12 - Initial Authorization to Operate Timeline Actions.pdf
PDF 294 KB Posted
- Attached to
- Perkins Loan Servicing Federal contract opportunity
- Solicitation number
- 91003124R0017
About this file
This document is the Initial Authorization to Operate Timeline Actions for a Perkins Loan Servicing contract opportunity. It outlines the required actions and timeline leading up to the granting of the initial system Authority to Operate (ATO) for the contract.
The key details are:
- The system, software integration, and development efforts must be finalized and frozen for the production-ready capability 66 calendar days prior to the planned Go-Live date.
- All system documentation required for the ATO must be delivered, approved by both the vendor and the Government, and ready for the independent assessment.
- The independent assessment will take place 52 days prior to the planned Go-Live date.
- The Authorizing Official will make the final ATO decision within 14 days (2 weeks) after the assessment.
This document is an attachment to the Perkins Loan Servicing solicitation, which requires offerors to review the attachments and complete applicable attachments as part of their proposal submission.
View the file
Other files for this federal contract opportunity
Show all 50
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of Education Office of Federal Student Aid
Perkins Loan Servicing
Attachment 12 – Initial Authorization to Operate Timeline Actions
The following actions shall be accomplished prior to granting the initial system Authority to Operate
(ATO):
• 66 calendar days prior to the planned Go-Live date o 52 days: Independent Assessment (Kick-off to AO Decision Date).
The system, software integration, and development efforts must produce and freeze the configuration of the production ready capability.
All system documentation required for the ATO must be delivered, in a final and approved format. Approved documents must include both vendor and Government approvals as required for the document type.
The vendor shall be ready to assist and provide all required access and support for the independent assessment team to conduct the assessment.
o 14 Days (2 weeks after the AO Decision on the timeline below): The Authorizing Official has reserved this time to make and process the final decision documentation.