" spacing (center-to-center) between conduits. Concrete encasement not required. | |
| 38 | Spec section 23 38 13, Kitchen Hood, what manufacture is the base’s of design for the kitchen hood? | See specialty equipment schedule on A6.02 | |
| 39 | S1.01, Option A is noted at the section cut details at column line F. Please clarify, this is to be bid option 1, which is to extend the slab and roof structure. Please confirm if this bid option is accepted, it will be selected for the contract award and not later in the project. This will affect the PEMB submittals and fabrication. | Correct, Option A is the first bid option, which is to extend the slab and roof structure. If it is accepted it will be at the time of contract award. | |
| 40 | The project duration of 12 months will not be long enough. With contracts, submittals, approval, and the 16–20-week lead time for delivery of the building. This will be a minimum of 16 months to complete the project. | Period of performance shall be continously evaluated during construction and is subject to change due to unforseen circumstances. The government will consider issuance of a partial NTP that would allow for approval of submittals and initiation of procurement for long lead items prior to issuing a NTP that commences the contract period of performance. | |
| 41 | We are requesting the bid date be extended, the Monday after a 4-day weekend holiday, is not desirable. Subs and vendors tend to be checked out for a needed time off, as I’m sure the government is as well. | The bid due date is January 10th at the time of this response. |