01770_Project_Cleanup_2026.pdf

PDF 91 KB Posted

Attached to
Urgent Repairs, Rehabilitation, and/or Replacement of Water and Wastewater Assets
Solicitation number
115581
Issued by
Prince George's County, Maryland

About this file

This is a Standard Specifications Section 01770 document for Project Cleanup issued by the Washington Suburban Sanitary Commission (WSSC Water) in Maryland, establishing requirements for cleanup, restoration, and disposal activities on water and wastewater infrastructure projects. The specifications require contractors to maintain continuous construction cleanup throughout project execution, removing mud, oil, grease, soil, debris, and excess materials to ensure safe job sites and prevent property damage. Final cleanup must be performed immediately before written request for final inspection and include specific surface treatments such as washing and polishing glass, removing marks from painted surfaces, scrubbing exposed slabs with detergent, hosing down asphalt paving, and cleaning aluminum per manufacturer recommendations. Contractors must restore and restabilize all disturbed areas including staging areas, construction strips, access roads, and areas within acquired right-of-way, following the Restoration Schedule on drawings and performing seeding, sodding, and paving when seasonal conditions permit. All temporary construction facilities must be disassembled and removed, with particular attention to preserving public and private signs, markers, guardrails, and fences in their existing condition unless written permission is obtained for removal and restoration.

The specifications establish that all cleanup, restoration, and disposal costs are considered incidental to the contract and will not be measured separately for payment. Contractors must dispose of construction waste and excess materials only in authorized County disposal areas or areas covered by current grading or sediment control permits, with three copies of grading permits required before use of any disposal site. Any materials or waste disposed of in unauthorized areas must be removed by the contractor at no cost to WSSC Water, and the affected area must be restored to its pre-disturbance condition. Materials determined by the Engineer to be unsuitable or non-compliant with contract documents must be removed from the site and disposed of in approved areas. The document applies to WSSC Water's Indefinite Delivery/Indefinite Quantity (IDIQ) and requirements contract for urgent repairs, rehabilitation, and replacement of water and wastewater assets throughout Prince George's and Montgomery Counties, Maryland.

View the file

Other files

File Type Posted
Urgent_Repairs,_Rehabilitation,_and_or_Replacement_of_Water_and_Wastewater_Assets_(Addendum_#7_Revision).pdf PDF
Prince_George's_County_Wage_Determinatio.pdf PDF
Montgomery_County_Wage_Determination_8.25.26.pdf PDF
Exhibit_A_-_Company_Experience_Statement.pdf PDF
Section_VI_-_Corrosion_Details.pdf PDF
Section_VIII_-_Sediment_Control_Details.pdf PDF
WSSC_Construction_IDIQ_Terms_and_Conditions.pdf PDF
OSHA_Recordkeeping_Forms_(PDF_Fillable).pdf PDF
Section_IV_-_Water_Details.pdf PDF
Section_III_-_Sewer_Details.pdf PDF
Section_II_-_Miscellaneous_Details.pdf PDF
SCENARIO_2_Watermain_Replacement_Pkg_R.pdf PDF
SCENARIO_1_Valve_Replacement_Pkg_R.pdf PDF
SCENARIO_3_Sewer_Replacement_and_SHC_Pkg_R.pdf PDF
Section_I_-_General_Notes_0.pdf PDF
03300_Cast-in-Place_Concrete_2026.pdf PDF
02958_Pipe_Bursting_2026.pdf PDF
13110_Cathodic_Protection_2026.pdf PDF
04200_Masonry_2026.pdf PDF
02510_Water_Distribution_System_2026.pdf PDF
05500_Metal_Fabrications_2026.pdf PDF
Section_VII_-_Pressure_Sewer.pdf PDF
03400_Precast_Concrete_Underground_Structures_2026.pdf PDF
Section_IX_-_Procurment_and_Manufacturing_Details_(1).pdf PDF
02315_Earthwork_for_Pipeline_Construction_2026.pdf PDF
02955_Sewer_Mains_Lateral_Rehabilitation_by_Lining_2026.pdf PDF
13112_Impressed_Current_Cathodic_Protection_for_Water_Sewer_Pipelines_2026.pdf PDF
02957_Sewer_Manhole_Rehabilitation_2026.pdf PDF
02530_Sanitary_Sewage_System_2026.pdf PDF
02960_Temporary_Bypass_Pumping_System_2026.pdf PDF
02920_Lawns-Grasses_2026.pdf PDF
02370_Slope-Watercourse_Protection_2026.pdf PDF
02441_Microtunneling_2026.pdf PDF
Sol_Urgent_Repairs_Exmaple_Invoice.xlsx XLSX spreadsheet
01330_Submittal_Procedures_2026.pdf PDF
02820_Fences-Gates_2026.pdf PDF
02930_Exterior_Plants_2026.pdf PDF
02950_Paving_Requirements_2026.pdf PDF
02533_Pressure_Sewer_System_2026.pdf PDF
02956_CCTV_Inspection_of_Sewer_Mains,_Manholes_and_Laterals_2026.pdf PDF
02959_Sewer_Main_and_Lateral_Connection_Sealing_2026.pdf PDF
02230_Site_Clearing_2026.pdf PDF
02512_Cleaning-Lining_Water_Mains_2026.pdf PDF
ESC_Minor_Utility_Permit,_Health_and_Safety_Qualification_Questionaire,_and_Example_Health_and_Safety_Plan_outline.pdf PDF
02510_Water_Distribution_System_Contractor_Furnishes_All_Materials_2026.pdf PDF
02511_Chlorination_and_Dechlorination_2026.pdf PDF
02446_Horiz_Directional_Drilling_2026.pdf PDF
01500_Temp_Facilities_Controls_2026.pdf PDF
02445_Boring-Jacking_2026.pdf PDF
01110_Summary_of_Work_2026.pdf PDF
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01770-1 2026

STANDARD SPECIFICATIONS

SECTION 01770

PROJECT CLEANUP

PART 1 GENERAL

1.1 DESCRIPTION

A. Section includes requirements for cleanup, restabilization restoration and disposal to maintain a safe and well-kept job site and properly repair disturbed areas.

1.2 CLEANUP

A. Proceed with construction cleanup as construction progresses.

1. Remove mud, oil, grease, soil, gravel, trash, scrap, debris, and excess materials that are unsightly or may cause accidents to persons or properties.

2. Remove water from floor areas where electrical power tools are to be used and prevent stains on concrete that will be exposed in finish work.

3. Select and employ cleaning materials and equipment with care to avoid scratching, marring, defacing, staining, or discoloring surfaces cleaned.

B. Final Cleanup: Perform immediately before written request for final inspection of

Contract Work or any portion thereof.

C. Besides normal "Broom Clean" requirements, clean exposed surfaces as listed.

1. Glass: Wash and polish.

2. Painted Surfaces: Remove marks, stains, fingerprints, and dirt.

3. Exposed Slabs: Wash, scrape, and scrub, using detergent to remove bond breaker, dirt, and discolorations.

4. Asphalt Paving: Remove mud, oil, grease, dirt, and trash and hose down.

5. Aluminum: Clean following manufacturer’s recommendations.

6. Other Surfaces: Remove blemishes, leave clean, uniform, and dust-free.

7. Premises and Site: Remove trash, debris, and surplus excavated material.

D. Leave premises orderly and "Broom Clean."

1.3 RESTORATION AND RESTABILIZATION

A. Restore and restablize disturbed areas including, but not limited to staging and stockpiling areas, construction strips, access roads, stream crossings, and areas within acquired right of way.

01770-2 2026

B. Proceed with final restoration and restabilization following Restoration Schedule on Drawings and requirements in Sections 02315 and 02920, including seeding, sodding, and paving when season allows.

C. Disassemble and remove all temporary construction facilities and leave site in orderly and restored condition following Contract Documents.

D. Preserve public and private signs, markers, guardrails, and fences, and maintain in existing locations and condition unless written permission is obtained for removal and restoration or replacement.

1. Remove conflicting facilities when grading operations begin and store in manner to keep them clean and in existing condition.

2. Restore to original or new locations at Engineer's direction.

3. Repair or replace damaged items when directed, at no cost to the Commission.

E. Perform restoration of turf areas following Section 02920.

F. Perform tree protection, repair, and replacement following Sections 02230 and 02930.

G. Restore gravel surfaces and roadway shoulders to their condition before being disturbed.

1. Do not reuse shoulder material if contaminated by foreign material.

a. Replace with new material of same quality and gradation.

2. Materials and Methods of Construction: Follow jurisdictional requirements and applicable permits secured for this Contract.

3. Surface areas adjacent to shoulders, if left unstable by construction, with stabilized gravel or other acceptable stabilizing material.

H. Restore pavement, curbs, other paved areas, and sidewalks following requirements elsewhere in Contract Documents.

1.4 DISPOSAL OF WASTE AND EXCESS MATERIALS

A. Dispose of construction waste and excess materials in authorized County disposal area or in area covered by current grading or sediment control permit.

1. See Section 01110.

2. Furnish 3 copies of grading permits to Engineer before use of disposal site.

B. Remove waste and excess material disposed of in unauthorized area, and restore area to its condition before disturbance, at no cost to the Commission.

C. Dispose of human waste in special sites designated therefor.

01770-3 2026

1.5 REMOVAL OF REJECTED MATERIAL

A. Remove material delivered to Contract site, which has been determined by Engineer to be unsuitable or not following Contract Documents and dispose of in approved area.

PART 2 PRODUCTS

NOT USED

PART 3 EXECUTION

NOT USED

PART 4 MEASUREMENT AND PAYMENT

4.1 Providing for and complying with requirements in this Section will not be measured for payment, but cost will be considered incidental to Contract.

**WSSC**

STANDARD SPECIFICATIONS
SECTION 01770
PROJECT CLEANUP
1.1 DESCRIPTION
1.2 CLEANUP
1.3 RESTORATION AND RESTABILIZATION
1.4 DISPOSAL OF WASTE AND EXCESS MATERIALS
1.5 REMOVAL OF REJECTED MATERIAL
4.1 Providing for and complying with requirements in this Section will not be measured for payment, but cost will be considered incidental to Contract.