01320 Const Prog Doc 100.doc

DOC document 44 KB Posted

Attached to
Construct Sidewalks at Rocky Mountain Laboratory, Hamilton, Montana
Solicitation number
09-SOL-00011
Issued by

About this file

Attachment J-1 - file 9 Spec Section 01320

View the file

Other files

File Type Posted
01700 Execution Requirements.doc DOC document
RML Interim Sidewalks Drawings.pdf PDF
01305 SECURITY.doc DOC document
SF 30 Amendment 1.pdf PDF
01700 Execution Requirements 100 —
RML Interim Sidewalks —
01700 Execution Requirements 100 —
RML Interim Sidewalks —
01700 Execution Requirements 100 —
RML Interim Sidewalks —
SF 24 Bid Bond.pdf PDF
01770 ADG CLOSE OUT PROCEDURES 100.doc DOC document
Interim Sidewalks Specifications.pdf PDF
01420 References 100 —
Specification Index 1 —
01140 Work Restrictions 100.doc DOC document
01700 Execution Requirements 100 —
2009.07.28 Wage Determination.doc DOC document
01500 TEMP FACILITIES CONTROL 100.doc DOC document
SF 25B Bond continuation form.pdf PDF
SF 1442 Solicitation.pdf PDF
01330 SUBMTL PROCEDURES 100.doc DOC document
01310 Proj Mngmt Coor 100.doc DOC document
SF 25 Performance Bond.pdf PDF
01270 Unit Prices 100 —
01400 Quality Requirements 100 —
01100 Summary 100 —
Section 02751 - Cement Concrete Pavement rev 5-09.doc DOC document
SPEC COVER —
RML Interim Sidewalks —
Section 02300 - Earthwork —
SF25A Payment Bond.pdf PDF
01731 Cutting Patching 100 —
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

04-436

08-827A

SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including Sections A through M of the Contract and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's Construction Schedule.

2. Construction photographs.

B. Related Sections include the following:

1. Division 1 Section "Project Management and Coordination" for submitting and distributing meeting and conference minutes.

2. Division 1 Section "Submittal Procedures" for submitting schedules and reports.

3. Division 1 Section "Quality Requirements" for submitting a schedule of tests and inspections.

4. Division 1 Section "Closeout Procedures" for submitting photographic negatives as Project Record Documents at Project closeout.

1.3 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor activity is an activity that must be completed before a given activity can be started.

B. Event: The starting or ending point of an activity.

C. Float: The measure of leeway in starting and completing an activity.

1. Float time belongs to Government.

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the following activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

D. Milestone: A key or critical point in time for reference or measurement.

1.4 SUBMITTALS

A. Preliminary Construction Schedule: Submit two printed copies; one a single sheet of reproducible media, and one a print.

B. Contractor's Construction Schedule: Submit two printed copies of initial schedule, one a reproducible print and one a blue- or black-line print, large enough to show entire schedule for entire construction period.

C. Construction Photographs: Submit color prints of each photographic view as part of the Agenda package provided at the monthly coordination meeting.

1. Format: Printouts of digital photographs are preferred. A maximum of four images to be printed on one 8 -1/2” x 11” sheet of photographic quality paper.

2. Identification: Provide a caption at the bottom of each print, with the following information:

a. Date photograph was taken.

b. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.

3. Electronic files: Submit electronic files on CD as a Project Record Document or when requested. Identify date photographs were taken.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.

B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from parties involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

C. Auxiliary Services: Cooperate with photographer and provide auxiliary services requested, including access to Project site and use of temporary facilities including temporary lighting.

PART 2 - PRODUCTS

2.1 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Procedures: Comply with procedures contained in AGC's "Construction Planning & Scheduling."

B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final Completion.

1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

C. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work. Comply with the following:

1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically allowed by Architect.

2. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

3. Submittal Review Time: Include review and resubmittal times indicated in Division 1 Section "Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's Construction Schedule with Submittals Schedule.

4. Startup and Testing Time: Include not less than 10 days for startup and testing.

5. Substantial Completion: Indicate completion in advance of date established for Substantial Completion, and allow time for Architect's administrative procedures necessary for certification of Substantial Completion.

D. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.

1. Products Ordered in Advance: Include a separate activity for each product. Include delivery date indicated in Division 1 Section "Summary." Delivery dates indicated stipulate the earliest possible delivery date.

2. Owner-Furnished Products: Include a separate activity for each product. Include delivery date indicated in Division 1 Section "Summary." Delivery dates indicated stipulate the earliest possible delivery date.

3. Work Stages: Indicate important stages of construction for each major portion of the Work, including, but not limited to, the following:

a. Subcontract awards.

b. Submittals.

c. Purchases.

d. Mockups.

e. Fabrication.

f. Sample testing.

g. Deliveries.

h. Installation.

i. Tests and inspections.

j. Adjusting.

k. Curing.

l. Startup and placement into final use and operation.

E. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion.

F. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall project schedule.

2.2 PRELIMINARY CONSTRUCTION SCHEDULE

A. Bar-Chart Schedule: Submit preliminary horizontal bar-chart-type construction schedule within seven days of date established for the Notice to Proceed.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line. Outline significant construction activities for first 60 days of construction. Include skeleton diagram for the remainder of the Work and a cash requirement prediction based on indicated activities.

2.3 CONTRACTOR'S CONSTRUCTION SCHEDULE (GANTT CHART)

A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal Gantt-chart-type, Contractor's Construction Schedule within 30 days of date established for the Notice to Proceed. Base schedule on the Preliminary Construction Schedule and whatever updating and feedback was received since the start of Project.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.

1. For construction activities that require 3 months or longer to complete, indicate an estimated completion percentage in 10 percent increments within time bar.

PART 3 - EXECUTION

3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.

1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.

2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.

3. As the Work progresses, indicate Actual Completion percentage for each activity.

B. Distribution: Distribute copies of approved schedule to the Contracting Officer, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.

1. Post copies in Project meeting rooms and temporary field offices.

2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.

3.2 CONSTRUCTION PHOTOGRAPHS

ARE THESE WARRANTED ON THIS SMALL PROJECT?

A. Photographic Film: Use digital camera.

B. Date Stamp: Unless otherwise indicated, date and time stamp each photograph as it is being taken so stamp is integral to photograph.

C. Preconstruction Photographs: Before starting construction, take at least 36 color photographs of Project site and surrounding properties from different vantage points, as directed by Contracting Officer. Show existing conditions adjacent to property.

1. The Contractor is to document the condition of the Work prior to beginning demolition. Damaged items will be considered damaged by the Contractor if their condition is not documented prior to beginning demolition work when reasonably believed damage occurred from construction activity. This documentation must be presented to the Contracting Officer prior to commencement of the demolition work.

D. Periodic Construction Photographs: Take a minimum of 24 color photographs monthly, coinciding with cutoff date associated with each Application for Payment. Photographer shall select vantage points to best show status of construction and progress since last photographs were taken.

1. Field Office Prints: Retain one set of prints of periodic photographs in field office at Project site, available at all times for reference. Identify photographs the same as for those submitted to Contracting Officer.

END OF SECTION 01320