This document includes a federal contract opportunity notice for the renovation of Building 1 at the National Institute of Standards and Technology (NIST) Boulder campus. The design-build project involves renovating Wing 4, Wing 5, and portions of the main corridor, with a minimum LEED Gold certification required. The base contract line item is for renovating Wing 5, with additional option line items to renovate Wing 4, the main corridor, and associated furnishings. The anticipated period of performance is 616 days for Wings 5 and 4, and 308 days for the main corridor. The solicitation number is 1333ND19RNB190004 and will be posted on or around June 3, 2019. The estimated value is over $10 million and it is a full and open competition with a NAICS code of 236220 and small business size standard of $36.5 million. A pre-proposal conference will be held as detailed in the forthcoming solicitation.

Attachment 10 - Historic Structure Report Attachments - Photos

View the file

Other files

File Type Posted
RFP-PII_22_Historic_Structure_Report_Attachments_-_Preservation_Brief_24.pdf PDF
RFP-PII_10_Conceptual_Planning_Report_by_Smith_Group_2012_from_PPR_Appendix_C.pdf PDF
RFP-PII_5_Geotech_Report_by_Empire_Labs_for_Wing_3_Addition_to_Building_1_from_PPR_Appendix_A.pdf PDF
RFP-PII_8_HVAC_Design_Data_and_Sizing_Summary_for_Wing_4_from_PPR_Appendix_A.pdf PDF
RFP-PII_0_Attach_E_Subcontracting_Plan_Requirements.pdf PDF
RFP-PII_16_Historic_Structure_Report_Attachments_-_Preservation_Brief_4.pdf PDF
RFP-PII_4_Geotech_Report_by_Empire_Labs_for_Wing_1_Addition_to_Building_1_from_PPR_Appendix_A.pdf PDF
RFP-PII_25_Wage_Determination_CO20180027.pdf PDF
RFP-PII_9_HVAC_Design_Data_and_Sizing_Summary_for_Wing_5_from_PPR_Appendix_A.pdf PDF
1333ND19RNB190004A002.pdf PDF
RFP-PII_18_Historic_Structure_Report_Attachments_-_Preservation_Brief_14.pdf PDF
RFP-PII_14_Historic_Structure_Report_Attachments_-_Preservation_Brief_1.pdf PDF
RFP-PII_1_Energy_Modeling_Data_from_PPR_Appendix_A.pdf PDF
RFP-PII_24_NIST_Bldr_Lab_&_Admin_Space_Planning_Study_2016.pdf PDF
RFP-PII_6_Geotech_Report_by_JA_Cesare_from_PPR_Appendix_A.pdf PDF
RFP-PII_11_Construction_Drawings_1960_from_PPR_Appendix_C.pdf PDF
RFP-PII_12_Construction_Drawings_by_HDR_for_Connector_to_B81_from_PPR_Appendix_C.pdf PDF
RFP-PII_20_Historic_Structure_Report_Attachments_-_Preservation_Brief_16.pdf PDF
RFP-PII_19_Historic_Structure_Report_Attachments_-_Preservation_Brief_15.pdf PDF
RFP-PII_2_Geotech_Report_by_Empire_Labs_for_Rear_Addition_to_Building_1_from_PPR_Appendix_A.pdf PDF
RFP-PII_13_Floor_Plans_for_Spine_from_PPR_Appendix_C.pdf PDF
RFP-PII_3_Geotech_Report_by_Empire_Labs_for_South_Addition_to_Building_1_from_PPR_Appendix_A.pdf PDF
RFP-PII_21_Historic_Structure_Report_Attachments_-_Preservation_Brief_18.pdf PDF
RFP-PII_17_Historic_Structure_Report_Attachments_-_Preservation_Brief_13.pdf PDF
RFP-PII_7_HVAC_Design_Data_and_Sizing_Summary_for_Spine_from_PPR_Appendix_A.pdf PDF
RFP-PII_15_Historic_Structure_Report_Attachments_-_Preservation_Brief_3.pdf PDF
RFP-PII_23_Historic_Structure_Report_Attachments_-_Preservation_Brief_41.pdf PDF
1333ND19RNB190004A001.pdf PDF
Attachment_A001_1333ND19RNB190004-B1RW5-4-S-RFI-GovResponse-2019-08-15.pdf PDF
Attendance_Roster_B1R.pdf PDF
1_NIST-B1R-W5-4-Spine-P1-Preproposal_Conf-8-8-19.pdf PDF
RFI_Sheet_Template.xlsx XLSX spreadsheet
RFP_Attach_8_Historic_Assessment_by_Goodwin_&_Assoc_from_PPR_Appendix_C.pdf PDF
RFP_Attach_B_NIST_AMD_Boulder_PPQ_Form.pdf PDF
RFP_Attach_12_Sustainable_Design_Review_for_LEED-NC_2018.pdf PDF
RFP_Attach_11_Historic_Structure_Report_Attachments_-_Zone_Maps.pdf PDF
RFP_Attach_A_Cons_&_Design_Exp_Proj-Data-Sheet.pdf PDF
RFP_Attach_7_Construction_Drawings_1952_from_PPR_Appendix_C.pdf PDF
RFP_Attach_2_General_Instructions_for_Conducting_Work_at_NIST_Boulder_-_22_August_2018.pdf PDF
RFP_Attach_C_ResumeFormKeyPersonnel.pdf PDF
RFP_Attach_4_Geotech_Report_by_CTL_Thompson_from_PPR_Appendix_A.pdf PDF
RFP_Attach_D_KeyPersonnelStatement.pdf PDF
RFP_Attach_5_Site_Plans_from_PPR_Appendix_A.pdf PDF
RFP_Attach_1_Statement_of_Work_B1_Renovation_W5_W4_Spine.pdf PDF
RFP_Attach_9_Historic_Structure_Report_-_PPR_Appendix_C.pdf PDF
RFP_Attach_E_Subcontracting_Plan_Requirements.pdf PDF
RFP_Attach_3_NIST_PPR-B1R-W5-W4-Spine-31Jul2019.pdf PDF
RFP_Attach_6_NIST_Boulder_Campus_Master_Plan_2017_from_PPR_Appendix_C.pdf PDF
Request_for_Proposal_1333ND19RNB190004.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Photo C-1. NIST Nain Entrance – Front of the House shown with library on the left side and auditorium on the right side of entrance (view southwest)

Figure C-2. Exposed Concrete Wall on West Elevation of Auditorium (view southeast)

Figure C-3. Concrete Spalling on West Elevation of Auditorium

Figure C-4. Detail of Auditorium Stone Wall

Figure C-5. North-Facing Exterior Door on the West Side of the Auditorium (view southwest). This door was replaced in 1981.

Figure C-6. Ramp to West Auditorium Stage Door, Stone and Brick Retaining Wall, and “Butterfly” Screen Wall (view northeast)

Figure C-7. Concrete Structure and Stone Walls on North Elevation of Auditorium (view southwest)

Figure C-8. Northeast Corner of Auditorium (view southwest)

Figure C-9. Ramp to East Auditorium Stage Door, Stone and Brick Retaining Wall, and “Butterfly” Screen Wall (view northeast)

Figure C-10. Cornerstone in East Wall of the Auditorium (view west)

Figure C-11. South Wall of Auditorium (view east)

Photo C-12. Roof over Auditorium (view northeast)

Figure C-13. Roof Drains and Membrane on Auditorium Roof (view northeast)

Photo C-14. North Elevation of Library (view west)

Photo C-15. Detail of North Elevation of Library (view southwest)

Photo C-16. West Elevation of Library (view south)

Photo C-17. East Elevation of Library (view north)

Photo C-18. South Elevation of Library (view north)

Photo C-19. Original Windows on South Elevation (view north)

Photo C-20. Building 1 Courtyard and Main Entrance to Lobby (view southwest)

Photo C-21. Vestibule and Main Entrance to Lobby (view west)

Photo C-22. Building 1 Courtyard (view south)

Photo C-23. Patched Columns in Courtyard

Photo C-24. West Elevation of Spine (view northeast)

Photo C-25. East Elevation of Spine (view northwest)

Photo C-26. West Elevation of Spine between Wings 3 and 5 (view northeast)

Photo C-27. Spine Window System

Photo C-28. Sunken Courtyard on West Elevation of Spine (view south)

Photo C.29. Roof of Spine (view northeast)

Photo C-30. South Elevation of the Rooftop Penthouse (view northeast)

Photo C-31. North Elevation of the Rooftop Penthouse (view southwest)

Photo C-32. 2017 Egress Stairway and Secondary Means of Egress on West Side of Penthouse and Spine (view southwest)

Photo C-33. South Elevation of the Spine between Wings 4 and 6 (view north)

Photo C-34. Orange Staining on Concrete and Replacement Windows on North Elevation of Wing 1 (view southeast)

Photo C-35. Original and Replacement Windows on North Elevation of Wing 1 (view southeast)

Photo C-36. Replacement Windows and Original Door on \South Elevation of Wing 1 (view north)

Photo C-37. Replacement Windows and Original Door on South Elevation of Wing 1 Hyphen (view north)

Photo C-38. Original Windows on North Elevation of Wing 1

Photo C-39. Original Door on North Elevation of Wing 1 (view southwest)

Photo C-40. Replacement Doors on North Elevation of Wing 1 (view southwest)

Photo C-41. Downspouts on Wing 1

Photo C-42. Annex C and Connecting Hyphen on the West Side of Wing 1 (view

Photo C-43. Annex D South of Wing 1 (view southeast)

Photo C-44. Rooftop of Wing 1 and Annexes E and F (view west)

Photo C-45. Connections between Annexes D and E to the Rooftop of Wing 1 (view northwest)

Photo C-46. Annexes D and E (view northwest)

Photo C-47. South and East Elevations of Wing 2 (view north)

Photo C-48 North Elevation of Wing 2 (view southwest)

Photo C-49. Concrete Wall Detail with Horizontal Pour Line, Vertical Control Joint, and Orange Concrete Stains; Typical of Wings 1, 2, and 4.

Photo C-50. Replacement Windows on North Elevation of Wing 2 (view northwest)

Photo C-51. South Elevation of Wing 2 (view north)

Photo C-52. Doors on South Elevation of Wing 2 (view north); the single-leaf door on the left is a later addition and is not an original feature of Wing 2

Photo C-53. Loading Dock on the North Elevation of the Hyphen between the Spine and Wing 2 (view southwest)

Photo C-54. Loading Dock on the East Elevation of Wing 2 (view north); the cantilevered shade and the metal pipe railings are not historic features of this elevation

Photo C-55. View of Roof of Wing 2 from the Roof of the Spine (view south)

Photo C-56. North Elevation of Wing 3 (view west).

Photo C-57. North and West Elevations of Wing 3 (view south)

Photo C-58. South and East Elevations of Wing 4 (view north)

Photo C-59. Typical Wing 4 Exterior Bay (view southwest)

Photo C-60. South Elevation of Wing 4 (view east)

Photo C-61. Doors on South Elevation (view north); the single-leaf door on the left is a later addition and is not an original feature of Wing 2

Photo C-62. Door on North Elevation (view west)

Photo C-63. East Elevation of Wing 4 (view west); three original windows have been removed from the first bay

Photo C-64. Wing 4, South Elevation (view northwest)

Photo C-65. Wing 5, North Elevation (view southwest)

Photo C-66. Wing 5, South Elevation (view northeast)

Photo C-67. Metal Awnings on North Elevation (view southwest)

Photo C-68. Failed Original Concrete Canopy and Metal Awnings on North Elevation (view west)

Photo C-69. West Elevation of Wing 5 (view southeast)

Photo C-70. South and East Elevations of Wing 6 (view west)

Photo C-71. East Elevation of Wing 6 (view west)

Photo C-72. Auditorium Interior (view northeast toward stage and north wall)

Photo C-73. Auditorium Stage (view north)

Photo C-74. East Wall of Auditorium (view southeast)

Photo C-75. South Wall of Auditorium (view southwest)

Photo C-76. Detail of Base on East and West Walls

Photo C-77. Projection Room (view southeast)

Photo C-78. Portal to Auditorium (view northeast)

Photo C-79. Room 1107

Photo C-80. Room 1108

Photo C-81. Room 1201

Photo C-82. Room 1201A

Photo C-83. Room 1203

Photo C-84. Library Entrance (view northwest)

Photo C-85. Library Stacks (view southeast)

Photo C-86. West and North Walls (view north)

Photo C-87. Library Front Desk (view northeast)

Photo C-88. Library Support Room (view northeast)

Photo C-89. Wood Paneled Wall in Library (view southeast)

Photo C-90. Building 1 Main Entrance and Vestibule (view northeast)

Photo C-91. Interior Planting Area in Vestibule (view northeast)

Photo C-92. View of Lobby toward the Foyer in the West Division (view northwest)

Photo C-93. Auditorium Entrance off of the Foyer (view northeast)

Photo C-94. West End of Foyer (view north)

Photo C-95. South Wall of the Foyer between the Entrances to the Lecture Rooms (view west)

Photo C-96. North Wall of the Foyer between the Entrances to the Auditorium (view east)

Photo C-97. South Wall of Lobby (view southeast)

Photo C-98. Lobby Stairs to Levels 1 and 2 of the Spine (view southwest); the handrails were originally 1.5-inch steel pipe

Photo C-99. Lobby Stairs to Levels 1 and 2 of the Spine (view southeast); the handrails were originally 1.5-inch steel pipe

Photo C-100. Detail of Terrazzo

Photo C-101. View from the Lobby toward the Corridor in the East Division (view

Photo C-102. Corridor in East Division (view southeast)

Photo C-103. Corridor in East Division (view southeast)

Photo C-104. East End of Corridor and Former Location of Original Conference Room (view southeast; the doors and finishes in this area are not original

Photo C-105. Lobby Area in Level 2 of the Spine (view southwest)

Photo C-106. Lobby Area in Level 1 of the Spine (view southwest)

Photo C-107. Restroom in Level 1

Photo C-108. Restroom in Level 1

Photo C-109. Reception Area (view southwest)

Photo C-110 Electrical Switches in the Reception Area

Photo C-111. Wood Wall Paneling in the Reception Area

Photo C-112. Room 1101B

Photo C-113. Room 1101C

Photo C-114. Quartz Crystal Oscillator and Emmy Award Displays in Lobby (view north)

Photo C-115. Plaque Listing Chamber of Commerce Donors in the Front of the House Corridor

Photo C-116. Award Display in the Front of the House Corridor

Photo C-117. Cornerstone Monument on the East Exterior Wall of the Auditorium (view

Photo C-118. Dedication Plaque on the East Exterior Wall of the Auditorium (view

Photo C-119. Former Cafeteria in Level 1 of the Spine (view southwest)

Photo C-120. Modern Metal Staircase in Sunken Terrace (view north)

Photo C-121. Corridor between Former Cafeteria Area and Boiler Room (view southwest)

Photo C-122. Boiler Room Area in Level 1 of Spine (view southwest)

Photo C-123. Double-Loaded Corridor on Level 2 of the Spine (view southwest)

Photo C-124. Original Door and Hardware within Level 2 of the Spine

Photo C-125. Newer Door within Level 2 of the Spine

Photo C-126. Upgraded Elevator within Level 2 of the Spine

Photo C-127. Double Loaded Corridor in Level 2 of the Spine, South of the Intersection of Wings 1 and 2 (view southwest)

Photo C-128. Interpretive Displays the Level 2 Spine Corridor

Photo C-129. Interpretive Displays the Level 2 Spine Corridor

Photo C-130. Interpretive Displays the Level 2 Spine Corridor

Photo C-131. Interpretive Displays the Level 2 Spine Corridor

Photo C-132. Interpretive Displays the Level 2 Spine Corridor

Photo C-133. Infilled Atomic Clock Viewing Window

Photo C-134. Painting at the South End of the Level 2 Corridor

Photo C-135. Level 3 Spine Corridor (view northeast)

Photo C-136. Level 3 Spine Corridor (view southwest)

Photo C-137. Typical Expansion Joint Cover

Photo C-138. Upgraded Elevator in Level 3 of the Spine

Photo C-139. Curtained Viewing Window in Level 4 of the Spine.

Photo C-140. Double-Loaded Corridor in Wing 1

Photo C-141. Original Doors in Wing 1

Photo C-142. Double-Loaded Corridor in Wing 2

Photo C-143. Original Doors in Wing 2

Photo C-144. Stairs to the Mezzanine Offices in Wing 2

Photo C-145. Double-Loaded Corridor in Wing 4

Photo C-146. Original Door and Asphalt Tile Flooring in Wing 4

Photo C-147. High Bay Laboratory Space in Wing 4

Photo C-148. Basement of Wing 5.

Photo C-149. Women’s Restroom in Basement of Wing 5.

Photo C-150. Level 3 of Wing 5.

Photo C-151. Level 5 (Monitor Level) of Wing 5.

Photo C-152. Wing 3 Interior

Photo C-153. Wing 6 Interior

Photo C-154. Spalls at Steel Embed

Photo C-155. Water Exposure and Cracks

Photo C-156. Cracks

Photo C-157. Sunshade Staining

Photo C-158. Column Cracks and Stains

Photo C-159. Cracking at Top of Column

Photo C-160. Cracks in Wall

Photo C-161. Cracks in Roof Beam

Photo C-162. Spall at Rusted Rebar

Photo C-163. Column Cracks

Photo C-164. Deterioration of Existing Canopy