100 SPECIFICATIONS 608-22-114 MANCHESTER NH Demo 2 Feb 2024.pdf
PDF 3 MB Posted
- Solicitation number
- 36C24124B0037
About this file
This solicitation is for the demolition of six buildings at the Manchester VA Medical Center in New Hampshire. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1 is seeking bids to demolish Building Numbers 2, 3, 4, 5, 13 and 14. Interested parties should submit bids in response to Solicitation Number 36C24124B0037 by the deadline of February 2, 2024. The solicitation includes demolition of the specified buildings as well as removal and disposal of all resulting debris. Bids are to be submitted following the instructions provided in the attached Invitation for Bid.
The solicitation provides the requirements for demolition of six buildings at the Manchester VA Medical Center campus. Interested contractors should review the attached specifications and submit bids in accordance with the instructions in the Invitation for Bid by February 2, 2024.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Manchester VAMC, New Hampshire
Project# 608-22-114
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-1i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS 1
1.2 GENERAL INTENTION 1
1.3 STATEMENT OF BID ITEM(S) 1
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR 2
1.5 CONSTRUCTION SECURITY REQUIREMENTS 2
1.6 OPERATIONS AND STORAGE AREAS 4
1.7 DISPOSAL AND RETENTION 9
1.8 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS 10
1.9 RESTORATION 11
1.10 PHYSICAL DATA 12
1.11 PROFESSIONAL SURVEYING SERVICES 13
1.12 LAYOUT OF WORK 13
1.13 AS-BUILT DRAWINGS 14
1.14 USE OF ROADWAYS 14
1.15 TEMPORARY TOILETS 15
1.16 AVAILABILITY AND USE OF UTILITY SERVICES 15
1.17 TESTS 15
1.18 PHOTOGRAPHIC DOCUMENTATION 16
1.19 HISTORIC PRESERVATION 17
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION
NO
DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-
00 11 21 Request for Proposal to Design Build 09-
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-
01 32
16.01
Architectural and Engineering CPM Schedules 03-
01 32
16.13
Network Analysis Schedules � Major
Construction Project Design-Bid-Build
05-
01 32
16.15
Project Schedules (Small Projects �
Design/Bid/Build
11-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-2i
SECTION
NO
DIVISION AND SECTION TITLES DATE
01 32
16.16
Network Analysis Schedules (Design-Build
Only)
05-
01 32
16.17
Network Analysis Schedules � Major
Design/Build Projects
06-
01 33 23 Shop Drawings, Product Data, and Samples 02-
01 35 26 Safety Requirements 10-
01 42 19 Reference Standards 11-
01 45 00 Quality Control 02-
01 45 29 Testing Laboratory Services 11-
01 45 35 Special Inspections 06-
01 57 19 Temporary Environmental Controls 01-
01 58 16 Temporary Interior Signage 07-
01 74 19 Construction Waste Management 04-
01 81 13 Sustainable Construction Requirements 10-
01 81
13.02
Sustainability Certification Requirements �
LEED V4 BD+C: New Construction and Major
Renovation
04-
01 81
13.03
Sustainability Certification Requirements �
LEED V4 BD+C: Healthcare
04-
01 81
13.12
Sustainability Certification Requirements �
LEED V4.1 BD+C: New Construction and Major
Renovation
04-
01 81
13.13
Sustainability Certification Requirements �
LEED V4.1: Healthcare
04-
01 81
13.14
Sustainability Certification Requirements �
LEED V4.1 BD+C: Data Centers
04-
01 81
13.15
Sustainability Certification Requirements �
LEED V4.1 BD+C: Warehouses and Distribution
Centers
04-
01 81
13.21
Sustainability Certification Requirements �
GREEN GLOBES
01-
01 91 00 General Commissioning Requirements 04-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-3i
SECTION
NO
DIVISION AND SECTION TITLES DATE
01 91
00.01
DVA/USACE Projects General Commissioning
Requirements
08-
DIVISION 02 � EXISTING CONDITIONS
02 21 13 Site Surveys 01-
02 41 00 Demolition 08-
02 65 00 Underground Storage Tank Removal 01-
02 82 11 Traditional Asbestos Abatement 01-
02 82
13.13
Glovebag Asbestos Abatement 01-
02 82
13.19
Asbestos Floor Tile and Mastic Abatement 01-
02 82
13.21
Asbestos Roofing Abatement 01-
02 82
13.31
Asbestos Transite Abatement 01-
02 82
13.41
Asbestos Abatement for Total Demolition
Project
01-
02 83
33.13
Lead-Based Paint Removal and Disposal 01-
DIVISION 03 � CONCRETE
03 23 00 Stressing Tendons 01-
03 30 00 Cast-in-Place Concrete 01-
03 30 53 (Short-Form) Cast-in-Place Concrete 01-
03 37 13 Shotcrete 01-
03 41 13 Precast Concrete Hollow Core Planks 01-
03 41 33 Precast Structural Pretensioned Concrete 01-
03 45 00 Precast Architectural Concrete 01-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-4i
SECTION
NO
DIVISION AND SECTION TITLES DATE
03 51 13 Cementitious Wood Fiber Decks 01-
03 51 16 Gypsum Concrete Roof Decks 01-
03 52 00 Lightweight Concrete Roof Insulation 01-
03 55 11 Gypsum Concrete Floor Decks 01-
DIVISION 04 � MASONRY
04 01 00 Maintenance of Masonry 01-
04 05 13 Masonry Mortaring 10-
04 05 16 Masonry Grouting 01-
04 20 00 Unit Masonry 08-
04 72 00 Cast Stone Masonry 01-
DIVISION 05 � METALS
05 12 00 Structural Steel Framing 11-
05 21 00 Steel Joist Framing 11-
05 31 00 Steel Decking 01-
05 36 00 Composite Metal Decking 01-
05 40 00 Cold-Formed Metal Framing 01-
05 50 00 Metal Fabrications 08-
05 51 00 Metal Stairs 01-
DIVISION 06 � WOOD, PLASTICS AND COMPOSITES
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-5i
SECTION
NO
DIVISION AND SECTION TITLES DATE
06 10 00 Rough Carpentry 10-
06 16 63 Cementitious Sheathing 01-
06 20 00 Finish Carpentry 01-
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01
50.19
Preparation for Re-Roofing 01-
07 08 00 Facility Exterior Closure Commissioning 01-
07 08
00.01
DVA/USACE Projects Facility Exterior Closure
Commissioning
08-
07 11 13 Bituminous Dampproofing 01-
07 12 00 Built-Up Bituminous Waterproofing 01-
07 13 00 Sheet Waterproofing 01-
07 13 52 Modified Bituminous Sheet Waterproofing 01-
07 14 21 Latex Mastic Deck Covering 01-
07 18 13 Pedestrian Traffic Coatings 01-
07 21 13 Thermal Insulation 01-
07 21 23 Loose-Fill Insulation 01-
07 22 00 Roof and Deck Insulation 01-
07 24 00 Exterior Insulation and Finish Systems 01-
07 27 26 Fluid-Applied Membrane Air Barrier, Vapor
Permeable
01-
07 27 27 Fluid-Applied Membrane Air Barrier, Vapor
Retarding
01-
07 31 13 Asphalt Shingles 02-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-6i
SECTION
NO
DIVISION AND SECTION TITLES DATE
07 31 26 Slate Shingles 01-
07 31
29.13
Wood Shingles 01-
07 32 13 Clay Roof Tiles 01-
07 40 00 Roofing and Siding Panels 01-
07 51 00 Built-Up Bituminous Roofing 12-
07 51
13.11
Hot-Applied Built-Up Asphalt Roofing 12-
07 51
13.13
Cold-Applied Built-Up Asphalt Roofing 12-
07 52
16.11
Cold Adhesive Styrene-Butadiene-Styrene
Modified Bituminous Membrane Roofing
12-
07 52
16.12
Hot-Mopped Styrene-Butadiene-Styrene Modified
Bituminous Membrane Roofing
12-
07 53 23 Ethylene-Propylene-Diene-Monomer Roofing 01-
07 54 16 Ethylene Interpolymer (KEE) Roofing 01-
07 54 19 Polyvinyl-Chloride (PVC) Roofing 12-
07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-
07 56 00 Fluid-Applied Roofing 01-
07 57 13 Sprayed Polyurethane Foam Roofing 12-
07 60 00 Flashing and Sheet Metal 01-
07 61 16 Batten Seam Copper Roofing 01-
07 71 00 Roof Specialties 01-
07 72 00 Roof Accessories 01-
07 81 00 Applied Fireproofing 07-
07 84 00 Firestopping 01-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-7i
SECTION
NO
DIVISION AND SECTION TITLES DATE
07 92 00 Joint Sealants 04-
07 95 13 Expansion Joint Cover Assemblies 01-
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-
08 11 73 Sliding Metal Fire Doors 01-
08 14 00 Interior Wood Doors 01-
08 17 10 Integrated Door Assemblies 01-
08 31 13 Access Doors and Frames 04-
08 32 13 ICU Sliding Glass Doors 01-
08 33 00 Coiling Doors and Grilles 01-
08 33 13 Coiling Counter Doors 01-
08 34 53 Security Doors and Frames 01-
08 34 59 Vault Doors and Day Gates 01-
08 35
13.13
Accordion Folding Doors 01-
08 36 13 Sectional Doors 01-
08 38 16 Flexible Traffic Doors 01-
08 41 13 Aluminum-Framed Entrances and Storefronts 01-
08 42 33 Revolving Door Entrances 01-
08 44 13 Glazed Aluminum Curtain Walls 04-
08 51 13 Aluminum Windows 01-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-8i
SECTION
NO
DIVISION AND SECTION TITLES DATE
08 51
13.11
Side-Hinged Aluminum Windows 01-
08 51 23 Steel Windows 01-
08 51
69.11
Aluminum Storm Windows 01-
08 56 19 Pass Windows 01-
08 56 53 Blast Resistant Windows 01-
08 56 59 Service and Teller Window Units 01-
08 56 66 Detention Window Screens 01-
08 63 00 Metal-Framed Skylights 01-
08 71 00 Door Hardware 05-
08 71 13 Automatic Door Operators 01-
08 71
13.11
Low Energy Power Assist Door Operators 01-
08 80 00 Glazing 01-
08 90 00 Louvers and Vents 01-
DIVISION 09 � FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-
09 06 00 Schedule for Finishes 01-
09 22 16 Non-Structural Metal Framing 06-
09 23 00 Gypsum Plastering 01-
09 24 00 Portland Cement Plastering 01-
09 26 00 Veneer Plastering 01-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-9i
SECTION
NO
DIVISION AND SECTION TITLES DATE
09 29 00 Gypsum Board 04-
09 30 13 Ceramic/Porcelain Tiling 01-
09 51 00 Acoustical Ceilings 12-
09 54 23 Linear Metal Ceilings 01-
09 63 13 Brick Flooring 01-
09 63 40 Stone Flooring 01-
09 65 13 Resilient Base and Accessories 01-
09 65 16 Resilient Sheet Flooring 06-
09 65 19 Resilient Tile Flooring 05-
09 66 13 Portland Cement Terrazzo Flooring 01-
09 66 16 Terrazzo Floor Tile 01-
09 67
23.20
Resinous Epoxy Base With Vinyl Chip Broadcast
(RES 2)
12-
09 67
23.30
Resinous (Epoxy Resin Composition) Mortar
Flooring (RES-3)
01-
09.67.23.
Resinous Poured In Place Resilient Flooring
(RES-4)
01-
09 67
23.50
Resinous Terrazzo Flooring (RES-5) 01-
09 67
23.60
Resinous Urethane and Epoxy Mortar Flooring
(RES-6A and RES 6B)
01-
09 68 00 Carpeting 01-
09 68 21 Athletic Carpeting 01-
09 69 00 Access Flooring 01-
09 72 16 Vinyl-Coated Fabric Wall Covering 01-
09 72 31 Polypropylene Fabric Wall Covering 01-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-10i
SECTION
NO
DIVISION AND SECTION TITLES DATE
09 78 23 Phenolic Interior Wall Paneling 01-
09 84 33 Sound-Absorbing Wall Units 01-
09 91 00 Painting 01-
09 94 19 Multicolor Interior Finishing 01-
09 96 59 Resinous Specialty Glazed Coating Systems for
Walls, Ceilings, Wallboard, and Block CMU
(RES-W1, RES-W2)
01-
DIVISION 10 � SPECIALTIES
10 11 13 Chalkboards and Markerboards 01-
10 11 23 Tackboards 01-
10 11 33 Glassboards (Magnetic & Non-Magnetic) 01-
10 13 00 Directories 01-
10 14 00 Signage 01-
10 21 13 Toilet Compartments 01-
10 21 16 Shower and Dressing Compartments 01-
10 21 23 Cubicle Curtain Tracks 01-
10 22 13 Wire Mesh Partitions 01-
10 22 19 Demountable Partitions 01-
10 22
26.13
Accordion Folding Partitions 01-
10 25 13 Patient Bed Service Walls 05-
10 26 00 Wall and Door Protection 01-
10 28 00 Toilet, Bath, and Laundry Accessories 01-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-11i
SECTION
NO
DIVISION AND SECTION TITLES DATE
10 44 13 Fire Extinguisher Cabinets 08-
10 75 00 Flagpoles 01-
DIVISION 11 � EQUIPMENT
11 05 12 General Motor Requirements for Equipment 01-
11 12 00 Parking Control Equipment 01-
11 17 36 Package Transfer Units 01-
11 26 00 Unit Kitchens 01-
11 40 11 Custom Fabricated Food Service Equipment 01-
11 40 21 Food Service Equipment-Utility Distribution
System
01-
11 41 00 Food Storage Equipment 01-
11 41 21 Walk-In Coolers and Freezers 01-
11 44 00 Food Cooking Equipment 01-
11 48 00 Cleaning and Disposal Equipment 01-
11 53 13 Laboratory Fume Hoods 01-
11 53 23 Laboratory Refrigerators 01-
11 53 53 Biological Safety Cabinets Laminar Airflow
Stations
01-
11 53 61 Custom Fabricated Laboratory Equipment 01-
11 53 71 Solution Warming Cabinets 01-
11 71 01 Medical Washing and Sterilizing Equipment 01-
11 71 02 Laboratory Washing and Sterilizing Equipment 01-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-12i
SECTION
NO
DIVISION AND SECTION TITLES DATE
11 73 00 Ceiling Mounted Patient Lift System 08-
11 78 00 Mortuary Equipment 01-
11 78 13 Mortuary Refrigerators 01-
11 79 13 Hydrotherapy Equipment 01-
11 82 19 Packaged Incinerators 01-
DIVISION 12 � FURNISHINGS
12 22 16 Drapery Track and Accessories 01-
12 24 00 Window Shades 08-
12 24 21 Lightproof Shades 01-
12 31 00 Manufactured Metal Casework 01-
12 32 00 Manufactured Wood Casework 01-
12 34 00 Manufactured Plastic Casework 01-
12 35
70.21
Medication Cabinet 01-
12 36 00 Countertops 12-
12 56
70.11
Suspended Table 01-
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-
Structural Components
01-
13 17 23 Therapeutic Pools 01-
13 17
23.11
Therapeutic Pool Accessories 01-
13 19 13 Kennel Enclosures and Gates 01-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-13i
SECTION
NO
DIVISION AND SECTION TITLES DATE
13 21 29 Constant Temperature Rooms 01-
13 21 49 Audiology Booth 01-
13 34 19 Metal Building Systems 01-
13 49 00 Radiation Protection 01-
DIVISION 14� CONVEYING EQUIPEMENT
14 12 11 Traction and Winding Drum Dumbwaiter 09-
14 21 00 Traction Elevator � New 09-
14 21 10 Traction Elevator � Modernization 09-
14 21 11 Traction Cartlift 09-
14 24 00 Hydraulic Elevator � New 09-
14 24 10 Hydraulic Elevator � Modernization 09-
14 24 11 Hydraulic Cartlift 09-
14 91 33 Gravity Soiled Linen Chutes 09-
14 91 82 Gravity Trash Chutes 09-
14 92 00 Pneumatic Tube System 09-
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-
21 08
00.01
DVA/USACE Projects Commissioning of Fire
Suppression Systems
08-
21 12 00 Manual Dry Standpipe Systems 06-
21 13 13 Wet-Pipe Sprinkler Systems 06-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-14i
SECTION
NO
DIVISION AND SECTION TITLES DATE
21 13 16 Dry-Pipe Sprinkler Systems 01-
21-22-00 Clean Agent Fire Suppression Systems 05-
21-30-13 Electric-Driven, Fire Pumps 05-
21-30-16 Diesel-Driven, Fire Pumps 05-
DIVISION 22 � PLUMBING
22 05 11 Common Work Results for Plumbing 01-
22 05 12 General Motor Requirements for Plumbing
Equipment
09-
22 05 19 Meters and Gages for Plumbing Piping 09-
22 05 23 General-Duty Valves for Plumbing Piping 09-
22 05 33 Heat Tracing for Plumbing Piping 09-
22 07 11 Plumbing Insulation 09-
22 08 00 Commissioning of Plumbing Systems 11-
22 08
00.01
DVA/USACE Projects Commissioning of Plumbing
Systems
08-
22 11 00 Facility Water Distribution 05-
22 11 23 Domestic Water Pumps 09-
22 12 16 Facility Elevated, Potable-Water Storage
Tanks
09-
22 13 00 Facility Sanitary and Vent Piping 09-
22 13 23 Sanitary Waste Interceptors 09-
22 13 29 Sanitary Sewerage Pumps 09-
22 13
29.13
Wet-Pit Mounted, Vertical Sewerage Pumps 09-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-15i
SECTION
NO
DIVISION AND SECTION TITLES DATE
22 13 33 Packaged, Submersible Sewerage Pump Units 09-
22 14 00 Facility Storm Drainage 09-
22 14 29 Sump Pumps 09-
22 14 33 Packaged, Pedestal Drainage Pump Units 09-
22 14 36 Packaged, Submersible, Drainage Pump Units 09-
22 15 00 General Service Compressed-Air Systems 09-
22 31 11 Water Softeners 09-
22 33 00 Electric Domestic Water Heaters 09-
22 34 00 Fuel-Fired Domestic Water Heaters 09-
22 35 00 Domestic Water Heat Exchangers 09-
22 40 00 Plumbing Fixtures 12-
22 42 26 Commercial Disposers 09-
22 61
13.74
Dental Compressed-Air Piping 05-
22 61
19.74
Dental Compressed-Air Equipment 09-
22 62 00 Vacuum Systems for Laboratory and Healthcare
Facilities
05-
22 62
19.74
Dental Vacuum and Evacuation Equipment 09-
22 63 00 Gas Systems for Laboratory and Healthcare
Facilities
05-
22 66 00 Chemical-Waste Systems for Laboratory and
Healthcare Facilities
09-
22 67
19.16
Reverse-Osmosis Water Equipment 09-
22 67 21 Water Dealkalizing System 09-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-16i
SECTION
NO
DIVISION AND SECTION TITLES DATE
DIVISION 23 � HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 10 Common Work Results for Boiler Plant and
Steam Generation
09-
23 05 11 Common Work Results for HVAC 03-
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
03-
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment
03-
23 05 51 Noise and Vibration Control for Boiler Plant 03-
23 05 93 Testing, Adjusting, and Balancing for HVAC 03-
23 05
93.01
DVA/USACE Projects Testing, Adjusting, and
Balancing for HVAC
11-
23 07 11 HVAC and Boiler Plant Insulation 02-
23 08 00 Commissioning of HVAC Systems 03-
23 08
00.01
DVA/USACE Projects Commissioning of HVAC
Systems
08-
23 08 11 Demonstrations and Tests for Boiler Plant 04-
23 09 11 Instrumentation and Control for Boiler Plant 04-
23 09 23 Direct-Digital Control System for HVAC 03-
23 10 00 Facility Fuel Systems 04-
23 11 23 Facility Natural-Gas Piping 04-
23 21 11 Boiler Plant Piping Systems 08-
23 21 13 Hydronic Piping 03-
23 21 23 Hydronic Pumps 03-
23 22 13 Steam and Condensate Heating Piping 08-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-17i
SECTION
NO
DIVISION AND SECTION TITLES DATE
23 22 23 Steam Condensate Pumps 04-
23 23 00 Refrigerant Piping 03-
23 25 00 HVAC Water Treatment 03-
23 31 00 HVAC Ducts and Casings 03-
23 34 00 HVAC Fans 03-
23 36 00 Air Terminal Units 03-
23 37 00 Air Outlets and Inlets 03-
23 38 13 Commercial-Kitchen Hoods 03-
23 40 00 HVAC Air Cleaning Devices 03-
23 50 11 Boiler Plant Mechanical Equipment 03-
23 51 00 Breechings, Chimneys, and Stacks 04-
23 52 25 Low-Pressure Water Heating Boilers 09-
23 52 28 Low-Pressure Steam Boilers 09-
23 52 33 Water Tube Boilers 09-
23 52 39 Fire Tube Boilers 09-
23 56 00 Solar Energy Heating System 03-
23 57 33 Geothermal Energy � Direct Use 03-
23 64 00 Packaged Water Chillers 03-
23 65 00 Cooling Towers 03-
23 72 00 Air-to-Air Energy Recovery Equipment 03-
23 73 00 Indoor Central-Station Air-Handling Units 03-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-18i
SECTION
NO
DIVISION AND SECTION TITLES DATE
23 74 13 Packaged, Outdoor, Central-Station Air-
Handling Units
03-
23 81 00 Decentralized Unitary HVAC Equipment 03-
23 81 23 Computer-Room Air-Conditioners 03-
23 81 43 Air-Source Unitary Heat Pumps 03-
23 81 46 Water-Source Unitary Heat Pumps 03-
23 81 49 Ground-Source Heat Pump 03-
23 82 00 Convection Heating and Cooling Units 03-
23 82 16 Air Coils 03-
23 84 00 Humidity Control Equipment 03-
DIVISION 25 � INTEGRATED AUTOMATION
25 10 10 Advanced Utility Metering System 02-
DIVISION 26 � ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-
26 05 13 Medium-Voltage Cables 11-
26 05 19 Low-Voltage Electrical Power Conductors and
Cables
11-
26 05 26 Grounding and Bonding for Electrical Systems 11-
26 05 33 Raceway and Boxes for Electrical Systems 11-
26 05 36 Wireways for Radiology Equipment 11-
26 05 39 Underfloor Raceways for Electrical Systems 11-
26 05 41 Underground Electrical Construction 11-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-19i
SECTION
NO
DIVISION AND SECTION TITLES DATE
26 05 73 Overcurrent Protective Device Coordination
Study
11-
26 08 00 Commissioning of Electrical Systems 11-
26 08
00.01
DVA/USACE Projects Commissioning of
Electrical Systems
08-
26 09 23 Lighting Controls 11-
26 11 16 Secondary Unit Substations 11-
26 12 19 Pad-Mounted, Liquid-Filled, Medium-Voltage
Transformers
11-
26 13 13 Medium-Voltage Circuit Breaker Switchgear 11-
26 13 16 Medium-Voltage Fusible Interrupter Switches 11-
26 20 11 Isolated Power Systems 11-
26 22 00 Low-Voltage Transformers 11-
26 23 00 Low-Voltage Switchgear 11-
26 23 13 Generator Paralleling Controls 11-
26 24 13 Distribution Switchboards 11-
26 24 16 Panelboards 11-
26 24 19 Motor Control Centers 11-
26 25 11 Busways 11-
26 26 00 Power Distribution Units for Static
Uninterruptible Power Systems
11-
26 27 26 Wiring Devices 11-
26 29 11 Motor Controllers 11-
26 29 21 Enclosed Switches and Circuit Breakers 11-
26 32 13 Engine Generators 11-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-20i
SECTION
NO
DIVISION AND SECTION TITLES DATE
26 33 53 Static Uninterruptible Power Supply 11-
26 35 26 Harmonic Filters 11-
26 36 23 Automatic Transfer Switches 11-
26 41 00 Facility Lightning Protection 11-
26 42 00 Cathodic Protection 11-
26 43 13 Surge Protective Devices 11-
26 51 00 Interior Lighting 11-
26 55 71 Medical and Surgical Lighting Fixtures 11-
26 56 00 Exterior Lighting 11-
DIVISION 27 � COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-
27 05 26 Grounding and Bonding for Communications
Systems
06-
27 05 33 Raceways and Boxes for Communications Systems 10-
27 05 61 Leased Space, Communication Equipment and
Systems
06-
27 08 00 Commissioning of Communications Systems 11-
27 08
00.01
DVA/USACE Projects Commissioning of
Communications Systems
08-
27 10 00 Control, Communication and Signal Wiring 06-
27 11 00 Telecommunications Room Fittings 06-
27 15 00 Communications Structured Cabling 01-
27 31 00 Voice Communications Switching and Routing
Equipment
06-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-21i
SECTION
NO
DIVISION AND SECTION TITLES DATE
27 31 31 Voice Communications Switching and Routing
Equipment - Extension
06-
27 32 41 Two-Way Radio Equipment and Systems 10-
27 41 31 Master Antenna Television Equipment and
Systems
06-
27 51 16 Public Address and Mass Notification Systems 11-
27 51 23 Intercommunications and Program Systems 06-
27 52 23 Nurse Call and Code Blue Systems 10-
27 52 41 Miscellaneous Medical Systems 06-
27 53 19 Distributed Radio Antenna (Within Building)
Equipment and System
10-
DIVISION 28 � ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and
Security
04-
28 05 13 Conductors and Cables for Electronic Safety and Security
10-
28 05 26 Grounding and Bonding for Electronic Safety and Security
09-
28 05
28.33
Conduits and Backboxes for Electronic Safety and Security
09-
28 08 00 Commissioning of Electronic Safety and
Security Systems
11-
28 08
00.01
DVA/USACE Projects Commissioning of
Electronic Safety and Security Systems
08-
28 13 00 Physical Access Control System 10-
28 13 16 Physical Access Control System and Database
Management
09-
28 13 53 Security Access Detection 09-
28 16 00 Intrusion Detection System 10-
28 23 00 Video Surveillance 09-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-22i
SECTION
NO
DIVISION AND SECTION TITLES DATE
28 26 00 Electronic Personal Protection System 09-
28 31 00 Fire Detection and Alarm 10-
28 52 31 Emergency Call System 06-
DIVISION 31 � EARTHWORK
31 20 00 Earthwork 08-
31 20 11 Earthwork (Short Form) 10-
31 23 19 Dewatering 10-
31 23
23.33
Flowable Fill 10-
31 32 23 Pressure Grouting Soil Stabilization 10-
31 62 00 Driven Piles 10-
31 63 16 Auger Cast Grout Piles 10-
31 63 26 Drilled Caissons 10-
DIVISION 32 � EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-
32 12 16 Asphalt Paving 09-
32 14 16 Brick Unit Paving 08-
32 17 23 Pavement Markings 08-
32 31 13 Chain Link Fences and Gates 06-
32 31 40 High Security Fences and Gates 08-
32 84 00 Planting Irrigation 08-
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 10-23i
SECTION
NO
DIVISION AND SECTION TITLES DATE
32 90 00 Planting 08-
DIVISION 33 � UTILITIES
33 08 00 Commissioning of Site Utility Systems 11-
33 08
00.01
DVA/USACE Projects Commissioning of Site
Utility Systems
08-
33 10 00 Water Utilities 03-
33 30 00 Sanitary Sewer Utilities 06-
33 40 00 Storm Sewer Utilities 12-
33 46 13 Foundation Drainage 10-
33 51 00 Natural-Gas Distribution 10-
33 63 00 Steam Energy Distribution 09-
DIVISION 34 � TRANSPORTATION
34 71 13 Passive Vehicle Barriers 04-
34 75
13.13
Active Vehicle Barriers 08-
DIVISION 48 � Electrical Power Generation
48 14 00 Solar Energy Electrical Power Generation
System
07-
48 15 00 Wind Energy Electrical Power Generation
System
07-
Manchester VAMC, New Hampshire 90% Construction Design
Project# 608-22-114 VHA Master Specifications Version 09-01-23
Buildings #2-5,13 & 14 Demo
01/01/2024Manchester VAMC, New Hampshire
00 01 10 - 1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
00 11 21 Request for Proposal to Design Build 09-21
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.01 Architectural and Engineering CPM Schedules 03-20
01 32 16.13 Network Analysis Schedules � Major Construction Project
Design-Bid-Build
05-22
01 32 16.15 Project Schedules (Small Projects � Design/Bid/Build 11-21
01 32 16.16 Network Analysis Schedules (Design-Build Only) 05-22
01 32 16.17 Network Analysis Schedules � Major Design/Build
Projects
06-19
01 33 23 Shop Drawings, Product Data, and Samples 0211-
01 35 26 Safety Requirements 10-22
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 06-21
01 57 19 Temporary Environmental Controls 01-21
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 04-22
01 81 13 Sustainable Construction Requirements 10-17
01 81 13.02 Sustainability Certification Requirements � LEED V4
BD+C: New Construction and Major Renovation
04-23
01 81 13.03 Sustainability Certification Requirements � LEED V4
BD+C: Healthcare
04-23
01 81 13.12 Sustainability Certification Requirements � LEED V4.1
BD+C: New Construction and Major Renovation
04-23
01 81 13.13 Sustainability Certification Requirements � LEED V4.1:
Healthcare
04-23
01 81 13.14 Sustainability Certification Requirements � LEED V4.1
BD+C: Data Centers
04-23
01 81 13.15 Sustainability Certification Requirements � LEED V4.1
BD+C: Warehouses and Distribution Centers
04-23
01 81 13.21 Sustainability Certification Requirements � GREEN
GLOBES
01-21
01 91 00 General Commissioning Requirements 04-22
01 91 00.01 DVA/USACE Projects General Commissioning Requirements 08-19
Buildings #2-5,13 & 14 Demo
01/01/2024Manchester VAMC, New Hampshire
00 01 10 - 2
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 02 � EXISTING CONDITIONS
02 21 13 Site Surveys 01-
2112-
02 41 00 Demolition 08-17
02 65 00 Underground Storage Tank Removal 01-21
02 82 11 Traditional Asbestos Abatement 01-21
02 82 13.13 Glovebag Asbestos Abatement 01-21
02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21
02 82 13.21 Asbestos Roofing Abatement 01-21
02 82 13.31 Asbestos Transite Abatement 01-21
02 82 13.41 Asbestos Abatement for Total Demolition Project 01-21
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 � CONCRETE
03 23 00 Stressing Tendons 01-21
03 30 00 Cast-in-Place Concrete 01-21
03 30 53 (Short-Form) Cast-in-Place Concrete 01-21
03 37 13 Shotcrete 01-21
03 41 13 Precast Concrete Hollow Core Planks 01-21
03 41 33 Precast Structural Pretensioned Concrete 01-21
03 45 00 Precast Architectural Concrete 01-21
03 51 13 Cementitious Wood Fiber Decks 01-21
03 51 16 Gypsum Concrete Roof Decks 01-21
03 52 00 Lightweight Concrete Roof Insulation 01-21
03 55 11 Gypsum Concrete Floor Decks 01-21
DIVISION 04 � MASONRY
04 01 00 Maintenance of Masonry 01-21
04 05 13 Masonry Mortaring 10-17
04 05 16 Masonry Grouting 01-21
04 20 00 Unit Masonry 08-17
04 72 00 Cast Stone Masonry 01-21
DIVISION 05 � METALS
05 12 00 Structural Steel Framing 11-18
05 21 00 Steel Joist Framing 11-18
05 31 00 Steel Decking 01-21
05 36 00 Composite Metal Decking 01-21
05 40 00 Cold-Formed Metal Framing 01-21
05 50 00 Metal Fabrications 08-18
05 51 00 Metal Stairs 01-21
Buildings #2-5,13 & 14 Demo
01/01/2024Manchester VAMC, New Hampshire
00 01 10 - 3
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 06 � WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
06 16 63 Cementitious Sheathing 01-21
06 20 00 Finish Carpentry 01-21
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 01-21
07 08 00 Facility Exterior Closure Commissioning 01-21
07 08 00.01 DVA/USACE Projects Facility Exterior Closure
Commissioning
08-19
07 11 13 Bituminous Dampproofing 01-21
07 12 00 Built-Up Bituminous Waterproofing 01-21
07 13 00 Sheet Waterproofing 01-21
07 13 52 Modified Bituminous Sheet Waterproofing 01-21
07 14 21 Latex Mastic Deck Covering 01-21
07 18 13 Pedestrian Traffic Coatings 01-21
07 21 13 Thermal Insulation 01-21
07 21 23 Loose-Fill Insulation 01-21
07 22 00 Roof and Deck Insulation 01-21
07 24 00 Exterior Insulation and Finish Systems 01-21
07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Permeable 01-21
07 27 27 Fluid-Applied Membrane Air Barrier, Vapor Retarding 01-21
07 31 13 Asphalt Shingles 02-21
07 31 26 Slate Shingles 01-21
07 31 29.13 Wood Shingles 01-21
07 32 13 Clay Roof Tiles 01-21
07 40 00 Roofing and Siding Panels 01-21
07 51 00 Built-Up Bituminous Roofing 12-21
07 51 13.11 Hot-Applied Built-Up Asphalt Roofing 12-21
07 51 13.13 Cold-Applied Built-Up Asphalt Roofing 12-21
07 52 16.11 Cold Adhesive Styrene-Butadiene-Styrene Modified
Bituminous Membrane Roofing
12-21
07 52 16.12 Hot-Mopped Styrene-Butadiene-Styrene Modified
Bituminous Membrane Roofing
12-21
07 53 23 Ethylene-Propylene-Diene-Monomer Roofing 01-21
07 54 16 Ethylene Interpolymer (KEE) Roofing 01-21
07 54 19 Polyvinyl-Chloride (PVC) Roofing 12-18
07 54 23 Thermoplastic Polyolefin (TPO) Roofing 01-21
07 56 00 Fluid-Applied Roofing 01-21
07 57 13 Sprayed Polyurethane Foam Roofing 12-21
07 60 00 Flashing and Sheet Metal 01-21
07 61 16 Batten Seam Copper Roofing 01-21
07 71 00 Roof Specialties 01-21
07 72 00 Roof Accessories 01-21
07 81 00 Applied Fireproofing 07-23
07 84 00 Firestopping 01-21
07 92 00 Joint Sealants 04-22
Buildings #2-5,13 & 14 Demo
01/01/2024Manchester VAMC, New Hampshire
00 01 10 - 4
SECTION NO DIVISION AND SECTION TITLES DATE
07 95 13 Expansion Joint Cover Assemblies 01-21
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21
08 11 73 Sliding Metal Fire Doors 01-21
08 14 00 Interior Wood Doors 01-21
08 17 10 Integrated Door Assemblies 01-21
08 31 13 Access Doors and Frames 04-22
08 32 13 ICU Sliding Glass Doors 01-21
08 33 00 Coiling Doors and Grilles 01-21
08 33 13 Coiling Counter Doors 01-21
08 34 53 Security Doors and Frames 01-21
08 34 59 Vault Doors and Day Gates 01-21
08 35 13.13 Accordion Folding Doors 01-21
08 36 13 Sectional Doors 01-21
08 38 16 Flexible Traffic Doors 01-21
08 41 13 Aluminum-Framed Entrances and Storefronts 01-21
08 42 33 Revolving Door Entrances 01-21
08 44 13 Glazed Aluminum Curtain Walls 04-20
08 51 13 Aluminum Windows 01-21
08 51 13.11 Side-Hinged Aluminum Windows 01-21
08 51 23 Steel Windows 01-21
08 51 69.11 Aluminum Storm Windows 01-21
08 56 19 Pass Windows 01-21
08 56 53 Blast Resistant Windows 01-21
08 56 59 Service and Teller Window Units 01-21
08 56 66 Detention Window Screens 01-21
08 63 00 Metal-Framed Skylights 01-21
08 71 00 Door Hardware 05-22
08 71 13 Automatic Door Operators 01-21
08 71 13.11 Low Energy Power Assist Door Operators 01-21
08 80 00 Glazing 01-21
08 90 00 Louvers and Vents 01-21
DIVISION 09 � FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21
09 06 00 Schedule for Finishes 01-21
09 22 16 Non-Structural Metal Framing 06-18
09 23 00 Gypsum Plastering 01-21
09 24 00 Portland Cement Plastering 01-21
09 26 00 Veneer Plastering 01-21
09 29 00 Gypsum Board 04-20
09 30 13 Ceramic/Porcelain Tiling 01-21
09 51 00 Acoustical Ceilings 12-18
09 54 23 Linear Metal Ceilings 01-21
09 63 13 Brick Flooring 01-21
09 63 40 Stone Flooring 01-21
Buildings #2-5,13 & 14 Demo
01/01/2024Manchester VAMC, New Hampshire
00 01 10 - 5
SECTION NO DIVISION AND SECTION TITLES DATE
09 65 13 Resilient Base and Accessories 01-21
09 65 16 Resilient Sheet Flooring 06-22
09 65 19 Resilient Tile Flooring 05-18
09 66 13 Portland Cement Terrazzo Flooring 01-21
09 66 16 Terrazzo Floor Tile 01-21
09 67 23.20 Resinous Epoxy Base With Vinyl Chip Broadcast (RES 2) 12-21
09 67 23.30 Resinous (Epoxy Resin Composition) Mortar Flooring
(RES-3)
01-21
09.67.23.40 Resinous Poured In Place Resilient Flooring (RES-4) 01-21
09 67 23.50 Resinous Terrazzo Flooring (RES-5) 01-21
09 67 23.60 Resinous Urethane and Epoxy Mortar Flooring (RES-6A and
RES 6B)
01-21
09 68 00 Carpeting 01-21
09 68 21 Athletic Carpeting 01-21
09 69 00 Access Flooring 01-21
09 72 16 Vinyl-Coated Fabric Wall Covering 01-21
09 72 31 Polypropylene Fabric Wall Covering 01-21
09 78 23 Phenolic Interior Wall Paneling 01-21
09 84 33 Sound-Absorbing Wall Units 01-21
09 91 00 Painting 01-21
09 94 19 Multicolor Interior Finishing 01-21
09 96 59 Resinous Specialty Glazed Coating Systems for Walls, Ceilings, Wallboard, and Block CMU (RES-W1, RES-W2)
01-21
DIVISION 10 � SPECIALTIES
10 11 13 Chalkboards and Markerboards 01-21
10 11 23 Tackboards 01-21
10 11 33 Glassboards (Magnetic & Non-Magnetic) 01-21
10 13 00 Directories 01-21
10 14 00 Signage 01-21
10 21 13 Toilet Compartments 01-21
10 21 16 Shower and Dressing Compartments 01-21
10 21 23 Cubicle Curtain Tracks 01-21
10 22 13 Wire Mesh Partitions 01-21
10 22 19 Demountable Partitions 01-21
10 22 26.13 Accordion Folding Partitions 01-21
10 25 13 Patient Bed Service Walls 05-23
10 26 00 Wall and Door Protection 01-21
10 28 00 Toilet, Bath, and Laundry Accessories 01-21
10 44 13 Fire Extinguisher Cabinets 08-18
10 75 00 Flagpoles 01-21
DIVISION 11 � EQUIPMENT
11 05 12 General Motor Requirements for Equipment 01-21
11 12 00 Parking Control Equipment 01-21
11 17 36 Package Transfer Units 01-21
11 26 00 Unit Kitchens 01-21
Buildings #2-5,13 & 14 Demo
01/01/2024Manchester VAMC, New Hampshire
00 01 10 - 6
SECTION NO DIVISION AND SECTION TITLES DATE
11 40 11 Custom Fabricated Food Service Equipment 01-21
11 40 21 Food Service Equipment-Utility Distribution System 01-21
11 41 00 Food Storage Equipment 01-21
11 41 21 Walk-In Coolers and Freezers 01-21
11 44 00 Food Cooking Equipment 01-21
11 48 00 Cleaning and Disposal Equipment 01-21
11 53 13 Laboratory Fume Hoods 01-21
11 53 23 Laboratory Refrigerators 01-21
11 53 53 Biological Safety Cabinets Laminar Airflow Stations 01-21
11 53 61 Custom Fabricated Laboratory Equipment 01-21
11 53 71 Solution Warming Cabinets 01-21
11 71 01 Medical Washing and Sterilizing Equipment 01-21
11 71 02 Laboratory Washing and Sterilizing Equipment 01-21
11 73 00 Ceiling Mounted Patient Lift System 08-20
11 78 00 Mortuary Equipment 01-21
11 78 13 Mortuary Refrigerators 01-21
11 79 13 Hydrotherapy Equipment 01-21
11 82 19 Packaged Incinerators 01-21
DIVISION 12 � FURNISHINGS
12 22 16 Drapery Track and Accessories 01-21
12 24 00 Window Shades 08-17
12 24 21 Lightproof Shades 01-21
12 31 00 Manufactured Metal Casework 01-21
12 32 00 Manufactured Wood Casework 01-21
12 34 00 Manufactured Plastic Casework 01-21
12 35 70.21 Medication Cabinet 01-21
12 36 00 Countertops 12-18
12 56 70.11 Suspended Table 01-21
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-21
13 17 23 Therapeutic Pools 01-21
13 17 23.11 Therapeutic Pool Accessories 01-21
13 19 13 Kennel Enclosures and Gates 01-21
13 21 29 Constant Temperature Rooms 01-21
13 21 49 Audiology Booth 01-21
13 34 19 Metal Building Systems 01-21
13 49 00 Radiation Protection 01-21
DIVISION 14� CONVEYING EQUIPEMENT
14 12 11 Traction and Winding Drum Dumbwaiter 09-23
14 21 00 Traction Elevator � New 09-23
14 21 10 Traction Elevator � Modernization 09-23
14 21 11 Traction Cartlift 09-23
Buildings #2-5,13 & 14 Demo
01/01/2024Manchester VAMC, New Hampshire
00 01 10 - 7
SECTION NO DIVISION AND SECTION TITLES DATE
14 24 00 Hydraulic Elevator � New 09-23
14 24 10 Hydraulic Elevator � Modernization 09-23
14 24 11 Hydraulic Cartlift 09-23
14 91 33 Gravity Soiled Linen Chutes 09-23
14 91 82 Gravity Trash Chutes 09-23
14 92 00 Pneumatic Tube System 09-23
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-16
21 08 00.01 DVA/USACE Projects Commissioning of Fire Suppression
Systems
08-19
21 12 00 Manual Dry Standpipe Systems 06-15
21 13 13 Wet-Pipe Sprinkler Systems 06-15
21 13 16 Dry-Pipe Sprinkler Systems 01-15
21-22-00 Clean Agent Fire Suppression Systems 05-15
21-30-13 Electric-Driven, Fire Pumps 05-15
21-30-16 Diesel-Driven, Fire Pumps 05-15
DIVISION 22 � PLUMBING
22 05 11 Common Work Results for Plumbing 01-23
22 05 12 General Motor Requirements for Plumbing Equipment 09-20
22 05 19 Meters and Gages for Plumbing Piping 09-20
22 05 23 General-Duty Valves for Plumbing Piping 09-20
22 05 33 Heat Tracing for Plumbing Piping 09-20
22 07 11 Plumbing Insulation 09-19
22 08 00 Commissioning of Plumbing Systems 11-16
22 08 00.01 DVA/USACE Projects Commissioning of Plumbing Systems 08-19
22 11 00 Facility Water Distribution 05-21
22 11 23 Domestic Water Pumps 09-15
22 12 16 Facility Elevated, Potable-Water Storage Tanks 09-15
22 13 00 Facility Sanitary and Vent Piping 09-20
22 13 23 Sanitary Waste Interceptors 09-20
22 13 29 Sanitary Sewerage Pumps 09-20
22 13 29.13 Wet-Pit Mounted, Vertical Sewerage Pumps 09-20
22 13 33 Packaged, Submersible Sewerage Pump Units 09-20
22 14 00 Facility Storm Drainage 09-15
22 14 29 Sump Pumps 09-15
22 14 33 Packaged, Pedestal Drainage Pump Units 09-15
22 14 36 Packaged, Submersible, Drainage Pump Units 09-15
22 15 00 General Service Compressed-Air Systems 09-20
22 31 11 Water Softeners 09-15
22 33 00 Electric Domestic Water Heaters 09-20
22 34 00 Fuel-Fired Domestic Water Heaters 09-20
22 35 00 Domestic Water Heat Exchangers 09-20
22 40 00 Plumbing Fixtures 12-22
22 42 26 Commercial Disposers 09-15
22 61 13.74 Dental Compressed-Air Piping 05-23
Buildings #2-5,13 & 14 Demo
01/01/2024Manchester VAMC, New Hampshire
00 01 10 - 8
SECTION NO DIVISION AND SECTION TITLES DATE
22 61 19.74 Dental Compressed-Air Equipment 09-20
22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 05-23
22 62 19.74 Dental Vacuum and Evacuation Equipment 09-15
22 63 00 Gas Systems for Laboratory and Healthcare Facilities 05-23
22 66 00 Chemical-Waste Systems for Laboratory and Healthcare
Facilities
09-20
22 67 19.16 Reverse-Osmosis Water Equipment 09-15
22 67 21 Water Dealkalizing System 09-15
DIVISION 23 � HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 10 Common Work Results for Boiler Plant and Steam
Generation
09-23
23 05 11 Common Work Results for HVAC 03-23
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
03-23
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
03-23
23 05 51 Noise and Vibration Control for Boiler Plant 03-22
23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23
23 05 93.01 DVA/USACE Projects Testing, Adjusting, and Balancing for HVAC
11-21
23 07 11 HVAC and Boiler Plant Insulation 02-20
23 08 00 Commissioning of HVAC Systems 03-23
23 08 00.01 DVA/USACE Projects Commissioning of HVAC Systems 08-19
23 08 11 Demonstrations and Tests for Boiler Plant 04-20
23 09 11 Instrumentation and Control for Boiler Plant 04-23
23 09 23 Direct-Digital Control System for HVAC 03-23
23 10 00 Facility Fuel Systems 04-20
23 11 23 Facility Natural-Gas Piping 04-20
23 21 11 Boiler Plant Piping Systems 08-23
23 21 13 Hydronic Piping 03-23
23 21 23 Hydronic Pumps 03-23
23 22 13 Steam and Condensate Heating Piping 08-23
23 22 23 Steam Condensate Pumps 04-20
23 23 00 Refrigerant Piping 03-23
23 25 00 HVAC Water Treatment 03-23
23 31 00 HVAC Ducts and Casings 03-23
23 34 00 HVAC Fans 03-23
23 36 00 Air Terminal Units 03-23
23 37 00 Air Outlets and Inlets 03-23
23 38 13 Commercial-Kitchen Hoods 03-23
23 40 00 HVAC Air Cleaning Devices 03-23
23 50 11 Boiler Plant Mechanical Equipment 03-22
23 51 00 Breechings, Chimneys, and Stacks 04-20
23 52 25 Low-Pressure Water Heating Boilers 09-23
23 52 28 Low-Pressure Steam Boilers 09-23
23 52 33 Water Tube Boilers 09-23
23 52 39 Fire Tube Boilers 09-23
Buildings #2-5,13 & 14 Demo
01/01/2024Manchester VAMC, New Hampshire
00 01 10 - 9
SECTION NO DIVISION AND SECTION TITLES DATE
23 56 00 Solar Energy Heating System 03-23
23 57 33 Geothermal Energy � Direct Use 03-23
23 64 00 Packaged Water Chillers 03-23
23 65 00 Cooling Towers 03-23
23 72 00 Air-to-Air Energy Recovery Equipment 03-23
23 73 00 Indoor Central-Station Air-Handling Units 03-23
23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 03-23
23 81 00 Decentralized Unitary HVAC Equipment 03-23
23 81 23 Computer-Room Air-Conditioners 03-23
23 81 43 Air-Source Unitary Heat Pumps 03-23
23 81 46 Water-Source Unitary Heat Pumps 03-23
23 81 49 Ground-Source Heat Pump 03-23
23 82 00 Convection Heating and Cooling Units 03-23
23 82 16 Air Coils 03-23
23 84 00 Humidity Control Equipment 03-23
DIVISION 25 � INTEGRATED AUTOMATION
25 10 10 Advanced Utility Metering System 02-10
DIVISION 22 - PLUMBING
22 05 11 Common Work Results for Plumbing 01-23
DIVISION 26 � ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22
26 05 13 Medium-Voltage Cables 11-22
26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22
26 05 26 Grounding and Bonding for Electrical Systems 11-22
26 05 33 Raceway and Boxes for Electrical Systems 11-22
26 05 36 Wireways for Radiology Equipment 11-22
26 05 39 Underfloor Raceways for Electrical Systems 11-22
26 05 41 Underground Electrical Construction 11-22
26 05 73 Overcurrent Protective Device Coordination Study 11-22
26 08 00 Commissioning of Electrical Systems 11-22
26 08 00.01 DVA/USACE Projects Commissioning of Electrical Systems 08-19
26 09 23 Lighting Controls 11-22
26 11 16 Secondary Unit Substations 11-22
26 12 19 Pad-Mounted, Liquid-Filled, Medium-Voltage Transformers 11-22
26 13 13 Medium-Voltage Circuit Breaker Switchgear 11-22
26 13 16 Medium-Voltage Fusible Interrupter Switches 11-22
26 20 11 Isolated Power Systems 11-22
26 22 00 Low-Voltage Transformers 11-22
26 23 00 Low-Voltage Switchgear 11-22
26 23 13 Generator Paralleling Controls 11-22
26 24 13 Distribution Switchboards 11-22
26 24 16 Panelboards 11-22
26 24 19 Motor Control Centers 11-22
26 25 11 Busways 11-22
Buildings #2-5,13 & 14 Demo
01/01/2024Manchester VAMC, New Hampshire
00 01 10 - 10
SECTION NO DIVISION AND SECTION TITLES DATE
26 26 00 Power Distribution Units for Static Uninterruptible
Power Systems
11-22
26 27 26 Wiring Devices 11-22
26 29 11 Motor Controllers 11-22
26 29 21 Enclosed Switches and Circuit Breakers 11-22
26 32 13 Engine Generators 11-22
26 33 53 Static Uninterruptible Power Supply 11-22
26 35 26 Harmonic Filters 11-22
26 36 23 Automatic Transfer Switches 11-22
26 41 00 Facility Lightning Protection 11-22
26 42 00 Cathodic Protection 11-22
26 43 13 Surge Protective Devices 11-22
26 51 00 Interior Lighting 11-22
26 55 71 Medical and Surgical Lighting Fixtures 11-22
26 56 00 Exterior Lighting 11-22
DIVISION 27 � COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 05 61 Leased Space, Communication Equipment and Systems 06-15
27 08 00 Commissioning of Communications Systems 11-16
27 08 00.01 DVA/USACE Projects Commissioning of Communications
Systems
08-19
27 10 00 Control, Communication and Signal Wiring 06-15
27 11 00 Telecommunications Room Fittings 06-15
27 15 00 Communications Structured Cabling 01-16
27 31 00 Voice Communications Switching and Routing Equipment 06-15
27 31 31 Voice Communications Switching and Routing Equipment -
Extension
06-15
27 32 41 Two-Way Radio Equipment and Systems 10-18
27 41 31 Master Antenna Television Equipment and Systems 06-15
27 51 16 Public Address and Mass Notification Systems 11-22
27 51 23 Intercommunications and Program Systems 06-15
27 52 23 Nurse Call and Code Blue Systems 10-18
27 52 41 Miscellaneous Medical Systems 06-15
27 53 19 Distributed Radio Antenna (Within Building) Equipment and System
10-18
DIVISION 28 � ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 08 00 Commissioning of Electronic Safety and Security Systems 11-16
Buildings #2-5,13 & 14 Demo
01/01/2024Manchester VAMC, New Hampshire
00 01 10 - 11
SECTION NO DIVISION AND SECTION TITLES DATE
28 08 00.01 DVA/USACE Projects Commissioning of Electronic Safety and Security Systems
08-19
28 13 00 Physical Access Control System 10-11
28 13 16 Physical Access Control System and Database Management 09-11
28 13 53 Security Access Detection 09-11
28 16 00 Intrusion Detection System 10-11
28 23 00 Video Surveillance 09-11
28 26 00 Electronic Personal Protection System 09-11
28 31 00 Fire Detection and Alarm 10-11
28 52 31 Emergency Call System 06-15
DIVISION 31 � EARTHWORK
31 20 00 Earthwork 08-23
31 20 11 Earthwork (Short Form) 10-12
31 23 19 Dewatering 10-12
31 23 23.33 Flowable Fill 10-12
31 32 23 Pressure Grouting Soil Stabilization 10-12
31 62 00 Driven Piles 10-12
31 63 16 Auger Cast Grout Piles 10-12
31 63 26 Drilled Caissons 10-12
DIVISION 32 � EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 12 16 Asphalt Paving 09-15
32 14 16 Brick Unit Paving 08-16
32 17 23 Pavement Markings 08-16
32 31 13 Chain Link Fences and Gates 06-18
32 31 40 High Security Fences and Gates 08-16
32 84 00 Planting Irrigation 08-16
32 90 00 Planting 08-16
DIVISION 33 � UTILITIES
33 08 00 Commissioning of Site Utility Systems 11-16
33 08 00.01 DVA/USACE Projects Commissioning of Site Utility
Systems
08-19
33 10 00 Water Utilities 03-17
33 30 00 Sanitary Sewer Utilities 06-13
33 40 00 Storm Sewer Utilities 12-17
33 46 13 Foundation Drainage 10-11
33 51 00 Natural-Gas Distribution 10-11
33 63 00 Steam Energy Distribution 09-17
DIVISION 34 � TRANSPORTATION
34 71 13 Passive Vehicle Barriers 04-18
34 75 13.13 Active Vehicle Barriers 08-16
Buildings #2-5,13 & 14 Demo
01/01/2024Manchester VAMC, New Hampshire
00 01 10 - 12
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 48 � Electrical Power Generation
48 14 00 Solar Energy Electrical Power Generation System 07-23
48 15 00 Wind Energy Electrical Power Generation System 07-23
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 1015-1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
GENERAL
GI001 COVER SHEET
GI002 SATELLITE PLAN VIEW - PHOTO
GR101 EXISTING CONDITIONS BLDG 2 ELEVATIONS
GR102 EXISTING CONDITIONS BLDG 2 PHOTOS
GR103 EXISTING CONDITIONS BLDG 2 PHOTOS
GR201 EXISTING CONDITIONS BLDG 3 ELEVATIONS
GR202 EXISTING CONDITIONS BLDG 3 PHOTOS
GR301 EXISTING CONDITIONS BLDG 4 ELEVATIONS
GR302 EXISTING CONDITIONS BLDG 4 PHOTOS
GR401 EXISTING CONDITIONS BLDG 5 ELEVATIONS
GR402 EXISTING CONDITIONS BLDG 5 PHOTOS
GR403 EXISTING CONDITIONS BLDG 5 PHOTOS
GR501 EXISTING CONDITIONS BLDG 13
GR502 EXISTING CONDITIONS BLDG 13 PHOTOS
GR601 EXISTING CONDITIONS BLDG 14
GR602 EXISTING CONDITIONS BLDG 14 PHOTOS
HAZARDOUS MATERIALS
HA101 HAZARDOUS MATERIALS ASBESTOS BUILDING 2
HA102 HAZARDOUS MATERIALS ASBESTOS BUILDING 3
HA103 HAZARDOUS MATERIALS ASBESTOS BUILDING 4
HA104 HAZARDOUS MATERIALS ASBESTOS BUILDING 5
HA105 HAZARDOUS MATERIALS ASBESTOS BUILDING 13
HA106 HAZARDOUS MATERIALS ASBESTOS BUILDING 14
HL101 HAZARDOUS MATERIALS LEAD BUILDING 2
HL102 HAZARDOUS MATERIALS LEAD BUILDING 3
HL103 HAZARDOUS MATERIALS LEAD BUILDING 3
HL104 HAZARDOUS MATERIALS LEAD BUILDING 4
HL105 HAZARDOUS MATERIALS LEAD BUILDING 4
HL106 HAZARDOUS MATERIALS LEAD BUILDING 5
HL107 HAZARDOUS MATERIALS LEAD BUILDING 5
HL108 HAZARDOUS MATERIALS LEAD BUILDING 13
HL109 HAZARDOUS MATERIALS LEAD BUILDING 14
SURVEY/MAPPING
VU101 TOPOGRAPHICAL SURVEY
CIVIL
C-001 CIVIL ABBREVIATIONS, SYMBOLS, AND GENERAL NOTES
C-002 STORMWATER POLLUTION PREVENTION PLAN
C-003 EXISTING UTILITY PLAN (FOR REFERENCE ONLY)
CD401 SITE DEMOLITION
CD402 HAZMAT STORAGE TRAILER RELOCATION
CD501 CIVIL DEMOLITION AND EROSION CONTROL DETAILS AND NOTES
CD502 CIVIL DEMOLITION AND EROSION CONTROL DETAILS AND NOTES
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 1015-2
CG401 FINISH GRADE PLAN
CU401 SANITARY AND STORMWATER DEMOLITION PLANS
CU402 ENLARGED ELECTRIC, TELEPHONE UTILITY PLANS EXISTING CONDITIONS,
DEMOLITION
CU403 ENLARGED OHW, GAS UTILITY PLANS EXISTING CONDITIONS, DEMOLITION
CU404 ENLARGED WATER UTILITY PLANS EXISTING CONDITIONS, DEMOLITION
LANDSCAPE
LP401 LANDSCAPE DEMO PLANS
FIRE PROTECTION
FA101 FIRE ALARM SYSTEM DEMOLITION
- - - END - - -
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 15 List of Drawing Sheets 05-20
00 11 21 Request for Proposal to Design Build 09-21
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 32 16.01 Architectural and Engineering CPM Schedules 03-20
01 32 16.13 Network Analysis Schedules � Major Construction Project
Design-Bid-Build
05-22
01 32 16.15 Project Schedules (Small Projects � Design/Bid/Build 11-21
01 32 16.16 Network Analysis Schedules (Design-Build Only) 05-22
01 32 16.17 Network Analysis Schedules � Major Design/Build
Projects
06-19
01 33 23 Shop Drawings, Product Data, and Samples 02-23
01 35 26 Safety Requirements 10-22
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-21
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 06-21
01 57 19 Temporary Environmental Controls 01-21
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 04-22
01 81 13 Sustainable Construction Requirements 10-17
01 81 13.02 Sustainability Certification Requirements � LEED V4
BD+C: New Construction and Major Renovation
04-23
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 1015-3
SECTION NO DIVISION AND SECTION TITLES DATE
01 81 13.03 Sustainability Certification Requirements � LEED V4
BD+C: Healthcare
04-23
01 81 13.12 Sustainability Certification Requirements � LEED V4.1
BD+C: New Construction and Major Renovation
04-23
01 81 13.13 Sustainability Certification Requirements � LEED V4.1:
Healthcare
04-23
01 81 13.14 Sustainability Certification Requirements � LEED V4.1
BD+C: Data Centers
04-23
01 81 13.15 Sustainability Certification Requirements � LEED V4.1
BD+C: Warehouses and Distribution Centers
04-23
01 81 13.21 Sustainability Certification Requirements � GREEN
GLOBES
01-21
01 91 00 General Commissioning Requirements 04-22
01 91 00.01 DVA/USACE Projects General Commissioning Requirements 08-19
DIVISION 02 � EXISTING CONDITIONS
02 21 13 Site Surveys 01-21
02 41 00 Demolition 08-17
02 65 00 Underground Storage Tank Removal 01-21
02 82 11 Traditional Asbestos Abatement 01-21
02 82 13.13 Glovebag Asbestos Abatement 01-21
02 82 13.19 Asbestos Floor Tile and Mastic Abatement 01-21
02 82 13.21 Asbestos Roofing Abatement 01-21
02 82 13.31 Asbestos Transite Abatement 01-21
02 82 13.41 Asbestos Abatement for Total Demolition Project 01-21
02 83 33.13 Lead-Based Paint Removal and Disposal 01-21
DIVISION 03 � CONCRETE
03 23 00 Stressing Tendons 01-21
03 30 00 Cast-in-Place Concrete 01-21
03 30 53 (Short-Form) Cast-in-Place Concrete 01-21
03 37 13 Shotcrete 01-21
03 41 13 Precast Concrete Hollow Core Planks 01-21
03 41 33 Precast Structural Pretensioned Concrete 01-21
03 45 00 Precast Architectural Concrete 01-21
03 51 13 Cementitious Wood Fiber Decks 01-21
03 51 16 Gypsum Concrete Roof Decks 01-21
03 52 00 Lightweight Concrete Roof Insulation 01-21
03 55 11 Gypsum Concrete Floor Decks 01-21
DIVISION 04 � MASONRY
04 01 00 Maintenance of Masonry 01-21
04 05 13 Masonry Mortaring 10-17
04 05 16 Masonry Grouting 01-21
04 20 00 Unit Masonry 08-17
04 72 00 Cast Stone Masonry 01-21
Buildings #2-5,13 & 14
Specifications
100% Bid Documents
02-02-24
00 01 1015-4
SECTION NO DIVISION AND SECTION TITLES DATE
DIVISION 05 � METALS
05 12 00 Structural Steel Framing 11-18
05 21 00 Steel Joist Framing 11-18
05 31 00 Steel Decking 01-21
05 36 00 Composite Metal Decking 01-21
05 40 00 Cold-Formed Metal Framing 01-21
05 50 00…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .