RFI.docx
DOCX document 32 KB Posted
- Attached to
- UPS System Maintenance Federal contract opportunity
- Solicitation number
- 1232SA26Q0411
About this file
This document is a compilation of Requests for Information (RFIs) and Government Responses regarding a Request for Quotation (RFQ) for UPS System Maintenance Services at the National Bio and Agro-Defense Facility (NBAF). The RFQ solicitation number 1232SA26Q0411, issued by the Department of Agriculture Agricultural Research Service, seeks comprehensive maintenance and repair services for Rectifier/Charger, Battery, and Uninterruptible Power Supply (UPS) systems. This is a Total Small Business Set-Aside acquisition under NAICS code 238210 (Electrical Contractors and Other Wiring Installation Contractors) with a small business size standard of $19.0 million. The contractor must provide all labor, supervision, equipment, supplies, tools, materials, transportation, and non-personal services necessary to perform preventative maintenance, repairs, battery replacements, and capacitor bank replacements, except for items explicitly identified as government-furnished.
Key clarifications addressed in the RFI responses include: (1) the contractor's responsibility for "all-inclusive" maintenance services is limited to tasks specifically outlined in Performance Work Statement (PWS) Section 3.3, with software and firmware updates amended to the scope prior to the initial RFI round; (2) regarding small, government-provided parts under Section 3.3.3, the government does not maintain a fixed list of parts, as these are determined by OEM recommendations, inspection findings, and preventive maintenance cycles—the contractor is responsible only for labor to install government-furnished parts at the time of service; and (3) the government does not maintain a forecasted quantity of parts to be replaced, with typical installation time for individual small parts referenced as less than one hour, meaning the contractor must price labor based on actual service requirements rather than predetermined part quantities.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Bid Schedule_rev2.xlsx | XLSX spreadsheet | |
| Sol_1232SA26Q0411_Amd_0007.pdf | ||
| Attachment 2 - PWS_v4.docx | DOCX document | |
| Sol_1232SA26Q0411_Amd_0006.pdf | ||
| Attachment 2 - PWS_v3.docx | DOCX document | |
| RFI1.docx | DOCX document | |
| Attachment 1 Bid Schedule_rev1.xlsx | XLSX spreadsheet | |
| Sol_1232SA26Q0411_Amd_0005.pdf | ||
| Sol_1232SA26Q0411_Amd_0004.pdf | ||
| Attachment 2 - PWS_v2.docx | DOCX document | |
| Sol_1232SA26Q0411_Amd_0003.pdf | ||
| Attachment 6 Site Visit Informationv2.docx | DOCX document | |
| Sol_1232SA26Q0411_Amd_0002.pdf | ||
| Attachment 6 Site Visit Information.docx | DOCX document | |
| Sol_1232SA26Q0411.pdf | ||
| Attachment 1 - Bid Schedule.xlsx | XLSX spreadsheet | |
| Attachment 3 - UPS Technical Exhibit.pdf | ||
| Attachment 5 - Site Visit Application.pdf | ||
| Attachment 4 - Wage Determination.pdf | ||
| Attachment 2 - PWS.docx | DOCX document | |
| Attachment 6 - Site Visit Information.docx | DOCX document |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFIs and Responses
1. The government response to question 1 did not clearly state if the contractor is responsible for omissions not specifically listed in SOW Section 3.3. The response still stated to provide “all-inclusive maintenance services….”. Given this “all-inclusive” statement, is the contractor responsible for omissions not specifically called out in Section 3.3? It is difficult for the contractor to determine what the government considers “all-inclusive”. For clarity the contractor feels this language should be removed and only be held to what is specifically called out in Section 3.3.
Edited in PWS- This is a non-personal services contract to provide comprehensive maintenance services and repair services for the National Bio and Agro-Defense Facility’s (NBAF) UPS Systems, including all necessary components, as detailed in this PWS.
a. For example, the software and firmware updates were not listed in the SOW until the contractor asked the question. Therefore, the contractor is concerned about the “all-inclusive” language and being responsible for performing services not clearly outlined in Section 3.3. The software and firmware tasks were updated and amended prior to receiving the first round of RFI questions due to current situation of not being covered withing the scope of the previous contract.
2. Referencing the government response to Question 6., the response has nothing to do with the question. Please provide a list of parts the contractor is responsible for replacing.
6. Referencing SOW item 3.3.3 it states “replace small, government-provided parts as a required component of the preventative maintenance service”. The contractor respectfully requests a list of parts they will be responsible for installing as the part will impact the amount of labor involved for installation.
Section 3.3.3 requires the Contractor to install small, Government‑provided parts as part of the preventive maintenance service. The intent of this requirement is that the Government will furnish the specific parts identified as faulty by the contractor during maintenance and repair tasks to be installed, and the Contractor is responsible solely for the labor to install them in accordance with manufacturer instructions.
Because these parts are Government‑furnished and may vary based on OEM recommendations, inspection findings, and preventive maintenance cycles, the Government does not maintain a fixed list of parts. The Contractor will only be responsible for installing the parts that the Government provides at the time of service.
This requirement does not obligate the Contractor to supply or identify the parts; it only obligates the Contractor to install Government‑furnished items and document the installation as part of the maintenance record.
3. Referencing the government response to Question 7. (Not 7a or 7b), the government never provided a quantity of parts expected to be replaced under this CLIN. Response to 7b stated parts replacements should take less than 1 hour. However, for accurate pricing the contractor needs to know approximately how many parts they are replacing as this increases the total amount of time on site.
The number and type of these parts vary based on OEM recommendations, system condition, inspection findings, and preventive maintenance cycles. Because these parts are Government‑furnished and are not predetermined, the Government does not maintain a forecasted quantity.
The Contractor is responsible for the labor to install the parts provided at the time of service, and the Government will furnish only those parts required based on actual system needs.
The reference to “less than 1 hour” in the response to Question 7b pertains to the typical installation time for individual small parts, not to the total number of parts or total labor hours.