14-04. Attachment C - Supplementary General Conditions - Osage WTP - Sed Basin Ph 2.pdf
PDF 111 KB Posted
- Solicitation number
- BVB 415-26 SEC
- Issued by
- Nueces County, Texas
About this file
This is a Supplementary General Conditions document for Bid No. BVB 415-26, issued by the City of Amarillo, Texas, for the Osage Water Treatment Plant Settling Basin Repairs Phase 2 – West Basin project. The document modifies standard contract terms and conditions to govern the construction work. Key modifications include changes to the definition of working days to include weekends and holidays, requirements for the contractor's superintendent to be present at all times during work performance, submission of an initial work progress schedule at the pre-construction conference with monthly updates required with pay requests, and provisions that estimated quantities in the contract documents are approximate with actual work amounts potentially differing from estimates. The contractor is required to provide written responses to new price requests within fifteen calendar days of receipt.
Additional modifications address contract administration procedures, including the elimination of weather day considerations in pay estimates, availability of contract documents in electronic format only with contractors responsible for printing hard copies, and deletion of specific insurance and bonding requirements from the original general conditions. The document clarifies that conflicts between the Uniform General Conditions and these Special Conditions are resolved in favor of the Special Conditions, establishing the framework for competitive bidding and project execution for the settling basin repair work at the municipal water treatment facility.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUPPLEMENTARY GENERAL CONDITIONS
Bid No. BVB 415-26
Osage WTP Settling Basin Repairs Phase 2 – West Basin
Note: Where there is a conflict between the Uniform General Conditions (revised 1/14/2020) and the Special Conditions, the terms and conditions of the Special Conditions take precedence.
1. Article 1 Definitions: Delete Paragraph 1.29 Weekend/Holiday in its entirety.
2. Article 1 Definitions: Replace Paragraph 1.31 “Working Day/Work Day” with the following:
“Working Day/Work Day” a calendar day, including Saturdays, Sundays and legal holidays observed by the Owner.
3. Article 2 Laws Governing Construction: delete paragraph 2.8.
4. Article 3. General Responsibilities of Owner & Contractor, Paragraph 3.3.2 Contractor’s Superintendent: Add the phrase “at all times when work is being performed” after “who will be present” in the first sentence.
5. Article 3. General Responsibilities of Owner & Contractor: Paragraph 3.4.1: add “not” after “standards of the Project are”.
6. Article 3. General Responsibilities of Owner & Contractor: Delete Paragraphs 3.6.2, 3.6.2.1, 3.6.2.2, 3.6.2.3, 3.6.2.4, and 3.6.3.
7. Article 5 Contract Documents: replace paragraph 5.1.1 Copies Furnished with the following:
Copies Furnished. An electronic version of the Contract Documents will be made available to the contractor. Hard copies can be printed by the contractor. The City will not provide hard copies.
8. Article 5. Contract Documents, Paragraphs 5.1.5 Estimate Quantities: Revise Paragraph
5.1.5.1 to read as follows:
“The Contract Documents are intended to clearly show all Work to be done and material to be furnished hereunder. The estimated quantities of Work to be done and material to be furnished under this Contract are approximate. The actual amount of Work to be done and material to be furnished under this Contract may differ somewhat from the estimates.”
9. Article 5. Contract Documents, Paragraphs 5.1.9 Lines and Grades, Paragraph 5.1.9.1:
Delete the phrase “Engineer furnished” from the last sentence.
10. Article 8 Project Scheduling Requirements: Paragraph 8.3 Work Progress Schedule: The Initial Work Progress Schedule is required to be submitted at the pre-construction conference.
11. Article 8 Project Scheduling Requirements: Paragraph 8.3.2 Schedule Updates: Updates to the project schedule are required on a monthly basis with the pay request submittal.
12. Article 9 Payments, Paragraph 9.3.1 Pay Estimate: Delete the phrase “and any requested weather days” in the third sentence.
13. Article 10, replace paragraph 10.8.1.1 with the following:
Contractor shall provide written response to new price request with fifteen (15) calendar days of receipt.