C05k Amendment 0002 1240LT26Q0137.pdf
PDF 853 KB Posted
- Attached to
- Lucky Peak Nursery New Greenhouse
- Solicitation number
- 1240LT26Q0137
- Issued by
-
Department of Agriculture Forest Service
About this file
This is an Amendment of Solicitation document (Amendment 0002) issued by the USDA Forest Service, CSA Intermountain Region for solicitation 1240LT26Q0137 regarding the Boise National Forest Lucky Peak Nursery New Greenhouse project. The amendment was issued on September 11, 2026, and is effective the same date. The quote due date remains September 25, 2026, at 4:00 PM Mountain Time, with a period of performance from October 15, 2026, to July 31, 2028. The amending contracting officer is Lonnie D. Root.
The amendment provides answers to three submitted questions regarding greenhouse controls systems. The key clarifications are: (1) bidders must provide an Axia control system platform rather than Titan, which is being phased out, and all references to Titan in Specification 133415 should be replaced with AXIA; (2) the approved control points list specifies inputs including inside sensor boxes for temperature, relative humidity, and light intensity, outside weather stations with anemometers and rain sensors, and crop sensors for soil moisture, electrical conductivity, and pH monitoring; and (3) vendors may provide their own suitable sequence of control operations rather than following a pre-approved sequence. The amendment states that all posted amendments will become part of any resulting award, and except as provided in this amendment, all prior terms and conditions remain unchanged and in full force and effect.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
1240LT26Q0137
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
40LT
OGDEN UT 84401-2310
324 25TH ST
USDA-FS CSA INTERMOUNTAIN 8
09/11/20260002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/06/2026
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
LONNIE D. ROOT
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Boise National Forest
Lucky Peak Nursery New Greenhouse
Amendment 0002
This amendment answers submitted questions below. All posted amendments will become a part of any resulting award.
The quote due date remains 9/25/2026, at 4:00 PM MT.
Period of Performance: 10/15/2026 to 07/31/2028
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
09/11/2026
Lucky Peak Nursery New Greenhouse - 1240LT26Q0137 Questions and Answers 002
Q1. Argus is the approved platform; however, the specs call out two (2) different platform options. Titan and AXIA. Please verify what platform to installed into this project, Titan or Axia.
A1. Please provide an Axia system. Titan is being phased out. Replace any reference in the Specification 133415 for Titan with AXIA.
Q2. Is there an approved control points list that shows the inputs that the end user wants monitored in each greenhouse, and what outputs are required for control?
A2. INPUT: Inside Sensor Box: Combined sensor for temperature, relative humidity, and light intensity
INPUT: Outside Weather Station: Anemometer (wind speed/direction), rain sensor, solar radiation sensor, and exterior temp/humidity sensor.
INPUT: Crop Sensors: Soil moisture sensors, EC (Electrical Conductivity) sensors, and pH sensors for nutrient solution monitoring.
OUTPUTS:
Heating
Air Flow
Irrigation booms/ Watering
Curtain Control
Operable roof Control
Lighting
Q3. Is there an approved sequence of operation for the equipment that must be met or is it up to the controls vendor to apply a sequence of operation suitable to the points list provided?
A3. Provide the controls vendors suitable sequence of control.
File details come from the government source that posted it. Updated .