This is a Special Notice regarding guarantee period services for an elevator construction contract at the Garland VA Medical Center. The solicitation requires offerors to provide one year of post-construction maintenance and support services for elevator systems following project completion.

Key requirements include: guarantee period services specifications are detailed in specification sections 14 21 10 and 14 24 10; a Service Contract Act wage determination applies to all employees performing work under this portion of the contract; upon award, the contractor must submit a detailed cost breakdown with separate line-item pricing for guarantee period services stated in both yearly and monthly totals, subject to Contracting Officer approval before first progress payment; all elevator maintenance work must be performed by Certified Elevator Mechanics and Apprentices; performance and payment bonds equal to 100% of contract price are required with coverage for guarantee period services, with bond values adjusted downward after construction completion but maintaining sufficient coverage through the full one-year service term; payment requests must be submitted as certified invoices, invoiced monthly or quarterly in arrears; the construction performance period is 512 calendar days from notice to proceed, but contract closeout is withheld until all guarantee period services are completed; and guarantee period services commence after completion and acceptance of the Garland Elevator construction project. The document includes a sample Partial Final Payment/Release document and post-construction maintenance schedule template identifying traction and hydraulic elevator systems with 12-month maintenance periods at specified monthly rates.

View the file

Other files

File Type Posted
0005 - VA Garland 2026 Elevator Inspection Reports.pdf PDF
01 - Specifications_6-5-2026.pdf PDF
36C77626R0061 0005.pdf PDF
0005 - Responses to Tech Questions - 6-5-26.pdf PDF
36C77626R0061 0004.pdf PDF
0004 - Responses to Tech Questions - 5-29-26.pdf PDF
0003 - Site Visit Sign-in Sheet 5-15-26.pdf PDF
0003 - SCA Wages - Dallas County - 05-13-2026.pdf PDF
0003 - DBA Wages - Dallas County - 05-18-2026.pdf PDF
36C77626R0061 0003.pdf PDF
36C77626R0061 0002.pdf PDF
0002 - Site Visit Campus Maps.pdf PDF
0002 - Site Visit Instructions.pdf PDF
36C77626R0061 0001.pdf PDF
0001 - Site Visit Sign-in Sheet 4-23-26.pdf PDF
0001 - SCA Wages - Dallas County - 04-29-2026.pdf PDF
12 - Site Visit Instructions.pdf PDF
14 - Project Information Sheet.docx DOCX document
RFP 36C77626R0061 - 4-14-26.pdf PDF
05 - Asbestos Survey Report.pdf PDF
08 - DBA Wages - Dallas County - 01-02-2026.pdf PDF
09 - SCA Wages - Dallas County - 12-03-2025.pdf PDF
11 - Division Cost Breakdown.xlsx XLSX spreadsheet
15 - PPQ.docx DOCX document
01 - Specifications_4-9-2026.pdf PDF
04 - Drawings.pdf PDF
06 - SAFETY PIN PCRA-ICRA.pdf PDF
10 - 852.219-75 Limitations on Subcontracting.pdf PDF
13 - Site Visit Campus Maps.pdf PDF
02 - Supplement to Spec Section 01 00 00.pdf PDF
03 - Narrative.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIAL NOTICE

GUARANTEE PERIOD SERVICES

A. Offerors are advised that this solicitation and any resulting contract contain guarantee period services. The requirements of these services are listed in specification sections 14 21 10 and 14 24 10.

B. A Service Contract Act wage determination has been included in the solicitation.

Payment for employees performing work under that portion of any resulting contract shall be in accordance with the wage determination and/or any amendments thereto.

C. Upon award of a contract, the contractor will be required to submit a schedule of costs/values with a cost breakdown of the branches of work. This breakdown will include a line-item cost for the guarantee period services portion of the contract for each system. The cost must state both the yearly total and the monthly total cost for the services. The cost must accurately reflect the current market rate for these services and must be approved by the Contracting Officer prior to the first progress payment being made.

D. Elevator maintenance work must be performed by Certified Elevator Mechanics and Apprentices.

E. Performance and payment bonds will be required in the amount of 100% of the contract price upon award. The bonds must include coverage for the guarantee period services portion of the contract. Upon completion of the actual construction, the value of the bonds will be adjusted downward for this portion of the contract but must maintain enough bonding to cover this portion of the contract through the full 1 year of service, following complete acceptance of the entire construction project.

F. Requests for payment for the guarantee period services are to be in the form of a certified invoice and may be invoiced monthly or quarterly in arrears. Payments will be made upon receipt and certification of the invoice in accordance with the appropriate payment clause.

G. The performance period (completion time) for the construction portion of the contract is 512 calendar days after issuance of the notice to proceed. However, the contract will not be closed out until ALL required guarantee period services have been provided.

H. The term of the guarantee period services commences after completion and acceptance of the Garland Elevator construction project.

I. The following pages contain a sample final payment/release document.

(Sample) PARTIAL FINAL PAYMENT / RELEASE DOCUMENT

Partial Final Payment and Release of Claims to Contract No. _________________, dated ________________, for ______________________________, at the Garland VA Medical Center.

1. For and in consideration of payments heretofore made for construction services, and payment of $_______________ [state the final amount of the construction contract, subtracting out the money to be held for payment of the guarantee period services] for performance of the above contract, the undersigned hereby releases and discharges the United States of America from all existing and future liabilities, obligations and claims whatsoever under or arising out of said contract for construction services, except for the guarantee period services as set forth below, and the following [list all claims here; if none, so state]:

2. Upon payment of $_______________ [fill in figure stated above] for construction services, all obligations of the contractor to perform further services and all obligations of the Government to make further payments shall cease with the exception of rights and liabilities associated with defects, guaranties, warranties, guarantee period services, or any excepted items as set forth above, relating to any activities or component parts furnished to the Government under the contract or agreement.

3. The Government agrees to pay the Contractor $_______________ [state the total amount withheld for payment of the guarantee period services] for guarantee period services to be performed during the maintenance schedule. Payment will be made in arrears pursuant to the schedule noted below or in the contract, upon satisfactory performance and presentation of a properly executed invoice. Post-contract guarantee period services shall commence upon acceptance of the installation of the warranted equipment by the Government as set forth in the contract.

(Sample) POST-CONSTRUCTION CONTRACT MAINTENANCE SCHEDULE

SYSTEM / EQUIPMENT RATE

A. TRACTION ELEVATORS 12 months @ $_____________ per month

B. HYDRAULIC ELEVATORS 12 months @ $_____________ per month

Accepted on: ________________

4. Upon payment of the last payment for each of the systems covered by guarantee period services, all obligations of the contractor to perform further services and all obligations of the Government to make further payments shall cease with the exception of rights and liabilities associated with defects, guaranties, or warranties relating to any activities or component parts furnished to the Government under the contract or agreement.

Contracting Officer Contractor