Am4 Attach1 QA Post Preproposal Meeting.xlsx

XLSX spreadsheet 23 KB Posted

Attached to
Rio Grande Supervisor's Office Construction Federal contract opportunity
Solicitation number
1282AK20R0003
Issued by
Department of Agriculture Forest Service R2-Rocky Mountain Region

About this file

This document contains a government file and related federal contract opportunity. The government file includes questions and answers from a pre-proposal meeting for the Rio Grande Supervisor's Office Construction project. This project involves remodeling a former high school building into an office for the Rio Grande National Forest Supervisor's Office in Del Norte, Colorado. The project includes demolishing approximately 60% of the existing 14,400 square foot building and renovating the remainder to meet federal building codes and requirements. The project scope also encompasses associated site work and utilities. The estimated timeline is 18 months, with an anticipated start date of January-February 2021. The estimated contract value ranges from $5-10 million, including all base work and option items. This opportunity is designated as an 8(a) Competitive Set Aside restricted to contractors with a verified SBA-approved bona fide office in Colorado.

View the file

Other files for this federal contract opportunity

Other files attached to Rio Grande Supervisor's Office Construction, newest first.
File Type Posted
Am4 Attach 3 Rio Grande_Schedule_of_Items-revised-08192020.pdf PDF
Am4 Attach 4 010250_Definition_of_Contract_Items_and_Measurement_and_Payment-Revision-08192020.pdf PDF
Am4 Attach 2 11 30 13 BSD-Residential Appliances.pdf PDF
Amendment4 SF30 1282AK20R0003.pdf PDF
Amendment3 SF30 1282AK20R0003.pdf PDF
Amendment2 Attachment 1 Questions and Answers.xlsx XLSX spreadsheet
SF30 Sol_1282AK20R0003_Amd_0002.pdf PDF
Amendment1 SF30 1282AK20R0003.pdf PDF
Former High School Walk Through - Inside Part2.mp4 MP4 file
Former High School Walk Through - Outside 07222020.mp4 MP4 file
Former High School Walk Through - Inside Part1.mp4 MP4 file
SF1442 RG SO Construction Sol Award Form.pdf PDF
SF1442 Solicitation Award Form.pdf PDF
Attach3 RGS0-100-3-Project Manual Vol I.pdf PDF
Solicitation Phase 2 FINAL.pdf PDF
Attach5 RGS0-100-5-Project Manual Vol III.pdf PDF
Attach2 RGS0-100-1-Drawings-Stamped.pdf PDF
Attach09 RFP Question Submission Form.xlsx XLSX spreadsheet
Attach08 Technical Proposal Submission Aid.docx DOCX document
Attach6 Appendix A-Geotech Report.pdf PDF
Attach07 Wage Rates.docx DOCX document
Attach4 RGS0-100-4-Project Manual Vol II.pdf PDF
Attach1 Rio Grande_Schedule_of_Items FINAL.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment Four Attachment One

Date SubmittedRFP LocationQuestionResponsible Party for Answer (for Government Use)Answer (Government Use)
8/4/20Upon review of the solicitation/contract documents we have NOT identified a requirement of having a bona fide office within the geographic region of this project. Please confirm that this is accurate, that this is not a requirement of the bidding contractor. If this is in fact a requirement, can you please confirm that we can provide this prior to project award to allow for ample time for this to be set up with the local SBA office instead of prior to bid submission?Christina SchofieldSee Section L, clause 52.219-18, Alternate 1 for the geographic region for this project.
8/4/20Solicitation DocumentWhen are the formal pre-bid RFIs/Questions due? What is the due date?Christina SchofieldThe presolicitation questions were to be submitted by July 31, 2020. The second RFIs/questions were to be submitted by 1600 August 14, 2020 as detailed in Amendement Two.
8/4/20Drawings (throughout) and Schedule of ItemsAre we to include the "Option Items/Option Work Items" in the schedule (required for the proposal)?Todd MichaelYes
8/4/20Drawings page C300, A020 and A902Is the detail on pages A020 (Detail W2080) and A902 (Optional Trash Enclosure) reference for the Trash Enclose shown on page C300? Confirm this is an "Optional Item/Optional Work Item."A/EOptional Item. Please refer to Spec Section 010250, Option Item list.
8/4/20Division 12, Sections 122400, Drawings pages A611, A616It is unclear as to whether window coverings (shades) are optional or a base item. Please clarify which window shades, if any, are part of the Base Items.A/EWindow shades are an optional item.
8/4/20Drawings page A030, Demolition General Notes, Note #8If each utility trade safes-off, caps, prepares their utility for demolition, could then all the building-related demo be performed by one subcontractor? For example, if the plumber capped-off their lines, and the mechanical capped off their lines and ducting, and the electrician's safed-off their work, could then a demo subcontractor demo all the work?A/EThis is a means and methods item and should be determined by the General Contractor on the best method for completing the project. The Government does not determine which sub contractors perform the work.
8/4/20Drawings page A002 - General Notes, Construction Note #7Could you provide examples of areas noted as "concealed spaces" and "chases" where fireblocking will be required? If so, please provide.A/EThis note is clarified on A010, under the heading 'CHAPTER 7 - FIRE AND SMOKE PROTECTION FEATURES > Concealed Spaces 718'
8/4/20Drawings pages A251, A750, E005Is the contractor to provide the video projector? If so, are there specifications available? If so, could the Government provide the specifications?Todd MichaelThe videow projector is government furnished and installed.
8/4/20Drawings page E002 (131 of 146) Detail #1 Note "D"; page E030 (136 of 146) Electrical Demolition Requirements Note "C", Page E040 (137 of 146) Electrical Demolition Requirements Note "C".There appears to be an exsiting fire alarm system, and the drawings indicate tying into the existing system as it pertains to door access security. However, under the Electrical Demolition Requirments, the drawings indicate to "Remove . . . all . . . fire alarm components." If the "all" fire alarm components are being removed, to what shall the impacted doors "interconnect" to? Furthermore, is replacing the fire alarm system components to be included this project?A/ESimilar to other fire alarm comment responses on the same topic, the existing fire alarm system and associated devices are to be demolished. A fire alarm system is not required for the project. Since there will be no FA, interconnection of the security system to an FA system is not required.
8/4/20See also page A010, "Project Data Summary," "Fire Alarm & Detection."No "Summary" was provided for the fire alarm and detection system. Could the Government provide information on the existing Fire Alarm System (As-Built drawings)? With the demolition of a portion of the facility, there would most likely also be a modification of the existing fire alarm system. No replacement devices are indicated. Please advise.Todd MichaelA fire alarm system is not required for the project. The fire alarm system and associated devices are to be demolished.
8/4/20See page A010 - Code Analysis, "Chapter 9 - Fire Protection".Is there a wet/dry-type fire suppression system in the existing facility? Will any of this be demo'd? After demolition of a portion of the facility, is there work that will need to be peformed to the existing system (if one exists) to reconnect? We found no information in the drawings or specifications on the fire suppression system. If there is an existing system, are calculations available? Are existing fire suppression system as-built drawings avaialbe? With interior renovations required of this contract, there would most likely be a need for modification of the existing fire suppression system. Please advise.Todd MichaelThere is no wet/dry-type fire suppression system in the existing facility. There is no new system either.
Pre-bidWhere identified submittals are required to be utilzed. Who pays the cost of the Submitttal Exchange project subscription?Todd MichaelThe government will pay the cost of the Submittal Exchange project subscription.
Pre-bidThe construction documents show footers to be demolished. Do the footers need to be removed or can they be abandoned in place?Todd MichaelRemove the footers.
Pre-bidDuring the site visit it was apparent there is residential property on several sides of the property. Are there any construction restrictions?Todd MichaelOn-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 5:00 p.m., Monday through Friday, except as otherwise arranged with Contracting Officer.
8/11/20Please confirm that the building is code compliant without a fire suppression system, either wet or dry type.Todd MichaelThe building is code compliant without a fire suppression system.
8/11/20Is there exsiting water supply onsite that can be utilized for dust mitigation, washing tools, mixing materials, etc.? If so, are there any limitations or requirements with respect to their use (e.g. metered)? Will the contractor incur costs for using the water source?Todd MichaelAs indicated in Section 015000 1.2 A. The contractor provides temporary water facilities for the duration of the project.
8/11/20Whose responsibility will it be to notify the local residents of access way closures? Upon the site visit, it was noted that many vehicles cut through the parking lot within the limits of construction. Access to this area will be closed off for construction activities and public safety.Todd MichaelThe Forest will coordinate the street shutdown with the town and provide notification.
8/11/20Are there any "protected plants or animal species" within the limitis of construction (bushes, trees, squirrels, etc.)?Todd MichaelTo our knowledge there are no protected plants or animal species within the limits of construction.
8/11/20Just outside the limits of construction it was noted that brush and bushes are over-growing and could potentially present as a fire hazard during peak fire hazard times. Who is responsible for keeping these areas under check to mitigate fire hazards?Todd MichaelThe Forest Service will minimize fire danger outside the designated project area. The contractor is responsible for mitigation inside the designated project area.
8/11/20Please confirm that the construction schedule provided as part of the technical requirements should reflect the 18-24 month project duration.Christina SchofieldConfirmed.
8/11/20It was mentioned on the post-site visit teleconference of 08/11/2020 that it was up to the discretion of the contractor the number of personnel who MUST be onsite. The question was asked specifically if the Scheduler and/or Project Manager MUST be onsite. The response was that it was up to the discretion of the contractor. Please confirm that if the contractor does not deem it necessary to have the Scheduler or Project Manager onsite, this will be acceptable.Christina SchofieldConfirmed.
8/11/20For the purposes of determining the start date for the construction schedule, December 2020 or January 2021 start date was indicated during the post-site visit teleconference. Could you please provide the anticipated start date?Christina SchofieldThe anticipated start date on the ground will begin in January-February 2021, after successful completion of Phase One of this project.
8/11/20Please confirm that the security system MUST be Linell.Todd MichaelThe access control and security system must be Lenel as described in specification 280500 1.1 B. and C. Additional paragraphs in this section outline requirements for Lenel VAR and certifications.
8/11/20Page E002, Detail 1 - Door Access Control System One-Line Diagram - Regarding the Access Card Reader.This detail directs the reader to E300 series drawings. There is no Page E300 as part of the contract drawings. Could you please provide us with the referenced series drawing?A/EThere is a typo on that detail. The reference should say "REFER TO SHEET E111, OFFICE TECHNOLOGY PLAN, …".
8/12/20No manufacturer has a mod furnace that will deliver the output capacity called out at that elevation on derated gas. You might be better off with a two stage, variable speed. Can you confirm what you want us to price?A/EPrice the modulating furnace as specified, or as described in the brand name or equal clause.
8/12/20If the Micro-metal economizer with Jade controls is put on, the EAT on the furnace will be less than the 55 degree minimum at design conditions. That will void the warranty, and add two thousand per furnace. Would it not be better to just put in HRV's and temper the incoming air?A/EPrice the economizer with Jade controls and warranty specified. Address concerns with voiding the warranty as an RFI after project award.
8/12/20SECTION 101400 SIGNAGESpecs mention exterior individual metal letter signage. I do not see any exterior signage called for in the plans, can you confirm?A/EThere are pin mounted letters on the entry desk, see A611.
8/12/20Sheet A030Callout - Salvage exterior wall veneer; is this intended to just have enough brick to make small patch repairs throughout, or does the Owner want all brick veneer salvaged and stored?A/EOnly salvage what is required for patches and repaired with construction. Any additional veneer shall be removed, not stored.
8/12/20Can we get a full size / scalable set of plans?Todd MichaelContractors can print the plans at any scale they need. The government does not provide prints of plans.
8/12/20Please provide a spec for the dishwasher.A/ESee Attachment 2 to Amendment Four.
8/12/20Can you confirm Fire alarm is not required? Vol II mentions it in footnote, Vol III mentions it as part of sequencing for access control, but no other mentionA/ESimilar to other fire alarm comment responses on the same topic, the existing fire alarm system and associated devices are to be demolished. A fire alarm system is not required for the project.
8/12/20KeyNote 12 Sheet E100“EV Charging Station Bollard Mount Base”; Can you provide a spec for the charging station or a detail on the base?A/EEV Charging Sepcification is located at Section 262726, Wiring Devices, Section 2.10. Provide base as required by manufacturer.
8/12/20LP103 N3The Q&A in Amendment 2 seems to have been misunderstood. LP103 N3 is for new trees, and your response regards existing trees. Since the Contractor is not responsible for new trees, only shrubs and perennials, and any new trees by the Owner would be at the end of the job, it seems this requirement is not needed. Can you confirm?A/EDHM: 1/LP103 is for existing and new trees. See note #1; "Existing trees to be protected during demolition and construction." Tree fencing for new trees will be the responsibility of the Government.
8/12/20SECTION 115213 PROJECTION SCREENSRegarding installation of the motorized projection screen Installer Qualifications, based on the review of the installation instructions, JITA Contracting believes we are capable of handling the installation in house, will this be acceptable?A/EGeneral Contractor may provide statement outlining qualifications of installer prior to instllation for consideration.
8/12/20Detail 1 sheet S504Regarding Detail 1 sheet S504, where in the plans is this detail used?A/EIt is a typical detail and not cut on the plans, but would apply to the connection of the W8x10 beam on grid line A between grids 13 and 16 and of the W8x18 beams on grids 11 and 12 at grid line B.
8/12/20S102On S102, the East entry vestibule, gridline 10 to 12, line B, there is an 8x10’ new beam shown – Could you lead us to where the beam connection is shown on the drawings or provide?A/EThe beam would be connected to the HSS4x4 posts per 1/S504
8/12/20Can you provide wage rate for flooring?Christina SchofieldThe Building Construction wage rate (CO20200001 01/24/2020) for Laborer appears most appropriate for flooring work for this project.
8/12/20What is the thickness of the existing asphalt?A/EPlease refer to Boring Logs included in Geotechnical Report for existing pavement thicknesses.
8/12/20Will asphalt millings be acceptable for use as general fill and embankment?A/EBase bid includes crushed/milled asphalt to be mixed with general fill for embankments.
8/12/20SECTION 078400 FIRESTOPPINGWe don't see any fire rated walls A011, so we do not see any areas that require firestoppingA/EThe walls around the IT room (112) are rated.
8/12/20SECTION 31 25 00 EROSION AND SEDIMENTATION CONTROLSWe do not foresee needing to do any dewatering, but you state that the Contractor "shall" obtain a permit. Can this be altered to say if needed?A/ESection 1.5 A states that all permits are to be obtained "if required"
8/12/20A301What does "otter" terminology refer to?A/EOtter is a color by Sherwin Williams, see Elevation Materials Legend
8/12/20OI 21 BlastingWhat do your engineers anticipate being required in the blasting line item?A/EPlease refer to Boring Logs included in Geotechnical Report for location of ash-flow tuff "bedrock". Utilities and possibly site grading are anticipated areas that may require blasting paid as an Optional Item.
8/12/20C300, Vol II page 53/417For the structural concrete slab for the Haz Mat building, did you want us to do a 6" slab? Would you be able to provide a detail on this or more info on what exactly you want?A/EStructural Slab shall be 8" thick with #5 rebar at 18" offsets and centered.
8/14/20Bid options 21, 22, 23. Please define how to price these options? Are you looking for assumed quantity of rock removal or for a unit price if we encounter rock ?Todd MichaelProvide price for a unit quantity as specified. The option will be utilized as needed based upon the conditions encountered during construction.
8/14/20Page P400 Note #3 says to provide new gas meter and yard line for the building. Is this contractor provided or is this provided by the gas company?A/EUtility owner is expected to install gas meter and service line. Contarctor to coordinate site access.
8/14/20Please confirm that the contractor is to facilitate the removal of the all existing utilities with local utilities providers?A/EYes. Contractor to perform or coordinate demo of existing utilities as designated on sheets C004 and E020.
8/14/20Please confirm that the Government will facilitate all the required paper work and cost associated with local utilities companies to install services to the building? And the contractor is only to coordinate the installation with the utilities companies?Todd MichaelThe Government will facilitate the paper work and costs associated with local utility companies to install services to the building. The contractor is required to coordinate the installation with the utility companies.
8/14/20Page P001 –DW1 is calling out a Dishwasher to be provided by the contractor. Equipment note # 23 said it’s a bid option but it’s not shown on the price schedule as a bid option. Please clarify?A/EDishwasher is to be base bid.
8/14/20If the dishwasher is to be provided by the contractor please provide make, model, and voltage?A/EReference Specification in Attachment Two of Amendment Four.
8/14/20Is the contractor required to permit the project through the State of Colorado?Todd MichaelThe contractor needs to obtain a stormwater permit. Building permits are not required.
8/14/20Line item 5, 6; C300Asphalt Employee Parking A, B - Please guide me to where in the plans it shows the delineation of these two lots? Are we assuming the striping for the optional asphalt items to be the same as the "Parking stalls not striped (for graphic puposes only). Typ." on LS101? Should we assume A is the closest to the building and stops at the valley pan on the west side? And should we assume with B that we will pave the connector road sections?A/EParking Lot A is closer to the building and includes asphalt from the limits of paving in Base Bid on the east, to the concrete pan on the West. Parking Lot B is further from the building and includes the parking lot and drive ailes from the limits of paving in Base Bid on the east, and the line marked 'Extents of Optional Asphalt Paving' on the West. Optional item striping is to match what is shown on LS101.
8/14/20Line item OI 8, Brick TuckpointingCan you please clarify scope for this? An estimated sq ft amount or more direction on how to determine where you will want this?A/EOption Item 8 will be changed to a unit price and reflected as a revised item of the revised Schedule of Items included in Amendment Four as Attachments Three and Four.
8/14/20M004 Details 3 and 4The plans have a detail for spiral pipe, but there isn't any called out on the plans, nor in the specs. Please advise.A/EAll exposed round duct noted on the plans should be spiral duct. This includes supply ductwork from the furnaces in the open office areas (including duct run above cloud ceilings) as well as the fitness room. Round duct that is fully concealed above ceilings may be rigid snap-lock type metal duct.

There are spiral duct mounted grilles in the Fitness 132 space. These should be based on detail 4/M-004. Detail 3/M-004 is an accidental carryover from a previous design iteration and no longer applies to the current design, please ignore detail 3/M-004.

8/14/20Sheet A801Wood WD1, WD2 - We cannot locate this in the finish plan, can you clarify where this will be located?A/EWD1 is used in the conf room at the termination point of the operable partion, see 1/A721. WD2 is used in at the mail cubbies behind the entry desk, see A742.
8/14/20SECTION 32 31 13 CHAIN LINK FENCES AND GATESWith tension wire on the bottom, often people don't also include a bottom rail, can you confirm that you want both?A/EConfirmed to include both.
8/14/20LS111AS-2 is the callout, but the Notes state AS-4, can you clarify? Callout says S-12, Notes say S-28, can you clarify? Callout says P-52, Notes say P-43, can you clarify?A/EAS-2 is correct.

S-12 is correct.

P-52 is correct.

8/14/20A801, A901Material list on A801 lists the PORB1 as Marozzi Portfolio Light Polish finish; this is not available. We assume you may be wanting Modern Formation like the floor tile, can you confirm? Can you confirm the finish?A/EProvide Modern Formation Light Polished Finish.
8/14/20A901Can you confirm this is a build-in-place shower (with no pre-fab component) and that you want the POR2 tile floor to continute in the shower floor?A/EConfirmed that this shower is built in place, not a prefab unit. Floor tile should be POR 1 though. Price epoxy grout at shower area floor and walls.
8/14/20SECTION 32 12 00 FLEXIBLE PAVING1. Will you allow Warm Mix in lieu of Hot Mix for the asphalt pavement?A/EHot Mix only
8/14/20SECTION 32 12 00 FLEXIBLE PAVING2. Will you allow a liquid antistrip such as Evotherm in lieu of Hydrated lime for the asphalt pavement?A/ENo
8/14/20S002Deferred Submittals - can you confirm if this engineering work has already been complete? It seems that with the stamp and signature this has been completed already. Does the metal framing contractor need to account for costs for engineering and shop drawings?A/EThe drawings show our design intent but do not show all the detail necessary for construction. The metal framing contractor should provide complete shop drawings stamped and signed.
8/14/20CD300Can you confirm that Detail 3 is not in the plans?A/EDetail 3 is to be used at sawcuts where new asphalt paving abuts existing. See sheet C300.
8/14/20CD300Can we assume Detail 6 would be 3" deep and 3' wide?A/EHorizontal measurements are as follows:

6" transition zone from normal to thickened depth.

1'-6" thickened zone to edge of finished grade at surface.

12" transition from thickened zone to buried toe of asphalt.

No Aggregate Base Course

8/14/20A801, Engineered StoneEngineered stone, do you want this 2cm or 3cm thickness?A/EEngineered stone should be 3/4" thickness, see specifcation 12 36 00
8/14/20A811 vs A901On A811 you call for POR1 on floors and POR2 on walls in all restrooms. On A901 you call for POR2 on the floor for the shower room. Is this correct?A/EThe floor finish in the shower room should be POR1, as indicated on A811, the annotation on A901 is incorrect.
8/14/20A611, A742, A801Where is the ES1?A/EAt restroom vanities, see 4/A630
8/14/20Section 321200 Flexible PavingPart 1.4.D.8 Sampling and Testing of asphalt concrete mixtures during paving operations. Paragraph c. states to perform at least one test for each days paving or 4,000s.f. of each lift. Does this refer to density, or asphalt cement content and maximum specific gravity tests also. For reference 4,000 s.f. at the maximum depth of 3” is about 75 tons of mix, and at a 2” thickness will be testing every 50 tons. Section 3.10 Field Quality Control D. Asphalt Density testing is defined at one per 2,000 square feet. Please clarify testing frequency and whether it is density or ac content and Rice values also. Testing frequency stated is much more typical for large scale production, not a 500 ton parking lot.A/EAsphalt density testing to be performed per 2,000 square feet per lift. AC content and RICE testing to be performed once per day or per 4000 sf for each lift, whichever is more stringent.
8/14/20Section 321200 Flexible PavingPart 2.1. E calls for a minimum sand equivalent of 45 for Asphalt Base Course Aggregates, and Part 2.1.F calls for a minimum sand equivalent of 50 for Surface Course Aggregates. CDOT requires a minimum of 45 for all asphalt aggregates. Our current mix designs fall between the 45 and 50 value, would the USFS Consider a 45 minimum value for the Surface Coarse Aggregates? If not a project specific mix design will be required at additional approximate cost of $6,000 for 500 tons of asphalt pavement.A/EMix design will be reviewed for all properties with project submittals. A minimum sand content meeting CDOT standards will be acceptable.
8/14/20Section 321200 Flexible PavingPart 3.2.D Tack Coat 1. State to apply in similar manner as prime coat, except as modified. No requirement for prime coat is found and in our opinion needed or desired. It has been decades since we prime coated a parking lot. Is a prime coat required? And if so, please provide specifications.A/EMix design will be reviewed for all properties with project submittals. A minimum sand content meeting CDOT standards will be acceptable.
8/14/20Section 321200 Flexible PavingPart 3.7 F. Lift Thickness: Table shows lift sequence for 5” paving, but not 5.5”. Top lift is specified to be 2” maximum thickness. Can bottom lift be installed at 3.5” or can top lift be 2.5” to match heavy duty pavement section.A/EMix design will be reviewed for all properties with project submittals. A minimum sand content meeting CDOT standards will be acceptable.
8/14/20Sheet CD302Thickened asphalt edge is very confusing. References are made to asphalt paving and aggregate base course in the same section. No width is identified for the thickened edge and thickness says varies. Please clarify.A/EMix design will be reviewed for all properties with project submittals. A minimum sand content meeting CDOT standards will be acceptable.