140P2022R0036-0008_Att01_QuestionsAndResponses_01-38_221110_0008.pdf

PDF 337 KB Posted

Attached to
STLI-312431, Rehab Exterior Systems of MIB (GAOA)
Solicitation number
140P2022R0036
Issued by

About this file

This document contains questions and responses related to solicitation number 140P2022R0036 for the rehabilitation of exterior systems at the Main Immigration Building on Ellis Island. The solicitation seeks proposals to replace clerestory windows, skylights, repair terra cotta tiles and repoint brick joints. The submission deadline was extended to December 2nd, 2022. Proposals should include pricing for base line work and optional additions such as replacing clerestory lighting. Questions addressed insurance requirements, the use of scaffolding, equipment access via bridge or barge, and clarified the quantities of asbestos abatement work required.

View the file

Other files

File Type Posted
140P2022R0036-0010_Att01_QuestionsAndResponses-Final_01-112_221129_0010.pdf PDF
140P2022R0036-0010_Att02-RevClausesAndProvisions_221129_0010.pdf PDF
140P2022R0036-0010_Att01a-Q55_ContractPriceSchedule-Final_221129_0010.xlsx XLSX spreadsheet
Sol_140P2022R0036_Amd_0010.pdf PDF
140P2022R0036-0009_Att01b-Q39_HazMatTestingReport_211119_0009.pdf PDF
140P2022R0036-0009_Att01a-Q39_EllisIslandHazMatSurvey-Finalwattachs_211108_0009.pdf PDF
Sol_140P2022R0036_Amd_0009.pdf PDF
140P2022R0036-0009_Att01_QuestionsAndResponses_01-58_221118_0009.pdf PDF
Sol_140P2022R0036_Amd_0008.pdf PDF
Sol_140P2022R0036_Amd_0007.pdf PDF
140P2022R0036-0007_Att02-STLI_305028-RevSpec085200-Wood_Windows_221107_0007.pdf PDF
140P2022R0036-0007_Att01_QuestionsAndResponses_01-34_221108_0007.pdf PDF
140P2022R0036-0006_Att01-DVB_GD_No_NY03_New_York-BHHR_221104_0006.pdf PDF
Sol_140P2022R0036_Amd_0006.pdf PDF
Sol_140P2022R0036_Amd_0005.pdf PDF
140P2022R0036-0005_Att01-SiteVisitSignIn_221103_0005.pdf PDF
Sol_140P2022R0036_Amd_0004.pdf PDF
140P2022R0036-0004-Att01a-Q06_MIBLimitedAsbestosInspectionReport_200722_0004.pdf PDF
140P2022R0036-0004_Att01_QuestionsAndResponses_01-18_221027_0004.pdf PDF
Sol_140P2022R0036_Amd_0003.pdf PDF
140P2022R0036-0002_Att01a-PreProposal_Mtg_Presentation_wNotes_221019_0002.pdf PDF
140P2022R0036-0002_Att03a-STLI_305028-Specifications-Rev_221017_0002.pdf PDF
140P2022R0036-0002_Att01b-PreproposalMeetingSignInSheet_221019_0002.pdf PDF
140P2022R0036-0002_Att03b-XRF_LBP_InspectionReport_200722_0002.pdf PDF
140P2022R0036-0002_Att02-RevClausesAndProvisions_221021_0002.pdf PDF
Sol_140P2022R0036_Amd_0002.pdf PDF
140P2022R0036-0001_Att01-_DVB_GD_No_NY03_New_York-BHHR_220916_0001.pdf PDF
Sol_140P2022R0036_Amd_0001.pdf PDF
140P2022R0036_Att01a-STLI_312431-Specifications-Final_220520.pdf PDF
Sol_140P2022R0036.pdf PDF
140P2022R0036_Att05-SubKPlanForm_220509.docx DOCX document
140P2022R0036_Att02a-STLI_312431-Drawings-Final_220601.pdf PDF
140P2022R0036_Att04a-ProposalSubmissionPackage_220602.zip ZIP file
140P2022R0036_Att02b-STLI_305028-Drawings-Final_220601.pdf PDF
140P2022R0036_Att03-DVB_GD_No_NY03_New_York-BHHR_220805.pdf PDF
140P2022R0036_Att04b_ProposalSubmissionPackage-Sample_220602.pdf PDF
140P2022R0036_Att06-StatementOfStructuralTestsSpecialInspections_220513.pdf PDF
140P2022R0036_Att07-Final_CloseoutProcedures_OM_220601.pdf PDF
140P2022R0036_Att01b-STLI_305028-Specifications-Final_210423.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P2022R0036 Questions and Answers – Amendment #0008 11/10/2022

The following is a consolidated list of current vendor questions. Responses in red shall address questions not previously responded to or provide updates to questions in which responses had been previously provided. Please note that responses in blue (other than email or web page links) are pending responses, which will be provided in a future amendment.

1. After review of the submittal schedule, we note that the pre‐proposal site visit is October 19, 2023, pre‐proposal questions must be submitted by October 24, and the proposal submittal date is November 2, 2022. This schedule does not provide adequate time to incorporate information from the site visit and NPS responses to questions into the final proposal. Therefore, [the Vendor] requests that the submittal date be extended to November 23, 2022.

Response: The date for submission of proposals has been extended to 2:00 pm EST, Friday, November 18, 2022. See Amendment 0002.

2. For Volume 1, Factor 5 Small Business Participation, what kind of documentation is NPS looking for proposing teams to submit to demonstrate supporting proposed quantitative participation?

Other than call log spreadsheets and binding commitments, what would NPS like to have submitted?

Response: A sample copy of the requirements identified in Section M, Paragraph C.e, (pages 55‐

56) have been provided for your use in the proposal submission package attachments included in the solicitation. Other forms of contractor developed information will be accepted.

3. Can previously completed/submitted Past Performance Forms be used for this submittal for relevant projects or are we required to seek new forms from each client?

Response: Previous project questionnaires may be reused; however, the past performance questionnaires must be submitted by the reference directly to NPS and the reference point of contact shall reference this project.

4. For Volume 1 Evaluation Factor 1 – Project Experience – requires that the proposing team demonstrate “barging experience for transporting equipment and materials.” Will the successful team be permitted to transport equipment and materials over the access bridge from Liberty State Park in New Jersey, or will barges need to be used?

Response: The barging experience requirement was erroneously incorporated into the evaluation factors and has been removed. See Amendment 0002.

5. In the clerestory windows drawings, A2.0 and A2.1 there is missing text pointing to scopes of work. Please clarify what that missing text next to the pointers yes.

Response: The leaders with no text on clerestory drawings A2.0 and A2.1 do not include additional scopes of work. The text removed from these drawings is scope that is included on the crack and patching repairs shown on the STLI 312431 construction drawings.

6. Please clarify if drawing H2.0 shows that window are ACM and require an Abatement Contractor to do the removals or if it’s just the caulking that can be removed prior to dismantling the windows.

Response: The drawing indicates the location of ACM at the exterior window glazing and “Exterior Window Frame Caulk – Gray”, please see the attached “Limited Asbestos Inspection Report at Main Immigration Building, Ellis Island, New York, NY”, prepared by AIM Environmental LLC., AIM Project # 20‐07‐210, dated July 22, 2020.

7. Drawings A3.0 calls out work at light fixtures are Bid Option 3 while the Bid Schedule calls it as 4.

Clarify which is correct Response: Work at light fixtures shown on drawing A3.0 of the clerestory window package is included in Bid Option 4.

8. Drawing A4.0 note 9 references Bid Option 1 as providing a secondary metal storm windows. Bid option 1 in the bid schedule is Atrium Skylight Replacement. Please clarify where to include the storm windows.

Response: Note 9 on Drawing A4.0 referencing secondary metal storm windows as Bid Option 1 is incorrect. Secondary metal storm windows for the clerestory windows are part of the base bid in CLIN 1. (STLI 312431 specification section 012700).

9. Please clarify the expected working hours of the project

Response: Per STLI 312341 specification section 011000, working hours are as follows:

On‐Site Work Hours:

1. Seven days a week, 6:00am to 6:00pm, subject to limitations on deliveries and hours for passing through USPP Security.

2. Liberty State Park opens at 0600.

3. Restrictions/Accommodations for special events may be encountered. Notification will be provided to give the Contractor as much advanced notice as possible. No additional costs will be provided for coordination with NPS events.

10. Please clarify if suspended scaffolding will be allowed for the exterior rehabilitation work.

Response: It is the contractor’s responsibility to determine appropriate means and methods to complete the work. However, in accordance with Specification Section 040322, scaffolding may not be mechanically fastened to the building.

11. Please provide load restrictions for the Ellis Island Bridge.

Response: Please see STLI 312431 specifications section 011100 ‐ SUMMARY OF WORK ‐

APPENDIX C.

12. Will a Crane and heavy machinery be allowed on site? If yes, please show points of entry for a barge or will be use of the bridge be allowed.

Response: Cranes and heavy machinery are allowed on‐site. Access for larger machinery may be limited by existing conditions (sidewalk widths, trees, etc.). Contractor shall get Contracting Officer’s approval for modifications to existing conditions for access purposes. Contractor is responsible for any additional costs associated with modifications to existing conditions for mobilization and operation. Contractors are allowed to use the bridge, following loading restrictions. See question 11 above.

13. Will a helicopter be allowed for the transportation of the skylights to the roof of the building?

Response: Yes, a helicopter may be permitted provided all appropriate safety, access and coordination plans are coordinated and approved by the Contracting Officer, STLI, United States Park Police and other applicable agencies.

14. In the façade scope, On Drawing A1.2 detail note 2/A1.2/A5.3 shows tile and lighting protection work while at the same time the note to the right says, “Existing terra cotta tile roof protect areas not in scope”. Please clarify if that not is actually in scope and not many tiles will have to be removed on each side.

Response: Contractor is required to protect the existing roof at all times. Removal and replacement of terra cotta tiles is required to complete some scope items. Work plans reflecting impacts to terra cotta tile and associated scope shall be submitted to Contracting Officer for approval prior to commencement of work.

15. Will scaffolding we allowed inside the rooms under the skylights that are to be replaced?

Response: Scaffolding will be allowed pending approval of proposed work plan.

16. Please provide the sign‐in list for the walkthrough dated 10.19.2022.

Response: See Amendment 0002.

17. Please provide the insurance requirements for this project.

Response: Insurance requirements are provided in contract clause 1452.228‐70, Liability Insurance (page 30 of 57 in the contract clauses). Specifications section 013100, paragraph 1.4.D.7 of the STLI 312431 specifications addresses the contractor’s requirement to provide a certificate of liability insurance. General liability, automobility and workman’s compensation must be provided by each firm performing on‐site work on this project.

18. Please verify if this project is CCIP or OCIP and if there is Builder’s Risk + deductable.

Response: Refer to Question 17 for insurance requirements. Insurance above and beyond the general requirements provided is at the contractor’s discretion.

19. After review of the project construction documents and based on information gathered during two site visits, [the vendor] believes that the current due date for this bid proposal, November 18, 2022, does not provide adequate time to incorporate into the final proposal. In addition, Requests for Information are due November 11, 2022, which only allows for a very brief window for review and incorporation of responses to the requests. Therefore, [the vendor] requests that the submittal date be extended to December 2, 2022.

Response: The submittal date for this solicitation is being extended to Friday, December 2, 2022, per Amendment 0007. The date for submission of questions is also extended, but has been changed from Wednesday, November 23, 2022, to Friday, November 18, 2022, due to the holiday per Amendment 0008.

20. Is only the removal and reinstallation of the existing lighting at the (6) Clerestory Windows to be included in Base Bid 001 Lump Sum price for Clerestory Window Replacement? If so, is only the addition of supplying new lighting to be included in Bid Option 4: Replace Clerestory Lighting?

Response: Yes, please include the removal and reinstallation of the existing lighting in the base bid. Please include only the additional price for the addition of new lighting and new lighting controls in Bid Option 4.

21. Please confirm that all “repair sill” comments shown on the Window Restoration Schedule are in reference to the wood sills of the window (not the stone sills).

Response: Correct, any repairs identified on the Window Restoration Schedule are for wood sills and all stonework is shown on other drawings within the Construction Drawing Set.

22. Where are the structural drawings mentioned in the Façade Package Drawings?

Response: All the structural drawings for this project are noted on the sheet list for STLI 312431 and included within that Construction Drawing Set.

23. Are pubic areas under the Reading Room (south), Listening Room (North), and Atrium Skylights able to be closed to the public during the skylight construction? If so, is there a time limit on the area being closed?

Response: Yes, subject to an approved work plan as reviewed and approved by the Park and Contracting Officer. All closures shall be minimized.

24. The allowed time defined for work is 6am to 6pm, seven days a week. Is the intention for there to be work ongoing 7 days a week in twelve hour shifts or would you like our proposals to reflect regular hours?

Response: Contractors may utilize their own work schedule to meet the period of performance within defined work hours. Work outside of these hours may be permitted pending request and approval by the Contracting Officer.

25. Are there any day or time constraints for delivering materials on site via loading bridge?

Response: Specification Section 01 1100 Appendix B under “Truck Deliveries & Access” indicates deliveries via Post IV may be arranged (7) days a week between 0700 and 1400 (48) hours in advance. Deliveries will be scheduled with NPS on a delivery‐by‐delivery basis. There will be coordination with other active construction projects.

26. Upon review of the Limited Asbestos Inspection Report, dated July 22, 2020, and specification

028200, the following quantities of asbestos were reported:

Roof 600 sf (Remove approximately 600 square feet of waterproofing tar and remnant flashing applied at flat roof parapet and roof transition)

Clerestory windows 3rd Floor – Exterior (Within Areas of Window Work) – 4,200 lf

Are these the quantities of asbestos requiring abatement?

Response: The quantities are provided for bidders; however, the contractor shall field‐verify all quantities prior to the start of construction. Any quantity difference between the contract documents and field‐verified condition shall be addressed via the contract changes clause.

What area of the roof requires abatement?

Response: Areas of the roof requiring asbestos abatement are shown on drawing ABT1.0 in the STLI 312431 construction drawings.

27. Is Drawing H1.0 referring to the correct location of windows requiring asbestos abatement? It appears to be in conflict with Drawing H2.0. Are the locations of the windows to be abated shown in red arrows below?

Response: Yes, drawing H1.0 shows the correct locations of windows requiring asbestos abatement. The 8 clerestory windows requiring abatement are shown on both H1.0 and H2.0;

however, the contractor shall field‐verify all quantities prior to the start of construction. Any quantity difference between the contract documents and field‐verified condition shall be addressed via the contract changes clause.

28. Stripping – Wood Windows: In reviewing the specification, it is not entirely clear whether the windows are to be stripped to bare wood or just scraped and painted. Which is being required?

Response: Per A4.5 “stripping” is required for all level 1 and level 2 windows. Stripping shall be full paint removal to bare wood so that all surfaces are sufficiently clean and free of paint prior to refinishing.

29. Removal – Wood Windows: Can the window sashes, wood trims, and hardware be restored offsite? The only place we see direction is in Part 3 ‐Execution. Section G. Protection of Openings:

where sash or windows are indicated for removal, cover resultant openings with temporary enclosures so that the openings are weather tight during the repair period. We find no indication anywhere for what windows are to be removed.

Response: Windows may be removed for restoration on or off‐site per Contractor’s means and methods. An inventory of all windows shall be conducted as noted in the Project Manual prior to removal to locate, identify, and label all elements appropriately.

30. Steel Windows: The steel windows for the same reasons as stated above should be removed for a complete rehabilitation. Can the steel windows be removed from the job site?

Response: Windows may be removed for restoration on or off‐site per Contractor’s means and methods. An inventory of all windows shall be conducted as noted in the Project Manual prior to removal to locate, identify, and label all elements appropriately.

31. Are the louvers on the Type A windows wood or aluminum?

Response: The louvers are metal – assumed to be aluminum.

32. Window Type B4 is marked as having a quantity of 2 on the Window Type Sheet. We have found only 1 Type B4 window on the Window Schedule. Is there only 1 Type B4 window?

Response: Yes, there is only one (1) B4 type window (1‐N.28).

33. Window Type C1 is marked as having a quantity of 12 on the Window Type Sheet. We have found only 9 on the Window Schedule. Which is correct?

Response: The Window Schedule is correct – there are nine (9) type C1 windows.

34. Windows Type C 3, and C4 are to be replaced. Can these windows be restored? Are they the original windows? Is the wood still good but they need to be altered in some way? Can we provide an alternate for restoration in lieu of new milling?

Response: Window Type C3 and C4 shall be replaced in accordance with the contract documents.

35. Are Unit Prices required to be submitted for all Façade details? In case, additional quantities are found?

Response: No, please submit pricing per the Contract Price Schedule.

36. “Bid Option #8 (Line Item 018) – Repoint Open Brick Joints 1000 LF” – Will pointing be quantified by LF for Brick Masonry? Or Square Foot?

Response: The specifications documents incorrectly reference SF. LF is correct per the Contract Price Schedule.

37. Are Unit Prices to be provided for both (Brick Repointing LF) & (Brick Repointing SF)

Response: No, please see response to question 36. Please submit pricing per the Contract Price Schedule.

38. Any acceptable preblended pointing mortar manufacturers? For example; Spec Mix?

Response: The Specifications are provided for bidders; however, the contractor may propose a substitution per Specification Section 01 33 23.

End of Questions