Attachmetn J-1 - file 4 Spec Section 01100
Text of this file
04-436
08-827A
SECTION 01100 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including Sections A through M of the Contract and other Division 1 Specification Sections, apply to this Section.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Identification: Project consists of the removing and replacing the existing chillers with centrifugal chillers and associated work.
1. Project Location: NIH-NIAID Rocky Mountain Laboratories, 903 South Fourth Street, Hamilton, MT 59840.
2. Owner: National Institutes of Health, 9000 Rockville Pike, Bethesda, Maryland, 20892.
B. Architect Identification: The Contract Documents, May 28, 2009, were prepared for Project by Architects Design Group PC.
C. The Work consists of work as shown and specified on the Contract Documents.
a. Concrete Sidewalks.
b. Composite tile paving system
c. Paint striping and paint signs as indicated.
d. Concrete dying as indicated on the drawings.
e. Chain link fence with gate.
1.3 CONTRACT
A. Project will be constructed under a general construction contract.
1.4 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
B. Concurrent Work: Government may award separate contract(s) for construction operations at the Project site. Those operations will be conducted simultaneously with work under this Contract.
1. Coordinate work with the Contracting Officer to minimize disruptions to the Government and other Contractors that may concurrently be on site.
1.5 WORK SEQUENCE
A. The Work shall be conducted in 1 phase.
1.6 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the 16-division format and CSI/CSC's "MasterFormat" numbering system.
1. Section Identification: The Specifications use section numbers and titles to help cross-referencing in the Contract Documents. Sections in the Project Manual are in numeric sequence; however, the sequence is incomplete. Consult the table of contents at the beginning of the Project Manual to determine numbers and names of sections in the Contract Documents.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
1.7 MISCELLANEOUS PROVISIONS
A. The Government’s equipment shall be protected from the Contractor’s construction activities at all times.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
END OF SECTION 01100
RML INTERIM SIDEWALKS ( NIH-NIAID RML ( HAMILTON, MT
SUMMARY 01100 - 2
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .