This notice announces a solicitation for operations, maintenance, and repair services of the Central Utility Plant at the National Institute of Standards and Technology Boulder Laboratory Site in Boulder, Colorado. The services include preventative and scheduled maintenance activities at field sites in Fort Collins, Colorado and Kekaha, Hawaii. The base period of performance is one year with four one-year option periods for a total potential period of 60 months. The solicitation will be posted on or about February 25, 2020 with a closing date of March 27, 2020. The North American Industry Classification System code is 811310 and the size standard is $8.0 million. A single award is anticipated. Interested parties should register to receive notification and submit any questions in writing referencing solicitation number 1333ND20RNB190010.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Job Plan : JP-C-AC-4Y Description : Contractor Job Plan Air Compressor 4 Year Task Task Task Description Task Long Description Sequence 0 1 PM ISSUED PM issued through NIST Maximo System.
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space Review manufacturer's instructions and equipment history record, if available.
0 7 EQUIPMENT SHUTDOWN SAFETY PRIOR TO ATTEMPTING ANY MAINTENANCE WORK, ENSURE
THAT:
1. ALL AIR PRESSURE IS FULLY DISCHARGED AND ISOLATED
FROM THE SYSTEM. IF THE AUTOMATIC BLOWDOWN VALVE IS
USED FOR THIS PURPOSE, THEN ALLOW ENOUGH TIME FOR IT
TO COMPLETE THE OPERATION.
2. THE MACHINE CANNOT BE STARTED ACCIDENTALLY OR
OTHERWISE, BY POSTING WARNING SIGNS AND FITTING
APPROPRIATE ANTI-STARTING DEVICES. LOCKOUT-TAGOUT
WILL BE ENFORCED.
3. ALL RESIDUAL ELECTRICAL POWER SOURCES (MAINS AND
BATTERY) ARE ISOLATED
4. APPROPRIATE PERSONAL PROTECTIVE EQUIPMENT IS WORN
5. ENSURE THAT THE ASSOCIATED EQUIPMENT'S OPERATION
WILL NOT BE AFFECTED
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 10 CHECK THE COOLERS CHECK THE COOLERS FOR BUILD-UP OF FOREIGN MATTER.
CLEAN IF NECESSARY BY BLOWING OUT WITH AIR.
PWS Attach 5 - Job Plans Page 1 of 99 1333ND20RNB190010 Amendment 0006
Job Plan : JP-C-AC-4Y Description : Contractor Jobplan Air Compressor 4 Year Task Sequence
Task Task Description Task Long Description
0 20 OPERATE SAFETY VALVES OPERATE SAFETY VALVES MANUALLY TO VERIFY THAT THE
VALVE MECHANISM IS FUNCTIONING CORRECTLY AND THAT A
SMALL AMOUNT OF AIR IS RELEASED.
0 40 LUBE BEARINGS LUBRICATE THE MAIN MOTOR DRIVE END BEARING AND THE
NON-DRIVE END BEARING
0 50 REBUILD VALVES REBUILD CONDENSATE SOLENOID VALVES USING FIELD KITS
0 60 INSPECT SILENCERS INSPECT THE BLOWDOWN SILENCERS NOTIFY COR IMMEDIATELY
IF ANY NEED TO BE REPLACED AND NOTE ON PM
0 70 CLEAN BREATHER CLEAN THE GEARCASE BREATHER
0 80 CHECK CALIBRATION CHECK THE CALIBRATION OF THE PRESSURE TRANSDUCERS.
0 90 REPLACE FILTER CHANGE THE AIR FILTER ELEMENT. NOTIFY COR IF FILTER IS
EXCEPTIONALLY DIRTY AND NOTE ON PM
0 100 REPLACE CHECK VALVE SEAT AND SPRING REPLACE CHECK VALVE SEAT AND SPRING USING FIELD KIT
0 110 FULLY INSPECT FULLY INSPECT CONDENSATE SEPARATORS, ALL EXTERNAL
SURFACES, AND FITTINGS. NOTE ON PM ANY EXCESSIVE
CORROSION, MECHANICAL OR OTHER IMPACT DAMAGE,
LEAKAGE OR OTHER DETERIORATION.
0 120 INSPECT THE STARTER INSPECT THE STARTER CONTACTORS. NOTIFY COR IMMEDIATELY
IF ANY NEED TO BE REPLACED AND NOTE ON PM
0 130 REBUILD BLOWNDOWN VALVE REBUILD BLOWNDOWN VALVE USING FIELD KIT.
0 140 CLEAN STRAINERS CLEAN THE CONDENSATE STRAINERS.
0 150 CHANGE OIL AND FILTER CHANGE THE LUBRICATING OIL AND FILTER ELEMENT.
0 160 REMOVE SAFETY VALVES REMOVE THE SAFETY VALVES FROM THE COMPRESSOR, INSPECT
AND RE-CALIBRATE.
0 170 REBUILD HYDRAULIC CYLINDER REBUILD HYDRAULIC CYLINDER USING FIELD KIT.
0 180 REPLACE ALL HOSES REPLACE ALL HOSES
PWS Attach 5 - Job Plans Page 2 of 99 1333ND20RNB190010
Job Plan : JP-C-AC-4Y Description : Contractor Jobplan Air Compressor 4 Year
Task Task Description Task Long Description
Sequence 0 999 COMPLETE PM Complete the PM through the NIST Maximo System noting condition, suspect problems, parts used, gauge/meter readings, etc.
NOTIFY COR IF ANY EQUIPMENT REQUIRES REPLACEMENT AND
NOTE ON PM.
Job Plan : JP-C-AC-A Description : Contractor Jobplan Air Compressor Annual
Task Task Description Task Long Description
Sequence 0 1 PM ISSUED PM issued through NIST Maximo System.
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space Review manufacturer's instructions and equipment history record, if available.
PWS Attach 5 - Job Plans Page 3 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 7 EQUIPMENT SHUTDOWN SAFETY PRIOR TO ATTEMPTING ANY MAINTENANCE WORK, ENSURE
THAT:
1. ALL AIR PRESSURE IS FULLY DISCHARGED AND ISOLATED
FROM THE SYSTEM. IF THE AUTOMATIC BLOWDOWN VALVE IS
USED FOR THIS PURPOSE, THEN ALLOW ENOUGH TIME FOR IT
TO COMPLETE THE OPERATION.
2. THE MACHINE CANNOT BE STARTED ACCIDENTALLY OR
OTHERWISE, BY POSTING WARNING SIGNS AND FITTING
APPROPRIATE ANTI-STARTING DEVICES. LOCKOUT-TAGOUT
WILL BE ENFORCED.
3. ALL RESIDUAL ELECTRICAL POWER SOURCES (MAINS AND
BATTERY) ARE ISOLATED
4. APPROPRIATE PERSONAL PROTECTIVE EQUIPMENT IS WORN
5. ENSURE THAT THE ASSOCIATED EQUIPMENT'S OPERATION
WILL NOT BE AFFECTED
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 10 CHECK THE COOLERS CHECK THE COOLERS FOR BUILD-UP OF FOREIGN MATTER.
CLEAN IF NECESSARY BY BLOWING OUT WITH AIR.
0 20 OPERATE SAFETY VALVES OPERATE SAFETY VALVES MANUALLY TO VERIFY THAT THE
VALVE MECHANISM IS FUNCTIONING CORRECTLY AND THAT A
SMALL AMOUNT OF AIR IS RELEASED.
0 30 CHECK ALL HOSES CHECK ALL HOSES FOR SIGNS OF DETERIORATION, CRACKS,
HARDENING ETC. NOTIFY COR IMMEDIATELY IF ANY NEED TO BE
REPLACED AND NOTE ON PM
0 40 LUBE BEARINGS LUBRICATE THE MAIN MOTOR DRIVE END BEARING AND THE
NON-DRIVE END BEARING
PWS Attach 5 - Job Plans Page 4 of 99 1333ND20RNB190010
0 50 REBUILD VALVES REBUILD CONDENSATE SOLENOID VALVES USING FIELD KITS
PWS Attach 5 - Job Plans Page 5 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 60 INSPECT SILENCERS INSPECT THE BLOWDOWN SILENCERS NOTIFY COR IMMEDIATELY
IF ANY NEED TO BE REPLACED AND NOTE ON PM
0 70 CLEAN BREATHER CLEAN THE GEARCASE BREATHER
0 80 CHECK CALIBRATION CHECK THE CALIBRATION OF THE PRESSURE TRANSDUCERS.
0 90 REPLACE FILTER CHANGE THE AIR FILTER ELEMENT. NOTIFY COR IF FILTER IS
EXCEPTIONALLY DIRTY AND NOTE ON PM
0 100 REPLACE CHECK VALVE SEAT AND SPRING REPLACE CHECK VALVE SEAT AND SPRING USING FIELD KIT
0 110 FULLY INSPECT FULLY INSPECT CONDENSATE SEPARATORS, ALL EXTERNAL
SURFACES, AND FITTINGS. NOTE ON PM ANY EXCESSIVE
CORROSION, MECHANICAL OR OTHER IMPACT DAMAGE,
LEAKAGE OR OTHER DETERIORATION.
0 120 INSPECT THE STARTER INSPECT THE STARTER CONTACTORS. NOTIFY COR IMMEDIATELY
IF ANY NEED TO BE REPLACED AND NOTE ON PM
0 130 REBUILD BLOWNDOWN VALVE REBUILD BLOWNDOWN VALVE USING FIELD KIT.
0 140 CLEAN STRAINERS CLEAN THE CONDENSATE STRAINERS.
0 150 CHANGE OIL AND FILTER CHANGE THE LUBRICATING OIL AND FILTER ELEMENT.
0 160 REMOVE SAFETY VALVES REMOVE THE SAFETY VALVES FROM THE COMPRESSOR, INSPECT
AND RE-CALIBRATE.
0 998 COMPLETE "NEW EQUIPMENT REPORT FORM" COMPLETE "NEW EQUIPMENT REPORT FORM" FOR DATA THAT
APPLIES TO THIS PIECE OF EQUIPMENT SEE EXAMPLE FORM
AND CLASSIFICATION & ATTRIBUTE TABLES; PROVIDED BY
YOUR COR.
0 999 COMPLETE PM Complete the PM through NIST Maximo System; noting condition, suspect problems, parts used, gauge/meter readings, etc.
NOTIFY COR IF ANY EQUIPMENT REQUIRES REPLACEMENT AND
NOTE ON PM.
PWS Attach 5 - Job Plans Page 6 of 99 1333ND20RNB190010
Job Plan : JP-C-AC-Q Description : Contractor Jobplan Air Compressor Quarterly
0 1 ISSUE PM PM issued through NIST Maximo System.
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space Review manufacturer's instructions and equipment history record, if available.
0 7 EQUIPMENT SHUTDOWN SAFETY PRIOR TO ATTEMPTING ANY MAINTENANCE WORK, ENSURE
THAT:
1. ALL AIR PRESSURE IS FULLY DISCHARGED AND ISOLATED
FROM THE SYSTEM. IF THE AUTOMATIC BLOWDOWN VALVE IS
USED FOR THIS PURPOSE, THEN ALLOW ENOUGH TIME FOR IT
TO COMPLETE THE OPERATION.
2. THE MACHINE CANNOT BE STARTED ACCIDENTALLY OR
OTHERWISE, BY POSTING WARNING SIGNS AND FITTING
APPROPRIATE ANTI-STARTING DEVICES. LOCKOUT-TAGOUT
WILL BE ENFORCED.
3. ALL RESIDUAL ELECTRICAL POWER SOURCES (MAINS AND
BATTERY) ARE ISOLATED
4. APPROPRIATE PERSONAL PROTECTIVE EQUIPMENT IS WORN
5. ENSURE THAT THE ASSOCIATED EQUIPMENT'S OPERATION
WILL NOT BE AFFECTED
PWS Attach 5 - Job Plans Page 7 of 99 1333ND20RNB190010
Job Plan : JP-C-AC-Q Description : Contractor Jobplan Air Compressor Quarterly
Task Task Description Task Long Description
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 10 CHECK THE COOLERS CHECK THE COOLERS FOR BUILD-UP OF FOREIGN MATTER.
CLEAN IF NECESSARY BY BLOWING OUT WITH AIR.
0 20 OPERATE SAFETY VALVES OPERATE SAFETY VALVES MANUALLY TO VERIFY THAT THE
VALVE MECHANISM IS FUNCTIONING CORRECTLY AND THAT A
SMALL AMOUNT OF AIR IS RELEASED.
0 30 CHECK ALL HOSES CHECK ALL HOSES FOR SIGNS OF DETERIORATION, CRACKS,
HARDENING ETC. NOTIFY COR IMMEDIATELY IF ANY NEED TO BE
REPLACED AND NOTE ON PM
0 40 LUBE BEARINGS LUBRICATE THE MAIN MOTOR DRIVE END BEARING AND THE
NON-DRIVE END BEARING
0 999 COMPLETE PM Complete the PM through the NIST Maximo System; noting condition, suspect problems, parts used, gauge/meter readings, etc.
Number of Records: 56
PWS Attach 5 - Job Plans Page 8 of 99 1333ND20RNB190010
Job Plan : JP-C-ACCU-S Description : JOBPLAN ACCU SEMI-ANNUAL
0 1 PM ISSUED PM issued through NIST Maximo System.
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space.
Review manufacturer's instructions and equipment history record, if available.
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment. Ensure that the people affected have been notified (COR to notify) and associated equipment's operation will not be affected.
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 10 CHECK UNIT FOR PROPER OPERATION(2) CHECK BOTH SIDES OF UNIT FOR EXCESSIVE NOISE, VIBRATION, SIGNS OF OIL LEAKAGE, ECT.
0 20 PRESSURE WASH COILS AND FANS PRESSURE WASH COILS AND FANS ON BOTH SIDES OF THE UNIT
WITH CLEANING SOLUTION
0 30 CHECK ELECTRICAL WIRING CHECK ELECTRICAL WIRING AND CONNECTIONS, TIGHTEN ALL
CONNECTIONS
0 40 LUBRICATE BEARINGS (If Applicable) LUBRICATE SHAFTS, BEARINGS, MOTOR BEARINGS AS REQUIRED
0 50 INSPECT FANS INSPECT FANS ON BOTH SIDES OF THE UNIT FOR PROPER
OPERATION, BENT OR DAMAGED BLADES, UNBALANCED BLADES,
REPAIR OR REPLACE AS NEEDED
0 60 INSPECT PIPING INSPECT PIPING AND VALVES ON BOTH SIDES OF THE UNIT FOR
LEAKS, REPAIR OE REPLACE AS NEEDED
0 70 CLEAN AREA CLEAN AREA AROUND EQUIPMENT
PWS Attach 5 - Job Plans Page 9 of 99 1333ND20RNB190010
Job Plan : JP-C-ACCU-S Description : JOBPLAN ACCU SEMI-ANNUAL
Task Task Description Task Long Description
0 100 CHECK ALARMS CHECK WITH OPERATING OR AREA PERSONNEL TO INSURE
THAT ALL ASSOCIATED ALARMS ARE CLEARED UPON
COMPLETION AND RESTART
0 999 COMPLETE PM Complete the PM through NIST Maximo system; noting condition, suspect problems, parts used, gauge/meter readings, etc.
Notify COR if any equipment requires replacement and note on PM
Number of Records: 14
PWS Attach 5 - Job Plans Page 10 of 99 1333ND20RNB190010
Job Plan : JP-C-AHU-A Description : JOB PLAN AHU ANNUAL
0 1 PM ISSUED PM issued through NIST Maximo System.
0 3 SCHEDULE THE PM - 48 HR LEAD Schedule the PM with the COR, MINIMUM 48 HOUR LEADTIME. NO equipment will be shut down without scheduling with the COR.
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment.
0 20 CHECK CONTROLS CHECK CONTROLS AND UNIT FOR PROPER OPERATION. AIR
HANDLER MAY HAVE DIGITAL OR PNEUMATIC CONTROLS.
0 30 CHECK FOR UNUSUAL NOISES CHECK FOR UNUSUAL NOISE OR VIBRATION
0 50 LUBRICATE BEARINGS LUBRICATE SHAFT AND MOTOR BEARINGS AS NECESSARY
0 60 REPLACE BELTS REPLACE BELTS, RE- TENSION, CHECK ALIGNMENT OF BELTS,
0 70 INSPECT PIPING AND VALVES INSPECT EXTERIOR PIPING AND VALVES FOR LEAKS; TIGHTEN
CONNECTIONS AS REQUIRED
0 80 CHECK OPERATION CHECK OPERATION OF ALL PIVOT POINTS AND LINKAGES AND
LUBRICATE AS NECESSARY
0 90 REPLACE FILTERS REPLACE 40% AIR FILTERS OR PRE FILTERS
0 100 CLEAN AREA CLEAN AREA AROUND EQUIPMENT. DISPOSE OF AIR FILTERS OR
FILTER MEDIA PROPERLY
0 999 COMPLETE PM Complete the PM through NIST Maximo System.
NOTIFY COR IF ANY EQUIPMENT REQUIRES REPAIR/
REPLACEMENT AND NOTE ON PM.
PWS Attach 5 - Job Plans Page 11 of 99 1333ND20RNB190010
Job Plan : JP-C-AHU-Q Description : AIR HANDLING UNIT QUARTERLY
Task Task Description Task Long Description
0 20 Grease supply fan motor If needed 0 50 Check tension, condition and alignment of belts Adjust belt if necessary If direct drive check blower wheel alignment / balance
0 30 Clean coil drain pan(s)
0 1 Issue PM PM issued through NIST Maximo System.
0 999 Complete PM Complete the PM through NIST Maximo System.
NOTIFY COR IF ANY EQUIPMENT REQUIRES REPAIR/
REPLACEMENT AND NOTE ON PM.
0 10 Replace filters
0 40 Check for unusual noise or vibration
Job Plan : JP-C-AHU-S Description : JOBPLAN AHU SEMI ANNUAL
0 1 Issue PM PM issued through NIST Maximo System.
0 3 SCHEDULE THE PM - 48 HR LEAD Schedule the PM with the COR, MINIMUM 48 HOUR LEADTIME. NO equipment will be shut down without scheduling with the COR.
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment.
0 20 CHECK CONTROLS CHECK CONTROLS AND UNIT FOR PROPER OPERATION. AIR
HANDLER MAY HAVE DIGITAL OR PNEUMATIC CONTROLS.
0 30 CHECK FOR UNUSUAL NOISES CHECK FOR UNUSUAL NOISE OR VIBRATION
0 50 LUBRICATE BEARINGS LUBRICATE SHAFT AND MOTOR BEARINGS AS NECESSARY
0 60 CHECK BELTS CHECK TENSION, CONDITION AND ALIGNMENT OF BELTS, ADJUST
AS NECESSARY
PWS Attach 5 - Job Plans Page 12 of 99 1333ND20RNB190010
Job Plan : JP-C-AHU-S Description : JOBPLAN AHU SEMI ANNUAL
Task Task Description Task Long Description
0 70 INSPECT PIPING AND VALVES INSPECT EXTERIOR PIPING AND VALVES FOR LEAKS; TIGHTEN
CONNECTIONS AS REQUIRED
0 80 CHECK OPERATION CHECK OPERATION OF ALL PIVOT POINTS AND LINKAGES AND
LUBRICATE AS NECESSARY
0 90 REPLACE FILTERS REPLACE 40% AIR FILTERS OR PRE FILTERS
0 100 CLEAN AREA CLEAN AREA AROUND EQUIPMENT. DISPOSE OF AIR FILTERS OR
FILTER MEDIA PROPERLY
0 999 COMPLETE PM Complete the PM through NIST Maximo System.
NOTIFY COR IF ANY EQUIPMENT REQUIRES REPAIR/
REPLACEMENT AND NOTE ON PM.
Number of Records: 31
PWS Attach 5 - Job Plans Page 13 of 99 1333ND20RNB190010
Job Plan : JP-C-W-AHU-
SWAP-F
Description : Contractor Job Plan WWV/B AHU (SWAMP COOLER) SHUT DOWN
0 1 PM ISSUED PM issued through NIST Maximo System.
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space.
Review manufacturer's instructions and equipment history record, if available.
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment. Ensure that the people affected have been notified (COR to notify) and associated equipment's operation will not be affected.
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 15 WATER SUPPLY TURN WATER OFF TO COOLER, DRAIN SUMP, NOTIFY COR OF
DEFICIENCIES
0 80 CLEAN AREA CLEAN SURROUNDING AREA OF DEBRIS
0 90 INSTALL COVER CONTACT AREA PERSONNEL AS TO STORAGE LOCATION OF
COVER AND INSTALL ON UNITS
0 999 COMPLETE PM Complete the PM through NIST Maximo System; noting condition, Notify COR if any equipment requires replacement and note on PM
PWS Attach 5 - Job Plans Page 14 of 99 1333ND20RNB190010
SWAP-S
Description : Contractor Jobplan WWV/B AHU (SWAMP COOLER) START UP
0 1 ISSUE PM PM issued through NIST Maximo System.
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space.
Review manufacturer's instructions and equipment history record, if available.
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment. Ensure that the people affected have been notified (COR to notify) and associated equipment's operation will not be affected.
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 10 CHECK UNIT FOR PROPER OPERATION CHECK UNIT FOR PROPER OPERATION, NOISE, VIBRATION, ECT
0 15 WATER SUPPLY TURN WATER ON TO COOLER, CHECK FLOAT, ADJUST AS NEEDED,
NOTIFY COR OF DEFICIENCIES
0 20 CHECK EVAPORATION PANNELS REPLACE PADS
0 30 LUBRICATE BEARINGS LUBRICATE FAN, BEARINGS,AND MOTOR
0 40 REPLACE BELT REPLACE BELT
0 50 INSPECT WIRING INSPECT WIRING FOR LOOSE CONNECTIONS, DETERIORATION,
TIGHTEN LOOSE CONNECTIONS, NOTIFY COR OF DEFECIENCIES.
0 60 CHECK PUMP CHECK PUMP FOR PROPER OPERATION, CLEAN INLET SCREEN
AND DISCHARGE LINE. NOTIFY COR OF DEFICIENCIES
0 65 CHECK WATER DISTRIBUTION TO PADS CHECK WATER DISTRIBUTION TO PADS, CLEAN IF NECESSARY, NOTIFY COR OF DEFICIENCIES
PWS Attach 5 - Job Plans Page 15 of 99 1333ND20RNB190010
SWAP-S
Description : Contractor Jobplan WWV/B AHU (SWAMP COOLER) START UP
Task Task Description Task Long Description
0 70 CLEAN SUMP CLEAN SUMP OF DIRT AND DEBRIS
0 80 CLEAN AREA CLEAN SURROUNDING AREA OF DEBRIS
0 90 REMOVE COVERS REMOVE COVERS ON UNITS, GIVE TO AREA PERSONNEL FOR
STORAGE
Number of Records: 26
PWS Attach 5 - Job Plans Page 16 of 99 1333ND20RNB190010
Job Plan : JP-C-BLR-A Description : Contractor Boiler Annual
0 1 ISSUE PM PM issued through NIST Maximo System.
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space.
Review manufacturer's instructions and equipment history record, if available.
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment. Ensure that the people affected have been notified (COR to notify) and associated equipment's operation will not be affected.
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 10 CHECK COMBUSTION CHAMBER FOR AIR OR GAS LEAKS CHECK COMBUSTION CHAMBER FOR AIR OR GAS LEAKS 0 20 CHECK FUEL LINES AND CONNECTIONS FOR DAMAGE CHECK FUEL LINES AND CONNECTIONS FOR DAMAGE
0 30 CHECK FOR PROPER OPERATIONAL RESPONSE OF
BURNER TO
CHECK FOR PROPER OPERATIONAL RESPONSE OF BURNER TO
POTENTIOMETER CONTROL
0 60 CHECK AND LUBRICATE BURNER AND BLOWER
MOTORS
CHECK AND LUBRICATE BURNER AND BLOWER MOTORS
0 70 CHECK MAIN FLAME FAILURE PROTECTION CHECK MAIN FLAME FAILURE PROTECTION AND MAIN FLAME
DETECTION SCANNER ON BOILER EQUIPPED WITH SPARK
IGNITION
0 80 CHECK ELECTRICAL WIRING TO BURNER CONTROLS
AND BLO
CHECK ELECTRICAL WIRING TO BURNER CONTROLS AND
BLOWER
0 90 CLEAN FIREBOX CLEAN FIRESIDE ON FIRETUBE BOILERS WITH VACUUM TYPE
TUBE CLEANING MACHINE
PWS Attach 5 - Job Plans Page 17 of 99 1333ND20RNB190010
Job Plan : JP-C-BLR-A Description : Contractor Boiler Annual
Task Task Description Task Long Description
0 100 CHECK OPERATION OF MERCURY CONTROL SWITCHES CHECK OPERATION OF MERCURY CONTROL SWITCHES (I.E.
STEAM PRESSURE, HOT WATER TEMERATURE LIMIT, ATOMIZING
OR COMBUSTION AIR PROVING, ETC.)
0 110 CHECK SAFETY PRESSURE RELIEF VALVE CHECK OPERATION AND CONDITION OF SAFETY PRESSURE
RELIEF VALVE
0 120 CHECK OPERATION OF BOILER LOW WATER CUT OFF
DEVICE
CHECK OPERATION OF BOILER LOW WATER CUT OFF DEVICES
0 130 CHECK HOT WATER PRESSURE GAUGES CHECK HOT WATER PRESSURE GAUGES
0 140 INSPECT AND CLEAN WATER COLUMN SIGHT GLASS INSPECT AND CLEAN WATER COLUMN SIGHT GLASS
0 150 ANALYZE FLUE GAS ANALYZE FLUE GAS AND MAKE ADJUSTMENTS AS NECESSARY. A
PRINTED REPORT ON THE FLUE GAS ANALYSIS WILL BE
PROVIDED TO THE COR FOR INSPECTION.
0 160 CHECK CONDITION OF FLUE PIPE, DAMPER AND
EXHAUST
CHECK CONDITION OF FLUE PIPE, DAMPER AND EXHAUST STACK
0 170 CHECK BOILER OPERATION THROUGH COMPLETE
CYCLE
CHECK BOILER OPERATION THROUGH COMPLETE CYCLE, UP TO
30 MINUTES
0 190 CLEAN AREA AROUND BOILER CLEAN AREA AROUND BOILER
0 998 COMPLETE "NEW EQUIPMENT REPORT FORM" COMPLETE "NEW EQUIPMENT REPORT FORM" FOR DATA THAT
APPLIES TO THIS PIECE OF EQUIPMENT SEE EXAMPLE FORM
AND CLASSIFICATION & ATTRIBUTE TABLES; PROVIDED BY
YOUR COR.
0 999 COMPLETE PM Complete the PM through NIST Maximo System.; noting condition, suspect problems, parts used, gauge/meter readings, etc.
NOTIFY COR IF ANY EQUIPMENT REQUIRES REPLACEMENT AND
NOTE ON PM.
PWS Attach 5 - Job Plans Page 18 of 99 1333ND20RNB190010
Job Plan : JP-C-BLR-M Description : Contractor Boiler Monthly
0 1 OBTAIN PM Obtain PM from COR. The PM may be issued in a handheld device or paper.
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space.
Review manufacturer's instructions and equipment history record, if available.
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment. Ensure that the people affected have been notified (COR to notify) and associated equipment's operation will not be affected.
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 10 CHECK COMBUSTION CHAMBER FOR AIR OR GAS LEAKS CHECK COMBUSTION CHAMBER FOR AIR OR GAS LEAKS 0 20 CHECK FUEL LINES AND CONNECTIONS FOR DAMAGE CHECK FUEL LINES AND CONNECTIONS FOR DAMAGE
0 30 CHECK FOR PROPER OPERATIONAL RESPONSE OF
BURNER
CHECK FOR PROPER OPERATIONAL RESPONSE OF BURNER TO
POTENTIOMETER CONTROL
0 70 CHECK MAIN FLAME FAILURE PROTECTION CHECK MAIN FLAME FAILURE PROTECTION AND MAIN FLAME
DETECTION SCANNER ON BOILER EQUIPPED WITH SPARK
IGNITION
0 100 CHECK OPERATION OF MERCURY CONTROL SWITCHES CHECK OPERATION OF MERCURY CONTROL SWITCHES (I.E.
STEAM PRESSURE, HOT WATER TEMERATURE LIMIT, ATOMIZING
OR COMBUSTION AIR PROVING, ETC.)
0 110 CHECK SAFETY PRESSURE RELIEF VALVE CHECK OPERATION AND CONDITION OF SAFETY PRESSURE
RELIEF VALVE
0 120 CHECK OPERATION OF BOILER LOW WATER CUT OFF
DEVICE
CHECK OPERATION OF BOILER LOW WATER CUT OFF DEVICES
PWS Attach 5 - Job Plans Page 19 of 99 1333ND20RNB190010
Job Plan : JP-C-BLR-M Description : Contractor Boiler Monthly
Task Task Description Task Long Description
0 130 CHECK HOT WATER PRESSURE GAUGES CHECK HOT WATER PRESSURE GAUGES compare pressures to digital Reliable System. Check for any fluctuations indicating a potential leak.
0 140 INSPECT AND CLEAN WATER COLUMN SIGHT GLASS INSPECT AND CLEAN WATER COLUMN SIGHT GLASS
0 160 CHECK CONDITION OF FLUE PIPE, DAMPER AND
EXHAUST
CHECK CONDITION OF FLUE PIPE, DAMPER AND EXHAUST STACK
0 190 CLEAN AREA AROUND BOILER CLEAN AREA AROUND BOILER
0 999 COMPLETE PM Complete the PM on handheld or paper; noting condition, suspect problems, parts used, gauge/meter readings, etc.
Job Plan : JP-C-BLR-Q Description : Contractor Boiler Quarterly
0 1 OBTAIN PM Obtain PM from COR. The PM may be issued in a handheld device or paper.
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space.
Review manufacturer's instructions and equipment history record, if available.
PWS Attach 5 - Job Plans Page 20 of 99 1333ND20RNB190010
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment. Ensure that the people affected have been notified (COR to notify) and associated equipment's operation will not be affected.
PWS Attach 5 - Job Plans Page 21 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 10 CHECK COMBUSTION CHAMBER FOR AIR OR GAS LEAKS CHECK COMBUSTION CHAMBER FOR AIR OR GAS LEAKS 0 20 CHECK FUEL LINES AND CONNECTIONS FOR DAMAGE CHECK FUEL LINES AND CONNECTIONS FOR DAMAGE
0 30 CHECK FOR PROPER OPERATIONAL RESPONSE OF
BURNER
CHECK FOR PROPER OPERATIONAL RESPONSE OF BURNER TO
POTENTIOMETER CONTROL
0 60 CHECK AND LUBRICATE BURNER AND BLOWER
MOTORS
CHECK AND LUBRICATE BURNER AND BLOWER MOTORS
0 70 CHECK MAIN FLAME FAILURE PROTECTION CHECK MAIN FLAME FAILURE PROTECTION AND MAIN FLAME
DETECTION SCANNER ON BOILER EQUIPPED WITH SPARK
IGNITION
PWS Attach 5 - Job Plans Page 22 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 100 CHECK OPERATION OF MERCURY CONTROL SWITCHES CHECK OPERATION OF MERCURY CONTROL SWITCHES (I.E.
STEAM PRESSURE, HOT WATER TEMERATURE LIMIT, ATOMIZING
OR COMBUSTION AIR PROVING, ETC.)
0 110 CHECK SAFETY PRESSURE RELIEF VALVE CHECK OPERATION AND CONDITION OF SAFETY PRESSURE
RELIEF VALVE
0 120 CHECK OPERATION OF BOILER LOW WATER CUT OFF
DEVICE
CHECK OPERATION OF BOILER LOW WATER CUT OFF DEVICES
0 130 CHECK HOT WATER PRESSURE GAUGES CHECK HOT WATER PRESSURE GAUGES
0 140 INSPECT AND CLEAN WATER COLUMN SIGHT GLASS INSPECT AND CLEAN WATER COLUMN SIGHT GLASS
0 160 CHECK CONDITION OF FLUE PIPE, DAMPER AND
EXHAUST
CHECK CONDITION OF FLUE PIPE, DAMPER AND EXHAUST STACK
0 170 CHECK BOILER OPERATION THROUGH COMPLETE
CYCLE
CHECK BOILER OPERATION THROUGH COMPLETE CYCLE, UP TO
30 MINUTES
0 190 CLEAN AREA AROUND BOILER CLEAN AREA AROUND BOILER
0 999 COMPLETE PM Complete the PM on handheld or paper; noting condition, suspect problems, parts used, gauge/meter readings, etc.
Number of Records: 59
PWS Attach 5 - Job Plans Page 23 of 99 1333ND20RNB190010
Job Plan : JP-CCH-C-2Y Description : Job Plan Chiller Cup - 2 YEAR
0 10 ISSUE PM PM issued through NIST Maximo System.
0 20 REVIEW Review manufacturer's instructions and equipment history record, if available.
0 50 REPLACE OIL FILTER REPLACE THE EXTERNAL OIL FILTER WITH A NEW OEM
FILTER
0 60 REPLACE OIL RECLAIM FILTER/STRAINER REPLACE THE OIL RECLAIM FILTER/STRAINER WITH A NEW OEM
FILTER/STRAINER IF ISOLATABLE
0 70 REPLACE REFRIGERANT DRIERS REPLACE THE REFRIGERANT DRIERS IF ISOLATABLE
0 80 OIL SAMPLE REMOVE AN OIL SAMPLE FOR LAB ANALYSIS - PROVIDE WRITTEN
REPORT ON FINDINGS
0 90 CHECK OPERATING AND SAFETY CONTROL CALIBRATE AS REQUIRED
0 100 INSPECT STARTER INSPECT STARTER AND/OR VARIABLE SPEED DRIVE (VSD)
SETTINGS AS REQUIRED
0 110 CALIBRATE MOTOR VOLTAGE AND AMPERAGE CALIBRATE MOTOR VOLTAGE AND AMPERAGE INPUT
READINGS
0 120 PUNCH TUBES 3 STEP PROCESS 1. ISOLATE THE CONDENSER, DRAIN AND REMOVE THE BLACNK
SIDE COVER FOR ACCESS TO THE CONDENSER TUBES. 2. BRUSH
CLEAN THE CONDENSER TUBES WITH A SOFT BRISTLE BRUSH 3.
REPLACE THE CONDENSER COVER WITH NEW OEM GASKET,
REFILL AND CHECK FOR WATER
LEAKS
0 140 REPORT DEPARTURE REPORT TO CUSTOMER ON DEPARTURE AND ADVISE ON ANY
ISSUES FOUND.
0 999 COMPLETE PM COMPLETE THE PM IN MAXIMO AND RECORD ANY ISSUES
PWS Attach 5 - Job Plans Page 24 of 99 1333ND20RNB190010
Job Plan : JP-CCH-C-2Y Description : Job Plan Chiller Cup - 2 YEAR
Task Task Description Task Long Description
0 40 CHECK AND RECORD ALARMS AND ALERTS AND
CONFIGURATIONS
0 130 CLEAN UP THE WORK STATION
0 5 REPORT TO CUSTOMER UPON ARRIVAL
0 30 LEAK TEST THE ENTIRE CHILLER
Job Plan : JP-CCH-C-A Description : Job Plan Chiller Cup - Annual
0 10 PM ISSUE PM issued through NIST Maximo System.
0 20 REVIEW Review manufacturer's instructions and equipment history record, if available.
0 50 REPLACE OIL FILTER REPLACE THE EXTERNAL OIL FILTER WITH A NEW OEM
FILTER
0 60 REPLACE OIL RECLAIM FILTER/STRAINER REPLACE THE OIL RECLAIM FILTER/STRAINER WITH A NEW OEM
FILTER/STRAINER IF ISOLATABLE
0 70 REPLACE REFRIGERANT DRIERS REPLACE THE REFRIGERANT DRIERS IF ISOLATABLE
0 80 OIL SAMPLE REMOVE AN OIL SAMPLE FOR LAB ANALYSIS - PROVIDE WRITTEN
REPORT ON FINDINGS
0 90 CHECK OPERATING AND SAFETY CONTROL CALIBRATE AS REQUIRED
0 100 INSPECT STARTER INSPECT STARTER AND/OR VARIABLE SPEED DRIVE (VSD)
SETTINGS AS REQUIRED
0 110 CALIBRATE MOTOR VOLTAGE AND AMPERAGE CALIBRATE MOTOR VOLTAGE AND AMPERAGE INPUT
READINGS
PWS Attach 5 - Job Plans Page 25 of 99 1333ND20RNB190010
Job Plan : JP-CCH-C-A Description : Job Plan Chiller Cup - Annual
Task Task Description Task Long Description
0 140 REPORT DEPARTURE REPORT TO CUSTOMER ON DEPARTURE AND ADVISE ON ANY
ISSUES FOUND.
0 999 COMPLETE PM COMPLETE THE PM IN MAXIMO AND RECORD ANY ISSUES
0 130 CLEAN UP THE WORK STATION
0 40 CHECK AND RECORD ALARMS AND ALERTS AND
CONFIGURATIONS
0 30 LEAK TEST THE ENTIRE CHILLER
0 5 REPORT TO CUSTOMER UPON ARRIVAL
Job Plan : JP-CCH-C-Q Description : Job Plan Chiller Cup - Quarterly
0 10 ISSUE PM PM issued through NIST Maximo System.
0 20 REVIEW Review manufacturer's instructions and equipment history record, if available.
0 60 CHECK VSD RAMP TIMES & SPEED SETTINGS IF APPLICABLE
PWS Attach 5 - Job Plans Page 26 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 180 REPORT TO CUSTOMER REPORT TO CUSTOMER ON DEPARTURE AND ADVISE ON ANY
ISSUES FOUND
0 999 COMPLETE THE PM COMPLETE THE PM IN MAXIMO AND RECORD ANY ISSUES
PWS Attach 5 - Job Plans Page 27 of 99 1333ND20RNB190010
0 50 CHECK POWER AND PIPING
0 80 CHECK COOLER REFRIGERANT TEMPERATURE AND
PRESSURE
0 110 CHECK COMPRESSOR DISCHARGE TEMPERATURE
0 150 CHECK AND LOG OIL LEVEL, OIL PRESSURE AND OIL
TEMPERATURE
0 140 CHECK REFRIGERANT LEVELS THRU THE APPROACH
METHOD
PWS Attach 5 - Job Plans Page 28 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 160 MAKE EQUIPMENT ADJUSTMENTS AS REQUIRED FOR
PROPER OPERATION
0 140 CHECK REFRIGERANT LEVELS THRU THE APPROACH
METHOD
0 5 REPORT TO CUSTOMER UPON ARRIVAL
0 110 CHECK COMPRESSOR DISCHARGE TEMPERATURE
0 30 CHECK GENERAL MACHINE OPERATION
0 90 CHECK CONDENSER REFRIGERANT TEMPERATURE AND
PRESSURE
PWS Attach 5 - Job Plans Page 29 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 90 CHECK CONDENSER REFRIGERANT TEMPERATURE AND
PRESSURE
0 150 CHECK AND LOG OIL LEVEL, OIL PRESSURE AND OIL
TEMPERATURE
0 120 CHECK COMPRESSOR DISCHARGE SUPERHEAT
TEMPERATURE
0 40 CHECK CONTROL PARAMETERS
0 70 CHECK AND RECORD STARTS AND RUN HOURS
0 100 CHECK COMPRESSOR THRUST BEARING TEMPERATURE
PWS Attach 5 - Job Plans Page 30 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 130 LOG WATER TEMPERATURES AND DIFFERENTIAL
PRESSURES
0 160 MAKE EQUIPMENT ADJUSTMENTS AS REQUIRED FOR
PROPER OPERATION
Number of Records: 111
PWS Attach 5 - Job Plans Page 31 of 99 1333ND20RNB190010
Job Plan : JP-C-LIEBERTS-Q Description : Contractor Job plan Quarterly for Liebert Units
0 2 SAFETY REQUIRMENTS - READ SAFETY SHOULD ALWAYS BE PARAMOUNT IN OPERATION AND
MAINTENANCE. BEFORE ATTEMPTING ANY MAINTENANCE, BE
CERTAIN THE EQUIPMENT CANNOT BE STARTED
ACCIDENTALLY. IF SYSTEM IS PUMPED DOWN AND/OR VALVES
ARE CLOSED, TAG OR LABEL TO INDICATE STATUS OF UNIT. BE
CERTAIN THERE IS NO PRESSURE IN THE MACHINE BEFORE
OPENING. ON A RECIPROCATING UNIT, LOOSEN (DO NOT
REMOVE) ALL NUTS ON A VALVE COVER. PRY IT LOOSE SO THAT
ANY TRAPPED GAS MAY ESCAPE. THE REMOVE ALL NUTS AND
THE COVER.
NOTICE: ALWAYS RECOVER REFRIGERANT AND USE ADEQUATE
VENTILATION. "FREON" TYPE REFRIGERANTS CAN BE
DANGEROUS; WHEN HEATED TO DECOMPOSITION, THEY EMIT
HIGHLY TOXIC FUMES OF PHOSGENE AND FLUORIDES.
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space.
Review manufacturer's instructions and equipment history record, if available.
0 7 EQUIPMENT SHUTDOWN SAFETY De-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and release pressure in lines before working on equipment when necessary.
Ensure that the people affected have been notified (COR to notify) and associated equipment's operation will not be affected.
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
PWS Attach 5 - Job Plans Page 32 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 10 AIR FILTER 1. Check/replace filters / Change air filters with a pleat 40% type. ( Filter pleat direction should run parallel to the direction of the short side of the filter/ Do not use long pleat filter construction because it can cause filter collapse.)
2. Grille area unrestricted
3. Wipe section clean
4. Coil clean
0 20 Blower Section 1. Blower wheels free of debris
2. Check belt tension and condition (replace if needed or every 30 months)Belt's should be replace with factory installed parts.
3. Check/lube bearings
4. Check sheave/ pulley (replace if worn)
5. Check motor mount
6. Motor amp draw L1 L2 L
0 30 Reheat
0 50 Infrared Humidifier
Compare to nameplate amps
1. Inspect elements
2. Check wire connections (inside reheat box)
3. Reheat amp draw
a. #1
a. #2
a. #3
1. Check drain lines and trap for clogs
2. Check /clean pan for mineral deposits
3. Clean reflector
4. Check water make-up valve for leaks
5. Check humidifier lamps (replace if burnt out)
6. Check wire connections (inside humidifier box)
7. Humidifier amp draw L1 L2 L3
PWS Attach 5 - Job Plans Page 33 of 99 1333ND20RNB190010
0 60 Condensate Pump 1. Check for debris in sump
2. Check operation of float(s) (free movement) 0 70 Refrigeration Piping 1. Check refrigerant lines (clamps secure/ no rubbing /no leaks
2. Check for moisture (sight glass) 0 90 Drain Piping 1. Check for free running drain system
2. Clear out obstructions and material buildup on tubing walls
3. Check for leaks
4. Check for tubing kinks or damage
0 100 Compressor Section 1. Check oil level
2. Check for oil leaks
3. Check compressor mounts ( springs/bushings)
4. Cap tubes (not rubbing)
5. Check wire connections (inside compressor box)
6. Compressor operation (vibration/noise)
7. Suction pressure Circuit #1 Circuit #2
8. Discharge pressure Circuit #1 Circuit #2
9. Superheat Circuit #1 Circuit #2
10. Low pressure switch cut out Circuit #1 Circuit #2
11. Low pressure cut in Circuit #1 Circuit #2
12. High pressure cut out Circuit #1 Circuit #2
13. Amp draw
0 110 Electrical Panel
1. Circuit # 1
a. L1 L2 L3
2. Circuit # 2
a. L1 L2 L3
1. Check fuses
2. Check contactors for pitting
3. Check wire connections
PWS Attach 5 - Job Plans Page 34 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 120 Controls
1. Check/verify control operation (sequence)
2. Check humidifier high water alarm operation
3. Check operation of the air safety switch
4. Check setting/ operation of the filter clog switch
5. Check/test water detection device(s)
PWS Attach 5 - Job Plans Page 35 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 130 Air-Cooled Condenser/ Dry cooler
1. Coil surfaces and fans free of debris(clean, wash and straighten fins as needed)(Power wash condenser coils, if coils are doubled, separate and power wash between coils.
Clean evaporator drain pan, blowers, fans, motors, and drain piping as required.
2. Fan motors securely mounted
3. Motor bearings in good condition
4. Check all piping and capillaries for vibration isolation ;
support and secure as necessary
5. Check fuses
6. Check contactors for pitting
7. Check wire connections
8. Fan speed control operation
9. Check operational sequence/thermostat setpoints
10. Check refrigerant/glycol lines for signs of leaks/repair leaks as found
11. Check refrigerant level in each Liebert Lee Temp receiver
12. Glycol level
13. Glycol solution %
14. Motor amp draw
#1 L1 L2 L3 (L1 and L2 on fan speed control motor) #2 L1 L2 L3 #3 L1 L2 L3 #4 L1 L2 L3 #5 L1 L2 L3 #6 L1 L2 L3 #7 L1 L2 L3 #8 L1 L2 L3
PWS Attach 5 - Job Plans Page 36 of 99 1333ND20RNB190010
Task Task Description Task Long Description Sequence 0 999 COMPLETE PM Complete the PM through NIST Maximo System.; noting condition, suspect problems, parts used, gauge/meter readings, etc.
NOTIFY COR IF ANY EQUIPMENT OR PARTS REQUIRE
Number of Records: 17
PWS Attach 5 - Job Plans Page 37 of 99 1333ND20RNB190010
Job Plan : JP-C-CT-A Description : Contractor Job Plan Cooling Tower Annual
0 1 OBTAIN PM PM issued through NIST Maximo System.
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW REVIEW ALL STEPS IN PM.
REVIEW SAFTEY REQUIREMENTS FOR THIS EQUIPMENT AND
SPACE.
REVIEW MANUFACTURER'S INSTRUCTIONS AND EQUIPMENT
HISTORY RECORD, IF AVAILABLE.
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment. Ensure that the people affected have been notified (COR to notify) and associated equipment's operation will not be affected.
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 10 CHECK STRUCTURAL MEMBERS CHECK STRUCTURAL MEMBERS FOR BRAKES, BROKEN WELDS,
LOOSE OR MISSING BOLTS. LOOK FOR EXCESSIVE RUST, PITTING,
AND CORROSION BOTH INSIDE AND OUTSIDE UNIT.
0 20 INSPECT GENERAL CONDITION INSPECT GENERAL CONDITION OF ELIMINATORS, CONNECTORS, SCREENS, AND DAMPERS. CLEAN, 0 30 CHANGE BELTS CHECK FAN, BEARINGS, SHEAVES, REPLACE BELTS.
0 40 LUBRICATE MOTORS, FAN BEARINGS, LUBRICATE MOTORS, FAN BEARINGS, AND DAMPER LINKAGE AS
RECOMMENDED BY MANUFACTURER.
0 50 CLEAN STRAINER CLEAN STRAINER NOTE STRAINER CONDITION. NOTIFY COR IF
STRAINER ISN'T PRESENT OR NEEDS REPLACEMENT.
0 60 CLEAN MAKE UP TANK CLEAN MAKE UP TANK, DRAIN AND WASHOUT W ITH HOSE.
0 70 INSPECT GENERAL CONDITION INSPECT GENERAL CONDITION OF SLATS, BAFFLES, SPLASH PANS
AND DECKS.
PWS Attach 5 - Job Plans Page 38 of 99 1333ND20RNB190010
Job Plan : JP-C-CT-A Description : Contractor Job Plan Cooling Tower Annual
Task Task Description Task Long Description
0 80 PRESSURE WASH PRESSUE WASH COOLING TOWER TANK AND EXTERIOR, MAKE
SURE TOWER IS FREE OF ALL SILT AND DEBRIS FROM POWER
WASHING.
0 90 INSPECT AND SET FLOAT VALVE. INSPECT AND SET FLOAT VALVE FOR PROPER OPERATION AND
WATER LEVEL.
0 120 INSPECT, TEST, AND ADJUST. INSPECT, TEST, AND ADJUST ALL ELECTRIC CONTROLS AND
PROTECTIVE DEVICES. CHECK ALL ELECTRICAL CONTACTS FOR
PITTING, BURNING, OR EXCESSIVE WEAR. MAKE SURE UNITS
HAVE PROPER SIZE FUSES, BREAKERS, AND MOTOR CONTROL
HEATERS.
0 998 COMPLETE "NEW EQUIPMENT REPORT FORM" COMPLETE" NEW EQUIPMENT FORM" FOR DATA THAT APPLIES
TO THIS PIECE OF EQUIPMENT. SEE EXAMPLES FORM AND
CLASSIFICATION& ATTRIBUTE TABLE; PROVIDED BY YOUR COR
0 999 COMPLETE PM Complete the PM through NIST Maximo System.; noting condition, Job Plan : JP-C-CT-M Description : Contractor Job Plan Cooling Tower Monthly
Task Task Description Task Long Description
0 1 OBTAIN PM PM issued through NIST Maximo System.
PWS Attach 5 - Job Plans Page 39 of 99 1333ND20RNB190010
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW REVIEW ALL STEPS IN PM.
REVIEW SAFTEY REQUIREMENTS FOR THIS EQUIPMENT AND
SPACE.
REVIEW MANUFACTURER'S INSTRUCTIONS AND EQUIPMENT
HISTORY RECORD, IF AVAILABLE.
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment. Ensure that the people affected have been notified (COR to notify) and associated equipment's operation will not be affected.
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 20 INSPECT GENERAL CONDITION OF ELIMINATORS... INSPECT GENERAL CONDITION OF ELIMINATORS, CONNECTORS, SCREENS, AND DAMPERS. CLEAN
PWS Attach 5 - Job Plans Page 40 of 99 1333ND20RNB190010
Task Task Description Task Long Description Sequence 0 25 WATER TREATMENT Maintain the following parameters or as directed by chemical company representative:
Cycles of concentration 5- to -7
Phosphate 2.0 to 3.0 PPM
Algae will be controlled using algaecide and biocides. I some areas (inside the building) odor is a problem; other means shall be used for the control of algae.
When chemical pumps malfunction contractor will be responsible for repair or replacement.
All other related equipment i.e. filters, valves, injection quills and feed lines shall be inspected on each visit. If they are not functioning properly or need replacement, notify COR for any corrective action.
Chemical tanks shall be prepared for 2-3 days of unattended operation on Fridays or before holiday weekends to insure that the water chemistry parameters are maintained throughout the unattended period.
A logbook of all readings shall be kept in each mechanical room, where the pumps supplying the cooling tower are located and a copy provided monthly to the COR. Contractor will provide all chemicals and testing equipment. Contractor is responsible for keeping one month of chemical and salt on hand at all times.
Testing reagents: If reagents are not testing properly, notify COR
PWS Attach 5 - Job Plans Page 41 of 99 1333ND20RNB190010
Task Task Description Task Long Description and they will be replaced by the chemical supplier.
COR shall be notified of any malfunction or problem that cannot be repaired by the contractor, on a daily basis and noted in the monthly log submitted to the COR.
>>>>>>This step in the PM shall be documented as complete on the following month's tower PM. <<<<<<
0 70 INSPECT GENERAL CONDITION OF SLATS... INSPECT GENERAL CONDITION OF SLATS, BAFFLES, SPLASH PANS
AND DECKS.
0 999 COMPLETE PM Complete the PM through NIST Maximo System.; noting condition, suspect problems, parts used, gauge/meter readings, etc.
PWS Attach 5 - Job Plans Page 42 of 99 1333ND20RNB190010
Job Plan : JP-C-CU-M Description : Job Plan Monthly removal of cotton from condensing units
Task Task Description Task Long Description
0 10 Clean cotton from condensing coils
Job Plan : JP-C-CU-Q Description : Contractor Job Plan Condensing Unit Quarterly
0 1 PM ISSUED PM issued through NIST Maximo System.
0 2 SAFTEY REQUIREMENTS SAFETY SHOULD BE PARAMOUNT IN OPERATION AND
MAINTENANCE. BEFORE ATTEMPTING ANY MAINTENANCE BE
CERTAIN THE EQUIPMENT CANNOT BE STARTED ACCIDENTALLY.
NOTICE: ALWAYS RECOVER REFRIGERANT AND USE ADEQUATE
VENTILATION. "FREON" TYPE REFRIGERANTS CAN BE
DANGEROUS WHEN HEATED TO DECOMPOSITION, THEY EMIT
HIGHLY TOXIC FUMES OF PHOSGENE AND FLUORIDES.
0 3 SCHEDULE THE PM Schedule the PM with the operating personnel. NO equipment will be shut down without scheduling with the area personnel.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space.
Review manufacturer's instructions and equipment history record, if available.
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment. Ensure that the people affected have been notified and associated equipment's operation will not be affected.
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
PWS Attach 5 - Job Plans Page 43 of 99 1333ND20RNB190010
Job Plan : JP-C-CU-Q Description : Contractor Job Plan Condensing Unit Quarterly
Task Task Description Task Long Description
0 10 CHECK UNIT FOR PROPER OPERATION CHECK UNIT FOR EXCESSIVE NOISE, VIBRATION, SIGNS OF OIL
LEAKAGE, ECT.
0 50 INSPECT FANS INSPECT FAN OF THE UNIT FOR PROPER OPERATION, REPORT
ANY BENT, DAMAGED, OR UNBALANCED BLADE,
0 60 INSPECT PIPING INSPECT ALL VALVES AND PIPING TO EVAPORATOR UNITS FOR
LEAKS,
0 70 CLEAN AREA CLEAN AREA AROUND EQUIPMENT, PROPERLY DISPOSE OF ALL
TRASH AND DEBRIS.
0 999 COMPLETE PM Complete the PM through NIST Maximo System; noting condition, suspect problems, parts used, gauge/meter readings, etc.
Job Plan : JP-C-CU-S Description : Contractor Job Plan Condensing Unit Semi-Annual
Task Task Description Task Long Description
0 1 PM ISSUED PM issued through NIST Maximo System.
PWS Attach 5 - Job Plans Page 44 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 2 SAFTEY REQUIREMENTS SAFETY SHOULD BE PARAMOUNT IN OPERATION AND
MAINTENANCE. BEFORE ATTEMPTING ANY MAINTENANCE BE
CERTAIN THE EQUIPMENT CANNOT BE STARTED ACCIDENTALLY.
NOTICE: ALWAYS RECOVER REFRIGERANT AND USE ADEQUATE
VENTILATION. "FREON" TYPE REFRIGERANTS CAN BE
DANGEROUS WHEN HEATED TO DECOMPOSITION, THEY EMIT
HIGHLY TOXIC FUMES OF PHOSGENE AND FLUORIDES.
0 3 SCHEDULE THE PM Schedule the PM with the operating personnel. NO equipment will be shut down without scheduling with the area personnel.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space.
Review manufacturer's instructions and equipment history record, if available.
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment. Ensure that the people affected have been notified and associated equipment's operation will not be affected.
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 10 CHECK UNIT FOR PROPER OPERATION CHECK UNIT FOR EXCESSIVE NOISE, VIBRATION, SIGNS OF OIL
LEAKAGE, ECT.
0 20 PRESSURE WASH COILS AND FANS PRESSURE WASH COIL AND FAN OF THE UNIT WITH AN
APPROVED COIL CLEANING SOLUTION AND RINSE
PWS Attach 5 - Job Plans Page 45 of 99 1333ND20RNB190010
0 30 CHECK ELECTRICAL CONTROLS PERFORM OPERATIONAL CHECK OF UNIT: MAKE ADJUSTMENTS
ON CONTROLS AND OTHER COMPONENTS AS REQUIRED FOR
PROPER OPERATION.
CLEAN ELECTRICAL WIRING AND CONNECTIONS ENSURE ALL
CONNECTIONS ARE SECURE.
INSPECT CONDITION & SIZING OF ANY FUSES, INCLUDING ONES
THAT MAY BE ON THE CONTROL CIRCUIT BOARDS.
CHECK RELAYS AND CONTRACTORS FOR WEAR AND OPERATION.
CHECK OPERATING AND SAFETY CONTROLS.
>>>>>CHECK AND RECORD MOTOR VOLTS-NAMEPLATE VS. N.P.
DATA<<<<<<
>>>>>CHECK AND RECORD MOTOR AMPS-NAMEPLATE VS N.P.
DATA<<<<<<
CHECK CRANKCASE HEATER IF EQUIPPED
>>>>>CHECK COMPRESSOR MOTOR WINDINGS WITH MEG
OHMMETER AND RECORD.<<<<<
CHECK HIGH AND LOW PRESSURE SWITCHES FOR OPERATION.
0 35 COMPRESSOR AND REFRIGERANT DURING OPERATION OF UNIT CHECK REFRIGERANT PRESSURE;
ADD REFRIGERANT IF NECESSARY NOTE AMOUNT ADDED.
CHECK CONDITION OF REFRIGERANT OIL USING " TOTAL TEST
TUBE" SYSTEM OR EQUAL AND REPORT RESULTS
CHECK AND RECORD AMBIENT TEMPERATURE
CHECK AND RECORD SUCTION PRESSURE
CHECK AND RECORD SUCTION TEMPERATURE
CHECK AND RECORD DISCHARGE TEMPERATURE
CHECK AND RECORD DISCHARGE HEAD PRESSURE
RECORD SUPER HEAT CALCULATION
RECORD ANY REPAIRS MADE OR REQUIRED
0 50 INSPECT FANS INSPECT FANS OF THE UNIT FOR PROPER OPERATION, REPORT
ANY BENT, DAMAGED, OR UNBALANCED BLADE,
PWS Attach 5 - Job Plans Page 46 of 99 1333ND20RNB190010
Task Task Description Task Long Description
0 60 INSPECT PIPING INSPECT ALL VALVES AND PIPING TO EVAPORATIVE UNIT FOR
LEAKS,
0 70 CLEAN AREA CLEAN AREA AROUND EQUIPMENT, PROPERLY DISPOSE OF ALL
TRASH AND DEBRIS.
0 999 COMPLETE PM Complete the PM through NIST Maximo System; noting condition, suspect problems, parts used, gauge/meter readings, etc.
PWS Attach 5 - Job Plans Page 47 of 99 1333ND20RNB190010
Job Plan : JP-C-DRY-Q Description : Contractor Job Plan Air Dryer Quarterly
0 1 OBTAIN PM PM issued through NIST Maximo System.
0 3 SCHEDULE THE PM Schedule the PM with the COR. NO equipment will be shut down without scheduling with the COR.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space Review manufacturer's instructions and equipment history record, if available.
0 7 EQUIPMENT SHUTDOWN SAFETY If shut-down is necessary; de-energize, tag, and lock out electrical circuits to motors, pumps, control circuits, etc and de-energize pressure in lines before working on equipment. Ensure that the people affected have been notified (COR to notify) and associated equipment's operation will not be affected.
0 8 ELECTRICAL SAFETY SAFETY: WHEN TAKING VOLTAGE OR CURRENT MEASUREMENTS,
USE THE PROPER EQUIPMENT IN AN APPROVED MANNER.
0 9 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any deficiencies.
0 10 CHECK OPERATING CONDITIONS CHECK OPERATING CONDITIONS, PURGE RATE LINE PRESSURE, INLET FLOW.
0 20 CHECK DRYER OPERATING CYCLE CHECK DRYER OPERATING CYCLE FOR PROPER OPERATION OF
VALVE OPERATORS, SOLENOID VALVES, DUMP VALVES, HEATERS,
PRESSURE SWITCHES AND TEMPERATURE CONTROLLER
0 30 CHECK THE OUTLET DEWPOINT CHECK THE OUTLET DEWPOINT
0 40 BLOW DOWN RELIEF VALVES BLOW DOWN RELIEF VALVES
0 50 CHECK HEATER OUTLET TEMP CHECK HEATER OUTLET TEMPERATURE, IT SHOULD BE
BETWEEN 400 AND 425 DEGREES F
0 60 VERIFY PRESSURE SWITCH OPERATION VERIFY PRESSURE SWITCH OPERATION
PWS Attach 5 - Job Plans Page 48 of 99 1333ND20RNB190010
Job Plan : JP-C-DRY-Q Description : Contractor Job Plan Air Dryer Quarterly
0 70 INSPECT PILOT AIR FILTER ELEMENT INSPECT PILOT AIR FILTER ELEMENT. IF ELEMENT SEEMS
CLOGGED, DIRTY OR DAMAGED, REPLACE FILTER
NOTIFY COR IMMEDIATELY IF ANY PARTS REQUIRE REPLACING
AND NOTE ON PM
0 998 COMPLETE "NEW EQUIPMENT REPORT FORM" COMPLETE "NEW EQUIPMENT REPORT FORM" FOR DATA THAT
APPLIES TO THIS PIECE OF EQUIPMENT SEE EXAMPLE FORM
AND CLASSIFICATION & ATTRIBUTE TABLES; PROVIDED BY
YOUR COR.
0 999 COMPLETE PM Complete the PM through NIST Maximo System; noting condition, suspect problems, parts used, gauge/meter readings, etc.
Number of Records: 15
PWS Attach 5 - Job Plans Page 49 of 99 1333ND20RNB190010
Job Plan : JP-C-EF-A Description : Contractor Job Plan Exhaust Fan Annual
0 1 PM ISSUED PM issued through NIST Maximo System.
0 3 SCHEDULE THE PM Schedule the PM with the AREA PERSONNEL. NO equipment will be shut down without scheduling.
0 5 REVIEW Review all steps in PM.
Review safety requirements for this equipment and space.
Review manufacturer's instructions and equipment history record, if available.
0 7 CHECK WITH OPERATING OR AREA PERSONNEL Check with operating or area personnel for any…