This document provides a phased implementation timeline for the Business Applications Solution. The timeline outlines a three phase implementation plan spanning fiscal years 2019 through 2025 for the Department of Commerce Office of the Secretary. Phase 1 go-live is scheduled for October 1, 2019 with subsequent phases to follow in fiscal years 2021 and 2023. Each phase will decommission legacy business systems with full transition targeted for October 1, 2025. The related solicitation seeks proposals for the Business Applications Solution through amendment A003 to solicitation number 1331L519R13OS0005. Changes are incorporated to sections C, H, and L of the solicitation as described in Standard Form 30.

J.2 Attachment 02 - Final BAS Proposed Phased Implementation Timeline

View the file

Other files

File Type Posted
1331L519R13OS0005_A003.pdf PDF
1331L519R13OS0005_A002.pdf PDF
1331L519R13OS0005_Response_to_Inquiries_Follow-up.pdf PDF
J.10_Attachment_10_A001.pdf PDF
1331L519R13OS0005_A001_conformed.pdf PDF
J.12_Attachment_12_A001.xlsx XLSX spreadsheet
J.11_Attachment_11_A001.pdf PDF
1331L519R13OS0005_A001_SF30.pdf PDF
J.1_Attachment_01_A001.xlsx XLSX spreadsheet
J.15_Attachment_15.pdf PDF
1331L519R13OS0005_A001_tracked_changes.pdf PDF
J.7_Attachment_07_A001.pdf PDF
J.14_Attachment_14.docx DOCX document
1331L519R13OS0005_Responses_to_Inquiries.pdf PDF
J.11_Attachment_11.pdf PDF
J.3_Attachment_03.pdf PDF
J.10_Attachment_10.pdf PDF
J.5_Attachment_05.pdf PDF
J.4A_Attachment_04A.pdf PDF
J.7_Attachment_07.pdf PDF
J.1_Attachment_01.pdf PDF
1331L519R13OS0005_BAS_Final_RFP.pdf PDF
J.13_Attachment_13.xlsx XLSX spreadsheet
J.6_Attachment_06.pdf PDF
J.12_Attachment_12.xlsx XLSX spreadsheet
J.8_Attachment_08.pdf PDF
J.4B_Attachment_04B.pdf PDF
J.9_Attachment_09.pdf PDF
1331L519R13OS0005_BAS_Draft_RFP.pdf PDF
BAS_Draft_Performance_Work_Statement.pdf PDF
BAS_Notional_CLIN_Structure_FFP.pdf PDF
Draft_RFP_&_PWS_Question_and_Comment_Template.xlsx XLSX spreadsheet
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Implementation Planning

Acquisition Planning and Execution

Dated 08/06/2019

Q3 Q2Q4 Q1 Q3 Q2Q4 Q1 Q3 Q2Q4 Q1 Q3 Q4

FY2019 FY2020 FY2021 FY2022

10/1:

Phase 1 Go-Live

BAS O&M

Legacy Business Systems Operations and Maintenance

Decomm Ph1 Legacy

Q2Q1 Q3 Q4

FY2023

Q2Q1 Q3 Q4

FY2024

Decomm Ph2 Legacy

10/1:

Phase 2 Go-Live

Decomm Ph3 Legacy

10/1:

Phase 3 Go-Live

Implementation Ph2

Implementation Phase 1

Q2Q1

FY2025

Attachment 02 – BAS Phased Implementation Timeline

Implementation Phase 3

Q3, FY20

Contract Award/Kick off