Attachment 1 (Updated) - NOAA Ship Okeanos Explorer FY 2026 Drydock Repair Specifications Revision 2.pdf
PDF 28 MB Posted
- Attached to
- NOAA SHIP OKEANOS EXPLORER FY26 DRYDOCK REPAIR
- Solicitation number
- 1305M225Q0151
About this file
This document is a comprehensive drydocking and repair specification for the NOAA Ship Okeanos Explorer for Fiscal Year 2026, detailing extensive maintenance and upgrade requirements across multiple ship systems. The specification covers over 50 specific work items including hull preservation, underwater equipment maintenance, propulsion system overhauls, cathodic protection, fire safety systems servicing, lifting appliance certifications, and scientific equipment preservation. Key technical requirements include replacing sea valves, servicing thrusters, performing stability testing, cleaning and painting the underwater hull and freeboard, renewing sacrificial anodes, inspecting and servicing life-saving equipment, and conducting comprehensive maintenance on various mechanical, electrical, and navigational systems.
The drydocking contract involves detailed technical specifications for preserving and upgrading the research vessel, with work to be performed under direct oversight of NOAA technical representatives and American Bureau of Shipping (ABS) surveyors. Critical tasks include ultrasonic thickness gauging, anti-fouling system servicing, transducer preservation, rudder and propeller inspections, and comprehensive cleaning of ship systems. The specification provides precise requirements for surface preparation, painting, equipment replacement, and testing, with a focus on maintaining the ship's operational readiness and scientific mission capabilities. Contractors are required to provide detailed documentation, conduct joint inspections, and ensure all work meets stringent maritime standards and regulatory requirements.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY 202 DRYDOCK REPAIR SPECIFICATIONS
NOAA Ship Okeanos Explorer (R-337)
FY 202
DRYDOCK REPAIR SPECIFICATIONS
Revision 2
WI Title WI Number CLIN General Requirements 07001 NSP Temporary Services at Contractors Facility 07003 CLIN 1000 Dock and Sea Trials 07005 CLIN 1000 Additional Items ORF Funding 07007 CLIN 3000 Additional Items PAC Funded 07008 CLIN 4000 Option Provide Post Industrial Period Berthing 07010 CLIN 7000 Stability Testing 07901 CLIN 1000
ABS SPECIAL SURVEY (5 YR) 10001 CLIN 1000
PAC STEEL REPAIRS 10101 CLIN 2000
PAC MISC Fitout Replacements 10102 CLIN 2000 PAC Replace Exterior Split AC units 10103 CLIN 2000
PAC OVERHAULING SEA VALVES (3 YR) 16301 CLIN 2000
PAC MCS Profi Bus upgrade 20205 CLIN 2000
PROPULSION MOTOR INSPECTION AND CLEANING 23501 CLIN 1000
TAIL SHAFT SURVEY (5 YR) 24401 CLIN 1000
FUEL OIL PURIFIER NO 1 MAINTENANCE (3 YR) 26401 CLIN 1000
SWITCHBOARD, TRANSFORMER AND BREAKER CLEANING (3 YR) 30002 CLIN 1000
PAC SSDG Overhauls 10k 31102 CLIN 2000 Kato Generator 3yr Maintenance 31103 CLIN 1000 PAC Replace EDG Radiator and Coolant System 31201 CLIN 2000 PAC Searchlight Replacement 32201 CLIN 2000
MISSION UPS SERVICE 36201 CLIN 1000
HOSE MCCANN MAINTENANCE 43201 CLIN 1000
PAC Safer at Seas Installation 43401 CLIN 6000 DP System, Furuno GMDSS, Radar and ECDIS SERVICE 45001 CLIN 1000 PAC EK60 Replacement 46101 CLIN 8000 PAC ADCP 38k Replacement 4610 CLIN 2000 PAC Replace AC Machinery Room Fans 51205 CLIN 2000 PAC Chill Water System Mods 51401 CLIN 2000 PAC Renew Weather Deck Drains 52601 CLIN 2000 PAC Various Pipe Replacements 52801 CLIN 2000
OILY WATER SEPARATOR SERVICING 52901 CLIN 1000
BALLAST WATER TREATMENT SYSTEM SERVICE 52902 CLIN 1000
MSD SYSTEM SERVICING 52903 CLIN 1000
FIRE DETECTION AND PREVENTION INSPECTIONS 55501 CLIN 1000
RUDDER INSPECTION (5 YR) 56201 CLIN 1000
BOW THRUSTER SERVICE (3 Yr) 56801 CLIN 1000
STERN THRUSTER MAINTENANCE (3 YR) 56802 CLIN 1000
LIFTING APPLIANCE CERTIFICATION AND INSPECTION (1 YR) 57301 CLIN 1000
LIFTING APPLIANCE CERTIFICATION AND INSPECTION (4 YR) 57302 CLIN 1000
ANCHORS, CHAINS AND LOCKERS (5 YR) 58101 CLIN 1000
Clean Inspect Aft Capstan 58201 CLIN 1000
LIFE SAVING EQUPMENT SERVICE 58301 CLIN 1000
DAVIT SERVICE (1 YR) 58302 CLIN 1000
FAST RESCUE BOAT SERVICE (1 YR) 58303 CLIN 1000
TRACTION WINCH, A-FRAME MAINTENANCE 59102 CLIN 1000
PAC Replace Wet Lab and Winch Room Doors 60004 CLIN 2000 PAC AC Room Deck Renewal 60005 CLIN 2000
PAC UNDERWATER HULL AND FREEBOARD PRESERVATION (3 YR) 63101 CLIN 2000
GENERAL CLEANING AND PAINTING 63104 CLIN 1000
PAC Service Antibiofouling System and Replace Anodes 63301 CLIN 2000
DRYDOCKING AND UNDOCKING THE VESSEL 90001 CLIN 1000
PROPELLER CLEAN AND POLISH (3 YR) 90003 CLIN 1000
PAC Underwater Scientific Equipment Preservation 90005 CLIN 2000
NOAA Okeanos Explorer
( TAGOS HALTER 337 )
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07001 CATEGORY "N" 2025-04-10
General Requirements Kusterer, Justin
07001 - 1
1.1 INTENT:
1.1.1 This item describes the intent, scope, and general
requirements that apply to this Work Package.
1.2 REFERENCES:
1.2.1 NOAA Standard Specification 000-1 - General Requirements for Ship Repair Work on NOAA Ships.
1.2.2 NOAA Standard Specification 630 - Preservation of Ship
Structures
1.2.3 NOAA Standard Specification 000-4 – Test Procedures for Ship Repair Contract Work on NOAA Ships
1.2.4 Drawing No. OE-601-101 - NOAA Ship Okeanos Explorer
General Arrangement
1.2.5 NOAA Form 57-17-09 – NOAA Hot Work Permit
1.2.6 NOAA Weight Report Form - Weight Report.xls
1.2.7 Drawing 631-6233576 – Paint Schedule
1.2.8 Government Furnished Material and Contractor Provided
Material
1.3 GOVERNMENT FURNISHED MATERIAL:
1.3.1 Listed individually under each work item and in Reference 1.2.8
1.4 REQUIREMENTS:
1.4.1 Reference 1.2.1 forms a part of these Detail
Specifications. All provisions and requirements contained therein are applicable to all work items, including all additional work items which are authorized by the Contracting Officer.
1.4.2 Some of the ship’s drawings have not been updated to
reflect modifications to the ship during activation and conversion in 2007. These drawings and reference documents are for planning purposes only. Actual shipboard configurations and conditions may be different from what is listed. Contractor shall be responsible for verifying all current configuration, construction, and arrangement changes, as necessary, to comply with and perform the work requirements of these specifications.
Contractors are encouraged and expected to review ship’s drawings and to perform a field inspection to inspect the locations and shipboard conditions where services are to be
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07001 CATEGORY "N" 2025-04-10
General Requirements Kusterer, Justin
07001 - 2 performed aboard the Okeanos Explorer prior to submitting a proposal. This inspection should satisfy potential contractors regarding all general and local conditions, (including locations, interferences, tolerances and necessary “work-arounds”, etc.) that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the sites constitute grounds for a change order or claim after contract award.
1.4.3 Ship’s drawings and technical publications may be
borrowed during the performance period. It would be preferable for the contractor to make copies of these drawing and technical publications if their intended use will be outside an office environment. All reference materials borrowed by the Contractor shall be signed for, and then returned to the COR after no further use of the reference materials is required.
1.4.4 Provide the COR with a project staffing plan by
trade/craft and subcontractor showing how the project will be appropriately staffed to be completed by the end of the performance period. The plan should be “resource loaded” showing the planned labor needed and actual labor hours assigned Schedules shall have enough granularity to show the number of workers, by trade, for all given tasks. Once a Notice to Proceed (NTP) is issued, all additional work shall be added to and reflect in the resource loaded production schedule within 24 hours. These deliverables shall be in Microsoft Project electronic format.
1.4.5 The contractor shall have daily production meetings with trade supervisors and the COR to discuss progress, milestones, labor staffing levels and other project issues. These production meetings shall be attended by both the project manager and project superintendent (trade superintendent or ship manager)
1.4.6 Contractor shall have a project manager and/or ship
superintendent assigned exclusively to the Okeanos Explorer for the duration of the project. Project Manager or COR approved alternate shall attend all shipboard safety meetings (normally at 0800 in the mess) during the contract period for all days in which the contractor will be performing work on the ship.
1.4.6.1 All subcontractors and contractors shall clean areas to the condition they were in prior to the beginning of work. Any
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07001 CATEGORY "N" 2025-04-10
General Requirements Kusterer, Justin
07001 - 3 areas of concern shall be documented by the Contractor prior to commencing work
1.4.6.2 Any and all areas damaged by media blasting and/or
paint overspray shall be sanded, primed and painted to match the surrounding area.
1.4.7 All new equipment and furnishings purchased by the
Contractor for installation on the vessel shall be provided with factory or vendor supplied certificates, technical manuals, and data sheets, complete with parts listings. Faxed copies of this information are not acceptable. This documentation shall be turned over to the COR after installation is completed.
Equipment technical manuals shall provide detailed information necessary to operate, maintain, troubleshoot, and repair the equipment. The manuals shall include detailed procedures for disassembly of equipment, parts lists, drawings, inspection criteria, troubleshooting, and test procedures. Provide four paper copies of each manual, plus one electronic copy in Abode Acrobat (PDF) format.
1.4.8 Submit all inspection, test, and quality reports to the COR in PDF or Microsoft Word electronic formats.
1.4.9 Weigh all materials and items removed, installed, or
relocated on the ship. Provide a summary report to the COR indicating the total weight in pounds of items and a breakdown of their locations by space, deck, frame, distance from centerline, and height above the deck. Reference 1.2.6 has been provided for the Contractor to identify, record, and document all weight changes for submitting the summary reports.
Contractor may use their own weight report form for documenting weight changes. All the information required must be tracked and documented on any form provided.
1.4.10 Unless otherwise stated in individual work items, prepare and coat all new steel, all existing steel surfaces identified to be cleaned and painted, and all paint systems disturbed while accomplishing work items, in accordance with Reference 1.2.2 and 1.2.7. Finish coat colors and paint type shall match those of the surrounding, unmodified area.
1.4.11 Ship’s force will maintain a minimal presence during
accomplishment of work to these specifications. Their availability to operate ship’s equipment will be limited. Crew availability is generally limited to the hours of 0800 and 1500 local time, Monday through Friday. Unless otherwise specified, GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07001 CATEGORY "N" 2025-04-10
General Requirements Kusterer, Justin
07001 - 4 provide a minimum of two working days’ prior notice for any equipment operations or system tag-outs.
1.4.12 All new and disturbed machinery and services shall be
operated for a period sufficient to indicate satisfactory performance, but not less than one hour, after all adjustments and deficiency corrective actions have been made, without further adjustment.
1.4.13 Provide manufacturer’s technical representatives where required in the individual work items, to witness and to provide technical guidance during operational testing of equipment and systems. All tests and trials of equipment or systems shall be witnessed by the COR, ABS, and/or USCG as applicable, to ensure compliance with regulatory body requirements to maintain the ship’s ABS class certification, and to complete all requirements of these specifications.
1.4.14 The Contractor and COR shall designate a “on-load/off-load” area of the ship that shall be covered by the appropriate media (planks/tarps/etc) as to not damage the existing deck or surrounding structures. Rails, handrails and gunnels shall have appropriate chaffing protecting as to protect the paint from any cables hanging over the side.
1.4.15 These Detailed Specifications are a combination of
“performance specifications” and “design specifications.”
Whenever possible, the Government has provided performance specifications, giving the Contractor the opportunity to accomplish the work requirements as best as he or she sees fit, while providing a fully functional repair and/or equipment/system installation in accordance with all work requirements. When specific details are required, the Government will provide design/detail specifications; this will be more the exception, than the rule.
1.4.16 Frame numbers and space names are derived from ship’s
drawings. All equipment changes and space modifications over the ship’s life span may not all be reflected in the referenced drawings. Contractors are encouraged to review all referenced drawings and to perform a field inspection of the ship prior to submitting a . Copies of drawings and technical manuals not included herein may be made available for review during any scheduled inspection and during the performance period. Contractors may review available drawings and technical manuals on board ship.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
07001 - 5
1.4.17 During the last 10 days of the contract period, the
contractor shall develop a requirements tractability matrix (Punchlist) of all outstanding items from the contract and have daily meetings to go through all remaining items.
1.4.18 Contractor shall empty, open, clean and certify (safe
for entry) all shipboard ballast tanks, Bilge tanks, CHT, grey water, fuel oil, potable water and waste Oil tanks to support work items.
1.4.19 The Ship’s crew will empty all tanks to the lowest point possible using the ships systems. All remaining fluid in the tanks that must be removed by the contractor to complete the tasks associated with these specifications will be the responsibility of the contractor at no additional cost to the Government.
1.4.20 For all hot-work completed on the ship, the contractor is required to fill out, maintain and comply with Reference
1.2.5. If the contractor has procedures and policies for hot-work, provide to the COR and Ship’s Force. As a minimum, any hot-work permit shall be reviewed by Ship’s Force prior to the start of any hot-work.
1.4.21 The contractor shall provide electronic copies all
material certificates to COR and ABS within 24 hours of work being completed. Material certificates include, but are not limited to, pipe, valves, gauges, steel and equipment.
1.4.22 The contractor shall be responsible for all TWIC
(Transpiration Worker Identification Card) requirements and escorts. The contractor shall be responsible for obtaining proper credentials for access to the facility to include all tiers of sub-contractors.
1.4.23 The contractor shall be responsible for obtaining
facility approval for use of any pier side crane and/or lifting apparatus. Approval may take up to two weeks. Contractor is to adhere to any weight limitations on the pier.
1.4.24 Government will compensate ABS for survey costs under a separate purchase order. Neither Government nor Contractor shall be compensated by the other for delay of a scheduled survey if delay is caused by ABS for which neither Contractor nor Government is at fault.
1.4.25 Schedule the services of an ABS Surveyor as required by ABS for performing inspections of all new installations, hull
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
07001 - 6 modifications, tank inspections, gauging inspections and load tests.
1.4.26 All ABS rules required to maintain the ship’s Class and Certificates shall be adhered to by the contractor. This includes all rules for material, fabrication, quality control, inspection, and ABS on-site survey of work. Specifications may call out ABS surveyor inspection, but not all ABS inspections are necessarily identified in the specifications. The contractor shall consult with ABS on the entire work package and changes and assure ABS involvement where required to maintain Class and Certificates.
1.5 QUALITY ASSURANCE:
1.5.1 All welders shall be certified and only perform welding or brazing for processes and filler materials in which they are certified. A list of all welders and their respective certifications who will be performing work aboard the vessel during the period of performance shall be provided to the COR within 3 days after the beginning of the period of performance.
1.5.2 Contractors shall ensure the ship remains water tight
during the repair period. This includes rain water, hydrostatic testing, system drainage and water from high pressure water jetting.
1.5.3 The contractor shall repair all damaged paint, insulation, flashing and nonskid preservation as a result of work performed by these specifications. Paint shall match surrounding area. Non-skid shall be repaired with American Safety Technologies MS-7CZ Anti-Corrosive Low VOC Metal Primer (MIL-PRF-24667B) (5 mils DFT), and a full coat of American Safety Technologies AS-2500 epoxy anti-slip deck coating, 8 mils DFT, color: gray.
1.5.4 All paint preparations and application shall be completed in accordance with NACE, SSPC, IMO or QP1 Standards. Other paint certifications may be submitted for consideration. A paint inspector shall be onsite during all painting and painting preparation activities and continually inspect the process, product, preparation and application during the process.
1.5.5 All steel repairs shall conform to the standards of ABS and shall be inspected and approved by ABS.
1.5.6 Offers, and the successful Contractor, are herewith
notified that Regulatory Body and NOAA inspections are independent of the Contractor’s function of Quality Assurance.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07001 CATEGORY "N" 2025-04-10
General Requirements Kusterer, Justin
07001 - 7
The Contractor is not to rely upon NOAA or Regulatory Bodies or their agents to perform quality control inspections or tests.
1.5.7 Where possible, all tests and inspections shall be
witnessed and inspected by the contractor prior to inspection or witness by the COR.
1.6 NOTES:
1.6.1 Contractors are encouraged to review ship’s drawings and are expected to attend the Okeanos Explorer inspection to inspect the locations and shipboard conditions of the work items in this package prior to submitting a proposal.
This inspection should satisfy potential contractors regarding all general and local conditions, compatibility, locations, material sizes and types, components, and accessibility that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the sites during the inspection constitute grounds for growth work, change order or claim after contract award.
1.6.2 Much of the ship’s original paint contains zinc
chromate. Contracts will encounter this paint during the work aboard the vessel and should take this into account when preparing their as it relates to the necessary work required to accomplish the specific tasks.
1.6.3 The contractor and all subcontractors, regardless of
tier, shall review other work items under this contact to determine their effect on each other.
1.6.4 Provide a copy of the order/invoice and estimated
delivery date of material in Reference 1.2.8 to the COR.
Reference 1.2.8 is not intended to be an all-inclusive list.
1.6.5 The contractor shall provide weekly status updates to the COR on the projected delivery dates for material.
1.6.6 The following descriptive data of the ship is provided
for information:
Length, Overall......................................224’ 0”
Length, BP...........................................194’ 0”
Beam, Molded..........................................43’ 0”
Mean Draft, Loadline..................................15’ 1”
Displacement, Loadline.............................2311.5 LT
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07001 CATEGORY "N" 2025-04-10
General Requirements Kusterer, Justin
07001 - 8
Displacement, Lightship............................1591.2 LT
Cruising Speed......................................11 knots
Officer & Crew Size
Scientists and Technicians
Electric Service.......450 VAC, 60 Hz, 3 PH, 800 Amp Service
Propulsion.......................Diesel electric, twin screw
1.6.7 NOAA Ship Okeanos Explorer is classed A1, E, AMS, ACCU and additional Notations BWT, PMP and identified with the following:
Official Number - CG023672
ABS ID - 8901987
IMO NUMBER – 8835114
1.6.8 The ship will be available for inspection.
All potential contractors are strongly encouraged to attend an inspection. Arrangements for inspection shall be made with NOAA Port Engineer ( ) ; email noaa.gov.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07003 CATEGORY "A" 2025-04-10
Temporary Services at Contractors Facility Kusterer, Justin
07003 - 1
1.1 Intent:
1.1.1 Provide Services, equipment, protective coverings, training, security, parking, cleaning, and other services outlined below for the duration of the repair contract period of performance.
1.2 References:
1.2.1 NOAA Standard Specification 000-2 - Temporary Services at Contractor Facilities
1.3 Government Furnished Material:
1.3.1 None
1.4 Requirements:
1.4.1 Provide all temporary services required in accordance
with Reference 1.2.1.
1.4.2 The following additional information and requirements
apply:
1.4.2.1 Gangways: Access areas for the gangways is 4’ wide. If Contractor plans to use wider gangways, Contractor will be responsible for removing and reinstalling handrails to accommodate the gangways.
1.4.2.2 Electric power: Provide two 450 VAC, 3 Phase, 60 Hertz, 400 Amp circuits [800 amps total] with NATO plugs and pig tails.
All power supplied to the ship shall be clean, with no indications of ground faults on the ship’s main switchboard.
Total Harmonic Distortion (THD) shall not be greater than 6%.
Voltage at the ship’s switchboard shall not vary by more than 3% of the prescribed 450 VAC requirement. All ground fault deficiencies associated with the Contractor’s power supplied to the ship, shall be corrected at the Contractor’s expense. Such expense shall include housing allowance for ship’s crew, if the ship is still habitable at the time the deficiency is noted.
1.4.2.3 Air: Provide 125 psi dry, filtered, compressed air to three manifolds on deck – forward, midships and aft. No connection shall be made by the contractors or their subcontractors to the ship’s compressed air distribution system.
1.4.2.4 Cooling Water: Provide 300 gpm @ 100 psig capacity, for ship’s auxiliary sea water system which supports all refrigeration plant cooling water, air conditioning plant cooling water, and sanitary system toilet flushing needs (NOTE, GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07003 CATEGORY "A" 2025-04-10
Temporary Services at Contractors Facility Kusterer, Justin
07003 - 2 the ship’s sea water system provides 600 gpm for full load – engines running). In the event the sea water or cooling water provided to these systems is disrupted or disabled, an alternate means of providing water service to these systems shall be the Contractor’s responsibility. Provide a pressure regulator on the discharge side of the Contractor’s cooling water supply to the ship’s systems capable of regulating pressure between 25 psig and 80 psig. Contractor may provide separate cooling water service connections to meet the ship’s cooling water systems needs at designated hook-up locations. See ship’s Chief Engineer for individual cooling water service hook-up locations and pressure requirements for the separate systems. Make-up temporary by-pass hose and/or piping arrangements to support the ship’s AC, firemain and refrigeration plant cooling water needs, in conjunction with the work requirements of other items in these specifications.
1.4.2.5 Grey and Black Water Discharge: Provide a connection
for the ship’s grey water overboard discharges, located on the starboard hull side, just forward of the Plimsoll mark. Collect and properly dispose of all grey water overboard discharges which shall meet the same requirements for sewage and turbid water disposal.
1.4.2.6 Crane Service: Offload and load a 20’ ISO Shipping
container (14,50 lbs), Deep Discoverer ROV (9,700 lbs) and Seirios ROV (4,050 lbs) to/from a flat bed trailer. Provide an additional total of 80 hours of crane time which includes, but not limited to, the following support services: rigger, forklift, and transportation services required for the exclusive purpose of off-loading, on loading, and stowage of Government stores, materials, and supplies not related to the work package.
Requests for said services shall be authorized by the COR only.
In addition, provide adequate clean and cleared pier space (approximately 1,0000 square feet) and vehicle access for staging mission equipment and loading provisions during the last two weeks of the contract period.
1.4.2.7 Service Interruption: In the event temporary services provided to the ship are reduced or disrupted due to the extent of contract work, thereby rendering the ship uninhabitable, an equitable adjustment to the contract shall be negotiated. The daily temporary service charge for all services as , but not provided shall be reduced and a credit provided to the government for the remainder of the contract period. Contractor shall make every effort to maintain all facilities and services
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
07003 - 3 required by this specification in a safe manner, so as not to render the ship uninhabitable.
1.4.2.8 Security/Safety of Ship Service: Provide onboard
Security/Safety of Ship Service from 1600 to 0800 on weekdays and 24 hours on weekends and federal holidays. Performance standards for watch members are as follows:
1.4.2.8.1 Training and vessel familiarization will be provided by the ship’s officers or designated crew members for the security watch supervisor and one initial group of security watch standers. Watch standers must be in uniform or a safety vest that identifies them as a watch stander. Watch standers are for safety of ship and must be unarmed. The company must have Security Guard Credentials, Certifications or Licenses;
individual guards do not. Watch standers will present themselves for their watch in sufficient time to be briefed on any changes to the routine or special instructions from the off going watch.
Approximately 10-15 minutes may be required to exchange the watch and transfer information. Watch standers will not depart the ship without being properly relieved following their watch.
1.4.2.8.2 The Watch standers shall provide hourly rounds, inspecting all spaces of the ship, excluding staterooms. 25 stations are set up with Detex, which will be logged using a ship provided Proxipen security wand. The watch standers are required to contact the designated Officer of the Day (OOD), duty engineer or CO if any unusual events occur. Unusual events are defined as, but not limited to: bridge alarms, fire, flooding, unauthorized personnel boarding, and other dangers that can affect the security and safety of the vessel, or spills affecting the marine environment. Rounds and all unusual events shall be noted in the vessel’s watch stander log. Watches shall be attentive to the responsibilities of their position and should limit the use of their personal phones to emergencies and duties related to their detail. Perceived excessive use of phones during watches will asked to be investigated by the contractor by the COR.
1.4.3 Toilet Facilities: Provide Two (2) “ship’s force only”
toilets and 1 wash station. Toilets shall be appropriately marked “ship’s force only”. One toilet shall be marked “Women Only.” The COR shall approve alternate locations of toilet facilities.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
07003 - 4
1.4.4 Trash and rubbish disposal: Provide trash and rubbish
disposal containers or dumpsters to be used by the ship’s crew during the period of performance.
1.4.5 Fueling and Stores: The Okeanos Explorer may take on
fuel and lube oil (barge or semi-truck), scientific equipment and stores in the final days of the contract performance period.
The Government will order and pay for all fuel and stores directly. Contractor shall support and coordinate arrival of fuel, lube oil and stores and provide shipyard services for ship to receive fuel, lube oil and stores in the event the shipyard moors vessels in a location that is not accessible by truck or barge.
1.4.6 Storage: Provide an area to store a Intermediate Bulk
Container (IBC) containing ethanol. Provide crane and material handling services to transport IBC from and back to ship.
1.4.7 Office Spaces: Provide 3 dockside office spaces. Provide three sets of keys of space to the COR. Offices shall be made available five days prior to the ship’s arrival at the Contractor’s facility and shall remain so until five days after the ship has departed.
1.4.8 Internet Service: Provide Internet Service in the
dockside office space.
1.4.9 Parking Spaces: Provide four (4) reserved vehicle parking spaces within 100 feet of the dockside office spaces. Identify additional parking spaces for fifteen (15) vehicles, 250 yards away from the dockside offices, within or outside the shipyard, which may be available for parking by ship’s personnel and other NOAA representatives.
1.4.10 Provide line handlers for all berthing, departures, docking and undocking.
1.4.11 Provide the COR a mailing address for the ship’s crew
and COR to send and receive mail.
1.5 Quality Assurance:
1.5.1 None.
1.6 Notes:
1.6.1 None.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07005 CATEGORY "A" 2025-04-10
Dock and Sea Trials Kusterer, Justin
07005 - 1
1.1 INTENT:
1.1.1 Perform dockside and at sea testing of the ship and
affected systems following repairs, servicing, overhauls and installation of equipment
1.2 REFERENCES:
1.2.1 NOAA Standard Specification 940-0 - Dock and Sea Trials
1.3 GOVERNMENT FURNISHED MATERIAL:
1.3.1 None
1.4 REQUIREMENTS:
1.4.1 Conduct Dock Trials IAW Reference 1.2.1.
1.4.1.1 Provide a dock trial report including all deficiencies and their projected resolutions to include material needed, material delivery dates, and labor levels needed, and estimated completion dates.
1.4.1.2 The contractor Project Manager shall provide a
“Statement of Readiness” 24 hours prior to the Dock Trials that indicates the contractor has completed all work and is ready to complete dock trials. The Statement of Readiness shall be signed by the Project Managers attesting to the readiness to conduct dock trials.
1.4.2 Conduct Sea Trials IAW Reference 1.2.1
1.4.2.1 The contractor shall determine which subcontractors and technical representative need to attend sea trials in order to commission, test, operate and calibrate equipment.
1.4.2.2 Should the total “pier-to-pier” sea trials time take
more than 24 hours, each contractor, technical representative, and subcontractor rider shall be cleared medically by NOAA and have submitted NOAA Forms 57-10-01 (Health Questionnaire) and 57-10-02 (Tuberculosis Screening Document).
1.4.2.3 Provide a supervisor or shipyard technician with access to contractor, subcontractor, and technical representative personnel in all trades to oversee the repair and adjustment of equipment installed and repaired by the Contractor.
1.4.2.4 The COR may approve the use of multi-skill tradesman on a case by case basis to reduce the number of riders on sea trials.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07005 CATEGORY "A" 2025-04-10
Dock and Sea Trials Kusterer, Justin
07005 - 2
1.4.2.5 Provide a sea trial report including all deficiencies and their resolutions to include material needed, material delivery dates, labor levels needed, and estimated completion dates
1.4.2.6 Correct all sea trial discrepancies before the ship
leaves the Contractor’s facility.
1.4.2.7 The contractor Project Manager shall provide a
“Statement of Readiness” 24 hours prior to the Sea Trials that indicates the contractor has completed all work and is ready to complete sea trials. The Statement of Readiness shall be signed by the Project Managers attesting to the readiness to conduct sea trials.
1.5 QUALITY ASSURANCE:
1.5.1 Tests, inspections, and reports shall be in accordance
with the approved schedule as required in paragraphs 1.4.1 and 1.4.2.
1.6 NOTES:
1.6.1 Provide the American Bureau of Shipping surveyor with
prior notice and the opportunity to inspect any or all portions of ongoing work during the dock trials or the sea trials.
Provide ABS the option to ride the ship for sea trials.
1.6.2 The following items have the potential to be performed
dock and/or sea trials. The items may require coordination between different technical representatives. This is not intended to be an all-inclusive list.
1.6.2.1 Dock Trials:
- Thrustmaster of Texas operational testing
- Kongsberg Dynamic Positioning interface testing
- Operational testing of rudder
- Operational testing of propulsion system
1.6.2.2 Sea Trials:
- Dynamic Positioning testing, tuning and scaling; will require Kongsberg and Thrustmaster of Texas support
- Operational testing of propulsion system, monitoring for leaks at stern tubes
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07007 CATEGORY "A" 2025-04-10
Additional Items ORF Funding Kusterer, Justin
07007 - 1
1.1 Intent:
1.1.1 Accomplish additional work items identified after start of repair period necessary to complete other repair work or repair mission-essential equipment. Hours of skilled production labor required will be determined at time work is identified.
1.2 References:
1.2.1 None
1.3 Government Furnished Material:
1.3.1 None
1.4 Requirements:
1.4.1 Provide up to 2,400 man-hours of labor to be used for
additional work if ordered by the Contracting Officer pursuant to the Additional Item Requirements Clause (Section H) or mutually agreed upon by the parties by supplemental agreement to accomplish additional work not required elsewhere in the work items. Such work shall be provided without change in the delivery date for the ship. (Note: Bidders should prepare their bids with this schedule in mind). Pursuant to the Additional Item Requirements Clause, the above specified man-hours are estimates and the Government reserves the right to order up to the total number of aggregate production man-hours set forth above.
1.4.2 The Contractor shall indicate in Section B (
) the man-hour reservation rate to be used in evaluation of the proposal and also to be used for negotiating changes as required by the Additional Item Requirements Clause. This rate shall be the rate for pricing changes negotiated under the Additional Item Requirements Clause up to the maximum man-hours specified therein.
1.4.3 Provide up to $100,000 for additional
material/subcontractor plus markup.
1.5 Quality Assurance:
1.5.1 As required by the activating item.
1.6 Notes:
1.6.1 The man-hours of labor contained within this item are in addition to those required to accomplish work specified within the remaining specifications.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07008 CATEGORY "A" 2025-04-10
Additional Items PAC Funded Kusterer, Justin
07008 - 1
1.1 Intent:
1.1.1 Accomplish additional work items identified after start of repair period necessary to complete other repair work or repair mission-essential equipment. Hours of skilled production labor required will be determined at time work is identified.
1.2 References:
1.2.1 None
1.3 Government Furnished Material:
1.3.1 None
1.4 Requirements:
1.4.1 Provide up to 2,000 man-hours of labor to be used for
additional work if ordered by the Contracting Officer pursuant to the Additional Item Requirements Clause (Section H) or mutually agreed upon by the parties by supplemental agreement to accomplish additional work not required elsewhere in the work items. Such work shall be provided without change in the delivery date for the ship. (Note: Bidders should prepare their bids with this schedule in mind). Pursuant to the Additional Item Requirements Clause, the above specified man-hours are estimates and the Government reserves the right to order up to the total number of aggregate production man-hours set forth above.
1.4.2 The Contractor shall indicate in Section B (
) the man-hour reservation rate to be used in evaluation of the proposal and also to be used for negotiating changes as required by the Additional Item Requirements Clause. This rate shall be the rate for pricing changes negotiated under the Additional Item Requirements Clause up to the maximum man-hours specified therein.
1.4.3 Provide up to $175,000 for additional
material/subcontractor plus markup.
1.5 Quality Assurance:
1.5.1 As required by the activating item.
1.6 Notes:
1.6.1 The man-hours of labor contained within this item are in addition to those required to accomplish work specified within the remaining specifications.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07010 CATEGORY "A" 2025-04-10
Option Provide Post Industrial Period Berthing Kusterer, Justin
07010 - 1
1.1.1 To establish a price for pier space and temporary
services for 14 days after the repair period of performance
1.2 References:
1.2.1 NOAA Standard Specification 000-2 - Temporary Services at Contractor Facilities
1.3 Government Furnished Material:
1.3.1 None
1.4 Requirements:
1.4.1 Quote the price to provide pier space berthing for the
vessel and following temporary services per day, for a period no longer than 14 days after the end of the repair period of performance
1.4.1.1 Provide adequate pier or dock space acceptable to the dimensions of the vessel and COR.
1.4.1.2 Electric power: Provide two 450 VAC, 3 Phase, 60 Hertz, 400 Amp circuits [800 amps total] with NATO plugs and pig tails.
All power supplied to the ship shall be clean, with no indications of ground faults on the ship’s main switchboard.
Total Harmonic Distortion (THD) shall not be greater than 6%.
Voltage at the ship’s switchboard shall not vary by more than 3% of the prescribed 450 VAC requirement. All ground fault deficiencies associated with the Contractor’s power supplied to the ship, shall be corrected at the Contractor’s expense. Such expense shall include housing allowance for ship’s crew, if the ship is still habitable at the time the deficiency is noted.
1.4.1.3 Grey and Black Water Discharge: Provide a connection
for the ship’s grey water overboard discharges, located on the starboard hull side, just forward of the Plimsoll mark. Collect and properly dispose of all grey water overboard discharges which shall meet the same requirements for sewage and turbid water disposal. Discharge up to 2500 gallons per day expected.
1.4.1.4 Potable Water: Provide potable water at 35 to 45 PSI
and 15 gallons per minute. Provide freeze protection to assure water supply does not freeze.
1.4.1.5 Security/Safety of Ship Service: Provide onboard
Security/Safety of Ship Service from 1600 to 0800 on weekdays
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
07010 - 2 and 24 hours on weekends and federal holidays. Performance standards for watch members are as follows:
1.4.1.5.1 Training and vessel familiarization will be provided by the ship’s officers or designated crew members for the security watch supervisor and one initial group of security watch standers. Watch standers must be in uniform or a safety vest that identifies them as a watch stander. Watch standers are for safety of ship and must be unarmed. The company must have Security Guard Credentials, Certifications or Licenses;
individual guards do not. Watch standers will present themselves for their watch in sufficient time to be briefed on any changes to the routine or special instructions from the off going watch.
Approximately 10-15 minutes may be required to exchange the watch and transfer information. Watch standers will not depart the ship without being properly relieved following their watch.
1.4.1.5.2 The Watch standers shall provide hourly rounds, inspecting all spaces of the ship, excluding staterooms. 25 stations are set up with Detex, which will be logged using a ship provided Proxipen security wand. The watch standers are required to contact the designated Officer of the Day (OOD), duty engineer or CO if any unusual events occur. Unusual events are defined as, but not limited to: bridge alarms, fire, flooding, unauthorized personnel boarding, and other dangers that can affect the security and safety of the vessel, or spills affecting the marine environment. Rounds and all unusual events shall be noted in the vessel’s watch stander log. Watches shall be attentive to the responsibilities of their position and should limit the use of their personal phones to emergencies and duties related to their detail. Perceived excessive use of phones during watches will asked to be investigated by the contractor by the COR.
1.4.2 Trash and rubbish disposal: Provide trash and rubbish
disposal containers or dumpsters to be used by the ship’s crew.
1.4.3 Pier Space: Provide pier space for loading of ship
stores.
1.4.4 Parking Spaces: Provide four (5) reserved vehicle parking spaces.
1.4.5 Provide line handlers for all berthing and departure.
1.4.6 Unless specifically approved by the contracting officer, the ship shall not be shifted/moved during this period. If
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
07010 - 3 shifting is required/approved a minimum three day notice shall be provided to the COR.
1.4.7 This option item will not take effect until all contract work has been completed.
1.4.8 This option is dependent on the contractor’s location and needs of the ship’s crew.
1.4.9 No shipyard work will be performed to the vessel during this period.
1.5 Quality Assurance:
1.5.1 None.
1.6.1 None.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07901 CATEGORY "A" 2025-04-10
Stability Testing Kusterer, Justin
07901 - 1
1. ABSTRACT
1.1 This item describes the requirements for performing a
Stability Test (AKA an Inclining Experiment) following the completion of all major work affecting lightship weight.
2. REFERENCES/ENCLOSURES
2.1 References
2.1.1 ASTM F-1321 (CURRENT REVISION) Standard Guide for
Conducting a Stability Test (Deadweight Survey and Inclining Experiment) to Determine the Light Ship Displacement and Centers of Gravity of a Vessel
2.1.2 NVIC 3-97 Stability Related Review Performed by the
American Bureau of Shipping for U.S. Flag Vessels
2.1.3 USCG MSC Plan Review Guideline GEN-02 Submission of
Stability Test (Deadweight Survey or Inclining Experiment) Results
2.1.4 USCG MSC Plan Review Guideline GEN-05 Submission of
Stability Test Procedures
2.2 Enclosures
2.2.1 GUIDANCE FOR ITEMS TO BE CONSIDERED PART OF LIGHT SHIP
3. GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES:
3.1 Government Furnished Equipment (GFE): NONE
3.2 Government Furnished Material (GFM): NONE
3.3 Government Furnished Services (GFS)
3.3.1 NOAA shipboard personnel will provide the CONTRACTOR
access to all spaces including locked compartments for the Survey of non-lightship items in those spaces.
3.3.2 NOAA shipboard personnel will operate shipboard
equipment as required to ensure all equipment is in its normal underway stowed position during the Stability Test.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07901 CATEGORY "A" 2025-04-10
Stability Testing Kusterer, Justin
07901 - 2
3.3.3 NOAA will cover the cost of REG BODY reviews and
attendance of SURVEYOR to observe the Stability Test on behalf of the REG BODY.
3.4 Government Furnished Information (GFI):
3.4.1 Drawing OE-601-101 – General Arrangement
3.4.2 Drawing OE-079-004 – Trim & Stability Booklet
3.4.3 Drawing OE-123-101 – Tank Sounding Tables
4. NOTES:
4.1 DEFINITIONS:
4.1.1 NOAA refers to National Oceanic and Atmospheric
Administration, Office of Marine and Aviation Operations.
Submissions to NOAA must be made to the NOAA point(s) of contact identified in paragraph 7.1.
4.1.2 COR refers to the onsite NOAA technical
representative that is witnessing the stability test.
4.1.3 CONTRACTOR refers to the organization (shipyard, engineering firm, etc.) under contract with NOAA to perform the Stability Test. Sub-Contractors may be used, but they must meet the requirements of this specification and will be considered CONTRACTOR employees.
4.1.4 REG BODY refers to the regulatory body providing
oversight and approval of the Stability Test; in this case the American Bureau of Shipping (ABS).
4.1.5 SURVEYOR refers to the onsite REG BODY representative
observing and certifying the Stability test. In this case, an ABS surveyor.
4.1.6 KNOWN WEIGHTS are items whose weight and center of
gravity are known exactly through measurement. Certificates from the equipment manufacturer or firm that performed the measurement are required for REG BODY acceptance.
4.1.7 BUSINESS DAYS are Weekdays (Monday through Friday).
Weekends (Saturday and Sunday) and Federal Holidays are not considered business days.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07901 CATEGORY "A" 2025-04-10
Stability Testing Kusterer, Justin
07901 - 3
4.2 Although the Contractor is required to generate all
documentation associated with the Stability Test, NOAA will be responsible for submission of those documents required to be sent to ABS as part of the Regulatory review process. Further, NOAA will pay for the required Regulatory reviews.
5. QUALITY ASSURANCE REQUIREMENTS:
5.1 The Stability Test Data will be considered satisfactory
only after both the COR and the ABS SURVEYOR sign off on the data collected during the Stability Test.
5.2 The Contractor shall have the Stability Test Report and the new lightship value reviewed and approved by ABS before NOAA will consider this work item complete.
6. STATEMENT OF WORK REQUIRED
6.1 The CONTRACTOR shall provide the services of a naval
architecture firm to conduct, oversee, provide specific guidance, and coordinate shipyard support requirements to perform the Stability Test. The CONTRACTOR and naval architecture firm shall work together to perform all aspects of the Stability Test.
6.2 The CONTRACTOR shall provide all labor, tools, material, and equipment necessary to accomplish a Stability Test in accordance with Reference 2.1.1 and the requirements in this specification. Where the requirements of this specification and Reference 2.1.1 are in disagreement, this specification shall take precedence.
6.2.1 NOAA will coordinate REG BODY reviews of the Stability
Test Procedure and Stability Test Report.
A NOAA will cover the cost of the initial review and one (1) resubmission of the Stability Test Procedure to the REG BODY.
B NOAA will cover the cost of the initial review and one (1) resubmission of the Stability Test Report to the REG BODY.
C NOAA will submit both the Stability Test Procedure and the Stability Test Report to the REG BODY for review on the CONTRACTORS behalf.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07901 CATEGORY "A" 2025-04-10
Stability Testing Kusterer, Justin
07901 - 4
6.2.2 NOAA will arrange for a SURVEYOR to observe the
Stability Test on behalf of the REG BODY.
6.2.3 The CONTRACTOR is responsible for paying all costs
associated with obtaining REG BODY approval of the Stability Test outside of the cost for REG BODY reviews and SURVEYOR attendance.
6.2.4 The CONTRACTOR is responsible for placing the ship the
condition required for the Stability Test as established in the Stability Test Procedure. This includes filling tanks, emptying tanks, and temporary relocation of non-lightship items from the ship.
6.2.5 The CONTRACTOR is responsible for gas freeing, certifying, and maintaining all empty tanks & voids “safe for entry” for the duration of the Stability Test. A minimum of one
(1) manhole cover per tank shall be removed to allow for inspection.
6.3 The Stability Test shall be listed as a significant
milestone on production planning schedules.
6.4 The Stability Test shall utilize solid inclining weights
rather than liquid transfer between the vessel’s tanks. Both the port and starboard maximum heel angles must exceed one (1) degree relative to the initial heel.
6.5 The Stability Test Procedure shall meet the requirements of the USCG Guidelines for Submission of Stability Test Procedure (Reference 2.1.4).
6.5.1 The procedure shall include the data collection forms
intended to be used during the Stability Test.
6.5.2 The drafts and freeboards form(s) shall include the
longitudinal position, keel plate thickness, deck edge height, deck edge thickness and if applicable, a column for the height of coaming, toe rail, or bulwarks above deck for each freeboard station.
6.5.3 The tank soundings forms shall list the tank name and
location designation and tanks shall be listed in the same order as in the current Trim and Stability Booklet’s example loading conditions.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07901 CATEGORY "A" 2025-04-10
tability Testing Kusterer, Justin
07901 - 5
6.5.4 The procedure shall include a sketch of the planned
mooring arrangement for when freeboards and pendulum offsets are read.
6.5.5 If inclining weights are to be shifted by crane, a
mooring arrangement plan view with crane reach capacity arcs and inclining weight footprint positions shall be included in the procedure.
6.5.6 The procedure and report shall use the same unit
system as the vessel’s draft marks and the same origin and location reference system as the current trim and stability booklet.
6.5.7 The procedure and report shall state if the vessel
does or does not have fixed ballast onboard.
6.6 The CONTRACTOR shall submit the draft Stability Test
Procedure to NOAA for review and comment at least eight (8) weeks prior to the scheduled date of the Stability Test.
CONTRACTOR shall address all NOAA comments before the Stability Test Procedure is submitted (by NOAA) to the REG BODY for approval.
6.6.1 The CONTRACTOR shall re-submit the draft procedure to
NOAA after addressing comments until all NOAA comments are cleared.
6.6.2 NOAA has 5 business days to perform each review.
6.6.3 CONTRACTOR is responsible for submitting the Stability
Test Procedure to NOAA in a timely manner, so REG BODY review and approval are complete prior to the Stability Test.
6.7 Pre-Stability Test Meetings:
6.7.1 The CONTRACTOR shall conduct a planning meeting
approximately one (1) week prior to the planned Stability Test date to be attended by representatives of the CONTRACTOR, the to-be-surveyed ship’s force, NOAA Port Engineer, COR, CONTRACTOR’s naval architecture firm, and NOAA’s Naval Architect, and attending ABS inspector.
A Teleconference capabilities are acceptable for those not able to attend in person.
GENERAL SERVICES AND REQUIREMENTS CONTRACT NO. FY26 Dry Dock
ITEM NO. 07901 CATEGORY "A" 2025-04-10
Stability Testing Kusterer, Justin
07901 - 6
6.7.2 At this planning meeting, the CONTRACTOR shall be
prepared to address attendees’ questions and discuss the details of the Stability Test Procedure, detailed schedule, planned vessel condition, mooring arrangements during the freeboard and draft readings and pendulum deflection measurements, equipment certifications, planned…
This is the start of the file's text. The full file is on GovTribe.