This document is a Modification/Explanation to the Change Order Fee for the Saint Louis Public Schools – CVPA & CSMB Entrance & Parking Lots Project. The document outlines the specific guidelines and percentages for overhead and profit that will be allowed for changes in work during the project. It provides detailed instructions on how cost changes should be computed, documented, and approved, with strict requirements for labor costs, material expenses, and subcontractor pricing.

The fee structure establishes maximum percentages for overhead and profit, which vary depending on whether work is performed by the Contractor's own forces or by subcontractors. For work performed with their own forces, both the Contractor and Subcontractors are allowed up to 12%, while work performed by other than their own forces is limited to 5%. The document emphasizes transparency in cost calculations, requiring itemized breakdowns of labor, materials, and additional scope, with daily tickets and verification by the Contractor's superintendent. The Owner reserves the right to reject any labor burden or cost calculations that are inconsistent with established agreements or market rates.

View the file

Other files

File Type Posted
7-A01 CVPA CSMB RFP 56-2025.pdf PDF
12-B04 004113D - SLPS CVPA CSMB Entrance Parking Lots Bid Summary (1).pdf PDF
5-W9 and Registration Process.pdf PDF
10-B02 004113a - SLPS CVPA CSMB Entrance Parking Lots Bid Form (1).pdf PDF
13-C01 006000a- SLPS CVPA CSMB Entrance Parking Lots A101-2017 GC Contract (1).pdf PDF
14-C02 006000b- SLPS CVPA CSMB Entrance Parking Lots A201-2017 GC Contract (1).pdf PDF
17-C05 006000E draft A312PerformanceBond-2010 - Working Draft - 001.pdf PDF
20-E01 250627-cvpa-csmb BID SPEC-combined.pdf PDF
15-C03 006000c- SLPS CVPA CSMB Entrance Parking Lots A201-2017 GC Contract (1).pdf PDF
1-Cost Pricing- fillable.pdf PDF
19-D02 004113e SLPS - MWBE Pre-Bid Information.pdf PDF
22-cchs-addendum 01r-250728 - v3.pdf PDF
9-B01 003113D - Point of Contact (1).pdf PDF
3-E Verify affadavit - fillable.pdf PDF
18-D01 008025B - Annual Wage Order 32.pdf PDF
8-A02 011000 - SLPS CVPA CSMB 056-2025 Entrance Parking Lots.pdf PDF
16-C04 006000D draft A312PaymentBond-2010 - Working Draft - 001.pdf PDF
4-BIDDER AFFIRMATION FORM- fillable.pdf PDF
2-E Verify agreement - fillable.pdf PDF
6-No Boycot Israel Certification - fillable form.pdf PDF
21-E02 250627-CVPA-CSMB - Combined Bid Set (1).pdf PDF
23-cchs-addendum 02-250728-complete.pdf PDF
24-1-Cost Pricing- fillable.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Saint Louis Public Schools – CVPA & CSMB Entrance & Parking Lots Project Modification/Explanation to the Change Order Fee

The maximum that will be allowed for overhead and profit on changes in work shall be as follows, expressed as a percentage of the basic cost of the change. The allowable percentages for profit or overhead may be less, depending on the nature, extent, or complexity of the change, where the percentage is not commensurate with the responsibility and administration involved (such as the Contractor merely processing substantial Change Order to a Subcontractor) but in no event shall they exceed the following:

To the Contractor and/or its Subcontractor for work performed with their own forces 12% To the Contractor for work performed by other than its own forces 5% To the Subcontractor/Supplier for work performed with their own forces 12% To the Subcontractor/Supplier for work performed by other than its own forces 5%

Not more than above specified percentages for overhead, profit and commission will be allowed to be added to the basic cost, regardless of the number of tiers of Contractors, Subcontractors or Sub-subcontractors.

The burden on labor may be indicated as a dollar/cents addition to the hourly rate or may be expressed as a percentage of the extended hourly rate costs. If required by the Owner, the Contractor shall provide a detailed breakdown to justify the labor burden. The Owner reserves the right to reject any labor burden which is inconsistent with other similar contractors or where the cost of fringe benefits are in excess of established labor agreements.

Material, equipment, and supply costs shall be quoted at the actual cost to the Contractor, or Subcontractor. Upon request, the Contractor (or Subcontractor) shall submit evidence to substantiate the costs. Said costs shall be quoted at trade discount prices, with quantity discounts also applied where the quantities warrant. In any proposal with material, equipment and supply credit, the credit shall be based on the actual Contract cost of the material (including trade and quantity discounts) less any charges actually incurred for handling or returning a material which has been delivered.

The percentages allowed for overhead and profit herein shall be deemed to include, and no further addition allowed the Contractor, Subcontractor or Sub-subcontractors for: (1) field and office supervision and administration, including the field superintendent and non-working foremen; (2) general insurance; (3) use or replacement of tools; (4) shop burden; (5) engineering costs; (6) performance (guaranty) and labor/material payment bonds; (7) cost of safety measures (including those imposed by OSHA); (8) permits, unless a new permit type is required; (9) and warranty costs.

Cost changes shall be computed by determining the basic costs enumerated below (as further specified under this Subparagraph), to which the overhead may be added, then the profit figure may be added, and finally adding the sales tax on materials if allowable.

For changes in the Work, the cost shall be determined as provided under this section. The Contractor shall submit an itemized list of quantities with the applicable unit costs and extended price for each, in such form and detail as required by the Owner. As a minimum, the detailed breakdown shall include and indicate the items enumerated below. Items (a) and (b) constitute the cost of labor, and items (a), (b), (c) and (d) constitute the basic costs referred to under this section.

a) Labor costs, itemized by each trade involved, showing the hourly rates for each, and the hours required for the change. Labor rates shall be the same for extra and credit computations and shall be the actual rate paid the workmen in accordance with established management labor agreements.

b) Burden on labor, which shall be only the actual costs of mandatory fringe benefits required by established agreements, taxes on labor, worker's or workmen's compensation, insurance on labor as affected by payroll, unemployment taxes and insurance, including FICA and FUTA. No other costs will be allowed as burden on labor.

c) Quantities of materials, equipment, and supplies, at their actual costs, with unit costs indicated.

d) The cost of subcontracted work computed in the same way as provided for under this section.

e) Overhead, profit and commission as set forth herein.

f) Applicable sales tax on materials, added after the above computations are complete.

Subcontractors (or Sub-subcontractors) shall compute their costs in the same way and are subject to the same conditions of what may be included in the cost and the same maximum percentages for overhead and profit. To the Subcontractor's price, the Contractor may add up to a maximum of five percent (5%).

For changes involving work of the Contractor with its own forces and work by a Subcontractor (or Sub-subcontractor), the commission shall be applied directly to the Subcontractor's price, with the overhead and profit figure applied only to the Work the Contractor performs with its own forces.

For changes involving both extra and credit amounts, the overhead and profit, or commission, shall be applied only to net difference where the extra exceeds the credit.

For changes resulting in a credit in the basic costs, a reasonable allowance for overhead, profit or commission may be required to be credited to the Owner, as approved by the Owner. In general, no credit for overhead, profit or commission will be required where the net change credit is minor or where the Change in Work indicates it is reasonable that no credit be allowed to the Owner due to the effort, cost or responsibility of the Contractor. In the event of substantial subcontract credits or for Work the Contractor does not provide or perform, a reasonable overhead, profit or commission credit shall be allowed to the Owner, as determined by the Owner.

If anytime, Contractor is directed to proceed in writing by the Owner or Owner’s Representative on a Time and Material Not to Exceed basis for a change, the Contractor must notify Owner’s Representative when work is beginning, when it is complete and daily tickets must be submitted as backup documentation.

Daily tickets to be signed daily and verified by the Contractor’s onsite superintendent and submitted daily to the Owner’s Representative. Any change order request submitted without these daily signed tickets will be rejected and will not be compensated.

Additional scope that is authorized to be completed on a Time and Material Not to Exceed (T&M NTE) basis on behalf of the Owner, shall be documented as follows:

a) Contractor shall issue daily tickets identifying hours worked, classification of worker, materials used, internally or externally rented equipment, and subcontractors utilized.

b) The additional scope should be delineated from the base bid scope.

c) Hours worked shall be verified by the General Contractor’s Superintendent and/or Authorized Owner’s Representative and indicated by signature on daily work tickets.

d) There should be a separate ticket for each day that additional scope of work takes place.

e) Unit costs, material costs and rental rates will be evaluated accordingly to typical market value.

f) The contractor is responsible for expending costs with the Owner’s best interest in mind.