J.2_Attachment_02.pdf
PDF 83 KB Posted
- Solicitation number
- 1331L519R13OS0005
About this file
This document provides a phased implementation timeline for the Business Applications Solution. The timeline outlines a three phase implementation plan spanning fiscal years 2019 through 2025 for the Department of Commerce Office of the Secretary. Phase 1 go-live is scheduled for October 1, 2019 with subsequent phases to follow in fiscal years 2021 and 2023. Each phase will decommission legacy business systems with full transition targeted for October 1, 2025. The related solicitation seeks proposals for the Business Applications Solution through amendment A003 to solicitation number 1331L519R13OS0005. Changes are incorporated to sections C, H, and L of the solicitation as described in Standard Form 30.
J.2 Attachment 02 - Final BAS Proposed Phased Implementation Timeline
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Implementation Planning
Acquisition Planning and Execution
Dated 08/06/2019
Q3 Q2Q4 Q1 Q3 Q2Q4 Q1 Q3 Q2Q4 Q1 Q3 Q4
FY2019 FY2020 FY2021 FY2022
10/1:
Phase 1 Go-Live
BAS O&M
Legacy Business Systems Operations and Maintenance
Decomm Ph1 Legacy
Q2Q1 Q3 Q4
FY2023
Q2Q1 Q3 Q4
FY2024
Decomm Ph2 Legacy
10/1:
Phase 2 Go-Live
Decomm Ph3 Legacy
10/1:
Phase 3 Go-Live
Implementation Ph2
Implementation Phase 1
Q2Q1
FY2025
Attachment 02 – BAS Phased Implementation Timeline
Implementation Phase 3
Q3, FY20
Contract Award/Kick off