B08_Att15_26R0002_Asbestos_Status_0001.pdf
PDF 2 MB Posted
- Attached to
- NIFC 100-ADM Repairs
- Solicitation number
- 140L0626R0002
About this file
This is an Asbestos-Containing Material (ACM) Survey and Abatement Cost Estimate report prepared by Tetra Tech for the U.S. Department of the Interior Bureau of Land Management (BLM) under BLM Task Order 135, BPA L09PA00228. The survey was conducted on the L2646 Old Administration Building (Building 100) at Fire and Aviation at the National Interagency Fire Center (NIFC) in Boise, Idaho, with a report date of March 8, 2012 and site survey date of January 18, 2012.
The survey identified four homogeneous materials containing greater than 1% asbestos by volume: 12"x12" vinyl floor tile and mastic (2% asbestos, 2,250 square feet, $16,100 abatement cost); 9"x9" vinyl floor tile and mastic (6% mastic asbestos and 5% tile asbestos, 4,470 square feet, $31,407 abatement cost); textured drywall and compound (3% asbestos, 32,272 square feet, $922,436 abatement cost); and pipe joint insulation (3% asbestos, 25 each, $1,423 abatement cost). Additional materials tested included suspended ceiling panels, ceiling tiles, and vinyl cove base, which tested negative for asbestos. The survey included 28 bulk samples analyzed using Polarized Light Microscopy (PLM) by Reservoirs Environmental, Inc., a NVLAP-accredited laboratory. Abatement cost estimates were provided by contractors without site visits and are based on standard assumptions including free access during business hours, single mobilization, utility availability at no cost, and standard state/local regulatory conditions. The report notes that concealed ACMs may exist in areas not investigated and recommends future replacement materials be checked for asbestos prior to installation.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AutoCAD SHX Text
STAIRWAY
AutoCAD SHX Text
ELEVATOR
AutoCAD SHX Text
STAIRWAY
AutoCAD SHX Text B13A
AutoCAD SHX Text B04
AutoCAD SHX Text B08
AutoCAD SHX Text B14
AutoCAD SHX Text B02
AutoCAD SHX Text B10
AutoCAD SHX Text B16
AutoCAD SHX Text B15
AutoCAD SHX Text B13
AutoCAD SHX Text B09
AutoCAD SHX Text N
AutoCAD SHX Text B03A
AutoCAD SHX Text B05A
AutoCAD SHX Text B18A
AutoCAD SHX Text B13B
AutoCAD SHX Text B15A
AutoCAD SHX Text B03
AutoCAD SHX Text B05
AutoCAD SHX Text B06
AutoCAD SHX Text B21
AutoCAD SHX Text B11
AutoCAD SHX Text B17
AutoCAD SHX Text B12
AutoCAD SHX Text B19
AutoCAD SHX Text B07
AutoCAD SHX Text B20
AutoCAD SHX Text B19A
AutoCAD SHX Text B01
AutoCAD SHX Text B18
AutoCAD SHX Text B20A
AutoCAD SHX Text Abated floor to concrete prior to 2021
AutoCAD SHX Text
TILE DATE UNKNOWN
AutoCAD SHX Text
TILE DATE UNKNOWN
AutoCAD SHX Text
CARPET DATE UNKNOWN
AutoCAD SHX Text
100 - ADMIN BASEMENT ASBESTOS STATUS
AutoCAD SHX Text
WALLS ABATED AND FLOOR REPLACED IN 2025
AutoCAD SHX Text
WALLS ABATED AND FLOOR REPLACED IN 2025
AutoCAD SHX Text Abated and tiled prior to 2021
AutoCAD SHX Text Abated in 2021 and 2025
AutoCAD SHX Text Floor abated & carpeted prior to 2021
AutoCAD SHX Text NOTE: THIS FLOOR PLAN IS BASED ON THE PRE-2021 LAYOUT AND DOES NOT REFLECT THE CURRENT BUILDING SCALE: 1/16"=1'-0" 7/9/26 MEJ m1johnson Text Box PROVIDED FOR HISTORICAL REFERENCE. SEE H-101 AND H-102 PLANS IN OTHER DOCUMENTS FOR ACTUAL ABATEMENT PLANS m1johnson Text Box
100-ADM REPAIRS
ATTACHMENT 14
ASBESTOS STATUS
MEJ 7/9/26
ELEVATOR
AutoCAD SHX Text
CHASE
AutoCAD SHX Text
DUCT
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 116A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
STAIRWAY
AutoCAD SHX Text
MEN
AutoCAD SHX Text
WOMEN
AutoCAD SHX Text
STAIRWAY
AutoCAD SHX Text 100A
AutoCAD SHX Text 100B
AutoCAD SHX Text 100C
AutoCAD SHX Text 100D
AutoCAD SHX Text
AutoCAD SHX Text 117A
AutoCAD SHX Text 111A
AutoCAD SHX Text 109A
AutoCAD SHX Text 104A
AutoCAD SHX Text 107A
AutoCAD SHX Text
100 - ADMIN MAIN LEVEL ASBESTOS STATUS
AutoCAD SHX Text
STORAGE
AutoCAD SHX Text
IDEA LAB
AutoCAD SHX Text Abated and tiled prior to 2021
AutoCAD SHX Text Abated in 2021 and 2025
AutoCAD SHX Text
CORE SIDE OF WALLS ABATED AND FLOOR REPLACED IN 2021 FOR CORE REMODEL
AutoCAD SHX Text
RACM DRYWALL AND JOINT COMPOUND (TYP)
AutoCAD SHX Text
WALLS ABATED AND FLOOR REPLACED IN 2025
AutoCAD SHX Text N
AutoCAD SHX Text
WALLS ABATED AND FLOOR REPLACED IN 2025
AutoCAD SHX Text
WALLS ABATED AND FLOOR REPLACED IN 2025
AutoCAD SHX Text Floor abated & carpeted prior to 2021
NOTE: THIS FLOOR PLAN IS BASED ON THE PRE-2021 LAYOUT AND DOES NOT REFLECT THE CURRENT BUILDING SCALE: 1/16"=1'-0" 7/9/26 MEJ
AutoCAD SHX Text 220A
AutoCAD SHX Text
AutoCAD SHX Text 220B
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 200B
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 200B1
AutoCAD SHX Text
AutoCAD SHX Text 200A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 219D
AutoCAD SHX Text
MEN
AutoCAD SHX Text
WOMEN
AutoCAD SHX Text
ELEVATOR
AutoCAD SHX Text
CHASE
AutoCAD SHX Text
DUCT
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text 219C
AutoCAD SHX Text 219B
AutoCAD SHX Text 219A
AutoCAD SHX Text 9'-11 "14"
AutoCAD SHX Text
STAIRWAY
AutoCAD SHX Text
STAIRWAY
AutoCAD SHX Text 18'-2 "14"
AutoCAD SHX Text
100 - ADMIN SECOND LEVEL ASBESTOS STATUS
AutoCAD SHX Text WALLS AND FLOORS ON ENTIRE SECOND FLOOR ABATED AND REPLACED IN 2025. ROOF FELT ABATED AND REPLACED IN 2025
AutoCAD SHX Text N
NOTE: THIS FLOOR PLAN IS BASED ON THE PRE-2021 LAYOUT AND DOES NOT REFLECT THE CURRENT BUILDING SCALE: 1/16"=1'-0" 7/9/26 MEJ
ASBESTOS-CONTAINING MATERIAL (ACM) SURVEY AND
ABATEMENT COST ESTIMATE
BLM Task Order 135, BPA L09PA00228 (NAB060001 Legacy Number)
L2646 - Old Admin - Bldg 100
43.56702 / -116.21217
Fire and Aviation at NIFC, Idaho
Report Date March 8, 2012 Site Survey Date January 18, 2012
ACM Identified in Building?* Yes ACM Abatement Cost Estimate* (Out of date)
*Subject to the assumptions and limitations as described in the following report.
Submitted by:
Aarcher, Inc.
910 Commerce Road Annapolis, Maryland 21401 410-897-9100 Program Manager: Mark R. Serio, P.G.
Submitted to:
U.S. Department of the Interior Bureau of Land Management (BLM) Building 50, Denver Federal Center Denver, Colorado 80225-0047 Attn: Suzanne Buntrock, PE m1johnson Text Box
PROVIDED FOR HISTORICAL REFERENCE. ALL FOLLOWING INFORMATION IS OUT OF DATE.
Tetra Tech
3801 Automation Way, Suite 100, Fort Collins, Colorado 80526
Tel 970.223.9600 Fax 970.223.7171 www.tetratech.com
March 8, 2012
Aarcher, Inc.
Mr. Mark Serio Vice President 910 Commerce Road Annapolis, Maryland 21401
RE: Asbestos-Containing Materials Survey and Asbestos Abatement Cost Estimates L2646 - Old Admin - Bldg 100 Fire and Aviation at NIFC, Idaho Tetra Tech Project Number 114-182213, Task 101
Dear Mr. Serio:
Tetra Tech is pleased to submit the attached Asbestos-Containing Materials Survey and Asbestos Abatement Cost Estimates report for the above-referenced site. This report includes the scope of work, procedures and methodologies, tables, figures, analytical laboratory results, and abatement cost estimate for each asbestos-containing material identified during this survey.
Tetra Tech appreciates the opportunity to perform these services for Aarcher, Inc. (AARCHER) and we look forward to working with you in the future. If you have questions or comments regarding the information in this report or if we can be of further assistance please do not hesitate to contact the Tetra Tech Fort Collins, Colorado office at (970) 223-9600.
Sincerely, Tetra Tech
Ryan Egan Mark Daley AHERA Accredited: AHERA Accredited:
Building Inspector/Management Planner Building Inspector/Management Planner Project Designer/Supervisor
Daniel Lawrence AHERA Accredited:
Building Inspector
L2646 - Old Admin - Bldg 100 Fire and Aviation at NIFC, Idaho i
TABLE OF CONTENTS
1.0 PURPOSE AND SCOPE OF SERVICES
2.0 GENERAL SITE CONDITIONS
3.0 REGULATORY STANDARDS
4.0 ASBESTOS-CONTAINING MATERIALS SURVEY AND ASBESTOS ABATEMENT COST
ESTIMATES
4.1 Homogeneous Materials
4.2 Hazard Assessment Factors
4.3 Sampling Strategy
4.4 Suspect Asbestos-Containing Material
4.5 Laboratory Analytical Results
5.0 ASBESTOS-CONTAINING MATERIALS SURVEY AND ASBESTOS ABATEMENT COST
ESTIMATES SUMMARY TABLE
6.0 CONCLUSIONS
7.0 ASSUMPTIONS AND LIMITATIONS
LIST OF APPENDICES
Appendix A: ACM Laboratory Analytical Results Appendix B: NIFC Map Appendix C: Site Drawing Appendix D: ACM Photographs
1.0 PURPOSE AND SCOPE OF SERVICES
The purpose of this project was to conduct an Asbestos-Containing Materials (ACM) survey and provide Asbestos Abatement Cost Estimates for identified ACM located in the L2646 - Old Admin - Bldg 100 located at Fire and Aviation at NIFC, Idaho. Tetra Tech provided services as outlined below:
Conduct a representative asbestos survey of the identified building, which includes the following:
1. Review existing asbestos reports for the building areas, if provided;
2. Survey all of the interior and exterior areas of the building, including building roofs;
3. Identify accessible suspect ACMs using Environmental Protection Agency (EPA) Asbestos
Hazard Emergency Response Act (AHERA) protocols;
4. Collect and analyze bulk samples of suspect friable and non-friable materials to eliminate suspect materials as asbestos containing;
5. Quantify ACMs, including material condition and location; and
6. Provide ACM abatement cost estimates for ACM identified during the survey of the building.
2.0 GENERAL SITE CONDITIONS
The building is a two story concrete framed structure, situated on a basement foundation, covered by a vinyl composite. The reported date of construction is 1969, and the structure is approximately 20,866 gross square feet in size. Interior finishes include vinyl floor tiles, ceiling panels, ceiling tiles, and textured drywall and compound. Exterior finishes consist of metal and concrete.
3.0 REGULATORY STANDARDS
The survey was performed in accordance with Federal, State and local rules for conducting asbestos surveys to meet Occupational Safety and Health Administration (OSHA) and United States Environmental Protection Agency (EPA) / National Emission Standards for Hazardous Air Pollutants (NESHAP) requirements. The work was also performed in general accordance with AARCHER Subcontract Number 020004-S-TT, dated September 18, 2011 and Task Orders 020004-S-TT-01, dated September 30, 2011 and 020004-S-TT-02, dated January 19, 2012.
4.0 ASBESTOS-CONTAINING MATERIALS SURVEY AND ASBESTOS
ABATEMENT COST ESTIMATES
Tetra Tech representatives Mr. Ryan Egan, Mr. Daniel Lawrence, and/or Mr. Mark Daley conducted the asbestos survey of the building on January 18, 2012. Mr. Egan is an AHERA accredited Building Inspector, Management Planner, Project Designer and Supervisor. Mr.
Daley is an AHERA accredited Building Inspector and Management Planner. Mr. Lawrence is an AHERA accredited Building Inspector. All field work was performed by and/or under the guidance of Mr. Ryan Egan.
The scope of the Asbestos-Containing Materials Survey included all of the accessible suspect building materials and finishes of the interior and exterior areas of the building, including building roofs. If ACM was identified in the building, Asbestos Abatement Cost Estimates were provided for each identified material.
Previous ACM survey reports for the building were not made available for review.
The building areas were visually inspected for the presence of building materials that are suspected to contain asbestos. Bulk samples of identified suspect ACMs were collected and placed into individual containers for transport to a National Voluntary Laboratory Accreditation Program (NVLAP)/American Industrial Hygiene Association (AIHA)-accredited laboratory for analysis. Materials visibly identified as non-asbestos (fibrous glass, foam rubber, wood, metal, etc.) were not sampled. The asbestos survey consisted of three basic procedures: 1) conducting a visual inspection of the structure and identifying functional spaces; 2) identifying homogeneous material areas of suspect surfacing, thermal system insulation, and miscellaneous materials; and 3) sampling accessible, friable and non-friable suspect materials.
4.1 Homogeneous Materials
Prior to collecting any samples, homogenous materials were identified and listed to develop a sampling strategy. A homogeneous material sampling area can be described as one or more areas of material that are similar in appearance and texture and that have the same installation date and function. The actual number of samples collected from each homogeneous sampling area was based upon criteria detailed in the following sections.
4.2 Hazard Assessment Factors
From the list of suspect homogeneous materials, a physical assessment was performed for each material on the list. A physical assessment includes evaluating the condition, assessing the potential for disturbance, and determining the friability of each material. Friability is a term used to describe the ease in which a building material inherently lends itself to disturbance. By definition, "friable" materials are those that can be crumbled or reduced to powder by hand pressure when dry. Each material on the list was further classified into one of three categories, which have specific sampling requirements for each category.
Surfacing Materials: Refers to spray-applied or troweled surfaces such as plaster ceilings and walls, fireproofing, textured paints, textured plasters, and spray applied acoustical surfaces.
Thermal System Insulation Refers to insulation used to inhibit heat gain or loss on pipes, boilers, tanks, ducts, and various other building components.
Miscellaneous Materials Refers to friable and non-friable products and materials that do not fit in any of the above two categories such as resilient floor covering, baseboards, mastics, adhesives, roofing material, caulking, glazing, and siding. This category also contains wallboard and joint compound wall systems and acoustical ceiling tile.
All confirmed ACMs were then assessed by their condition as good (no visible damage or showing only very limited damage or deterioration), damaged (less than 25% localized damage or 10% distributed damage), significantly damaged (25% or greater localized damage or 10% or greater distributed damage) per Title 40 Code of Federal Regulations Part 63.
4.3 Sampling Strategy
The asbestos inspection was conducted in general accordance with the AHERA requirements using a minimum number of samples collected for each homogenous material, which also meet the sampling requirement found in 29 CFR 1926.1101.
If the analytical results indicated that all the samples collected per homogenous material did not contain asbestos, then the homogenous material would be considered a non-ACM. However, if the analytical results of one or more of the samples collected per homogenous material indicate that asbestos is present in quantities of greater than 1 percent asbestos by weight (as defined by EPA), all of the homogenous material would be treated as an ACM regardless of any other analytical results. Material which can visually be determined to be non-asbestos (i.e., fibrous glass, foam rubber, metal, etc.) by the accredited inspector are not required to be sampled.
Miscellaneous materials require adequately representative sampling, which is typically done by collecting from one to three samples per material. Inspectors typically rely on other survey observations such as the condition, friability, and quantity of material to determine what would be a sufficient amount of samples to accurately evaluate the presence or absence of asbestos content. For this survey, three samples per each homogenous miscellaneous material were collected.
Actual collection of a bulk asbestos sample involves physically removing a small piece of material and placing it in a marked, airtight container. Sample containers are marked with a unique identification number, which is also noted in the field notes.
4.4 Suspect Asbestos-Containing Material
28 bulk asbestos samples were collected from the building and 36 sample layers were analyzed by Polarized Light Microscopy (PLM) based on the number of distinct layers (materials) associated with each bulk sample. For example, floor tile and associated mastic are collected as one bulk sample but are analyzed as two distinct materials by the asbestos laboratory, as required by NVLAP.
4.5 Laboratory Analytical Results
Bulk samples were analyzed by Reservoirs Environmental, Inc. analytical laboratory located in Denver, Colorado, using PLM according to EPA method 600/R-93/116. This laboratory participates in the NVLAP, a quality assurance program for PLM.
Any material that contains greater than 1 percent (>1%) asbestos by PLM is considered an ACM and must be handled according to OSHA, EPA, and applicable state and local regulations.
In addition, the U.S. Occupational Safety and Health Administration (OSHA) define asbestos as building materials containing between one tenth of one percent and one percent (0.1%-1%).
For friable materials, when the amount of asbestos in the sample material is reported as “None- Detected” by PLM analysis, no further verification of the sample results by Point Counting Methodology is recommended.
For friable materials, when the amount of asbestos in the sample material is reported as “Trace Asbestos Detected” or less than 10% asbestos by PLM analysis, the client may either assume the amount to be greater than 1% and treat the material as ACM or require further verification of the amount by Point Counting Methods. If the result obtained by Point Counting is different from the result obtained by PLM analysis, the Point Count Method result should be used.
For non-friable materials, when the amount of asbestos in the sample material is reported as greater than 1% asbestos by PLM analysis, no further verification of the sample results by alternative methods of identification such as Transmission Electron Microscopy (TEM) Chatfield Method is recommended.
For non-friable materials such as vinyl/asphaltic products (floor tiles/floor sheeting, mastics, shingles, etc.), where small, thin asbestos fibers may have been potentially milled into the nonorganic binder matrix, when the amount of asbestos in the sample material is reported as “None-Detected” by PLM analysis, due to the difficulty in analyzing such small, thin asbestos fibers in resinously bound materials by PLM analysis, EPA recommends but does not require that these types of materials, which were reported as non-ACMs by PLM, be further analyzed using TEM Chatfield Method. Tetra Tech did not conduct such analysis.
The results of the laboratory analysis are summarized in tabular form in Section 5.0. The laboratory analytical report and corresponding chain-of-custody documents are included in Appendix A. Results are reported in percent asbestos by volume and indicate the types of asbestos. Other common non-asbestos components may also be noted on the analytical reports. A drawing(s) showing bulk sample locations is provided in Appendix B. Inspector and laboratory accreditations are provided in Appendix C, and Appendix D presents photographs of all ACM’s identified in the building (if present).
5.0 ASBESTOS-CONTAINING MATERIALS SURVEY AND ASBESTOS ABATEMENT COST
ESTIMATES SUMMARY TABLE
ACM Bulk Sampling Results
Fire and Aviation at NIFC, Idaho
Homogeneous
Material
Material
Category
Required
Number of
Samples to be
Collected
Number of
Samples
Collected
Sample
Number(s) Location of Material Condition
Friable
(Yes/No)
Approximate
Material
Quantity
Asbestos
Content
ACM
Abatement
Cost
Estimate
12"x12" Vinyl floor tile and mastic
M N/A 3 F2.1A-C Basement of structure G No 2,250 SF 2% $16,100.00
9"x9" Vinyl floor tile and mastic M N/A 3 F3.1A-C Basement of structure G No 4,470 SF
6%
Mastic
5%
Tile
$31,407.00
Suspended ceiling panels M N/A 3 M5.1A-C Ceilings throughout structure G Yes 13,360 SF ND $0.00
12"x12" Ceiling tiles M N/A 3 M6.1A-C
Ceilings above suspended panels throughout structure G Yes 60 SF ND $0.00
Vinyl cove base and mastic M N/A 3 M11.1A-C
Wall bases throughout structure G No 250 SF
Trace
Mastic $0.00
Vinyl cove base and mastic M N/A 3 M11.2A-C
Wall bases throughout structure G No 950 SF ND $0.00
Textured drywall and compound
SM 7 7 S1.1A-G Walls throughout structure G Yes 32,272 SF 3% $922,436.00
Pipe joint insulation
TSI 3 3 T2.1A-C
Plumbing system throughout structure G Yes 25 EA 3% $1,423.00
AHERA Guidelines for Determining the Number of Samples to Collect ND = None Detected N/A = Not Applicable
MATERIAL CATEGORY:
M = Miscellaneous Material
SM = Surfacing Material
TSI = Thermal System Insulation
APPROXIMATE MATERIAL QUANTITIES:
SF = Square Feet
LF = Linear Feet
Ea = Each
CONDITION:
G = Good
D = Damaged
SD = Significantly Damaged
Homogeneous Material
Category
Homogeneous
Material Quantity Number of Samples Required
Surfacing Materials
<1000 SF 3
1000 - 5000 SF 5
>5000 SF 7 or more
Thermal System Insulation No Stipulation 3 (Must also sample all repair patches)
Miscellaneous Materials No Stipulation
Per AHERA, these materials must be sampled "in a manner sufficient to determine whether or not they contain asbestos." To satisfy National Emission
Standards for Hazardous Air Pollutants (NESHAP) requirements, a minimum of 3 samples were generally collected.
6.0 CONCLUSIONS
The results of the asbestos survey conducted at the L2646 - Old Admin - Bldg 100, Fire and Aviation at NIFC, Idaho facility building indicate that: four (4) of the accessible suspect building materials sampled were found to contain more than 1% asbestos.
Contractors and employees working in this building should be made aware of the possibility that concealed ACMs may be found during demolition/renovation. They should be advised not to disturb known or suspect ACMs without owner approval.
Any concealed building materials discovered during maintenance or renovation activities, which are suspected to contain asbestos, should be sampled and analyzed to confirm the presence of asbestos prior to disturbing.
The EPA has not prohibited the manufacture and import of miscellaneous materials, such as vinyl floorings, mastics, roofing materials, etc. As a result, any future replacement materials should be checked for the presence of asbestos prior to installation.
7.0 ASSUMPTIONS AND LIMITATIONS
The results, findings, conclusions, and recommendations expressed in the report are based only on conditions that were noted during Tetra Tech’s inspection of the L2646 - Old Admin - Bldg 100 structure located at the Fire and Aviation at NIFC, Idaho.
The selection of sample locations and frequency of sampling was based on Tetra Tech’s observations and the assumption that like materials in the same area are homogeneous in content. Limited destructive investigation was conducted as needed. Concealed ACMs may exist in concealed areas not investigated or identified.
The report is designed to aid the client in understanding the extent of ACM issues as they pertain to the “Recognition and Measurement of Asbestos-Related Cleanup Costs,” Technical Bulletin 2006-1, prepared by the Federal Accounting Standards Advisory Board, dated September 28, 2006 and to the renovation/demolition areas of the facility building areas. It should be noted that this report is not a complete Asbestos Abatement Specification or Work Plan.
Our professional services have been performed, our findings obtained, and our conclusions prepared in accordance with customary principles and practices in the fields of environmental science and engineering. This statement is in lieu of other statements either expressed or implied. This report does not warrant against future operations or conditions, nor does it warrant against operations or conditions present of a type or at a location not investigated.
Asbestos abatement cost estimates were obtained from asbestos abatement contractors who have not visited the site and have not seen the ACM to be abated. The costs provided herein, are magnitude estimates of costs with the following assumptions made:
Assumes free and clear access to the work area during working hours.
Assumes one mobilization to complete the abatement of one ACM.
Assumes both Power and water at no cost to contractor.
Assumes protect in place all above ceiling electrical wiring, fire alarm, and WiFi cables.
Does not include the demolition of any building components other than ACM.
Pricing assumes that any required inspections and air testing is provided by the building owner or owner’s representative.
Assumes that no special conditions are added by any State or local regulatory agency.
Work hours 7:00 AM to 5:00 PM Monday through Friday.
Not be held responsible for packaging, moving or damage to items being moved, nor for providing storage and/or inventory of these items. If storage or inventory is needed the owner will provide what is necessary. Responsibility of any personal items is the owner’s.
No delays interfering with the diligent execution of the work beyond the contractor’s control will be encountered.
APPENDIX A
ACM LABORATORY ANALYTICAL RESULTS
Laboratory Code: RES Subcontract Number: NA Laboratory Report: RES 229120-1 Project # / P.O. # 114-182213 Task 101 Project Description:
Ryan Egan
RES 229120-1
Sincerely, Anita Grigg Robert R. Workman Jr.
Bethany Nichols Anya Angst
February 10, 2012
Analyst(s): _________________________ Paul D. LoScalzo Wenlong Liu Michael Scales Adam Humphreys is the job number assigned to this study. This report is considered highly confidential and the sole property of the customer. Reservoirs Environmental, Inc. will not discuss any part of this study with personnel other than those of the client. The results described in this report only apply to the samples analyzed. This report must not be used to claim endorsement of products or analytical results by NVLAP or any agency of the U.S. Government. This report shall not be reproduced except in full, without written approval from Reservoirs Environmental, Inc. Samples will be disposed of after sixty days unless longer storage is requested. If you have any questions about this report, please feel free to call 303-964-1986.
Jeanne Spencer Orr President
Dear Customer, Reservoirs Environmental, Inc. is an analytical laboratory accredited for the analysis of Industrial Hygiene and Environmental matrices by the National Voluntary Laboratory Accreditation Program (NVLAP), Lab Code 101896-0 for Transmission Electron Microscopy (TEM) and Polarized Light Microscopy (PLM) analysis and the American Industrial Hygiene Association (AIHA), Lab ID 101533 - Accreditation Certificate #480 for Phase Contrast Microscopy (PCM) analysis. This laboratory is currently proficient in both Proficiency Testing and PAT programs respectively.
Reservoirs Environmental, Inc. has analyzed the following samples for asbestos content as per your request. The analysis has been completed in general accordance with the appropriate methodology as stated in the attached analysis table. The results have been submitted to your office.
Tetra Tech (Ft. Collins) 3801 Automation Way Ft. Collins CO 80525
BLM - L2646 / Fire & Aviation at NIFC - Old Admin - Bldg. 100
P: 303-964-1986 F: 303-477-4275
5801 Logan Street, Suite 100 Denver, CO 80216
1-866-RESI-ENV
www.reilab.com
TABLE PLM BULK ANALYSIS, PERCENTAGE COMPOSITION BY VOLUME
RES Job Number:
Client:
Client Project Number / P.O.:
Client Project Description:
Date Samples Received:
Analysis Type:
Turnaround:
Date Analyzed:
Client Non Non- Sample Sub Asbestos Fibrous Number Physical Part Fibrous Components
Description (%) Mineral Visual Components (%) Estimate (%) (%)
T2.1A EM 860389 A White resinous material w/ white fibrous woven material
5 ND 80 20
B Yellow fibrous material 40 ND 90 10 C White fibrous plaster 55 Chrysotile 3 10 87
T2.1B EM 860390 Not Analyzed T2.1C EM 860391 Not Analyzed
F3.1A EM 860392 A Black mastic 2 Chrysotile 6 0 94 B White tile w/ blue paint 98 Chrysotile 5 0 95
F3.1B EM 860393 Not Analyzed F3.1C EM 860394 Not Analyzed
F2.1A EM 860395 A Brown mastic TR ND TR 100 B White tile 100 Chrysotile 2 0 98
F2.1B EM 860396 Not Analyzed F2.1C EM 860397 Not Analyzed
M5.1A EM 860398 A Gray/white ceiling tile 100 ND 60 40
M5.1B EM 860399 A Gray/white ceiling tile 100 ND 60 40
M5.1C EM 860400 A Gray/white ceiling tile 100 ND 60 40
RESERVOIRS ENVIRONMENTAL, INC.
NVLAP Lab Code 101896-0
TDH Licensed Laboratory # 30-0136
ID Number L A Y E R
Lab
PLM, Short Report 3-5 Day
Asbestos Content
RES 229120-1
February 9, 2012
114-182213 Task 101 BLM - L2646 / Fire & Aviation at NIFC - Old Admin - Bldg. 100
Tetra Tech (Ft. Collins)
February 6, 2012
ND=None Detected TR=Trace, <1% Visual Estimate Trem-Act=Tremolite-Actinolite Note: Further analysis by TEM is recommended for organically bound material (i.e. floor tile) if PLM results are <1%.
Data QA
RES Job Number:
Client:
Client Project Number / P.O.:
Client Project Description:
Date Samples Received:
Analysis Type:
Turnaround:
Date Analyzed:
Client Non Non- Sample Sub Asbestos Fibrous Number Physical Part Fibrous Components
Description (%) Mineral Visual Components (%) Estimate (%) (%)
RESERVOIRS ENVIRONMENTAL, INC.
NVLAP Lab Code 101896-0
TDH Licensed Laboratory # 30-0136
ID Number L A Y E R
Lab
PLM, Short Report 3-5 Day
Asbestos Content
RES 229120-1
February 9, 2012
114-182213 Task 101 BLM - L2646 / Fire & Aviation at NIFC - Old Admin - Bldg. 100
Tetra Tech (Ft. Collins)
February 6, 2012
M11.1A EM 860401 A Brown mastic 5 Trem-Act TR 5 95 B Tan mastic 10 ND 0 100 C Black resinous material 85 ND 0 100
M11.1B EM 860402 A Brown mastic TR Trem-Act TR 5 95 B Tan mastic 5 ND 0 100 C Black resinous material 95 ND 0 100
M11.1C EM 860403 A Brown mastic 5 Trem-Act TR 5 95 B Tan mastic 5 ND 0 100 C Black resinous material 90 ND 0 100
M11.2A EM 860404 A Gray resinous material 100 ND 0 100
M11.2B EM 860405 A Tan adhesive TR ND 0 100 B Gray resinous material 100 ND 0 100
M11.2C EM 860406 A Gray resinous material 100 ND 0 100
S1.1A EM 860407 A White/tan drywall w/ white paint 100 ND 15 85
S1.1B EM 860408 A White paint 5 ND 0 100 B White texture 5 Chrysotile 3 0 97 C White/tan drywall 90 ND 15 85
ND=None Detected TR=Trace, <1% Visual Estimate Trem-Act=Tremolite-Actinolite Note: Further analysis by TEM is recommended for organically bound material (i.e. floor tile) if PLM results are <1%.
RES Job Number:
Client:
Client Project Number / P.O.:
Client Project Description:
Date Samples Received:
Analysis Type:
Turnaround:
Date Analyzed:
Client Non Non- Sample Sub Asbestos Fibrous Number Physical Part Fibrous Components
Description (%) Mineral Visual Components (%) Estimate (%) (%)
RESERVOIRS ENVIRONMENTAL, INC.
NVLAP Lab Code 101896-0
TDH Licensed Laboratory # 30-0136
ID Number L A Y E R
Lab
PLM, Short Report 3-5 Day
Asbestos Content
RES 229120-1
February 9, 2012
114-182213 Task 101 BLM - L2646 / Fire & Aviation at NIFC - Old Admin - Bldg. 100
Tetra Tech (Ft. Collins)
February 6, 2012
S1.1C EM 860409 A White paint w/ white plaster 5 ND 0 100 B White/multi-layered paint 5 ND 0 100 C White/multi-layered paint 5 ND 0 100 D White texture 5 Chrysotile 3 0 97 E White compound 5 Chrysotile 3 0 97 F White/tan drywall 75 ND 15 85
S1.1D EM 860410 Not Analyzed S1.1E EM 860411 Not Analyzed S1.1F EM 860412 Not Analyzed S1.1G EM 860413 Not Analyzed
M6.1A EM 860414 A White fibrous material 100 ND 20 80
M6.1B EM 860415 A White fibrous material 100 ND 20 80
M6.1C EM 860416 A White fibrous material 100 ND 20 80
ND=None Detected TR=Trace, <1% Visual Estimate Trem-Act=Tremolite-Actinolite Note: Further analysis by TEM is recommended for organically bound material (i.e. floor tile) if PLM results are <1%.
APPENDIX B
NIFC MAP
Parking
S ou th D ev el op m en t A ve nu e
Gate #2
Gate #1
140 Main Gate 5
Gate #3
Parking
Perimeter Fence
Security Check
120 Inflation Tower
3803 S.
Development
Ave
Wildland Firefighter Monument
301 JW Cabana Mec h
K ru m m
R oa d
K ru m m
A cc es s
R oa d
418 Guard 2071 W. Robinson Rd.
Robinson Road
Secured Area
200 Fire Retardant Office
2529 W. Robinson Rd.
Tanker Base
Storage
Storage 131 Operations 130
Mobilization Area 3830 S. Vista Av
P ar ki ng
210 Ramp Services
2455 Robinson Rd.
211 Ramp Storage 2451 W. Robinson Rd.
220 FS Air Ops 2243 W. Robinson Rd.
Parking
400 Tool Shop 2225 W. Robinson Rd
Equipment
Storage 2083 W. Robinson Rd.
Landscape
Storage 2081 W. Robinson Rd.
NIFC Campus Facilities Map
August 3, 2011
Parking
Parking
Parking
ParkingParking
Chiller
ParkingNorth
Identification will be required at Main Gate. All employees and visitors are required to wear I.D.
while on campus.
Vehicles may be subject to search.
P ar ki ng
215 Great Basin Cache Warehouse
2399 W. Robinson Rd.
NA
TI
ON
AL
INTERAGENCY FIRE CENTER
Boise, Idaho
Commerce Road
S o
V is ta A ve nu e
Personnel Gate
3950 So. Vista Ave
115 NWS
3807 S. Development Av
110 GB Training 3815 S. Development Av.
100 Old Administration 3906 S. Vista Av.
102 Shoshone-Paiute 2362 W. Robinson Rd.
106 Owyhee 2350 W. Robinson Rd.
205 Paraloft 2525 W. Robinson Rd.
300 Jack F. Wilson Building
(Headquarters) 3833 S. Development Av.
415 Maintenance 2075 W. Robinson Rd.
405 Hangar 2239 W. Robinson Rd
410B Radio Cache 2121 W. Robinson Rd.
410A Information Systems 2133 W. Robinson Rd.
410C RAWS
W. Robinson Rd.
420 Returns Warehouse
W. Robinson Rd.
Parking
Law Enforcement
General Parking
Reserved for Disabled
Overnight Parking
Maintenance, Security, and Deliveries Only Wildland Firefighter Monument Motorcycle Parking Electric Vehicle Parking
LS
Bicycle Parking
APPENDIX C
SITE DRAWING
(100)
(S01)
(S02)
(101)
(102)
(103)
(105)
(106)
(104)
(107)
(108)
(109)(110)(111)
(112)
(114)
(113)
(115)
(116)
(117)
(118)
(119)
(120)
(121)
(122) (123)
(124)
(130)
(129)
(133)
(125)
(126)
(127)
(128)
(134)
(131)
(132)
(B11)
M6.1A
M6.1B
M6.1C
M11.2A
M11.2B
M11.2C
S1.1A
S1.1B
S1.1C
M5.1B
Figure 1
Old Administration - First Floor - Bldg L2646
Sample Location Map
NORTH
January 2012Project No. 114-182213
Sample Location
(S01)
(B11)
(S02)
(200) (201) (202) (203)
(204) (205)
(206)
(207)
(208)
(209)
(210) (211)
(212)
(213)
(214)
(215)
(216)
(217)
(218)
(219)
(220)
(221)
(222)
(223) (224)
(225)
(226)
(227)
(228) (229) (230)
(232)
(231)
S1.1D
S1.1E
S1.1F
S1.1G
M5.1C
Figure 2
Old Administration - Second Floor - Bldg L2646
Sample Location Map
NORTH
(B02)(B01) (B03) (B04) (B05) (B06) (B07) (B08)
(B09)
(B14) (B20)
(B23)
(S01)
(S02) (B11)
(B10)
(B12)
(B15) (B16)
(B17)
(B18)
(B19)
(B13)
(B21)
(B22)
(B25)
(B24)
T2.1A
T2.1B
T2.1C
M5.1A
F2.1A
F2.1B
F2.1C
F3.1A
F3.1B
F3.1C
M11.1A
M11.1B M11.1C
Figure 3
Old Administration - Basement - Bldg L2646
Sample Location Map
NORTH
Figure 4
Old Administration - First Floor - Bldg L2646
RACM Drywall and Joint Compound Location Map
NORTH
January 2012Project No. 114-182213
RACM Drywall and Joint
Compound
Figure 5
Old Administration - Second Floor - Bldg L2646
RACM Drywall and Joint Compound Location Map
NORTH
January 2012Project No. 114-182213
RACM Drywall and Joint
Compound
Figure 6
Old Administration - Basement - Bldg L2646
ACM Floor Tile Location Map
NORTH
January 2012Project No. 114-182213
ACM Floor Tile Only
ACM Floor Tile & Mastic
APPENDIX D
ACM PHOTOGRAPHS
Site & ACM Photographs
Fire and Aviation at NIFC
Photograph 1 – ACM 12"x12" Floor Tile
Photograph 2 – ACM 9"x9" Floor Tile & Mastic
Site & ACM Photographs
Fire and Aviation at NIFC
Photograph 3 – ACM Textured Drywall & Compound
Photograph 4 – ACM Pipe Joint Insulation
File details come from the government source that posted it. Updated .